Methodology<br />
As per strategy, defined under NRHM, The team of district health society facilitated the<br />
DHAP processes at various levels with support of DFID - BTAST. For preparing district<br />
health action plan, below mentioned STEPs were followed:<br />
At Dariyarapur PHCs of saran Dist<br />
ANM exercising the PLAN<br />
STEP: 1<br />
STEP: 2<br />
� Developed the required formats refereeing the IPHS<br />
guidelines.<br />
� Ensuring the required information from various<br />
departments through proper communication.<br />
� Finalizations of the checklist for the data collection at HSC<br />
and Block level.<br />
� Sharing of received communication Lt.-30068 No. Dt.12 TH<br />
SEPT2011 FROM SHS, <strong>BIHAR</strong>.<br />
� Develop understanding on process of Dist, Block and HSC <strong>Health</strong><br />
<strong>Action</strong> <strong>Plan</strong> for FY -2012-13.<br />
� <strong>Plan</strong> development for Organizing Capacity building training to all<br />
ANMs and Nodal point Persons for developing HSC <strong>Action</strong> <strong>Plan</strong>.<br />
� Finalization of the CBT Dates And fixing of responsibility‟s to Nodal<br />
point persons for facilitating the BHAP, HSC <strong>Action</strong> plan.<br />
STEP:5<br />
� Time line As per direction from State <strong>Health</strong><br />
Society Bihar<br />
� Organizing Capacity Building Training to all ANM<br />
and Nodal Persons by 24 th -29 th Oct2011. to<br />
develop HSC and BHAP.<br />
� Submission of HSC wise situation Analysis and<br />
PIP format by 7 th Nov 2011.<br />
� Consolidation of HSC plan into BHAP 25 th of<br />
Dec2011<br />
� Consolidation of BHAP into DHAP by 10 th of<br />
Jan2012.<br />
STEP: 4<br />
� Future plan and course of actions 2012-13<br />
� Training at all level (Dist, Block and HSC level)<br />
For<br />
� HSC <strong>Action</strong> <strong>Plan</strong><br />
� Block <strong>Health</strong> <strong>Action</strong> <strong>Plan</strong>.<br />
� Developing Dist <strong>Health</strong> <strong>Action</strong> <strong>Plan</strong> FY12-13<br />
STEP:3<br />
� Formation of core team at dist level to monitor the<br />
progress.<br />
� Formation of team to facilitate the CB sessions at Block<br />
level to complete the planning exercise.<br />
� Extended regular support to all BHMs, BAM and ANM<br />
to ensure the timely completion of the planning exercise<br />
as prescribed formats and quality check.<br />
22 | P a g e D i s t r i c t H e a l t h A c t i o n P l a n 2 0 1 2 - 1 3 D H S , S a r a n