CM September 2020
The CICM magazine for consumer and commercial credit professionals
The CICM magazine for consumer and commercial credit professionals
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
LEGAL MATTERS<br />
SPARK OUT<br />
A landmark case may have far-reaching<br />
consequences for liquidators and creditors.<br />
AUTHORS – Jackie Ray FCI<strong>CM</strong> and Jennifer Guthrie<br />
THIS case of Bresco<br />
Electrical Services Ltd (in<br />
liquidation) v Michael J<br />
Lonsdale (Electrical) Ltd<br />
concerned the right of a<br />
company in liquidation to<br />
have its claim relating to a construction<br />
contract referred to an independent<br />
adjudicator under the Construction<br />
Adjudication Regime set up in 1996.<br />
In 2014 Bresco had been contracted to<br />
carry out electrical works for Lonsdale.<br />
Lonsdale later claimed more than £300,000<br />
from Bresco as compensation for failing<br />
to complete work due under the terms of<br />
the contract. Bresco claimed it was owed<br />
some £219,000 by Lonsdale for services it<br />
had provided under the contract. Bresco<br />
had since gone into liquidation.<br />
The liquidator referred the matter to<br />
an Adjudicator, but Lonsdale claimed<br />
that cross-claims could not be referred<br />
to Adjudication where one company is<br />
in liquidation, as insolvency legislation<br />
(principally the 1986 Insolvency Act)<br />
provides for cross claims in these<br />
circumstances to be set-off between the<br />
company in liquidation and its creditors,<br />
resulting in a simple net balance owed.<br />
Effectively, they argued, insolvency<br />
set-off rendered the claims under the<br />
contract void, so it could not be referred<br />
to Adjudication.<br />
PERCEIVED CONFLICT<br />
Essentially, therefore, the case concerns<br />
a perceived conflict between the<br />
construction Adjudication regime and<br />
the set-off provisions of the insolvency<br />
legislation. Lonsdale applied to the<br />
Technology and Construction Court for an<br />
injunction stopping the adjudication on<br />
that the basis that the set-off requirement<br />
rendered the cross-claims replaced by a<br />
single net balance, so there were no longer<br />
any claims to be referred to an adjudicator,<br />
and the adjudicator accordingly had no<br />
jurisdiction (the ‘Jurisdiction’ point).<br />
The Court accepted that argument and<br />
granted Lonsdale’s injunction. Bresco<br />
considered that the decision was wrong as<br />
a matter of insolvency law and appealed.<br />
In the Court of Appeal, the Jurisdiction<br />
argument was overturned, but the Court<br />
of Appeal introduced a new argument,<br />
on the basis of ‘futility’. Effectively,<br />
Court of Appeal said that Adjudications<br />
by insolvent companies would be<br />
futile since it is highly unlikely that any<br />
award in favour of an insolvent company<br />
would be enforced by a Court. Bresco then<br />
appealed to the Supreme Court. Lonsdale<br />
cross-appealed on the Jurisdiction point.<br />
The Supreme Court decision was<br />
unanimous. Lord Briggs delivered the<br />
judgment that found in favour of Bresco<br />
on both points. He emphasised that the<br />
Construction Adjudication Scheme has<br />
been highly successful as a means of<br />
alternative dispute resolution, saving<br />
huge sums in legal fees and valuable<br />
time that would otherwise have been<br />
spent in litigation through the Courts.<br />
It is also evident that Adjudication<br />
decisions are rarely challenged, as the<br />
parties are generally prepared to treat<br />
the Adjudication as binding. Or, as Lord<br />
Briggs phrased it during the hearing,<br />
the parties are generally not ‘sufficiently<br />
unhappy’ to pursue matters further after<br />
an Adjudication decision.<br />
In upholding the Court of Appeal<br />
judgment on the Jurisdiction point, Lord<br />
Briggs said that the insolvency set-off does<br />
not mean there is no longer any dispute<br />
under the terms of the construction<br />
contract, or that the respective claims<br />
are invalidated. Bresco would still<br />
have had the right to have the value<br />
of its claim determined in Court or<br />
through arbitration. It followed that the<br />
claim could also be referred to<br />
Adjudication.<br />
In allowing Bresco’s appeal on the<br />
Futility point, Lord Briggs made clear<br />
that the starting point is that it would<br />
ordinarily be inappropriate for a Court<br />
to interfere with the exercise of a<br />
statutory and contractual right. Indeed,<br />
Adjudication in the circumstances was<br />
an effective means for the liquidator to<br />
determine the value of the net balance.<br />
Enforcement of an Adjudication decision<br />
by way of summary judgment, rather than<br />
affecting the utility of the Adjudication<br />
process, is properly to be addressed<br />
at the enforcement stage, if there<br />
is one.<br />
Advancing the credit profession / www.cicm.com / <strong>September</strong> <strong>2020</strong> / PAGE 22