24.08.2020 Views

CM September 2020

The CICM magazine for consumer and commercial credit professionals

The CICM magazine for consumer and commercial credit professionals

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

LEGAL MATTERS<br />

SPARK OUT<br />

A landmark case may have far-reaching<br />

consequences for liquidators and creditors.<br />

AUTHORS – Jackie Ray FCI<strong>CM</strong> and Jennifer Guthrie<br />

THIS case of Bresco<br />

Electrical Services Ltd (in<br />

liquidation) v Michael J<br />

Lonsdale (Electrical) Ltd<br />

concerned the right of a<br />

company in liquidation to<br />

have its claim relating to a construction<br />

contract referred to an independent<br />

adjudicator under the Construction<br />

Adjudication Regime set up in 1996.<br />

In 2014 Bresco had been contracted to<br />

carry out electrical works for Lonsdale.<br />

Lonsdale later claimed more than £300,000<br />

from Bresco as compensation for failing<br />

to complete work due under the terms of<br />

the contract. Bresco claimed it was owed<br />

some £219,000 by Lonsdale for services it<br />

had provided under the contract. Bresco<br />

had since gone into liquidation.<br />

The liquidator referred the matter to<br />

an Adjudicator, but Lonsdale claimed<br />

that cross-claims could not be referred<br />

to Adjudication where one company is<br />

in liquidation, as insolvency legislation<br />

(principally the 1986 Insolvency Act)<br />

provides for cross claims in these<br />

circumstances to be set-off between the<br />

company in liquidation and its creditors,<br />

resulting in a simple net balance owed.<br />

Effectively, they argued, insolvency<br />

set-off rendered the claims under the<br />

contract void, so it could not be referred<br />

to Adjudication.<br />

PERCEIVED CONFLICT<br />

Essentially, therefore, the case concerns<br />

a perceived conflict between the<br />

construction Adjudication regime and<br />

the set-off provisions of the insolvency<br />

legislation. Lonsdale applied to the<br />

Technology and Construction Court for an<br />

injunction stopping the adjudication on<br />

that the basis that the set-off requirement<br />

rendered the cross-claims replaced by a<br />

single net balance, so there were no longer<br />

any claims to be referred to an adjudicator,<br />

and the adjudicator accordingly had no<br />

jurisdiction (the ‘Jurisdiction’ point).<br />

The Court accepted that argument and<br />

granted Lonsdale’s injunction. Bresco<br />

considered that the decision was wrong as<br />

a matter of insolvency law and appealed.<br />

In the Court of Appeal, the Jurisdiction<br />

argument was overturned, but the Court<br />

of Appeal introduced a new argument,<br />

on the basis of ‘futility’. Effectively,<br />

Court of Appeal said that Adjudications<br />

by insolvent companies would be<br />

futile since it is highly unlikely that any<br />

award in favour of an insolvent company<br />

would be enforced by a Court. Bresco then<br />

appealed to the Supreme Court. Lonsdale<br />

cross-appealed on the Jurisdiction point.<br />

The Supreme Court decision was<br />

unanimous. Lord Briggs delivered the<br />

judgment that found in favour of Bresco<br />

on both points. He emphasised that the<br />

Construction Adjudication Scheme has<br />

been highly successful as a means of<br />

alternative dispute resolution, saving<br />

huge sums in legal fees and valuable<br />

time that would otherwise have been<br />

spent in litigation through the Courts.<br />

It is also evident that Adjudication<br />

decisions are rarely challenged, as the<br />

parties are generally prepared to treat<br />

the Adjudication as binding. Or, as Lord<br />

Briggs phrased it during the hearing,<br />

the parties are generally not ‘sufficiently<br />

unhappy’ to pursue matters further after<br />

an Adjudication decision.<br />

In upholding the Court of Appeal<br />

judgment on the Jurisdiction point, Lord<br />

Briggs said that the insolvency set-off does<br />

not mean there is no longer any dispute<br />

under the terms of the construction<br />

contract, or that the respective claims<br />

are invalidated. Bresco would still<br />

have had the right to have the value<br />

of its claim determined in Court or<br />

through arbitration. It followed that the<br />

claim could also be referred to<br />

Adjudication.<br />

In allowing Bresco’s appeal on the<br />

Futility point, Lord Briggs made clear<br />

that the starting point is that it would<br />

ordinarily be inappropriate for a Court<br />

to interfere with the exercise of a<br />

statutory and contractual right. Indeed,<br />

Adjudication in the circumstances was<br />

an effective means for the liquidator to<br />

determine the value of the net balance.<br />

Enforcement of an Adjudication decision<br />

by way of summary judgment, rather than<br />

affecting the utility of the Adjudication<br />

process, is properly to be addressed<br />

at the enforcement stage, if there<br />

is one.<br />

Advancing the credit profession / www.cicm.com / <strong>September</strong> <strong>2020</strong> / PAGE 22

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!