WEM_02_2019

vakbladen.com
from vakbladen.com More from this publisher
24.05.2019 Views

energy magazine #2 Volume 6 June 2019 Grid Connection When wind farms become power stations Wieringermeer Wind Farm Vattenfall is currently working on one of the largest Dutch onshore wind projects. What are the challenges building in an area of around 300 km²? u Page 06 - 09 Interview Prysmian Group Future grid capacity is a hot topic in the Netherlands at the moment. What are the requirements in terms of cable designs? u Page 20 - 23 Solving the gridlock The acceleration of the energy transition requires extra grid capacity. Is the grid ready for the future influx of renewable energy? u Page 30 - 33

energy<br />

magazine<br />

#2<br />

Volume 6<br />

June<br />

<strong>2019</strong><br />

Grid<br />

Connection<br />

When wind farms become power stations<br />

Wieringermeer Wind Farm<br />

Vattenfall is currently working on one<br />

of the largest Dutch onshore wind<br />

projects. What are the challenges<br />

building in an area of around 300 km²?<br />

u Page 06 - 09<br />

Interview Prysmian Group<br />

Future grid capacity is a hot topic in<br />

the Netherlands at the moment.<br />

What are the requirements in terms<br />

of cable designs?<br />

u Page 20 - 23<br />

Solving the gridlock<br />

The acceleration of the energy<br />

transition requires extra grid<br />

capacity. Is the grid ready for the<br />

future influx of renewable energy?<br />

u Page 30 - 33


Change the World. Join Atlas! Apply now at www.atlasprofessionals.com


Editor’s note<br />

In transition…<br />

With the effects of climate change<br />

being felt all over the world, the<br />

pressure is high for all countries to<br />

quickly reduce their CO2 emissions.<br />

Moving away from fossil fuels, increasing the share<br />

of renewable energy, electrification of the industry<br />

and transport, these are just some examples of<br />

solutions at hand. Found somewhere at the bottom of<br />

the EU’s sustainable energy ranking list, the pressure<br />

is even higher for the Netherlands.<br />

We are facing an Energy Transition of such magnitude<br />

that it will affect every aspect of our daily lives. It requires<br />

changes and adaptions from all parties involved; energy<br />

producers, electricity network operators, (national, regional<br />

and local) governments, but also the energy consumers,<br />

whether they are the industry or individual households.<br />

But how can we reduce our CO2 emissions fast if there is lack of<br />

agreement on the best practise? As the word transition already<br />

suggests, everyone is still looking into best ways. Should we stop<br />

immediately with gas and nuclear power or should these be phased-out<br />

slowly while we are getting used to new ways? What alternative energies should<br />

prevail? Lessons will have to be learned and innovations to be made.<br />

30<br />

Dutch<br />

electricity<br />

network<br />

© TENNET<br />

Whichever way we choose, it will affect the existing electricity network. Like the veins<br />

and the heart keep the blood flowing, the electricity network ensures that all the energy<br />

produced (supply) is delivered where it is needed (demand). With (large) renewable<br />

energy projects being built in regions all over the country, including regions with low<br />

energy demand, we are moving away from a centralised energy system. This will no<br />

doubt require modifications to the existing electrical network system.<br />

In this edition we explain the existing electricity network in the Netherlands and we<br />

spoke to some of the players that are directly involved; like cable manufacturer<br />

Prysmian Group and HSM Offshore who build the offshore substations for connecting<br />

offshore wind farms with the national grid. We spoke also to Vattenfall who are working<br />

on a large-scale onshore repowering project, Wieringermeer Wind Farm, where<br />

formerly scattered wind turbines are replaced by more powerful wind turbines in<br />

arranged line positions. Their experience provides an insight into the challenges that<br />

are already being felt when it comes to grid connection.<br />

Restyle<br />

The Wind Energy titles are also going through a transition phase. We carried out a<br />

restyle of the magazine as a first step. Our news sites Windenergie-nieuws.nl (NL) and<br />

Windenergy-magazine.com (EN) will follow soon. Keep an eye on these websites as<br />

they will offer you a useful starting point from which to explore the Dutch wind<br />

industry and its players.<br />

The Energy<br />

Transition will<br />

impact the<br />

electricity network<br />

Sabine Lankhorst<br />

Editor in Chief<br />

Wind Energy Magazine<br />

presswem@vakbladen.com<br />

<strong>02</strong>-<strong>2019</strong> | 3


Contents<br />

Wind farm in focus<br />

Wind Energy Magazine Vol. 6 | <strong>02</strong>-<strong>2019</strong><br />

energy<br />

magazine<br />

#2<br />

Volume 6<br />

June<br />

<strong>2019</strong><br />

Wieringermeer Wind Farm 06<br />

Theme: grid connection<br />

Future offshore wind farms require bold solutions 14<br />

Storms, sea mines and sand dunes 16<br />

Stepping up to serve the future grid 20<br />

The beating heart of a wind farm 24<br />

Solving the gridlock 30<br />

Grid<br />

Connection<br />

Innovation<br />

Island at Sea 34<br />

When wind farms become power stations<br />

Ocean Grazer 38<br />

Wieringermeer Wind Farm<br />

Vattenfall is currently working on one<br />

of the largest Dutch onshore wind<br />

projects. What are the challenges<br />

building in an area of around 300 km²?<br />

Page 06 - 09<br />

Cover<br />

Interview Prysmian Group<br />

Future grid capacity is a hot topic in<br />

the Netherlands at the moment.<br />

What are the requirements in terms<br />

of cable designs?<br />

Page 20 - 23<br />

Solving the gridlock<br />

The acceleration of the energy<br />

transition requires extra grid<br />

capacity. Is the grid ready for the<br />

future influx of renewable energy?<br />

Page 30 - 33<br />

The Ocean Grazer Concept is a<br />

hybrid modular offshore system that<br />

combines wind, wave & storage and<br />

potentially other sources of renewable<br />

energy.<br />

Regular features<br />

Onshore Wind Farm News 10<br />

Column ENVIR Advocaten 13<br />

Offshore Wind Farm News 28<br />

General news 40<br />

Agenda & Publication dates 42<br />

Page 38<br />

GRID<br />

Theme:<br />

Grid Connection<br />

Colofon<br />

energy<br />

magazine<br />

VOLUME 6 | JUNE <strong>2019</strong> | ISSUE <strong>02</strong><br />

Wind Energy Magazine, a quarterly trade<br />

magazine for professionals who are involved or<br />

interested in onshore and offshore wind energy<br />

developments in the Netherlands.<br />

Publication:<br />

Wind Energy Magazine is a quarterly publication.<br />

Publisher:<br />

Roeland Dobbelaer<br />

Publishing company:<br />

Vakbladen.com<br />

Rijswijkseweg 60 (13e etage), 2516 EH Den Haag,<br />

PO box 19949, 2500 CX Den Haag,<br />

The Netherlands<br />

Website:<br />

www.windenergy-magazine.com<br />

www.windenergie-nieuws.nl<br />

Editor in Chief:<br />

Sabine Lankhorst<br />

Contributors to this edition:<br />

Erick Vermeulen, Martijn Bongaerts, Bart Stam,<br />

Mirjam Tielen, Marieke Kaajan (ENVIR Advocaten)<br />

Cover image:<br />

Ocean Grazer BV<br />

Advertising:<br />

Archer Media B.V.<br />

Peter van den Bosch, account manager<br />

Tel. +31 (0)6 29035649<br />

E-mail: p.vandenbosch@archermedia.nl<br />

Artwork:<br />

Archer Media B.V.<br />

E-mail: traffic@archermedia.nl<br />

Tel. +31 (0) 88 2266 690<br />

Subscription service:<br />

Mijntijdschrift.com<br />

Curieweg 16<br />

8013 RA Zwolle<br />

Tel. +31 (0)88 22 666 80<br />

E-mail: abonnementen@vakbladen.com<br />

Subscription fees, annual:<br />

The Netherlands/Belgium:<br />

€ 40 (incl. VAT)<br />

EU & ROW: € 60 (incl. VAT)<br />

Subscriptions may start at any moment and will be<br />

automatically renewed after a year. Subscriptions<br />

can be cancelled two months prior to the end of the<br />

subscription period.<br />

ISSN 2352-7560<br />

Copyright © <strong>2019</strong> Vakbladen.com<br />

The publisher does not necessarily agree with the<br />

views expressed by the contributors, nor does he<br />

accept any responsibility for any errors of<br />

translation in the subject matter of this publication.<br />

No part of this publication may be reproduced and/<br />

or published by means of print, photocopy, microfilm<br />

or any other medium, without the prior written<br />

consent of the publisher.<br />

Personal data:<br />

Wind Energy Magazine records reader data for the<br />

purpose of distribution of the magazine. These data<br />

may be used to inform you about our other services<br />

or products.<br />

Design:<br />

Content Innovators<br />

Printed by: Veldhuis Media, Raalte<br />

4 | <strong>02</strong>-<strong>2019</strong>


Vattenfall: Jorrit Lousberg<br />

20<br />

Interview: Prysmian Group<br />

Future grid capacity is currently a hot topic in<br />

the Netherlands. With the wind projects<br />

becoming larger, especially at sea, what are<br />

the requirements in terms of cable designs?<br />

06<br />

24<br />

The beating heart of a wind farm<br />

In 20<strong>02</strong>, HSM Offshore built the offshore substation<br />

for the first offshore wind farm, Danish<br />

Horns Rev A. 17 years later, the manufacturing<br />

company is still building offshore platforms.<br />

Realising the largest Dutch<br />

repowering project<br />

Wieringermeer Wind Farm<br />

Vattenfall is currently building one of the largest Dutch wind farms in the<br />

Wieringermeer. In this enormous stretched area, covering around 300 square<br />

kilometres, the wind has free play at all times. With 82 wind turbines, this is also<br />

the company’s largest Dutch onshore wind project developed by themselves.<br />

30 38<br />

Solving the gridlock<br />

There is an acceleration of the energy transition: in more and<br />

more places, renewable energy is being produced. This supply<br />

of renewable energy requires extra capacity of the grid.<br />

Ocean Grazer - When supply and demand meet<br />

The University of Groningen developed the Ocean Grazer<br />

Concept, a hybrid modular offshore system that combines<br />

wind, wave & storage.<br />

<strong>02</strong>-<strong>2019</strong> | 5


Wind Farm in Focus<br />

Sabine Lankhorst<br />

Vattenfall: Jorrit Lousberg<br />

6 | <strong>02</strong>-<strong>2019</strong>


Wieringermeer Wind Farm<br />

Realising the<br />

largest Dutch<br />

repowering project<br />

Vattenfall is currently building one of the largest Dutch wind farms in the<br />

Wieringermeer. In this enormous stretched area, covering around 300 square<br />

kilometres, the wind has free play at all times. With 82 wind turbines, this is also<br />

the company’s largest Dutch onshore wind project developed by themselves.<br />

We talked to Ruben Lindenburg, Project Director<br />

Construction for the wind farm to hear the experience<br />

so far.<br />

Vattenfall will build 82 of a total of 100 wind turbines that<br />

shape Wieringermeer wind farm. Are you still working with<br />

the developers of the remaining 17 wind turbines?<br />

Wieringermeer wind farm is a repowering project. The Dutch<br />

Government provided a permit for 100 wind turbines. The permit<br />

would be granted to one party only. Vattenfall already had some<br />

small wind farms in this area. Together with research centre ECN<br />

and Windcollectief Wieringermeer, we joined forces to apply for<br />

the permit. In September 2017, we acquired the 32 turbines from<br />

Windcollectief Wieringermeer. Up to the decision of the Council<br />

of State (Raad van State) we worked together with ECN but once<br />

the permits were in place, we each followed our own path.<br />

Of the 82 wind turbines, 78 are located on agricultural land<br />

and 4 in the Robbenoordbos forest. Was it really necessary<br />

to build in the forest?<br />

We often get this question. And if you look at the surroundings as<br />

an outsider, I can understand the question. The layout of the wind<br />

farm was determined by the Government’s so-called<br />

‘Structuurvisie’ (structural concept), around 12 years ago. For one,<br />

the turbines had to be installed in single line position. That already<br />

rules out parts of the area. Also, back then, the Government invited<br />

all the stakeholders from the region. During the stakeholder<br />

process, all stakeholders, varying from farmers, communities, defence,<br />

airport, energy companies, nature conservation organisations,<br />

etcetera, could provide their input or restrictions. In the initial<br />

plan, 6 wind turbines were located in the forest but after research<br />

and consultation with our ecological experts, two wind turbines<br />

were scrapped. To construct the four wind turbines in the forest,<br />

around 3.5 has of space had to be cleared. But we are planting new<br />

trees in an adjacent area of 4 has, so we are returning more than<br />

we removed. All was done in good cooperation and in consent with<br />

nature conservation organisation Staatsbosbeheer who wish to<br />

combine forests with renewable energy production. In the design,<br />

we made sure the wind turbines would be optimally integrated in<br />

the landscape. We also provided special facilities for bats as this<br />

area is a popular place for bats.<br />

What is the current status of the construction activities?<br />

At the moment, 42 foundations and around 70% of the road and<br />

internal cable construction have been completed. Hearing me say<br />

this actually makes me realise how happy I am to see that we are<br />

half way and have made this progress. We have faced quite some<br />

challenges along the way and this has affected the original planning.<br />

Next week, the components of the first Nordex wind turbines<br />

should be arriving. I sincerely hope that the turbine installation will<br />

be a smooth process. Fingers crossed!<br />

You mention there were some challenges. Can you mention<br />

a few?<br />

Keep in mind that the Wieringermeer wind farm is a rather unique<br />

case for Vattenfall in the Netherlands. This is the largest onshore<br />

wind project that we are developing on our own here and I don’t<br />

think we will see many more of this size in this highly populated<br />

country. The total site covers an area of 300 square kilometres.<br />

<strong>02</strong>-<strong>2019</strong> | 7


This is the largest onshore wind<br />

project that we are developing on<br />

our own here and I don’t think<br />

we will see many more of this size<br />

in this highly populated country<br />

In this enormous area we are installing 82 turbines. Imagine, it takes<br />

a 175 kilometre long round to drive from turbine to turbine.<br />

This requires quite some organisation.<br />

We already knew we had to relocate a glider airport and so we did.<br />

The new glider facility is taken over since October last year and is<br />

fully operational. Next, the soil conditions in the Wieringermeer<br />

are varying and hence challenging. We need to examine those before<br />

we create a technical design. At the start of the process, soil<br />

samples are taken at different spots across the area to determine<br />

the site specifics. Based on this, the technical design is created.<br />

For Wieringermeer, it took 5 months to create this design.<br />

Wieringermeer is built on a combination of clay and sand<br />

grounds. These require different construction approaches for the<br />

roads, crane hardstands and to a lesser extent, the foundations.<br />

People tend to think that the transportation and installation of<br />

the wind turbine components (tower, hub and blades) are the<br />

most challenging aspects of building a wind farm. However, the<br />

construction of the roads, the crane hardstands, and the foundations<br />

are the most critical part. You have to imagine that ten<br />

thousands loads of sand, concrete, asphalt and steel are required<br />

during the road, cable and foundation construction work. The<br />

municipality did reinforce some existing bridges in the area to ensure<br />

that the heavy weight transport could pass. The crane hardstands<br />

have to be able to support the heavy installation cranes<br />

and their loads, and the foundations need to be able to support<br />

the turbines and towers.<br />

As an example of the variety of soil condition, in the north-western<br />

section there is an underground current running which was formed<br />

back in the ice age. Using vibro piles would be impossible as the<br />

concrete would flow away. Here we had to use pre-fab piles. The<br />

crane hardstands had to be piled in this area. Also, the ground water<br />

in the Wieringermeer is relatively salty when you go a little bit<br />

deeper than usual. As a result, excess water that is pumped up during<br />

the cable burial work cannot be released in the surrounding<br />

ditches. We had to use pipes, of sometimes 7 kilometres in length<br />

and with a diameter of 60 centimetres, to transport the excess water<br />

all the way from the western part of the site to the IJsselmeer lake.<br />

All this has to be taken into consideration when creating the technical<br />

design. However carefully you design every aspect, you might<br />

learn that for some practical reasons, some of the elements are not<br />

viable in reality. This could be a road being allocated where there is<br />

a crossing or an underground cable running. You will have to modify<br />

the route. However, this means that you first have to take new<br />

Vattenfall: Aerophoto Schiphol<br />

soil samples again. If the soil is for example softer, then you will<br />

have to use concrete instead of asphalt.<br />

It is not only the contractors that request for a change in the design.<br />

The farmers on which lands we are building the turbines have<br />

their expectations as well. It has happened more than once that<br />

when we were about to start construction activities, we were pointed<br />

at a possible problem. For example, where a road would cross a<br />

drainage system. Then the question rises where to lay the cable,<br />

above or below the drainage system? There is no standard burial<br />

depth for drainage systems and we hit drainage canals quite some<br />

times. In addition, there are several flower farmers that will raise<br />

their ground water levels in July, August. It would be impossible to<br />

install a crane then. These are all examples that kept on occurring,<br />

leading to additional expenses and delay. That’s why we have<br />

two-weekly meetings with the farmers involved, to take them<br />

through our plans and to provide them with the opportunity to express<br />

possible concerns or share ideas.<br />

Another change in the plan concerned the activities of our contractors.<br />

In the initial plan, Van Gelder would be responsible for the<br />

construction of the roads, the staging areas and the cable installation.<br />

BAM would follow to build the foundations and then Nordex<br />

would install the turbines. Seven months down the road, we had to<br />

change this. In some parts of the area, BAM did start before Van<br />

Gelder, building temporary roads to start the construction of the<br />

foundations, followed by Van Gelder, Nordex and in the end Van<br />

Gelder again to finish up.<br />

The project was delayed for nine months due to problems<br />

with the substation. What is the current status?<br />

In the wind farm, all our turbines are connected in groups to 15<br />

small client stations. An electrical engineer would say we have 15<br />

small wind farms. These client stations are connected by Liander<br />

to the substation at the Agriport A7 business park in Middenmeer.<br />

8 | <strong>02</strong>-<strong>2019</strong>


This substation is a project by regional operator Liander and national<br />

grid operator TenneT. Initially the completion of the substation<br />

was planned for July 2018 but this was delayed. It’s the chicken-and-egg<br />

story really, both TenneT and Liander wouldn’t start<br />

with the construction until we confirmed that we were going to<br />

build the wind farm and we couldn’t build the wind farm if there<br />

was no guaranteed grid connection. When we finally managed to<br />

find a short-cut, they didn’t have a contractor available. The result<br />

was a delay of 9 months. This meant we had to postpone our tender<br />

for contractors also. The substation was ready and switched on<br />

in December last year but was shut down again soon after to already<br />

extend the substation for new customers.<br />

Do you know when you can expect to get the wind farm<br />

connected to the substation?<br />

We had hoped to make the next available connection slot, in<br />

March, but unfortunately this didn’t happen either. Currently,<br />

u Wind farm facts<br />

Owner: Vattenfall<br />

Total power: 295.2 MW<br />

Wind turbines: 3.6 MW (Nordex N117/3600)<br />

Number of turbines: 82<br />

Site preparations: Van Gelder<br />

Construction foundations: BAM<br />

Client stations: 15<br />

Substation: TenneT & Liander. 150/20 kV at Agriport A7<br />

business park in the municipality of Hollandse Kroon<br />

Cables: 20 Kv<br />

Cable installation: Combinatie HPV (Heijmans,<br />

Gebroeders Pol, Van Voskuilen) by order of Liander<br />

Operational: expected in <strong>2019</strong><br />

we’re about to energize the first client station and we’re thrilled we<br />

came to this stage. Again, it’s a complex situation where the substation<br />

will not solely connect our wind farm. At the moment there<br />

are many developments taking place in this region. Google is going<br />

to build their facility, Microsoft is expanding and the Ministry of<br />

Waterways and Public Works is doing work at the Afsluitdijk. In the<br />

meantime we need electricity, for all the drainage systems and the<br />

work on the client stations. Last month, for example, we installed<br />

the first client station. In order to continue with our work we rented<br />

a mobile green battery to ensure electricity is available.<br />

Sustainability is high on the agenda for Vattenfall. You already<br />

mentioned the green battery, are there more examples<br />

of sustainable initiatives?<br />

Vattenfall aims to become fossil free within one generation. With<br />

everything we do, we try to do it in a most sustainable way. For<br />

example, the information centre/office that we have set up on site is<br />

almost energy neutral. We use wind energy, heat pumps, led lightning<br />

and re-use rain water. This building will be removed when the<br />

wind farm is operational but the new service station, the clubhouse<br />

of the former glider airfield, will be fully energy neutral. We recently<br />

finished this service centre. At the wind farm, our employees drive<br />

electric cars or cars driven by blue diesel (Hydrotreated Vegetable<br />

Oil). In March, we won our company’s ‘Environmental Award’<br />

award and we’re really proud we’re taking a step extra to build this<br />

wind farm as environmentally friendly as possible.<br />

Talking about sustainability, have you considered installing<br />

solar fields near the wind turbines?<br />

We did look at it but we decided first to concentrate on this wind<br />

farm and later in the project look at the possibilities to install solar<br />

panels. We know it is possible because we are realizing this also in<br />

other places. And if we do, they can easily be connected to the<br />

available grid system.<br />

<strong>02</strong>-<strong>2019</strong> | 9


Onshore<br />

Wind Farm News<br />

8<br />

5<br />

© WINDPARK KRAMMER<br />

1<br />

Wieringermeer Wind<br />

Farm<br />

See page 6 - 9.<br />

2<br />

De Drentse Monden en<br />

Oostermoer Wind Farm<br />

At the start of May, the<br />

foundation for the first wind<br />

turbine was built. The turbine,<br />

type N131 from Nordex, is<br />

expected to be installed<br />

during June. It is the first of 7<br />

wind turbines in a line. Also<br />

completed were the cables<br />

(and a pipe for the optical<br />

fibre cable) that connect the 7<br />

wind turbines to the client<br />

station from where the<br />

generated electricity is<br />

supplied to the electricity<br />

network. The wind farm will<br />

comprise 45 wind turbines in<br />

total, to be installed in 6 single<br />

line positions in an area in the<br />

municipalities of Borger-<br />

Odoorn and Aa en Hunze.<br />

3<br />

De Veenwieken Wind<br />

Farm<br />

In April, a ground-breaking<br />

ceremony took place to mark<br />

the start of the construction.<br />

By mid-May, the piling<br />

activities for the foundations<br />

were completed. Throughout<br />

the summer, contractor Meyer<br />

Sonderbau will build the<br />

concrete foundations. The<br />

wind farm is located between<br />

Dedemsvaart, Ommen and<br />

Hardenberg, in the eastern<br />

part of the Netherlands. 10<br />

Enercon, type E-103, wind<br />

turbines will rise here. Six are<br />

owned by De Wieken<br />

(Windunie, Greenchoice and<br />

ABN Amro Energy Transition<br />

Fund) and 4 by Raedthuys<br />

Pure Energie.<br />

4<br />

Samen Voor de Wind<br />

Wind Farm<br />

All 7 wind turbines alongside<br />

the Overijsselse tocht, nearby<br />

Swifterbant in the municipality<br />

of Dronten, have been<br />

dismantled. A start is made on<br />

the construction of the<br />

foundations, starting with<br />

piling activities. The old<br />

Enercon, type E66, turbines<br />

are replaced by 7 Enercon,<br />

type E82, turbines. These<br />

generate approximately<br />

35,000,000 KWh annually, the<br />

equivalent of the total energy<br />

consumption of around 9,000<br />

households, against 1,500<br />

households previously. Samen<br />

Voor de Wind is an initiative of<br />

7 farmers. It will supply<br />

electricity to Greenchoice.<br />

4<br />

5<br />

Zeewolde Wind Farm<br />

All the contracts are in place<br />

for the 320 MW wind farm.<br />

The 83 wind turbines that will<br />

replace the old 220 wind<br />

turbines will be supplied by<br />

German wind turbine<br />

manufacturer Enercon and will<br />

consist of 74 EP3 and 9 EP2<br />

wind turbines. Dura Vermeer<br />

and GMB will be responsible<br />

for the installation of roads,<br />

cables and foundations.<br />

Vattenfall will purchase the<br />

electricity under a 15-years<br />

agreement. The operationaltechnical<br />

management<br />

contract has been concluded<br />

with specialist company<br />

OutSmart. ABB Power Grids<br />

will supply the substation and<br />

the 6.5-kilometre long cable<br />

connection between the<br />

substation and the TenneT<br />

high-voltage grid. It will also<br />

supply two 240 MVA<br />

transformers. Construction<br />

activities are planned to start<br />

at the end of <strong>2019</strong>. Zeewolde<br />

wind farm is owned by a<br />

partnership of 220 farmers,<br />

wind turbine owners and<br />

residents.<br />

6<br />

Energy Park Rijnenburg<br />

en Reijerscop<br />

The municipality of Utrecht<br />

has plans to facilitate the<br />

development of up to 11 wind<br />

turbines and 227 hectares of<br />

solar parks in the Rijnenburg<br />

and Reijerscop polders near<br />

Utrecht. In April, the Municipal<br />

Executive of Utrecht<br />

presented a draft proposal for<br />

this energy park which could<br />

potentially provide 96,000<br />

local households with green<br />

energy in the future. The<br />

initiators Rijne Energie, Eneco<br />

and BHM Solar will explore the<br />

possibilities, together with the<br />

communities.<br />

7<br />

Energie A16<br />

In April, representatives of<br />

governments, initiators and<br />

neighbourhood and<br />

community councils signed a<br />

new covenant for the<br />

development of wind energy<br />

along the highway A16. In<br />

2<strong>02</strong>0, 28 wind turbines with a<br />

combined power of 100 MW<br />

will be installed in an area of 1<br />

km on both sides of the<br />

highway. The project is an<br />

initiative of the province,<br />

together with the<br />

municipalities of Breda,<br />

Drimmelen, Moerdijk and<br />

Zundert.<br />

8<br />

© WINDPARK ZEEWOLDE<br />

Krammer Wind Farm<br />

On May 15, the wind farm was<br />

officially openend. In<br />

December 2018, the last of 34<br />

Enercon E 115 wind turbines<br />

was installed. At the end of<br />

March the 1<strong>02</strong> MW wind farm<br />

was fully operational.<br />

Krammer is a project by the<br />

cooperatives Zeeuwind and<br />

Deltawind. With around 5,000<br />

members, it is the largest<br />

citizens’ initiative in the<br />

Netherlands.<br />

10 | <strong>02</strong>-<strong>2019</strong>


1<br />

2<br />

4<br />

3<br />

5<br />

6<br />

8<br />

7<br />

Read the full news<br />

on www.windenergymagazine.com<br />

(EN) or<br />

www.windenergienieuws.nl<br />

(NL)<br />

<strong>02</strong>-<strong>2019</strong> | 11


SMART<br />

MARITIME<br />

TECHNOLOGY<br />

Disruptieve technologie in de maritieme sector<br />

13 JUNI <strong>2019</strong><br />

Welke technologie brengt de komende jaren revoluties teweeg in de maritieme<br />

sector? Vakblad Maritiem Nederland organiseert in juni <strong>2019</strong> voor de tweede maal<br />

het congres Smart Maritime Technology (SMT).<br />

Dit congres laat managers en technici uit de maritieme sector zien wat de<br />

technologie is waar we op moeten inzetten, om de boot straks niet te missen.<br />

Tijdens SMT krijgen de deelnemers, naast een inspirerende netwerkdag,<br />

een overzicht van baanbrekende technologieën, waar ieder maritiem bedrijf<br />

zich in zou moeten verdiepen en in mee zou moeten gaan om ook op lange<br />

termijn succesvol te zijn.<br />

Locatie VNAB<br />

Kennis- en ontmoetingscentrum,<br />

Rotterdam<br />

Datum: 13 juni <strong>2019</strong><br />

Tijd: 11.00 - 17.30 uur<br />

Kosten: € 175,-<br />

Korting voor abonnees<br />

Abonnees van<br />

dit blad ontvangen<br />

50 euro korting<br />

op de toegangsprijs!<br />

Een samenwerking van:<br />

smt.maritiemnederland.com voor programma en aanmelden


Column<br />

Marieke Kaajan<br />

Lawyer ENVIR Advocaten<br />

Grid connections<br />

The energy transition presents us all with a major challenge. Electricity companies<br />

are forced to think about other, more sustainable forms of energy production.<br />

Onshore and offshore wind energy are the best known of these. However, it is<br />

generally accepted that wind farms are not sufficient to achieve the objectives of<br />

the energy transition. Other known forms are solar energy and the electrification of transport.<br />

Consideration is also being given to the possibilities of storing sustainably produced electricity.<br />

Consider, for example, the plans for an energy island in the North Sea. Saving energy is also<br />

a permanent part of the energy transition. Other solutions are still needed, solutions that are<br />

perhaps still in their infancy and for which it is not yet clear whether they will be able to<br />

contribute to the energy transition on a larger scale.<br />

All this also has consequences for the electricity grid in the Netherlands. On 8 January <strong>2019</strong>,<br />

the Financieele Dagblad (FD) reported that the electricity grid in the Northern Netherlands<br />

is almost full and that no room could be offered for all initiatives in this region to install solar<br />

panels, in particular. Another report in the FD, dated 7 May <strong>2019</strong>, shows that an<br />

entrepreneur had to wait more than a year for a grid connection for an electric sand motor.<br />

Furthermore, many SDE subsidy schemes include the obligation to start the subsidy period<br />

within a certain period of time after obtaining a subsidy decision, regardless of whether the<br />

activity to be subsidised has been taken into use. If a timely start is not possible, it is often<br />

impossible to postpone the date on which the subsidy-period starts. Uncertainties in this area<br />

will, of course, be taken into account when deciding whether or not to invest in a sustainable<br />

energy development. Think also of Amsterdam’s announcement that consideration is being<br />

given to not allowing diesel and petrol cars into the city from 2030. To the extent that this<br />

plan is feasible, it will also mean a major change for the network in Amsterdam.<br />

All this shows that attention to sufficient network capacity should be an essential and integral<br />

part of the energy transition. In the case of large(r) initiatives, the involvement of a network<br />

operator occurs relatively quickly, so that a (more or less timely) network connection will be<br />

available in this way. In the case of offshore wind energy, this has now been enshrined in law.<br />

But it is expected that the smaller initiatives will become an essential part of the energy<br />

transition. It is important to prevent these initiatives from being delayed to such an extent<br />

that they abandon a sustainable solution. After all, it is undesirable for restrictions in the<br />

electricity grid to result in people being forced to choose a less sustainable solution, as it were.<br />

Sufficient<br />

network capacity<br />

should be an<br />

essential and<br />

integral part of<br />

the energy<br />

transition<br />

Not only do network companies need to be closely involved in the (national, regional and<br />

local) energy strategies so their expertise can be used as a basis for thinking about the timing<br />

of various forms of policy. It is also important, however, that sufficient resources are available<br />

to set the network up in such a way that it does not so much follow already known and certain<br />

developments, but also includes (sufficient) room for the connection of new sustainable<br />

developments. This is precisely how the network can contribute to achieving the objectives of<br />

the energy transition.<br />

<strong>02</strong>-<strong>2019</strong> | 13


Grid Connection<br />

Bart Stam<br />

Future offshore wind farms require bold solutions<br />

Bigger, higher<br />

and further<br />

The Netherlands faces an enormous challenge of producing 49 terawatt<br />

hours of electricity from wind turbines at the North Sea by the year 2030.<br />

The only solution seems to be ever larger turbines far away from the coast,<br />

but how do we ensure that offshore wind energy remains competitive?<br />

PHOTO: TENNET<br />

This was discussed at the National Wind Energy Event<br />

April 17 in Rotterdam. Offshore wind energy in the<br />

Netherlands literally has the wind at its back. For<br />

example, the 2030 Roadmap by the Ministry of<br />

Economic Affairs and Climate Policy aims for no less than 10.6<br />

gigawatts (10,600 megawatts) in the Dutch part of the North Sea.<br />

Of this, 3.5 GW must be installed by 2<strong>02</strong>3 and 6.1 GW by 2030.<br />

By way of comparison: the four existing offshore wind farms have<br />

a combined capacity of 957 MW. So, there’s work to do!<br />

The designated zones for the third generation (2<strong>02</strong>3-2030) of<br />

offshore wind farms are ‘Hollandse Kust (West)’ (1,400 MW), ‘Ten<br />

Noorden van de Waddeneilanden’ (700 MW) and ‘IJmuiden Ver’<br />

(4,000 MW or 4 GW). The latter’s name (‘IJmuiden Far’) has been<br />

chosen aptly, because the location is situated at no less than eighty<br />

kilometres from the coast, near the British Exclusive Economic Zone.<br />

Here, Swedish developer Vattenfall will build the Norfolk Vanguard<br />

and Norfolk Boreas wind farms, both accounting for 1.8 GW.<br />

Enormous distances<br />

Such distances between wind farms and the mainland pose<br />

considerable challenges. In the run-up to IJmuiden Ver offshore<br />

wind farm, which is scheduled to go into production between<br />

2<strong>02</strong>7 and 2030, TenneT is already working on the development of<br />

a new generation of 2 gigawatt (GW) transformer stations and 525<br />

kilovolt (kV) electricity cables, in order to get the enormous<br />

amount of electricity on land efficiently. “Offshore wind energy is<br />

currently showing a paradox”, claims Rob van der Hage MSc,<br />

Manager Offshore Grid Development at TenneT NL. “While the<br />

If there’s no demand from<br />

the industry, then there’s no<br />

business case<br />

costs for construction, operation and investment are steadily<br />

decreasing, transport and connection costs are increasing due to<br />

longer distances. This can pose a threat to the cost reduction of<br />

offshore wind energy.”<br />

For the upcoming wind farms in 2<strong>02</strong>3, TenneT can suffice with<br />

transformer stations of 700 MW. However, new solutions are<br />

needed for IJmuiden Ver sized wind farms. For example, as grid<br />

manager TenneT has calculated, from about 80 kilometres off the<br />

coast, DC cables are more efficient than AC cables. Of course, the<br />

Arnhem-based grid operator also takes into account the 10 MW<br />

and 12 MW wind turbines that will make their debut in a few<br />

years’ time. For example, General Electric is currently building the<br />

world’s largest wind turbine, Haliade-X 12 MW, in the port of<br />

Rotterdam. This test model will have three rotor blades of 107<br />

metres and a rotor diameter of no less than 220 metres. A test<br />

period of five years will start by mid-<strong>2019</strong>.<br />

Energy islands<br />

Together with Gasunie, Port of Rotterdam and Energinet.dk from<br />

Denmark, TenneT has been investigating the feasibility of artificial<br />

energy islands in the North Sea since 2016. It goes without saying<br />

that these ‘NorthSea Windpower Hubs’ will not be realised<br />

overnight, so TenneT and its partners are aiming for 2030 and<br />

beyond. The aim of these islands is not only to bundle large<br />

quantities of electricity from neighbouring wind farms and bring it<br />

ashore in North-West Europe via an advanced network of<br />

connectors and cables, but also to use the electricity produced on<br />

site for, hydrogen production, for example. In addition,<br />

maintenance and assembly of wind turbines could also take place<br />

there. Such energy islands do require far-reaching European<br />

cooperation. Especially, if in the distant future the entire North<br />

Sea is likely to host 150 GW (or more) of offshore wind farms.<br />

For Kees-Jan Rameau, chief strategic growth officer at energy<br />

company Eneco, it is important that the price of wind energy<br />

14 | <strong>02</strong>-<strong>2019</strong>


Artist’s impression of IJmuiden Ver offshore substation station<br />

continues to fall in the coming years. “At Luchterduinen in 2011,<br />

investment costs were 170 euros per megawatt hour. At Borssele 3<br />

and 4, December 2016, this rate had already fallen to 54 euros<br />

and the end is not yet in sight. That’s why nowadays, we can build<br />

offshore wind farms without government subsidies.”<br />

According to Rameau, this cost reduction can only continue if we<br />

succeed in balancing supply and demand of electricity from wind<br />

farms at sea. “In 2030, most of the demand for clean electricity<br />

will come from industry, approximately some 18 terawatt hour.<br />

After all, for their production processes companies will have to<br />

switch from natural gas to electrification in the coming years.”<br />

For this view, Rameau gets support from Hans Timmers,<br />

chairman of NWEA (Netherlands Wind Energy Association), and<br />

Allard Castelein, CEO of the Port of Rotterdam. Rameau: “We are<br />

currently building large-scale wind turbines, and also solar panels,<br />

without asking if there’s a demand for this electricity by the<br />

industry, households or the transport sector. This has to change.”<br />

Coastal areas<br />

According to Rameau, it is also important that the electricity<br />

generated offshore is directly transported to the large industries in<br />

the coastal areas. In his view, this will prevent billions of euros in<br />

investments in new high-voltage lines and onshore grid upgrades.<br />

With Tata Steel in IJmuiden, but also with the large petrochemical<br />

and process industry in the ports of Rotterdam, Amsterdam,<br />

Vlissingen/Terneuzen and Eemshaven, the Netherlands has an<br />

excellent position.<br />

Timmers (NWEA) also believes that the national industry is<br />

essential for the success - or failure - of offshore wind energy. “If<br />

there’s no demand from the industry, then there’s no business<br />

case.” Timmers does not foresee any problems with the first 10.6<br />

gigawatts of wind farms at the North Sea. However, the situation<br />

will be different at around 60 to 75 GW in the year 2050. The<br />

‘Planbureau voor de Leefomgeving’ (Netherlands Environmental<br />

Assessment Agency) has calculated this is most likely the<br />

maximum capacity of the Dutch Exclusive Economic Zone.<br />

Timmers: “That’s about 20 to 25 percent of the total area. At that<br />

stage, we have to think very carefully about what the infrastructure<br />

at sea should look like, how we are going to get all that electricity<br />

on land and what is going to happen with it.”<br />

Although the Netherlands is currently almost at the bottom of the<br />

European Union with only 7.28% renewable energy, according to<br />

the chairman of the NWEA, we are making up for lost ground in<br />

the field of offshore wind energy. “In 2030, The Netherlands will<br />

be the third country in the North Sea with a capacity of 10.6 GW,<br />

after Great Britain (30 GW) and Germany (15 GW). In addition,<br />

we have a strong supply industry that is involved in three quarters<br />

of all European wind farms.” Timmers mentions TenneT, SIF<br />

Offshore Foundations, Huisman, Royal IHC, Boskalis, Van Oord<br />

and Seaway Heavy Lifting as fine examples.<br />

Opportunities for Rotterdam<br />

Allard Castelein of the Port of Rotterdam also sees offshore wind<br />

energy as an important tool to become an energy-neutral port in<br />

2050. “We have 200 MW of wind turbines in the port area and<br />

can still grow to around 300 MW, but unfortunately there is no<br />

more space in our port. That is why we are looking at the North<br />

Sea with extra interest. This must become our new national energy<br />

province.”<br />

According to Castelein, offshore wind can largely take care of the<br />

electrification and sustainability of Rotterdam’s industry. “In the<br />

future, the petrochemical and process industry will not only need<br />

large amounts of sustainable electricity, but also large amounts of<br />

heat of about 1400 degrees Celsius. Offshore wind farms are<br />

extremely suitable for converting this electricity into hydrogen via<br />

electrolysis, as source for this heat.”<br />

Castelein is convinced that the port of Rotterdam can benefit<br />

greatly from offshore wind energy. “Ten thousand jobs will be<br />

created in 2<strong>02</strong>0, and ten years later it will be doubled. We must<br />

not miss this opportunity!”<br />

<strong>02</strong>-<strong>2019</strong> | 15


Grid Connection<br />

Nadine Huiskes<br />

Challenging site investigations for Hollandse Kust Zuid 1 & 2<br />

Storms, sea mines<br />

and dunes<br />

Even though there is not so much to see, the preparatory works for the Hollandse<br />

Kust Zuid 1 & 2 wind farm - the first subsidy-free Dutch wind farm - is in full swing.<br />

In the coming years, Vattenfall will build a wind farm off the coast of The Hague and<br />

Noordwijk that can supply 1 to 1.5 million households with renewable energy.<br />

Until summer, many researchers work day and night<br />

offshore to find out as much as possible about the location<br />

of the wind farm. Using high-tech equipment,<br />

they scan underwater for bombs and shipwrecks and<br />

map the seabed. During this process they are faced with various<br />

challenges.<br />

The work started in February, but soon storms Freya and Gareth<br />

disrupted the works. The two research vessels, with a total of thirty<br />

crew members, were forced to take shelter in the Scheveningen<br />

harbor. “Of course it’s very frustrating to have such bad weather<br />

right from the start, but there’s not much you can do about it,”<br />

says Daniel Jenkins, project manager at Bibby HydroMap, the<br />

company that carries out the geophysical surveys. “The vessels are<br />

built for worse weather conditions, but the equipment is very sensitive.<br />

We know that if we collect data during bad weather, it will<br />

be of poor quality. That is simply not an option.”<br />

According to Aidan Marchand, who oversees the technical implementation<br />

of the project from Vattenfall, it was already known upfront<br />

that the North Sea does not always offer the best (weather)<br />

conditions for site investigations. “That is why our original planning<br />

already includes a number of weeks in which we cannot collect<br />

data.” Due to the turbulent weather, the research vessels have<br />

to make the most of the calm periods in order to catch up. Jenkins:<br />

“The crew collects data 24 hours a day, thus also at night. In this<br />

way, we make optimal use of the favorable weather windows.”<br />

The mobile sand dunes at the<br />

bottom of the sea make the construction<br />

of the wind farm<br />

complex<br />

Every ten days, research vessels Bibby Athena and Bibby Tethra<br />

arrive at the port of Scheveningen to take in supplies or to change<br />

crew members.<br />

Sonar and Soil samples<br />

The seabed is examined until August, using scanning equipment<br />

that does not disturb the environment. This research is followed by<br />

the collection of soil samples. In addition to the geophysical surveys<br />

by Bibby HydroMap, Fugro conducts the geotechnical surveys.<br />

Marchand explains the difference: “The geophysical research<br />

mainly uses scan sensors that are towed in the water behind the<br />

vessels. This results in an image of the seabed and the objects that<br />

are located there. This is important for the next step: the geotechnical<br />

studies, in which Fugro drills into the seabed and takes samples<br />

to determine the composition and strength of the seabed.”<br />

The results are used to design the most efficient foundations as<br />

well as the cable routing for the wind farm.<br />

From mine to plain bomb<br />

The North Sea contains many traces of history. Explosives can be<br />

found in many shapes and sizes. During both World War I and II,<br />

countless sea mines were dropped; less than a quarter of these<br />

were cleared afterwards. Hollandse Kust Zuid is located just north<br />

of the most important flying route of the Allied Forces. Planes often<br />

crashed into the sea or dropped their bombs too early. In addition,<br />

fighting took place offshore, often between Allied aircraft and<br />

German war vessels. It was not uncommon for torpedoes, bombs,<br />

missiles and cannons to miss their target and end up on the seabed.<br />

Ships that were hit sank. In later times, these unexploded<br />

ordnances (UXO) regularly ended up in fishing nets, after which<br />

they were thrown overboard again. This often happened in the<br />

proximity of well-known shipwrecks, which fishermen avoided<br />

anyway.<br />

“It is relatively easy to identify shipwrecks,” says Jenkins. “This is<br />

more difficult for UXO. We make a list of objects and their magne-<br />

16 | <strong>02</strong>-<strong>2019</strong>


Bibby Tethra Photo: Vattenfall/Hans-Peter van Velthoven<br />

tic characteristics, size, shape and depth. A specialized agency then<br />

analyzes this data.” The next step is to dismantle explosives.<br />

Marchand: “We share the data with the coastguard, who calls in<br />

the Royal Dutch Navy to clear the UXO.” Many shipwrecks have<br />

already been recorded on navigation maps, but strong currents<br />

may have moved or buried them. Sometimes the help of archaeologists<br />

is called in.<br />

Predicting sand dunes<br />

Mapping wrecks and explosives is just one part of the site investigations.<br />

In order to optimally design the wind farm - specifically<br />

the foundation and cable routes - it is necessary to collect as<br />

much data as possible. Thanks to the relatively shallow water and<br />

sandy seabed, the North Sea is a great location for wind turbines.<br />

There are, however, a number of issues that require attention.<br />

“The mobile sand dunes at the bottom of the sea make the construction<br />

of the wind farm complex,” says Marchand. “In some<br />

places there is a mobile layer of sand of up to four meters thick.<br />

These sand dunes are moving, which can lead to problems in the<br />

future. Not so much for the foundations, they can withstand a<br />

changing seabed. But cables are usually buried one to three meters<br />

deep under the seabed and we don’t want them to be exposed.”<br />

The solution lies in the predictive power of high-tech models.<br />

“These can predict the behavior of the sand dunes on the<br />

longer term, which allows us to make the best possible design for<br />

the cable routes.”<br />

Avoiding sand dunes<br />

Jenkins points out that the sand dunes pose another challenge: the<br />

equipment can strike a sandbank, which can lead to gaps in the<br />

data collection. “The vessels sail at around nine kilometers per<br />

hour. If a large sandbank suddenly appears, that is a risk for the<br />

equipment, which is often towed in the water a few hundred meters<br />

behind the vessel. We want to keep the sonar as close as possible<br />

to the seabed. And at the same level, so that the data collection<br />

is constant. We have a Remotely Operated Towed Vehicle (ROTV)<br />

on board that scans the seabed and automatically intervenes in<br />

case of a sand dune. But on some occasions this does not work<br />

so well, which means you have to adjust the equipment manually.<br />

We need to keep an eye on this at all times.”<br />

This attention also applies to the high waves that are also very<br />

characteristic for the North Sea. Research vessels Bibby Athena<br />

and Bibby Tethra sometimes have to deviate considerably from<br />

the planned sailing direction to ensure that the equipment under<br />

water follows the intended path.<br />

High-tech equipment<br />

With less than thirty meter in length, the vessels are maneuverable<br />

and built for researching large areas. Thanks to the Small<br />

Waterplane Area Twin Hull (SWATH) design, visible in the<br />

characteristic hull of Bibby Athena and Bibby Tethra, they can<br />

easily sail the turbulent sea. The vessels are also equipped with a<br />

so called ‘A-frame’ that deploys the equipment, with a platform<br />

specifically designed to recover equipment and with an impressive<br />

collection of other high-tech research equipment. The collection<br />

and storage of data is done securely thanks to cameras on deck,<br />

cooled and soundproof units in which the data is stored, and<br />

emergency power supply. On board there is room for sixteen people,<br />

who can use modern conveniences such as air conditioning<br />

and satellite TV. Every ten days the vessels arrive at the port of<br />

Scheveningen to take in supplies or to change crew members.<br />

eyes and ears on board<br />

<strong>02</strong>-<strong>2019</strong> | 17


VATTENFALL/HANS-PETER VAN VELTHOVEN<br />

Hollandse Kust Zuid is located<br />

just north of the most important<br />

flying route of the Allied Forces<br />

A Vattenfall representative is also present on the vessels. “We are<br />

Vattenfall’s eyes and ears,” says Tom Gray from East Point Geo, a<br />

consultancy firm for onshore and offshore geo projects. Based on<br />

their expertise, the representatives can properly assess the ongoing<br />

site investigations. Gray points out that the works are not only<br />

technically very complex, but are also carried out in a high-risk environment.<br />

“The representatives ensure that all procedures are<br />

carried out safely and correctly. In addition, it is a working environment<br />

where the crew and research teams operate under considerable<br />

pressure. We therefore also keep an eye on for example<br />

stress levels.”<br />

When Bibby Athena and Bibby Tethra are in the harbor due to<br />

bad weather, the representatives of East Point Geo ensure that<br />

vessels and equipment are maintained and that the crew remains<br />

ready to sail when the weather changes. “It is important that the<br />

research equipment on both vessels is calibrated equally so that<br />

data is collected in the same way,” Gray explains. “The crew is<br />

subdivided into a crew that maintains the vessels and a crew that<br />

maintains the research equipment,” adds Jenkins. “When the vessels<br />

are in the port of Scheveningen, everyone stays on board.<br />

Together they ensure that the moral remains high and that the<br />

equipment stays ready for use.”<br />

Design process<br />

Until the end of <strong>2019</strong>, Bibby HydroMap and Fugro will analyze,<br />

test and interpret the collected data. This is essential input for designing<br />

the cabling, foundations and wind turbines. The engineers<br />

must take many aspects into account. Marchand: “The technology<br />

for offshore wind is developing very fast. The wind turbines that<br />

will be installed in 2<strong>02</strong>2 will be different from the ones being produced<br />

now. With our international experience in wind energy, we<br />

can properly assess these developments and ensure that the infrastructure<br />

is flexible and therefore suitable for newer technologies.”<br />

The engineers also take environmental issues into account. By<br />

doing so, they aim to preserve the local ecology as much as possible,<br />

both during construction as well as during operations of the<br />

wind farm.<br />

Ambitions<br />

At the end of 2<strong>02</strong>2, Hollandse Kust Zuid 1 & 2 will produce its<br />

first renewable energy. This is an important step for Vattenfall in<br />

realizing its ambition for the future: enabling fossil-free living<br />

within one generation. With a capacity of around 760 megawatts,<br />

the wind farm also makes a significant contribution to the Dutch<br />

ambition to have 4,500 megawatts of installed capacity at sea in<br />

2<strong>02</strong>3. Until then, the strong wind that makes the North Sea so<br />

ideal for generating wind energy is an unpredictable factor for the<br />

research teams at sea.<br />

18 | <strong>02</strong>-<strong>2019</strong>


EPCI Platform and Module Fabricators<br />

112507<br />

• Platforms<br />

• Jackets<br />

• Compression Modules<br />

• Reception Modules<br />

• Living Quarters<br />

• Process Modules<br />

• Offshore High Voltage Substations<br />

HSM Offshore BV | Westfrankelandsedijk 9, 3115 HG Schiedam NL | T +31 (0)10 - 427 92 00 | E sales@hsm.nl | I www.hsmoffshore.com


Interview<br />

Sabine Lankhorst<br />

Hans Schwirtz & Mario Loi of Prysmian<br />

Stepping up to serve<br />

the future grid<br />

Future grid capacity is currently a hot topic in the Netherlands. With the wind<br />

projects becoming larger, especially at sea, what are the requirements in terms<br />

of cable designs?<br />

Wind Energy Magazine spoke to Mario Loi and<br />

Hans Schwirtz at the Delft production facility and<br />

head office for the Nordics of international energy<br />

and telecom cable and system provider Prysmian.<br />

Hans Schwirtz, Commercial Manager Projects of Prysmian<br />

PowerLink S.r.l., is responsible for the company’s subsea activities<br />

in the Nordics. “After the telecom boom, following the<br />

introduction of the internet, we now see a huge hype in power,<br />

both onshore and offshore, in interconnecting countries,<br />

connecting wind farms but also in optimising the grid”, he tells.<br />

While the Netherlands is moving away from gas towards a more<br />

electricity-based energy system, with large influx from renewable<br />

energy in the future, this will have a big impact on the current<br />

national distribution network, for both the national Transmission<br />

System Operator and distribution network operators.<br />

Mario Loi, as Business Manager Utilities Netherlands responsible<br />

for the onshore market, explains: “There are already difficulties in<br />

keeping up with the current renewable energy influx, especially<br />

with solar energy.” We are currently working on several highvoltage<br />

networks to keep up but it seems that already in the near<br />

future this won't be enough, he stresses. All parties involved are<br />

still debating on this topic.<br />

“Nobody wants wind farms in their backyard but they neither<br />

want these huge high-voltage pylons. Something has to happen.”<br />

Prysmian is taking this very serious, he stresses, regular meetings<br />

have been set up with all parties involved to discuss this topic.<br />

When you step up to 220 kV, the<br />

present cable designs need a<br />

fundamental change<br />

"Where are we headed in the electricity market, what is the desired<br />

capacity and how does this affect our company? Should we and<br />

when do we adapt our production process is one continuous<br />

question we ask ourselves."<br />

Bigger and longer<br />

One thing is sure, cables will become bigger in size and capacity<br />

and larger. For one, clients opt for cables with better efficiency.<br />

This generally means cables will be larger in diameter. Another<br />

reason is the growth in wind turbine size. Schwirtz elaborates: “20<br />

years ago, we talked about kilowatts and now we are talking about<br />

megawatts. Old turbines are being replaced by modern, more<br />

powerful turbines. As voltages and currents increase, these require<br />

higher transmission powers. This has an impact on the size of<br />

cables and the installation components.” Offshore, he sees not only<br />

an increase in turbine size but also in wind farm size and wind<br />

farms being built further offshore. “We are now already building<br />

700 MW wind farms. After 2<strong>02</strong>5 we will see 2 to 4 GW wind sites.<br />

These are no longer wind farms but proper power plants!”<br />

With regards to the inter-array cables, 66 kV cables are becoming<br />

the standard. “The 33 kV inter-array cables will still be used for<br />

smaller wind farms or nearshore, such as Fryslân Wind Farm. The<br />

turbines in the range of 9.5 to 12 MW that are currently being<br />

developed already require 66 kV cables. Those in the range of 15<br />

to 20 MW will even need 132 kV cables. We are already designing<br />

these.” After that, he warns, it will become a challenge. When you<br />

step up to 220 kV, the present cable designs need a fundamental<br />

change. Because of the continuous force on the cables, caused by<br />

the movement of the wind turbines, the cables need to be light and<br />

very flexible. Lead sheaths or aluminium sheaths cannot stand<br />

much movement although they are still the best solutions to keep<br />

the cable dry. The company is already talking to a number of<br />

parties in the offshore wind to look into this. Also, the bigger the<br />

offshore turbines, the bigger the distance required between the<br />

turbines. This means longer inter-array cables are needed.<br />

20 | <strong>02</strong>-<strong>2019</strong>


66 kV subsea cable<br />

for offshore wind<br />

Schwirtz sees examples of wind farms where they require interarray<br />

cables of 15 km.<br />

The size and the far away location also affects the length and size<br />

of export cables. Schwirtz: “We already produce export cables with<br />

a diameter of 30 cm that weigh around 170 kilos per metre. That’s<br />

almost a redoubling from the first 33 kV cables used at one of the<br />

early Dutch offshore wind farms.” The current standard is 220 kV<br />

AC but the market is moving towards 275 kV AC and 320 to 500<br />

kV DC. AC cables loose efficiency on longer distances. DC cables<br />

are cheaper but require expensive converters. However, these pay<br />

themselves back with each kilometre of cable. There is a grey area<br />

around 700 MW and 70 km in which, on a project-by-project<br />

base, the optimum AC-DC solution has to be evaluated, he<br />

explains. As to the capacity of the export cables, Prysmian recently<br />

showed with the contract for the 600 kV Western HVDC link,<br />

connecting the Scottish and the English/Wales power grids, that it<br />

is able to provide high capacity cables.<br />

Onshore, Loi also sees an increase in size and length of the cables.<br />

“Take Fryslân Wind Farm, we are talking about one complete<br />

connection of at least 55 km! This has an impact on the grid but<br />

also on the permitting process.” The latter, he explains, is much<br />

more complicated than offshore as it involves many more players,<br />

both governmental and private, especially if a cable route is<br />

intersecting multiple municipality borders. In the case of Fryslân<br />

Wind Farm, the situation is even more complicated as a large<br />

section of the cable will be installed in the Afsluitdijk, at the same<br />

time as the Ministry of Waterways and Public Works is working on<br />

a dike reinforcement project. He also sees a shift towards the use<br />

of DC connections. When DC is used for connecting offshore<br />

wind farms to the land station it means that parts of the onshore<br />

track will also consist of DC cables. Due to the high capacity, less<br />

cables (2 instead of 3), and thus less space, are required.<br />

Growing focus on sustainability<br />

Sustainability is a focus area for Prysmian. Until 30, 40 years ago,<br />

Prysmian still produced paper insulated, lead covered (PILC)<br />

<strong>02</strong>-<strong>2019</strong> | 21


cables. However, pressure was placed on the cable manufacturers<br />

to look into more cleaner solutions. This lead to the introduction<br />

of XLPE (crosslinked polyethylene) and EPR (ethylene propylene<br />

rubber) cables. These materials are not easy to recycle though.<br />

Around ten years ago, Prysmian developed their P-Laser<br />

insulation material. P-Laser is an eco-friendly cable, manufactured<br />

using thermoplastic materials. Its production process utilises ‘zerogas’<br />

technology, reducing CO2 emissions. It is also capable to<br />

perform at higher temperatures, allowing for higher voltages.<br />

Prysmian currently only produces P-Laser cables for onshore use<br />

but is already in the process of developing them for subsea use<br />

also.<br />

“We were pioneers in this field. Unfortunately the use of<br />

sustainable materials currently only takes up around a small<br />

percentage of our market”, Loi says, “in fact, European tender<br />

regulations even prevented us back then to include the product in<br />

a tender on grounds of preventing a level playing field!”<br />

Nowadays, as the interest and sense of necessity for sustainable<br />

solutions is growing amongst clients, there is more competition in<br />

the market. For most clients, however, cost is still a deciding<br />

factor.<br />

QA, monitoring and prediction<br />

Schwirtz: “Cables are a critical product. They take up a relatively<br />

small percentage of the total value of a wind farm but if they are<br />

not functioning, there is no revenue. This becomes even more so<br />

important with subsidy-free wind farms.” Extreme QA is applied<br />

to the cable production, especially to subsea cables. “Half of the<br />

time is spent on testing. With each new production step the entire<br />

cable is tested again”, he adds. Prysmian has test labs in the UK,<br />

Italy and the Netherlands. The company also decided to invest in<br />

their own mobile diagnostic and testing facilities from the Delft<br />

facility. With mobile road-transportable equipment, high voltage<br />

cables can be tested under extreme voltages. It is currently the<br />

only mobile diagnostic and testing facility where very long export<br />

cables can be tested before being put into operation. The export<br />

cable for the Gemini offshore wind farm was tested for this reason,<br />

even though Prysmian did not provide the cable itself.<br />

However, he explains, an offshore cable generally does not get<br />

damaged because of production errors but due to external<br />

elements; by trawling and sometimes by errors made during<br />

installation. Most of the time, a cable breaks down when it is<br />

operating at its highest capacity, when there are strong winds. This<br />

is also the worst weather situation to pick up the broken cable,<br />

repair it and install it again. It also depends on the availability of<br />

the required equipment at that time. “When an onshore cable is<br />

damaged it will take between 2 to 7 days to repair the cable.<br />

Offshore, this could take a few months.”<br />

It is for this reason that monitoring of subsea cables is extremely<br />

important. The quality of a cable can be determined by measuring<br />

the temperature. This is done by making use of the optical fibres,<br />

sending a thin light-pulse and wait for the reflection. Schwirtz:<br />

“We can measure the temperature and location with a precision of<br />

up to a few metres. By correlating current and temperature, we<br />

can see if a cable is heating up disproportionally or is not heating<br />

up as expected. These situations can be caused by a cable part that<br />

was buried too deep or a cable being exposed. Both scenarios can<br />

put a cable at a risk.” This method is now also used for inter-array<br />

cables.<br />

The most important indicator of the quality of the cable, however,<br />

is the insulation. Prysmian has developed its own system based on<br />

partial discharge sensoring. Schwirtz: “Damage on the insulation<br />

leads to small electrostatic discharge. We can, say with some<br />

restrictions, measure these discharges. By integrating this add-on<br />

system with temperature measurement we can not only determine<br />

the actual quality of a cable but also predict future quality. This<br />

way we can plan repair activities at a more convenient time, for<br />

example during planned maintenance activities, better weather<br />

windows, or when the required equipment is available. This leads<br />

to better cost-efficiency.”<br />

Future outlook Prysmian<br />

In the offshore wind market the two Prysmian men see a trend<br />

towards project developers using less contracts. Schwirtz<br />

elaborates: “For the UK Gwynt y Môr offshore wind project, our<br />

client managed around 120 contracts. For the Westermeerwind<br />

Wind Farm, only one contractor was assigned for the complete<br />

wind farm installation.” Prysmian can perform both supply only,<br />

as is the case for Borssele 3 & 4, or turn-key projects, as required<br />

in for instance TenneT’s tenders for the 220 kV offshore<br />

connections. Playing a different role can at times create tension.<br />

Schwirtz: “Sometimes you are a supplier and sometimes a<br />

competitor. You have to carefully consider each project because<br />

there can easily be a conflict of interest.” Fortunately he sees the<br />

market becoming more mature.<br />

Even though the power market is booming, it does not mean it<br />

necessarily is a growth market. Schwirtz: “Due to cables becoming<br />

more efficient, the cable market itself in general is not growing<br />

substantially, not in volume nor profit. We use less cables and<br />

therefore need less volume per megawatt. To survive in this<br />

market, it is necessary to scale up your business. Prysmian’s<br />

strategy is to acquire other healthy cable companies that<br />

complement our existing activities. With the acquisition of Draka<br />

and General Cables we showed that we have been able to do so<br />

successfully.”<br />

When an onshore cable is<br />

damaged it will take between 2 to 7<br />

days to repair the cable. Offshore,<br />

this could take a few months<br />

22 | <strong>02</strong>-<strong>2019</strong>


Prysmian Group<br />

Prysmian Group is active in both the<br />

onshore and offshore wind markets.<br />

The company provides all the required<br />

cables for the wind industry, low, mid<br />

and high voltage cables, inter<br />

connectors, optical fibres and -cables,<br />

auxiliary equipment, testing and<br />

monitoring and maintenance. On land,<br />

Prysmian doesn’t perform the civil<br />

work itself but works with external<br />

partners. Offshore, it is able to supply<br />

cables or deliver turn-key projects.<br />

There is a strong focus on large interconnection<br />

projects and to a lesser<br />

extent the inter-array installation.<br />

At the Delft facility, originally the head<br />

office of Nederlandse Kabelfabriek, all<br />

land cables for the Dutch market are<br />

produced. Although Prysmian is<br />

specialist in large cable drums, due to<br />

limited storage space and no proper<br />

access for the large cable laying<br />

vessels, the production of subsea<br />

cables is taking place outside the<br />

Netherlands; in Finland, Germany,<br />

Norway and Italy. The company owns<br />

3 cable laying vessels; Ulisse, Giulio<br />

Verne and Cable Enterprise. All with a<br />

minimum load capacity of 7,000<br />

tonnes and the Giullio Verne with<br />

capability to install at water depths of<br />

up to 3,000 metres. A fourth one is on<br />

its way.<br />

Cable laying vessel Cable Enterprise<br />

5,000mt carousel in Drammen loaded with cables for an offshore wind farm<br />

<strong>02</strong>-<strong>2019</strong> | 23


Interview<br />

Sabine Lankhorst<br />

Jaco Lemmerzaal, Managing Director of HSM Offshore<br />

The beating heart<br />

of a wind farm<br />

In 20<strong>02</strong>, HSM Offshore built the offshore substation for the first offshore wind<br />

farm, the Danish Horns Rev A. Almost 17 years and several wind farm<br />

generations later, the Dutch manufacturing company is still building offshore<br />

platforms for the wind energy industry.<br />

The latest being the Borssele Alpha and Beta platforms.<br />

Wind Energy Magazine spoke to Jaco Lemmerzaal at<br />

HSM Offshore in Schiedam.<br />

You won the contracts for both the Borssele Alpha and<br />

Beta substations, how are the activities developing?<br />

The contract for the Offshore High Voltage Substations include<br />

the jackets and the topsides. At the moment, we just completed<br />

the topside of Borssele Alpha. We signed the contract for this 700<br />

MW offshore platform in March 2017. In the Summer of 2018 we<br />

already installed the jacket. We are now waiting for the right<br />

weather window to transport it to the site. The installation is<br />

contracted to Seaway 7. Once the topside is installed, it will take a<br />

few months to organise and connect everything. The whole<br />

platform should be operational by the end of August.<br />

You also made a start on the construction of the Borssele<br />

Beta platform. Are there any differences to mention?<br />

We have also just completed the jacket for Borssele Beta. Like with<br />

the Borssele Alpha topside, we are currently waiting for it to be<br />

transported. We now continue focusing on the construction of the<br />

topside for Borssele Beta which is planned to be installed spring<br />

2<strong>02</strong>0. Borssele Alpha and Beta are the first platforms to be built<br />

following TenneT’s standardised offshore connection design. The<br />

hearts of the platforms are the same but the full design is adapted<br />

to the site specific requirements such as water depth. Alpha is a<br />

pilot, so most work went into this platform. Due to the time<br />

At the peak of construction<br />

activities there are over 400<br />

persons involved<br />

pressure, we had to start the construction while we were still<br />

optimising the design. There are, of course, always some lessons<br />

learned when you build a first platform but nothing major in this<br />

case. For example, for Borssele Beta, we researched how we could<br />

make the construction process for the jacket more efficient. We<br />

didn’t change anything in the jacket design itself but we did<br />

change the construction method.<br />

What are the main challenges in building an offshore<br />

platform?<br />

TenneT holds the responsibility to ensure that an offshore<br />

platform is operational at all times in order to guarantee a<br />

continuous electricity supply to its clients, the energy companies.<br />

Therefore, the platform needs a high availability. Great care and<br />

attention is paid to this, both in the design and during the<br />

construction of the platform, to prevent future failure of the<br />

systems. All this requires a well thought design and a properly<br />

organised coordination. At the peak of construction activities there<br />

are over 400 persons involved. These are our own people and<br />

temporary contracted personnel like welders and fitters. We have<br />

also subcontracted several activities, including electrical and<br />

instrumentation, piping and HVAC. And then you have the<br />

representatives from TenneT and our vendors and the inspection<br />

people. You can imagine the coordination it requires to ensure that<br />

everything is working smoothly!<br />

Will the other OHVS’ also work with the same design?<br />

Tennet has become the owner of the design. This design was<br />

included in new tender packages and was used as the basic design<br />

for the next platforms. The builders of these platforms will<br />

probably add their own design elements and remain responsible<br />

for the total design, as EPCI Contractor. For example, for the<br />

Borssele Alpha and Beta platforms we introduced our own HVAC<br />

design to prevent overheating of the system which may lead to a<br />

system break down. The builders of the next platforms might have<br />

a different view on this.<br />

24 | <strong>02</strong>-<strong>2019</strong>


u Borssele Alpha & Beta<br />

Dimensions<br />

Topside: 58 x 32 x 26 m<br />

Jacket Alpha: 50 x 28 x 55 m<br />

Jacket Beta: 50 x 28 x 57.5 m<br />

Piles: 61 m each<br />

Weight<br />

Topside: 3,700 t<br />

Jacket: 2,900 t (including<br />

cable deck and J-tubes)<br />

Piles: 1,400 t<br />

Capacity<br />

Total power: 700 MW<br />

(2 x 350 MW)<br />

Intake: 66 kV<br />

Export: 220 kV<br />

Jacket Borssele Alpha installed<br />

<strong>02</strong>-<strong>2019</strong> | 25


Load-out topside Borssele Alpha at HSM Yard, Schiedam. Photo: Robert Nagelkerke<br />

How have offshore platforms developed over time?<br />

Our first offshore platform for offshore wind, the Horns Rev<br />

Alpha, looked completely different! At that time, our client did not<br />

have any offshore experience yet and thought a simple case of<br />

‘copy - paste’ of their onshore experience would suffice. So instead<br />

of installing a topside on a jacket foundation, like we are doing<br />

right now, we had to pile the platform on location in a frame.<br />

When we were awarded the contract for Horns Rev B and later C,<br />

it was already a different situation. And it doesn’t stop, offshore<br />

turbines are getting bigger and more powerful, wind farms are<br />

getting larger, and so will the offshore substations. Our challenge is<br />

to build platforms in a most efficient manner and at the same time<br />

in a cost-effective way. But also, how can we install the platforms as<br />

economically as possible? Perhaps the use of suction buckets instead<br />

of piling could become more of an option. The engineers will also<br />

be challenged in designing a large platform that is not too heavy.<br />

What you also see is a new way of looking at the accessibility and<br />

maintenance of platforms. Modern platforms need to be lowmaintenance<br />

and in principle unmanned. Borssele Alpha and Beta<br />

will not have a helideck. A helideck might look simple. However,<br />

there’s a lot to take into consideration with regards to safety<br />

requirements, fire protection, navigation, etcetera. By means of<br />

state-of-the-art technology, the platform can be monitored from a<br />

land-based office. Even though we do not design own products,<br />

we do keep an eye on the market in order to be able to offer stateof-the-art<br />

platforms to our clients.<br />

Borssele Alpha and Beta are only the first of a<br />

standardised offshore grid connection introduced<br />

by TenneT. Would it not have made sense<br />

to have one party build all platforms?<br />

In total, there are 8 standardised platforms to be built. TenneT<br />

decided to split the purchase of the platforms in 4 phases.<br />

We won the contracts for the two first standardised platforms.<br />

Unfortunately we did not win the next two, those for Hollandse<br />

Kust Zuid 1 & 2. These contracts were awarded to Petrofac Norge<br />

BV. The platforms will be built in Dubai. The contracts for the<br />

next three platforms (Hollandse Kust Noord and West) are now<br />

being tendered. For these substations we know that we are<br />

confronted with global competition, including India and China.<br />

TenneT is a state-owned company, therefore it has to comply with<br />

European tender policies. To be honest, this can be quite frustrating<br />

to us at times. In the Netherlands, our Government advocates an<br />

open market and therefore also an open economic policy. This<br />

means that contracts are put out to tender internationally. Let me<br />

be clear, we do not mind competition but there should be a level<br />

playing field. Here we are, a country with an open market yet<br />

surrounded by countries that apply protectionism as their economic<br />

policy. Take for example France, this country is developing a large<br />

domestic market for offshore wind. For a company outside of<br />

France it is practically impossible to compete on this market. The<br />

UK also applies a certain level of protectionism. Here, you must<br />

meet high requirements in the area of local content. This could be<br />

up to 60% of the work. In general, the more South you go, the more<br />

difficult it becomes to get foothold on a market.<br />

In addition, as our market is open to international businesses, we<br />

have to compete in our own market against offers from companies<br />

based in low-wage countries such as the aforementioned Dubai,<br />

India and China. It is not so much that we are competing for<br />

component costs. What makes their offering more attractive is the<br />

low labour cost. We would be happy to have the same people<br />

working here in The Netherlands for a comparable wage. With the<br />

living conditions here, they would probably even prefer to work<br />

here. However, this is not possible because in the Netherlands, all<br />

wages need to be in line with the market to protect our national<br />

26 | <strong>02</strong>-<strong>2019</strong>


Installation jacket Borssele Alpha, photo: Izak van Maldegem<br />

workers and provide equal opportunities. There is a paradox here.<br />

We are visited on a regular base by representatives of the<br />

Government and TenneT, praising us for the work we do here.<br />

They are proud of this piece of local economy and national<br />

strength. We do our best to participate in everything, from providing<br />

guest lectures, offering apprenticeships, etcetera. However,<br />

that same Government that is concerned about protecting our<br />

national workforce is happy to outsource a contract to low wage<br />

countries which means a lost opportunity for more jobs.<br />

Do you think we will see a more protectionist approach<br />

being introduced by the Dutch Government in the near<br />

future?<br />

We have been lobbying for some time now to achieve a situation<br />

where a level playing field is achieved but it is difficult. Over time,<br />

our ‘partners in crime’ Heerema Zwijndrecht and Hollandia<br />

Offshore have pulled back from the offshore wind market so we<br />

are fighting this battle almost alone now.<br />

Do the low wages make up for the fact that there are cost<br />

involved having to transport the platform from across the<br />

world back to the Netherlands?<br />

At first glance they do. Prices from companies in de Middle or fast<br />

East are competitive because the wage component, and we<br />

Everyone thinks wind is<br />

booming but the energy demand<br />

for oil and gas in particular is<br />

still growing<br />

estimate this on approximately half of the total costs, is much<br />

lower. In China, the wages are almost a tenth of what we are<br />

paying. It is clear that this is very attractive indeed. However, if<br />

you look at the carbon footprint of building a platform on the<br />

other side of the world it is starting to make less sense. Besides the<br />

obvious factor, the transportation of the completed platform, there<br />

is also the transportation of a lot of equipment and parts that are<br />

produced here in the Netherlands or Europe which have to be sent<br />

to China or Dubai. In addition, numerous flights back and<br />

forward are necessary to perform the necessary inspections.<br />

Where do you see HSM Offshore going in the next years?<br />

We have always focused on several markets, being civil<br />

construction for HSM Steel Structures, such as the construction<br />

of bridges, the traditional offshore OiI & Gas sector as well as the<br />

offshore wind sector. The past years, wind has been one of our<br />

main focus areas and when we look at the national roadmap for<br />

2030 we are confident that we will get our share. We mainly look<br />

at the North Sea, Irish Sea and Baltic Sea. Denmark is going to<br />

invest again in offshore wind. We also participated in a tender for<br />

two offshore platforms in Belgium recently. In this case, the<br />

Belgian Government chose to only tender out this contract to<br />

North Western European companies with fabrication facilities in<br />

the European Union, to keep better control of the process.<br />

Fortunately we see that experience is becoming more valuable<br />

while before, as a company you only needed to show that you were<br />

financially able to perform an activity. We have no ambition to look<br />

outside Europe.<br />

For the future we expect a healthy mix again. Everyone thinks<br />

wind is booming but the energy demand for oil and gas in<br />

particular is still growing. Prices are going up again and new<br />

investments are expected to be made.<br />

<strong>02</strong>-<strong>2019</strong> | 27


Offshore<br />

Wind Farm News<br />

1<br />

© GE<br />

4<br />

© TENNET<br />

1<br />

IJmuiden Ver<br />

TenneT announced it will deploy<br />

two 2 GW direct current<br />

connections for the far offshore<br />

wind project IJmuiden Ver.<br />

These will consist of converter<br />

stations and cables. The cables<br />

have a voltage level of<br />

525 kV. Due to the large capacity<br />

only 2 instead of 6 cables<br />

will be required. The 4 GW<br />

IJmuiden Ver site is located<br />

some 80 km from the coast<br />

and is part of the Roadmap<br />

2<strong>02</strong>4-2030.<br />

2<br />

Fryslân Wind Farm<br />

The first construction activities<br />

have started on the 382.7<br />

MW nearshore wind farm in<br />

the IJsselmeer, to the south of<br />

the Afsluitdijk. In total, 14 cable<br />

pipes, with a total length of<br />

around 4.2 km were installed<br />

at Breezanddijk. By the end of<br />

2<strong>02</strong>0, the infield cables will be<br />

pulled through here.<br />

Zuiderzeewind, a consortium<br />

consisting of Van Oord and<br />

Siemens Gamesa Renewable<br />

Energy, is responsible for the<br />

construction of the wind farm.<br />

It will comprise 89 SWT-<br />

DD-130 wind turbines with a<br />

capacity of 4.3 MW and a rotor<br />

diameter of 130 metres each.<br />

The wind farm is intended to<br />

be fully operational by 2<strong>02</strong>1.<br />

3<br />

Hollandse Kust Zuid 1 & 2<br />

Vattenfall has selected<br />

Siemens Gamesa to supply 76<br />

of its 10 MW wind turbine. The<br />

turbine, the SG 10.0-193 DD,<br />

has 94 metre blades and a<br />

rotor diameter of 194 metre.<br />

Seaway 7 is contracted for the<br />

transport and installation of<br />

the monopile foundations and<br />

the laying of the inter-array<br />

cables. The port of IJmuiden<br />

will be used as O&M base. A<br />

new service hub will be constructed<br />

here for this purpose.<br />

Commissioning of the wind<br />

farm is planned for 2<strong>02</strong>3.<br />

Physical preparatory works<br />

have already started. See p.16.<br />

4<br />

Haliade-X 12 MW<br />

Royal HaskoningDHV has<br />

been contracted to design the<br />

foundation for the Haliade-X<br />

12 MW prototype, the world’s<br />

biggest wind turbine. The design<br />

is based on a piled foundation,<br />

with a large concrete<br />

block on top that has a diameter<br />

of 28 metres and thickness<br />

of 4 metres in the centre. GE<br />

Renewable Energy and<br />

FutureWind (a Joint Venture<br />

between Pondera<br />

Development and SIF Holding<br />

Netherlands) will build the<br />

prototype of the 12 MW<br />

offshore turbine at the SIF<br />

premises at the Maasvlakte in<br />

Rotterdam.<br />

5<br />

Borssele 1 & 2<br />

HSM Offshore (see p.24) completed<br />

the topside for TenneT’s<br />

700 MW Borssele Alpha<br />

offshore substation. It will be<br />

installed at the Borssele 1 & 2<br />

site sometime during May. In<br />

April, Boskalis already laid the<br />

first of two 61 kilometre export<br />

cables (from NKT Cables) that<br />

connect the offshore station<br />

with the onshore station in<br />

Borssele. The second is due to<br />

be installed in May. Borssele 1<br />

& 2 is a project by Ørsted. It<br />

will comprise 94 wind turbines<br />

from Siemens Gamesa with<br />

each a power of 8 MW. The<br />

commissioning of the 752 MW<br />

wind farm is scheduled for the<br />

end of 2<strong>02</strong>0.<br />

© ROBERT NAGELKERKE<br />

3<br />

5<br />

© SIEMENS GAMESA<br />

28 | <strong>02</strong>-<strong>2019</strong>


1<br />

2<br />

3<br />

4<br />

5<br />

Read the full news<br />

on www.windenergymagazine.com<br />

(EN) or<br />

www.windenergienieuws.nl<br />

(NL)<br />

<strong>02</strong>-<strong>2019</strong> | 29


Grid Connection<br />

Martijn Bongaerts<br />

The electrical grid in the Netherlands<br />

Solving<br />

the gridlock<br />

On March 13, the Netherlands Environmental<br />

Assessment Agency (PBL) published their<br />

assessment of the Draft Climate Agreement.<br />

Though the PBL has second thoughts as to the<br />

feasibility of the climate goals, distribution network<br />

operators have noticed in practice that the energy<br />

transition is in full swing.<br />

The continuous growth of in particular land based<br />

renewable energy generation makes the effects on the<br />

electrical grid already noticeable during operations. In<br />

January, newspaper headlines gave it a lot of attention:<br />

‘Shortage of power cables impedes transition to green energy.’<br />

‘Electrical grid squeaks and creaks under growth of solar panels.’<br />

And: ‘Energy from solar panels clogs electrical grid.’ Just a few of<br />

the many recent headlines in the media. What is the matter with<br />

the electrical grid in the Netherlands? And what are, if needed, the<br />

solutions?<br />

In the growing economy, the demand for electricity and power increases<br />

fast, especially by industry. Also, there is an acceleration of<br />

the energy transition: in more and more places, renewable energy<br />

is being produced. Onshore wind energy generation is growing<br />

steadily, but recently the growth of solar panels installed on rooftops<br />

and in fields is remarkably fast. This supply of renewable energy<br />

requires extra capacity of the grid.<br />

The last two years, for instance, about € 10 billion has been committed<br />

to subsidies for solar projects, and that has led to solar<br />

parks booming. Especially sparsely populated areas, where the price<br />

of land is low, are interesting for developers of solar fields.<br />

Many solar panels and wind<br />

turbines are installed in areas<br />

with a reduced demand for<br />

electricity<br />

Take for instance the province of Friesland. Distribution network<br />

operator Liander takes into account that in Friesland until the year<br />

2050 about 6,100 MW of solar installations must be fitted into the<br />

grid. To put this into perspective: at the end of 2018 the total installed<br />

solar power was about 300 MW. This means that during the<br />

next thirty years the supply of solar power in Friesland will grow<br />

twentyfold.<br />

The electrical grid (see also Box) was designed a century ago to<br />

transport electricity from fossil power stations, especially those fuelled<br />

by gas and coal, to the customers. It concerned a centralised<br />

system, where most capacity resided ‘up’ in the grid, to transport<br />

the electricity from the power stations. The more one moved towards<br />

the ‘capillaries’ of the grid, the lower the required capacity,<br />

and therewith a smaller diameter of the power cables. Many solar<br />

panels and wind turbines are installed in areas with a reduced demand<br />

for electricity, and where subsequently the grid is rather<br />

30 | <strong>02</strong>-<strong>2019</strong>


Electrical substation. Photo by Liander<br />

‘thin’. However, those wind turbines and solar roofs and fields require<br />

a high capacity, and in general the grid has not been constructed<br />

to deal with that. By investing in new cables and stations,<br />

the electrical grid can be extended, but that will be expensive, will<br />

put strains on the public space and takes time.<br />

Difference between wind turbines and solar<br />

panels<br />

During the last approximately twenty years, quite a lot of wind<br />

turbines have been installed on land in the Netherlands, and generally<br />

connecting them to the electrical grid created no serious problems.<br />

Why are there now problems arising with the current<br />

growth of solar panel installations?<br />

The main difference lies in the length of the trajectory towards a<br />

wind turbine or wind farm and the more central directing that has<br />

been applied here in the past, as described in the so-called structural<br />

vision document Windenergie op Land. Installing a wind turbine<br />

leads to extensive procedures for amongst other things planning<br />

and permits. The procedures can take many years, and this provides<br />

the distribution network operators with sufficient time to make<br />

those investments in the electricity grid that are required for the<br />

transport of wind energy. Thus, the distribution network operators<br />

know in advance where the grid capacity would need extension.<br />

Nowadays, the time required for procedures that lead to the installation<br />

of large solar roofs and fields is substantially shorter. There<br />

are solar parks that are fully operational within a year. When the<br />

grids are inadequate, their upgrading may take a considerable longer<br />

time than the installation of the solar project itself. The current<br />

electrical power of solar installations requires investments in the<br />

high voltage substations that are the responsibility of both the distribution<br />

network operators and TenneT. It takes several years to<br />

expand a station, let alone to build a new station. That could require<br />

easily five years or more. Thus, the time scales of projects on<br />

<strong>02</strong>-<strong>2019</strong> | 31


Sometimes, the distribution<br />

network operator is forced to<br />

put a limit on the transport<br />

volume<br />

the one hand and the adaptation of the grids on the other hand, lie<br />

far apart.<br />

The investments of the distribution network operator are fully paid<br />

(through the tariffs) by the end users. The supervisor requires efficacy<br />

of the distribution network operators, so that upgrades of the<br />

grid will be performed once the investments are justified.<br />

Therefore, an investment will be made (or the upgrading will be<br />

started) once the distribution network operator is certain that the<br />

capacity will be required. Because of the difference in time scales<br />

between realisation of solar parks and expansion of the electrical<br />

grid, the distribution network operator often cannot be informed<br />

in due time of the precise location of the solar park.<br />

Joint planning<br />

Because of the long process times, the high costs and the impacts<br />

on spatial development, an important direction to solve the problems<br />

as sketched above lies in more control and coordination during<br />

the planning of renewable energy generation. By formulating<br />

local energy ambitions and making plans for the numbers and locations<br />

of installations for generating solar and wind energy, the<br />

local municipalities (province, town) should take the required<br />

energy infrastructures in consideration. By incorporating the grids<br />

in the plans right away from the start, procedures may well take<br />

place at an accelerated pace.<br />

If early on the distribution network operator is involved in the<br />

planning, it is possible to quickly gain awareness of possible issues<br />

that may arise as far as the capacity of the grid is concerned and<br />

of what is required to solve those difficulties. Authorities can then<br />

assist to make sure that procedures such as zoning plans, permits<br />

and others issues are handled more quickly. An important tool to<br />

make this joint scheme feasible, are the Regional Energy Strategies<br />

(RES), that are now drawn up in every region of the Netherlands.<br />

By incorporating in these RES’s both the impact and the capacity<br />

of the electricity grids, it is easier to estimate beforehand the possible<br />

expansions of the infrastructure.<br />

u The lay-out of the traditional electrical grid<br />

The electrical system in the Netherlands consists of<br />

three parts: power stations, transmission grid and<br />

distribution grids.<br />

Power stations<br />

In the power stations, electricity is generated. The locations<br />

of the power stations are spread across the country, but<br />

mostly near sea ports (Eemshaven, Borssele, Maasvlakte).<br />

The main power supplying companies in the Netherlands<br />

are, amongst others, Vattenfall, Essent, Electrabel, Intergen,<br />

Delta and E.ON.<br />

Apart from large power stations, there is an increasing<br />

amount of small renewable power sources where electricity<br />

is generated (wind farms, biogas plants, cogeneration, etcetera).<br />

This power is also transported to consumers through<br />

the transmission grid.<br />

What is the transmission grid?<br />

The transmission grid is necessary to transport electricity<br />

from those power plants to the regions where it is used. The<br />

transport of large amounts of electricity requires a high voltage<br />

grid. The 220 kV and 380 kV connections form the<br />

main transmission grid. They serve as the highway for the<br />

transport of electrical power. They are meant for large-scale<br />

transregional transport. The 110 kV and 150 kV grids can be<br />

seen as trunk roads, responsible for the regional distribution<br />

of electricity. Transmission system operator TenneT oversees<br />

the operation of the complete high-voltage grid, from<br />

380 kV to 110 kV, throughout the Netherlands.<br />

What is the distribution net?<br />

Distribution network operators such as Enexis, Liander and<br />

Stedin are responsible for the transport of electricity at voltages<br />

lower than 110 kV. This grid starts at the electrical<br />

substations where high voltage is transformed to medium<br />

voltage. The electrical substations are the shared responsibility<br />

of both the respective regional utility company and<br />

TenneT. The grids at medium and low voltage are the distribution<br />

nets to which end-users, both consumers and industry,<br />

are connected. Before electricity leaves the power point,<br />

the voltage has been reduced to 230 V. That is accomplished<br />

in distribution transformers.<br />

Source: www.randstad380kv-zuidring.nl<br />

Else…<br />

Thus, the distribution network operators are facing a considerable<br />

challenge, an interesting complex puzzle comprised of technology,<br />

uncertainty, costs, distribution of costs, spatial consequences and legislation<br />

and regulations. Unfortunately, the result is that at the moment<br />

a local grid does not always contain on time the desired capacity<br />

to accommodate for the fast growing demand for electricity.<br />

Sometimes, the distribution network operator is forced to put a limit<br />

on the transport volume. In that case, the distribution network<br />

operator is not able to grant all requests for electrical power by major<br />

energy users. New customers will be connected to the grid, but<br />

with a minimal power capacity. Existing customers that require additional<br />

electrical power will have to wait until the expansion of the<br />

grid has been realised. In the concerning region, the limited electrical<br />

power transport has no impact on small consumers, such as residences,<br />

and the power consumption by existing customers.<br />

Innovative solutions<br />

But maybe the large investments and the amount of work in the<br />

grids can be reduced or even prevented by using innovative solutions.<br />

A possible solution is the setting up of a flexibility market.<br />

Liander already implements that in Nijmegen-Noord. This distribution<br />

network operator carefully adjusts there the balance of supply<br />

and demand to prevent both peak loads well as the associated<br />

32 | <strong>02</strong>-<strong>2019</strong>


High Voltage pylon. Photo byTenneT<br />

necessary reinforcement of the grid. For the time being, this seems<br />

to be a temporary solution, as in this flexibility market the distribution<br />

network operators must buy available capacity from customers<br />

in a market that has not yet matured.<br />

Another solution is cable pooling, in which user and producer use<br />

the same cable. In that case, a higher capacity utilisation of existing<br />

grids and connections is achieved that prevents the need for<br />

new grid investments.<br />

Dutch distribution network operators also investigate the occurrence<br />

of situations where when connecting renewable electricity<br />

sources they can relinquish the principle of redundancy.<br />

Redundancy means that there are extra cables and installations in<br />

the electrical grid that make restoring power after an outage easier<br />

and quicker. This also enables maintenance of the grid without leaving<br />

large groups of customers without power. By relinquishing<br />

the redundancy for wind and solar parks, less cables are required.<br />

Easing the redundancy requirement for new, renewable ‘infeeders’,<br />

those can be connected at an earlier stage. This results in a more<br />

efficient use of the available capacity of the electrical grid. To realise<br />

this, it is necessary to put in writing that during outages and<br />

maintenance, these infeeders of renewable energy cannot rely<br />

upon the usual transport service. The current legislation and regulations<br />

makes no distinction between users and producers of<br />

electricity.<br />

Furthermore, it is considered whether distribution network operators<br />

could be allowed to invest in a more anticipatory way, which<br />

means that they take more financial risks when they are allowed to<br />

invest without hundred percent certainty that the grids will be<br />

used. Nowadays, distribution network operators are not allowed to<br />

lay cables under the ground if they are not certain that those cables<br />

will be used.<br />

In short<br />

The energy transition is not just an issue of supply and demand of<br />

energy, because the electrical grid forms a crucial part of it. With<br />

an integrated consideration of the problems and incorporation of<br />

solutions in the plans, many issues that could arise in the future<br />

when connecting renewable generated electricity to the grid may<br />

be prevented.<br />

u This articled was originally published in Dutch in WindNieuws <strong>02</strong>, <strong>2019</strong>.<br />

<strong>02</strong>-<strong>2019</strong> | 33


Interview<br />

Mirjam Tielen<br />

Chris Westra and Ernst van Zuijlen of Offshore Service Facilities<br />

An island at sea,<br />

from dream to<br />

reality?<br />

Chris Westra and Ernst van Zuijlen – two old hands in wind energy – have been<br />

working on their plan for building an island at sea for a long time. The two men of<br />

Offshore Service Facilities are now prepared to unveil their plans.<br />

Often during the interview, the replies go astray or they<br />

both burst out with laughter about all their<br />

experiences. Clearly, they harbour a great enthusiasm<br />

for ‘their’ island.<br />

What does your plan comprise of?<br />

Van Zuijlen: “Basically, it consists of a simple island with room for<br />

one or more substations, where the transformation of electrical<br />

power generated by wind farms at sea to direct current as well as<br />

the transport of the power to mainland is controlled. When that is<br />

just all that you do there, an island with a size of about 50 hectares<br />

or 120 acres is sufficient.”<br />

Westra: “Once you start building such an island, however, it<br />

becomes increasingly interesting if there are additional uses for it.<br />

A hotel for maintenance personnel is a very attractive alternative<br />

to the service operation vessels on which those people now have to<br />

stay. The island can also become a convenient location for coastal<br />

guard operations, to rescue people and vessels, and for yachting it<br />

can be a safe port of call. Maybe we can produce hydrogen gas<br />

there, use it as a base for seaweed farms and the reintroduction of<br />

oyster reefs, or it may even offer the opportunity to build data<br />

centres there…”<br />

Building islands at sea is like<br />

a new kind of Delta Works,<br />

co-operation with partners is<br />

crucial<br />

Van Zuijlen: “Obviously, such things cannot happen just like that –<br />

funds need to be available, and it has to be permittable. We are<br />

talking about a project that could easily be worth a couple of<br />

hundred million euros. But… all those additional options are very<br />

inspiring and a motivation to realise this island.”<br />

Westra: “To some people, it may seem very easy, building an<br />

island, but such an achievement has not been accomplished yet.<br />

To manage that for the first time in the North Sea will probably<br />

be difficult, but we are certain that in the future there will be an<br />

even greater demand for such islands, also for other purposes, and<br />

then such a pilot project is required to obtain the necessary<br />

experience.”<br />

How does your island relate to the floating islands of<br />

MARIN?<br />

Westra: “That project is about experimental, large floating<br />

elements in the ocean. It is a very nice research project, but it will<br />

require much more knowledge before it can be marketed.”<br />

Van Zuijlen: “A real island is much ‘easier’; the Dutch dredging<br />

companies are well capable to build islands. There are existing<br />

examples, for instance in Dubai, though building an island in the<br />

middle of the sea will be quite a different story and that makes our<br />

plan so interesting. For the first array of substations for offshore<br />

wind farms, a solid instead of a floating island is for now a<br />

relatively safe choice.”<br />

When did you start making these plans to build an island<br />

at sea?<br />

Westra: “It started in 2004, the idea came up during the We@Sea<br />

project. With a group of people, we made some first sketches.<br />

Many parties were already enthusiastic; it was called HEDEN,<br />

34 | <strong>02</strong>-<strong>2019</strong>


Chris Westra<br />

Ernst van Zuijlen<br />

‘HavenEiland Duurzame Energie Noordzee’, (Port Island<br />

Renewable Energy North Sea). Former Minister of Economic<br />

Affairs, Maria van der Hoeven, wished to pledge a million euro for<br />

a feasibility study, but with the fall of the Fourth Balkenende<br />

cabinet, that pledge evaporated. Due to the financial crisis,<br />

moreover, the support for the project subsided.”<br />

You have both worked for a very long time in the wind<br />

energy sector. How did that come to be?<br />

Van Zuijlen: “I started in the wind sector as consultant, and then<br />

became project developer, lobbyist, R&D manager and now again<br />

a project developer, but in this case of an infrastructural project.<br />

Until now, I have been more busy with the generation of wind<br />

power, but these days enough people are involved with that. An<br />

island is the next challenge.”<br />

Westra: “For me, it started with the Amsterdam politician Roel<br />

van Duijn, who asked me to build a small wind turbine. I<br />

considered wind energy a democratic form of energy, in fact good<br />

for all and everything. But solar energy made me enthusiastic as<br />

well. I did various solar energy projects in Africa. Furthermore, I<br />

am always ready to take on crazy, new things, and this island is<br />

right in line.”<br />

It seems an exceptional step to want to build an island.<br />

Isn’t that a strange step for you?<br />

Westra: “I think it is a very logical step, because we cannot afford<br />

to lose time with the energy transition, and reduction of costs and<br />

safer working conditions are very important to offshore wind<br />

power generation. Wind energy is also a lot of fun because all the<br />

time new aspects come up. First there was only wind power on<br />

land, then followed offshore wind power with many new aspects to<br />

consider, such as shipping routes, safety, personnel transfer, the<br />

growing number of wind farms. A next logical step is: how to get<br />

there once all those wind farms are built, without repeating the<br />

building platform trick that the oil and gas industry used. How on<br />

Earth are we going to accomplish that with all those offshore wind<br />

turbines?”<br />

Van Zuijlen: “Right from the starting days of the renewable<br />

generation of electricity, everyone said that storage and<br />

controllability would become an issue. In fact, it was obvious that<br />

up to 2<strong>02</strong>0 there would be no problem, but now the time to act<br />

has really arrived. On an island, things can be done about it, for<br />

instance by using wind energy to produce hydrogen gas, or by<br />

connecting offshore wind farms to both the Netherlands and<br />

England. But it is especially ‘the human factor’ that makes an<br />

island at sea important. What spatial organisation of the North Sea<br />

is required when so much wind power must be generated? I find it<br />

hard to imagine that in about twenty years hundreds or thousands<br />

maintenance workers stay for weeks at service operation vessels, a<br />

kind of floating hotel ships. Conditions at sea can be harsh and<br />

then it can be really enjoyable to be able to stand regularly with<br />

both feet firmly on the ground. The island at sea makes working at<br />

sea also more safe, requiring less sailing to and fro and thus<br />

reducing the traffic on shipping routes that become increasingly<br />

crowded.”<br />

Westra: “Platforms and boats are not a good match to a renewable<br />

solution for offshore wind power generation. Imagine being a<br />

maintenance crew, you first need to sail a long distance, arrive<br />

sick, be able to step onto the platform and then have to climb up<br />

carrying heavy things, and only then the work there can finally<br />

begin. That is not how it should be done, and in fact it is<br />

irresponsible.”<br />

<strong>02</strong>-<strong>2019</strong> | 35


Island at Sea, photo TenneT<br />

You will not build yourselves. Which partners are<br />

important for you?<br />

Van Zuijlen: “The project requires a lot of different knowledge,<br />

thus apart from contractors, we have been in contact with applied<br />

scientific research institutes, environmental organisations,<br />

electricity companies, the government and we consider the public<br />

opinion. Building islands at sea is like a new kind of Delta Works.<br />

Co-operation with several partners is crucial and together we are<br />

going to start something that is new. That is the way we want to<br />

develop it, as a project that will make everybody happy and proud.”<br />

Westra: “A main wish is that all Non-Governmental Organisations<br />

will find common ground in this. That will not be easy. However,<br />

building an island as such is quite easy; it requires just moving a<br />

huge amount of sand. Such an island has never been built before,<br />

and everyone has an opinion ready. Apart from technical issues,<br />

our work will for 80 percent consist of stakeholder management.<br />

The technology we leave for a large part in the hands of others; the<br />

whole bunch of issues around that, that is where we are of<br />

importance, and good at.”<br />

What additional benefits can an island offer?<br />

Westra: “A huge benefit is that by building an island, you create a<br />

stable area for maintenance, storage, transit of renewable energy,<br />

and in due time possibly the additional opportunity to offer a<br />

guaranteed security of supply. The idea is to combine various<br />

kinds of things.”<br />

Van Zuijlen: “There will be a lot of energy arriving from the sea,<br />

but possibly also sustainable produced food and there are many<br />

opportunities to improve the environmental conditions in the<br />

North Sea. The combination of offshore wind energy generation<br />

and the idea of an island at sea make those other options a lot<br />

more realistic. Therefore, an island at sea offers a great<br />

opportunity.”<br />

What are the drawbacks of an island at sea?<br />

After some joking (‘There aren’t any!’ and ‘The sea is an<br />

obstacle!’) follows a moment of silence… Van Zuijlen: “Building<br />

an island at sea is an intervention in the ecological system. We are<br />

very aware of that, and therefore we find it imperative that we can<br />

also make use of the ecological opportunities that an island offers,<br />

such as oyster reefs, restoration of the marine ecology and for<br />

instance the farming of seaweed. An island at sea can easily be<br />

regarded as a translocation of activities from the main land to the<br />

sea, or even as a colonisation of the sea. That image we wish to<br />

avoid as much as possible.”<br />

Westra: “Another drawback could be that quite a lot of sand will<br />

be required and sand is becoming scarcer, though that applies<br />

mainly to sand extraction near the coast. Not so much a<br />

disadvantage but a wrong approach is to view the building of an<br />

island as a wish to tame the sea.”<br />

What is your drive to undertake this artificial island<br />

venture?<br />

Westra: “It is addictive to do something that has never been done<br />

before. To go all the way for it because you like it. I am not solely<br />

driven by technology. Technology is beautiful, but the real issue is<br />

that we really should tackle the energy transition now, the sooner<br />

the better, if we want to keep conditions on earth somewhat<br />

liveable for future generations.”<br />

Van Zuijlen: “I strongly believe that we need very quickly drastic<br />

technological measures to save the environment as much as<br />

possible. Offshore wind turbines and islands at sea are both<br />

technological solutions that contribute to the energy transition.<br />

Human behaviour is important as well, but changing that is a lot<br />

harder when all you do is telling people that things are going<br />

wrong. Behaviour is strongly influenced, I think, by political<br />

choices, for instance taxation policies and legislations.”<br />

When should the island be realised on ‘your’ spot, near the<br />

designated wind farm zone IJmuiden Ver?<br />

Van Zuijlen: “The island IJVER should be ready in 2<strong>02</strong>5 to be<br />

useful when in 2<strong>02</strong>7 transmission system operator Tennet wants to<br />

connect a substation to the new wind farms in the area. That<br />

means we have just six years to realise it, as building the substation<br />

will also take time, to make sure that two years later the power<br />

cables can be connected.”<br />

u This articled was originally published in Dutch in WindNieuws <strong>02</strong>, <strong>2019</strong>.<br />

36 | <strong>02</strong>-<strong>2019</strong>


Duurzame energie voor en door iedereen<br />

Veiligheid als<br />

sluitstuk<br />

Ynso Suurendonk<br />

en Jesse Don<br />

www.duurzameenergie.org<br />

Probeer WindNieuws nu vrijblijvend met een<br />

proefabonnement van twee nummers voor € 10,-<br />

ontwerp-<br />

energiestructuurVisie<br />

coöperaties<br />

wind op Zee<br />

stomen door!<br />

Ad. Littel<br />

Siward Zomer<br />

nr.3 | 2014<br />

windpark<br />

Duurzame energie voor en door iedereen<br />

noordoostpolder<br />

Frans A. van der Loo<br />

EEn goEdE basis dE wind<br />

Wouter Pustjens in drEnthE<br />

Mirjam Tielen<br />

www.duurzameenergie.org<br />

nr.5 | 2014<br />

waardEvollE aanbEvEling<br />

wind<br />

wind op zEE<br />

Frans A. van der Loo van nii<br />

Linda Wes<br />

Friesland<br />

reactie<br />

in de Wind op essay<br />

Mirjam Tielen pieter Boot<br />

Krispijn Beek<br />

www.duurzameenergie.org<br />

Windenergie<br />

is kinderspel<br />

Evert Kuiken<br />

nr.6 | 2014<br />

WindturBines<br />

en externe<br />

veiligheid<br />

Tom van der Linde<br />

en Jeroen Eskens<br />

Zuid-Holland:<br />

Van woorden<br />

naar daden<br />

Mirjam Tielen<br />

GedraGscode<br />

onder de<br />

juridiscHe loep<br />

Aaldert ten Veen<br />

en Derek Sietses<br />

de waarde<br />

Van een<br />

onafHankelijk<br />

windrapport<br />

Erik Holtslag, Bob<br />

Schulte, Rolf de Vos<br />

nr.1 | 2015<br />

wind op land<br />

en de proVinciale<br />

staten<br />

Verkie ZinGen<br />

Ad. Littel<br />

VRIJDENKEN<br />

OVER HET<br />

ELEKTRICITEITS-<br />

NET<br />

VERMINDEREN<br />

VAN EFFECTEN<br />

VAN WIND-<br />

TURBINES OP<br />

VLEERMUIZEN<br />

PARTICIPATIE<br />

BIJ WIND OP ZEE<br />

WINDDAGEN<br />

2018<br />

BEURS EN<br />

PRESENTATIES<br />

The international leading event<br />

on Offshore Wind and<br />

Marine Renewable Energy<br />

www.seanergy<strong>2019</strong>.com<br />

ode windnieuws<br />

ode WindnieuWs<br />

ode decentraal WindnieuWs<br />

nr.3 | 2017<br />

ode windnieuws<br />

Bent u geïnteresseerd in<br />

windenergie? Wilt u meer<br />

lezen over de ontwikkeling<br />

van windenergie in een<br />

maatschappelijke context<br />

van voors en tegens?<br />

odE windniEuws<br />

Duurzame energie voor en door iedereen<br />

Duurzame energie voor en door iedereen<br />

www.duurzameenergie.org<br />

Windenergie. Hoe doe je dat met elkaar?<br />

Neem een abonnement<br />

op WindNieuws!<br />

Duurzame energie voor en door iedereen<br />

Klimaatverandering<br />

en wind<br />

interview<br />

richard<br />

Klatten -<br />

Qurrent<br />

airborne<br />

windenergie-<br />

systemen<br />

www.duurzameenergie.org<br />

lessen van<br />

houten<br />

het proces en<br />

de<br />

betrokkenen<br />

slimme<br />

smart grid<br />

in gotland<br />

ODE DECENTRAAL WINDNIEUWS<br />

NR.4 | 2018<br />

Duurzame energie voor en door iedereen<br />

Oesters en<br />

windturbines<br />

www.duurzameenergie.org<br />

WindNieuws is hèt onafhankelijke Nederlandstalige vakblad voor de windsector,<br />

uitgegeven door ODE Decentraal. WindNieuws heeft een verdiepingsfunctie en<br />

biedt een platform om achtergrondkennis en -informatie te delen en te vinden.<br />

WindNieuws verschijnt sinds 1983 zes keer per jaar.<br />

Meer weten of aanmelden?<br />

windnieuws@duurzameenergie.org<br />

www.windnieuws.nl


Innovation<br />

Sabine Lankhorst<br />

Ocean Grazer<br />

When supply and<br />

demand meet<br />

With the upscaling of renewable energy production, there is<br />

an increased demand for flexibility in the electricity<br />

network. The University of Groningen developed the Ocean<br />

Grazer Concept, a hybrid modular offshore system that<br />

combines wind, wave & storage and potentially other<br />

sources of renewable energy.<br />

Frits Bliek got involved with<br />

Ocean Grazer in 2018.<br />

Trained as physicist, he has<br />

a long track record in innovation<br />

management and energy management<br />

consultancy, guiding startups.<br />

He explains how the whole idea<br />

emerged. “In 2011, Wout Prins, teacher<br />

at the Engineering and<br />

Technology institute Groningen, got<br />

inspired to develop a more efficient<br />

technology for harvesting the energy<br />

created by waves at high seas than<br />

available at that time.”<br />

This resulted in Ocean Power, a patented<br />

wave energy converter that consists<br />

of individual floater elements that, together,<br />

form a blanket. By means of<br />

sensors, connected to a monitoring<br />

system, real-time decisions can be<br />

made on the optimal configuration of<br />

the floater elements for each wave<br />

height and period so a wide spectrum<br />

of waves can be covered simultaneously.<br />

The next step was to develop a storage<br />

system where the energy, produced<br />

by the Ocean Power, could be<br />

stored. The Ocean Battery functions<br />

like a floating reservoir where use is<br />

made of the pressure at the bottom of<br />

the seabed. To store energy it pumps a<br />

fluid via pistons through a pipe into<br />

flexible bladders that are deflated by<br />

the pressure of the ocean. This fluid is<br />

based on fresh water enhanced with<br />

biological additives. In combination<br />

with Ocean Power, the floaters power<br />

the adaptive pumps.<br />

Later on, the idea was created that the<br />

storage system could also be a perfect<br />

solution for storing energy created by a<br />

wind turbine at times when the demand<br />

for energy on land is low. The<br />

Ocean Foundation, a new multi-functional<br />

foundation type, was designed<br />

which could also house the Ocean<br />

Power and Ocean Battery. The three<br />

together form the Ocean Grazer, an<br />

integrated energy system that combines<br />

wind and wave energy and storage.<br />

Balancing supply and<br />

demand<br />

The Ocean Grazer offers advantages in<br />

many areas. When used at wind farms,<br />

it is the Ocean Battery that offers the<br />

main advantage as it responds to the<br />

demand for flexibility in the electricity<br />

system. When there are high winds,<br />

thus high energy production, but low<br />

demand, the surplus energy can temporarily<br />

be stored in the Ocean<br />

Battery. At peak hours, the stored<br />

energy can be released and fed into the<br />

grid. This creates a balance between<br />

supply and demand.<br />

Bliek: “Based on calculations we made<br />

at our test lab, an Ocean Foundation<br />

with a diameter of 60 metres could<br />

have a storage capacity of up to 7<br />

MWh per wind turbine.” The Ocean<br />

Grazer could potentially lower the<br />

LCOE with 1 ct p/kWh,” he adds, “all<br />

depends on the water depth. The<br />

deeper, the more efficient.” These are<br />

preliminary figures, he stresses, prototype<br />

testing will have to determine<br />

more definite numbers.<br />

38 | <strong>02</strong>-<strong>2019</strong>


The Ocean<br />

Battery could<br />

also be used as<br />

a stand-alone<br />

device<br />

Multi-use of wind farms<br />

Another advantage is the multi-use of<br />

the system. He explains: “With a growing<br />

demand for electricity, how can<br />

we upscale the energy production?<br />

There is only limited space on land.<br />

The North Sea still offers space<br />

for the development of renewable<br />

energy but we have<br />

to use this space efficiently.<br />

I can see an added<br />

value in smarter<br />

cooperation. It is important<br />

for the different<br />

North Sea users to<br />

look at, and learn from,<br />

each other; what does the<br />

other want? How can we<br />

work together? Multi-use of<br />

wind farms is a good example.”<br />

“Research centre MARIN is already<br />

working on a project for multi-use of<br />

spatial area in wind farm. We can use<br />

the complete Ocean Grazer system at<br />

wind farms, including the Ocean<br />

Power wave converter. In case of high<br />

wind speeds, when the wind force is<br />

12 for example, the floaters of the<br />

Ocean Power system will be pulled<br />

down. We could do the same when<br />

maintenance has to be performed on a<br />

wind turbine”, he explains. In the future,<br />

Ocean Grazer could combine<br />

even more renewable energy sources,<br />

such as floating solar. The system is<br />

very flexible and modular and, depending<br />

on the project needs, one could<br />

use the integrated hybride system or<br />

only a combination, he adds. The<br />

Ocean Battery could also be used as a<br />

stand-alone device.<br />

Sustainability<br />

The Ocean Grazer offers several advantages<br />

in the area of sustainability.<br />

The foundation surface allows for marine<br />

life to grow, potentially creating a<br />

new underwater habitat. In addition,<br />

the foundation is quicker to install as it<br />

can be assembled in the port, towed<br />

and installed at the wind farm site in<br />

once piece. There is no need for piling,<br />

so there is no effect of noise on marine<br />

mammals. Bliek: “We are also looking<br />

how to remove the foundation in the<br />

most efficient way.” There is still research<br />

required to determine the lifespan<br />

of the system, which is currently estimated<br />

to exceed 25 years. Because the<br />

pressure inside the system is the same<br />

as that on the outside, there is not<br />

much wear and tear.<br />

Leaving the lab<br />

Following years of intensive research<br />

and testing at the university’s own laboratory,<br />

with over 60 students involved,<br />

the university is now ready to take<br />

Ocean Grazer to the next step of prototyping,<br />

followed by commercial deployment.<br />

As this is beyond the capabilities<br />

of the university, a<br />

special-purpose company, Ocean<br />

Grazer BV, was set up in 2018 to take<br />

the technology out of the laboratory<br />

and onto the market. Bliek joined the<br />

start-up to help guide this process.<br />

“When you try to develop everything<br />

at the same time, you’re bound to face<br />

some setbacks. Therefore each technology<br />

was developed separately before<br />

we would integrate them into one<br />

well-functioning system. We are now<br />

ready to look for partners and investors<br />

to work towards a prototype that<br />

can be tested outside.”<br />

The technologies comprise proven<br />

technologies. The uniqueness is in the<br />

configuration. This makes it easier to<br />

find the right partners to build a prototype.<br />

“There are, for example, already<br />

experienced gravity-based foundation<br />

builders in the market. We<br />

would also have to look into scour protection.<br />

Partners like Deltares can help<br />

us to develop this. We demonstrated in<br />

the lab that the technology works.<br />

Now the question is, how can we scale<br />

up and make it cost-efficient to<br />

build?”, he explains.<br />

Next year, the company will install a<br />

prototype in Eemshaven. “Here we can<br />

perform sea trials in a relatively protected<br />

and easy accessible environment.<br />

A next step would be to install a<br />

prototype in a true offshore environment,<br />

perhaps near an oil platform.”<br />

u www.oceangrazer.com<br />

The Ocean Grazer offers a solution for multi-use at wind farms and enables balance in energy production and demand<br />

<strong>02</strong>-<strong>2019</strong> | 39


General news<br />

IHC IQIP invests in further<br />

development BLUE Piling<br />

Technology<br />

IHC IQIP is investing in the BLUE Piling<br />

Technology, a way of driving piles for offshore<br />

wind using hydropower. It joins forces with<br />

Jasper Winkes, the developer of the hammer<br />

with the BLUE Piling Technology.<br />

The technology enables larger monopiles to<br />

be installed, reduces fatigue in the pile and<br />

reduces noise by tackling the noise at the<br />

source. Tests with the hammer using the<br />

technology have demonstrated the potential<br />

of the technology. IHC IQIP will start working<br />

with a modernised, slightly adjusted version<br />

of the BLUE Piling technology and expects to<br />

achieve positive results soon.<br />

Research into effects of<br />

large-scale offshore wind farm<br />

implementation in the North Sea<br />

Large-scale implementation of offshore<br />

wind farms in the southern North Sea can<br />

have a large impact on the functioning of<br />

the North Sea. This is the conclusion from<br />

an exploratory study performed by knowledge<br />

centre Deltares, in cooperation with<br />

KNMI, Whiffle and Wageningen Marine<br />

Research, by order of the Department of<br />

Waterways and Public Works<br />

(Rijkswaterstaat). The study is part of the<br />

multiannual Wind at Sea Programme (Wind<br />

op Zee Programma). The preliminary results<br />

show that already the wind speed is affected<br />

near the water surface at existing wind<br />

farms and dozens of kilometres downwind.<br />

This is also applicable to the wave height,<br />

the turbidity and stratification of the water<br />

and the tide dynamic. This affects the bio<br />

diversity. More study in cooperation with<br />

neighbouring countries is required.<br />

Offshore Wind Innovation<br />

Challenge <strong>2019</strong><br />

The Offshore Wind Innovation Challenge is<br />

an initiative of Offshore Wind Innovators and<br />

aims to accelerate applied innovations in the<br />

offshore wind industry. On 13 May, the kickoff<br />

for the second edition of the Challenge<br />

took place. On this day, companies that take<br />

part in the challenge presented their technical<br />

challenge to the Offshore Wind<br />

Innovators community. Interested start-ups<br />

and SME’s have 4 weeks to submit their solution<br />

to one of the presented challenges.<br />

During the summer months, the companies<br />

and entrepeneurs with solutions will participate<br />

in a Masterclass and Bootcamp.<br />

The finals will take place on September 12.<br />

Last year’s finalists were Ridderflex (winner),<br />

with a new fender for SeaZip Offshore<br />

Service. Skeye and Prodrone with blade inspections<br />

at night, and Mel Systems and<br />

Filtertechnik with on the spot oil analyses.<br />

Van Oord and AdBm demonstrate new noise<br />

mitigation system<br />

PHOTO: VAN OORD<br />

The DP2 Walk to Work vessel Acta<br />

Centaurus was built by Ulstein Verft in<br />

Norway. It is 93 m long and has a load capacity<br />

of 3,200 t and 6 m draft. It is<br />

equipped with hybrid battery packs and<br />

hull designs X-BOW® and X-STERN®<br />

for better performance in heavy seas. It features<br />

a motion compensated gangway<br />

Van Oord and AdBm Technologies have<br />

successfully demonstrated the new AdBm<br />

Noise Mitigation System (NMS), with support<br />

from TNO. Van Oord will be deploying<br />

the system at Borssele 3, 4 & 5.<br />

The NMS system reduces underwater noise<br />

resulting from offshore pile driving activities<br />

for wind turbine foundations. It uses<br />

special acoustic resonators designed and<br />

produced by AdBm Technologies which reduce<br />

the noise from pile driving. As a result,<br />

specific frequencies can be targeted<br />

which produce the most noise. The system<br />

was designed and built at Van Oord.<br />

Acta Marine welcomes Acta Centaurus<br />

PHOTO: ACTA MARINE<br />

and a 3D motion compensated knuckle<br />

boom crane by SMST which can handle 6<br />

t cargo in sea conditions up to Hs 2.5 metres.<br />

The vessel has accommodation for up<br />

to 120 persons and cargo areas of 1,000<br />

square metres in total, indoors and outdoors.<br />

It joins the Acta Auriga and Acta<br />

Orion.<br />

40 | <strong>02</strong>-<strong>2019</strong>


General news<br />

WindDays <strong>2019</strong><br />

On 12 & 13 June, the annual WindDays<br />

will take place at the World Trade Centre in<br />

Rotterdam. This annual event, consisting of<br />

a conference and exhibition, connects all<br />

stakeholders within the Dutch wind sector,<br />

thereby giving an important impulse to the<br />

development of wind energy both on- and<br />

offshore.<br />

‘Without demand, no supply?<br />

This is the theme of WindDays <strong>2019</strong>. At<br />

the opening session on 12 June, three speakers,<br />

Giles Dickson (CEO WindEurope),<br />

Dorine Bosman (Vice-President Wind at<br />

Shell) & Medy van der Laan (Chairperson<br />

Energie Nederland), will address this topic<br />

from their area of expertise.<br />

During the two-days event, other current<br />

topics in the Dutch onshore and offshore<br />

wind energy market are discussed through<br />

sessions, debates and masterclasses. At the<br />

end of the first day there will be a conference<br />

dinner at the Harbour Club at the<br />

foot of the Euromast.<br />

At the exhibition, up to 50 companies, including,<br />

amongst others Vestas, DNV-GL,<br />

Siemens Gamesa, Enercon, Lagerwey and<br />

Deutsche Windtechnik, will be showcasing<br />

their products or services. Dedicated areas<br />

are allocated for lawyers and bankers and<br />

for start-ups.<br />

Climate neutral<br />

To provide a good example, the<br />

WindDays event will be organised for the<br />

first time in a climate-neutral way. The<br />

event location already has taken climate-friendly<br />

measures. To compensate for<br />

the remaining CO2 emission, the organisers<br />

of WindDays invest in a wind energy<br />

project in India. It is doing so in cooperation<br />

with Groenbalans.<br />

Wind Energy Magazine will be available in<br />

the media corner.<br />

www.winddays.nl<br />

SDE+ Spring <strong>2019</strong><br />

During the SDE+ Spring <strong>2019</strong> subsidy application<br />

round, RVO.nl received applications<br />

for 43 wind energy projects with a combined<br />

power of 143 MW. The total subsidy claim for<br />

these projects is 309 million Euro.<br />

SDE+ Autumn 2018<br />

The budget for the SDE+ Autumn 2018<br />

round was fully used. 4,618 projects, with a<br />

budget claim of 6 billion Euro, received a<br />

positive decision. Of these, 143 are wind<br />

energy projects, with a combined power of<br />

758 MW. The budget claim for these wind<br />

projects is 1,874 million Euro.<br />

Subsidy ‘Proeftuin op de<br />

Noordzee’<br />

Off the coast of The Hague, just outside<br />

the port of Scheveningen, a unique test<br />

area of 10 by 10 nautical miles will be developed<br />

where companies, universities,<br />

SME’s and start-ups in the maritime or watersports<br />

industry can test and demonstrate<br />

their innovations at open sea. A subsidy<br />

(MKB Stimuleringsregeling Proeftuin<br />

op de Noordzee) has been made available<br />

for start-ups and SME’s. The total available<br />

budget is € 375,000. Each interested party<br />

can apply for max. € 25,000 (against a<br />

personal contribution of the same<br />

amount). The subsidy runs till 31<br />

December 2<strong>02</strong>1 and is only available for<br />

SME’s and start-ups from the The Hague<br />

region or for innovations that will have direct<br />

effect on this region.<br />

Smart Maritime Technology<br />

13 June, Rotterdam<br />

On 13 June, the second edition of the Smart<br />

Maritime Technology event will take place at<br />

the VNAB centre in Rotterdam.<br />

Disruptive technologies<br />

Smart Maritime Technology is a conference<br />

that discusses disruptive technologies for<br />

the maritime industry. What are the technologies<br />

that the maritime sector should focus<br />

on to stay/become future-proof?<br />

Engineers and (innovation) managers will learn<br />

about the latest developments in 3D<br />

printing, artificial intelligence, augmented<br />

reality and smart maintenance.<br />

Confirmed speakers include, Toine<br />

Cleophase of Damen Shipyards, Diederick<br />

Nab of WAGO NL, Egbert Ypma of MARIN,<br />

Robert Hekkenberg of TU Delft, Lucas<br />

Janssen of CEAD, and others.<br />

Wind Energy Magazine subscribers receive<br />

discount. More information can be found at:<br />

smt.maritiemnederland.com<br />

<strong>02</strong>-<strong>2019</strong> | 41


Page 06 - 09<br />

nieuws<br />

Page 20 - 23<br />

Page 30 - 33<br />

<strong>2019</strong><br />

magazine<br />

Agenda<br />

<strong>2019</strong> Publication dates<br />

<strong>2019</strong><br />

WindDays<br />

12 & 13 JUNE, ROTTERDAM<br />

www.winddays.nl<br />

OCTOBER EDITION<br />

Theme: Operation & Maintenance<br />

Distribution at Offshore Energy<br />

NOVEMBER EDITION<br />

Theme: Combining Energies<br />

Distribution at WindEurope Offshore<br />

Smart Maritime Technology<br />

13 JUNE, ROTTERDAM<br />

smt.maritiemnederland.com<br />

Global Offshore Wind<br />

25 & 26 JUNE, LONDON, UK<br />

events.renewableuk.com/gow19<br />

READ WIND ENERGY MAGAZINE<br />

WITH 25% DISCOUNT<br />

Subscribe at<br />

Windenergie-magazine.nl/abonneren<br />

Wind Energy Magazine Vol. 6 | <strong>02</strong>-<strong>2019</strong><br />

energy<br />

Grid<br />

Connection<br />

When wind farms become power stations<br />

Wieringermeer Wind Farm<br />

Va tenfa l is cu rently working on one<br />

of the largest Dutch onshore wind<br />

projects. What are the cha lenges<br />

building in an area of around 300 km²?<br />

magazine<br />

Interview Prysmian Group<br />

Future grid capacity is a hot topic in<br />

the Netherlands a the moment.<br />

What are the requirements in terms<br />

of cable designs?<br />

Solving the gridlock<br />

The acceleration of the energy<br />

transition requires extra grid<br />

capacity. Is the grid ready for the<br />

future influx of renewable energy?<br />

#2<br />

Volume 6<br />

June<br />

WindEurope Technology Workshop<br />

27 & 28 JUNE, BRUSSELS, BE<br />

Windeurope.org<br />

WindDays South East Asia<br />

7 & 8 OCTOBER, NUSA DUA, BALI<br />

www.winddayssoutheastasia.com<br />

DAILY REPORTING<br />

ON THE DUTCH<br />

WIND ENERGY INDUSTRY<br />

IN ENGLISH AND DUTCH!<br />

Offshore Energy<br />

7 – 9 OCTOBER, AMSTERDAM<br />

www.offshore-energy.biz<br />

energy<br />

magazine<br />

AWEA Offshore WINDPOWER<br />

22 & 23 OCTOBER, BOSTON, USA<br />

www.awea.org<br />

energy<br />

Floating Offshore Wind<br />

11 – 12 NOVEMBER, LONDON, UK<br />

www.newenergyupdate.com<br />

Windenergie-nieuws.nl (NL)<br />

Windenergy-magazine.com (EN)<br />

WindEurope OFFSHORE<br />

26 - 28 NOVEMBER, COPENHAGEN, DK<br />

windeurope.org/offshore<strong>2019</strong><br />

For advertising or content contribution go to<br />

www.windenergie-magazine.nl/contact<br />

42 | <strong>02</strong>-<strong>2019</strong>


We know which way<br />

the wind blows.<br />

ENVIR Advocaten is the expert if it comes to wind energy projects, whether<br />

it concerns permits or administrative proceedings. Together with our clients<br />

ENVIR Advocaten creates a fast, efficient and uncomplicated permit process.<br />

We combine our expertise and experience for clear analyses and practical<br />

solutions, so together we achieve the best result.<br />

ENVIR Advocaten The specialist in environmental law and administrative law<br />

www.envir-advocaten.com


Evolution in action.<br />

FAST CREW SUPPLIER 2710<br />

The Twin Axe is back! And this time it’s bigger than ever.<br />

The new FCS 2710 features increased comfort, flexibility, deck space<br />

and accommodation. And, with an extra metre in height for improved<br />

seakeeping, this Sea Axe is truly a chopper suited to choppy seas.<br />

DAMEN.COM

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!