4.2.2 Notice of Audits<br />

Audits will be announced approximately <strong>on</strong>e week in advance by the Manager of Quality Assurance or<br />

the assigned auditor(s), as appropriate by means of a written notice (audit plan). The following parties<br />

shall be informed as a minimum:<br />

General Manager<br />

Director of Projects<br />

Project Manager<br />

Project QA Engineer<br />

Recipient Department Audit Project Audit<br />

Manager QA Department X X<br />

Department Manager X X<br />

Discipline Manager<br />

Main Auditees X X<br />

X<br />

X<br />

X<br />

X<br />

X<br />

The assigned auditor(s) shall address the following audit program aspects:<br />

project documentati<strong>on</strong> that will be assessed;<br />

• audit date, schedule (timing) and locati<strong>on</strong>;<br />

• name(s) of auditee(s);<br />

• name(s) of auditor(s);<br />

• name(s) of possible observer(s);<br />

• proposed timing and locati<strong>on</strong> of pre and post-audit meeting.<br />

and inform all c<strong>on</strong>cerned to ensure that required resources, facilities, informants and project documents<br />

needed for the document review and the audit are available.<br />

https://www.red-bag.com/general-procedures/33-cm-qa-001-procedure-for-internal-quality-audits.html<br />

Charlie Ch<strong>on</strong>g/ Fi<strong>on</strong> Zhang

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!