06.08.2018 Views

[James_H._Harlow]_Electric_Power_Transformer_Engin(BookSee.org)

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

mounted transformers can have arresters too, especially those at the end of a radial line, and they can<br />

be inside the tank, plugged into dead-front bushings, or at a nearby riser pole, where primary lines<br />

transition from overhead to underground.<br />

FIGURE 2.2.39 Cutaway showing CSP components. (By permission of ABB Inc., Jefferson City, MO.)<br />

set the breaker on its emergency position, which allows the transformer to temporarily supply a higher<br />

overload until the utility replaces the unit with one having a higher kVA capacity. The secondary oil<br />

breaker is also handy to disconnect load from a transformer without touching the primary connections.<br />

2.2.13.6 CSP ®2 <strong>Transformer</strong>s<br />

Overhead transformers that are built with the combination of secondary breaker, primary protective link,<br />

and external lightning arrester are referred to generically as CSPs (completely self-protected transformers).<br />

This protection package is expected to prevent failures caused by excessive loads and external voltage<br />

surges, and to protect the system from internal faults. The breaker is furnished with a signal light and<br />

an emergency control as described above. The protective link is often mounted inside the high-voltage<br />

bushing insulator, as seen in Figure 2.2.39.<br />

2.2.13.7 Protection Philosophy<br />

CSP transformers are still in use, especially in rural areas, but the trend is away from secondary breakers<br />

to prevent transformer burnouts. Continued growth of residential load is no longer a foregone conclusion.<br />

Furthermore, utilities are becoming more sophisticated in their initial transformer sizing and are using<br />

computerized billing data to detect a transformer that is being overloaded. Experience shows that modern<br />

distribution transformers can sustain more temporary overload than a breaker would allow. Most utilities<br />

would rather have service to their customers maintained than to trip a breaker unnecessarily.<br />

2.2.13.8 Lightning Arresters<br />

Overhead transformers can be supplied with primary lightning arresters mounted nearby on the pole<br />

structure, on the transformer itself, directly adjacent to the primary bushing, or within the tank. Pad-<br />

2<br />

CSP ® is a registered trademark of ABB Inc., Raleigh, NC.<br />

2.2.14 Economic Application<br />

2.2.14.1 Historical Perspective<br />

Serious consideration of the economics of transformer ownership did not begin until the oil embargo<br />

of the early 1970s. With large increases in the cost of all fuels, utilities could no longer just pass along<br />

these increases to their customers without demonstrating fiscal responsibility by controlling losses on<br />

their distribution systems.<br />

2.2.14.2 Evaluation Methodology<br />

An understanding soon developed that the total cost of owning a transformer consisted of two major<br />

parts, the purchase price and the cost of supplying thermal losses of the transformer over an assumed<br />

life, which might be 20 to 30 years. To be consistent, the future costs of losses have to be brought back<br />

to the present so that the two costs are both on a present-worth basis. The calculation methodologies<br />

were published first by Edison <strong>Electric</strong> Institute and recently updated in the form of a proposed ANSI<br />

standard (IEEE, 2001).The essential part of the evaluation method is the derivation of A and B factors,<br />

which are the utility’s present-worth costs for supplying no-load and load losses, respectively, in the<br />

transformer as measured in $/W.<br />

2.2.14.3 Evaluation Formula<br />

The proposed ANSI guide for loss evaluation expresses the present value of the total owning cost of<br />

purchasing and operating a transformer as follows (in its simplest form):<br />

TOC <strong>Transformer</strong> Cost A No Load Loss B Load Loss<br />

(2.2.8)<br />

where<br />

A = loss-evaluation factor for no-load loss, $/W<br />

B = loss-evaluation factor for load loss, $/W<br />

The guide develops in detail the calculation of A and B factors from utility operating parameters as<br />

shown in Equation 2.2.9 and Equation 2.2.10, respectively:<br />

SC EC HPY<br />

A <br />

FCR 1000<br />

SC RFEC LSF HPY PL<br />

B <br />

FCR 1000<br />

where SC = GC + TD<br />

SC = avoided cost of system capacity<br />

GC = avoided cost of generation capacity<br />

TD = avoided cost of transmission and distribution capacity<br />

EC = avoided cost of energy<br />

HPY = hours per year<br />

FCR = levelized fixed-charge rate<br />

RF = peak responsibility factor<br />

LSF = transformer loss factor<br />

PL = equivalent annual peak load<br />

2<br />

(2.2.9)<br />

(2.2.10)<br />

© 2004 by CRC Press LLC<br />

© 2004 by CRC Press LLC

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!