Request for Proposal for establishing e-Governance Systems<br />
Sr.<br />
No.<br />
Item Expected Date <strong>of</strong><br />
Submission from ‘T’<br />
System design T + 3 weeks for E-ticketing<br />
and Financial Planning and<br />
Budgeting Modules<br />
4. Training for Go-Live for Electronic<br />
Communication Module<br />
5. Go-Live for Electronic<br />
Communication Module<br />
6. Preparation <strong>of</strong> User Acceptance<br />
test cases and test plan for<br />
Modules 2 and 3<br />
7. Commissioning <strong>of</strong> environment<br />
for Prototype Development for eticketing<br />
Module<br />
8. Sign-<strong>of</strong>f from stakeholders after<br />
Prototype demonstration<br />
9. Data Migration Plan for Financial<br />
Planning and Budgeting Module<br />
10. Procurement and deployment <strong>of</strong><br />
datacenter and IT infrastructure<br />
11. Preparation for User Acceptance<br />
Test for Financial Planning and<br />
Budgeting Module<br />
Final<br />
acceptance<br />
post review<br />
Payment<br />
Milestone<br />
RFP Volume 2: Commercial and Bidding Terms Page 16<br />
any)<br />
Deliverables<br />
System Design document (SDD)<br />
T+ 3 weeks Within 1 week Evaluating Training Feedback and<br />
training content / methodology<br />
T + 6 weeks Within 2 week [M 1] Roll-out checklist and plan<br />
T + 6 weeks Within 2 weeks User Acceptance Test Cases<br />
T + 6 weeks Within 2 weeks<br />
post review<br />
User Acceptance Plan<br />
Development <strong>of</strong> Prototype and Functional<br />
acceptance on Prototype<br />
T + 8 weeks Within 1 week Workshop for review and sign-<strong>of</strong>f<br />
T + 12 weeks Within 1 week Detailed Plan for Data Migration<br />
T + 14 weeks Within 2 weeks Certifications <strong>of</strong> deployment completion<br />
at each site given to bidder by concerned<br />
ASI <strong>of</strong>ficial / third party<br />
T + 12 weeks Within 1 week User Acceptance Test Cases<br />
User Acceptance Plan