Request for Proposal<br />
For establishing e-Governance Systems<br />
For<br />
<strong>Archaeological</strong> <strong>Survey</strong> <strong>of</strong> <strong>India</strong><br />
<strong>Project</strong> <strong>Requirements</strong><br />
November9, 2011
Request for Proposal for establishing e-Governance Systems<br />
Table <strong>of</strong> Contents<br />
1 INTRODUCTION AND BACKGROUND .................................................................................................... 8<br />
2 ABOUT ARCHEOLOGICAL SURVEY OF INDIA .......................................................................................... 9<br />
3 CURRENT STATUS AND VISION FOR E-GOVERNANCE .......................................................................... 10<br />
3.1 ELECTRONIC COMMUNICATION ................................................................................................................... 11<br />
3.2 E-TICKETING ........................................................................................................................................... 11<br />
3.3 FINANCIAL PLANNING AND BUDGETING SYSTEMS ........................................................................................... 12<br />
4 PROJECT VISION AND PHASES ............................................................................................................ 14<br />
5 SCOPE OF WORK FOR THE SYSTEM INTEGRATOR ................................................................................ 15<br />
5.2 PHASE 1: PROJECT PLANNING PROCESS ........................................................................................................ 15<br />
5.3 PHASE 2: REQUIREMENTS ANALYSIS ............................................................................................................ 15<br />
5.4 PHASE 3: SOLUTION DESIGN ...................................................................................................................... 16<br />
5.5 PHASE 4: SYSTEM DEVELOPMENT ............................................................................................................... 16<br />
5.6 PHASE 5: SOLUTION PROTOTYPE ................................................................................................................. 16<br />
5.7 PHASE 6: ENTRY OF HISTORICAL DATA ......................................................................................................... 17<br />
5.8 PHASE 7: TESTING AND ACCEPTANCE ........................................................................................................... 17<br />
5.9 PHASE 8: DOCUMENTATION ....................................................................................................................... 18<br />
5.10 PHASE 9: USER TRAINING, OPERATIONS, AND MAINTENANCE .......................................................................... 18<br />
6 IMPLEMENTATION MODEL................................................................................................................. 20<br />
7 KEY DELIVERABLES ............................................................................................................................. 21<br />
7.1 E-GOVERNANCE PROJECT APPLICATION DEVELOPMENT AND INFRASTRUCTURE DEPLOYMENT ................................. 21<br />
7.2 E-GOVERNANCE PROJECT APPLICATION AND INFRASTRUCTURE MAINTENANCE .................................................... 22<br />
7.3 E- TICKETING OPERATIONS ......................................................................................................................... 22<br />
8 FUNCTIONAL REQUIREMENTS ............................................................................................................ 24<br />
8.2 SYSTEM SECURITY REQUIREMENTS .............................................................................................................. 39<br />
8.3 GOVERNANCE STRUCTURE ......................................................................................................................... 40<br />
8.4 DOCUMENTATION STANDARDS AND REQUIREMENTS ....................................................................................... 40<br />
9 SERVICE LEVEL AGREEMENTS ............................................................................................................. 41<br />
9.1 SOFTWARE APPLICATION DEVELOPMENT AND DEPLOYMENT ............................................................................ 41<br />
9.2 SOFTWARE APPLICATION AND INFRASTRUCTURE MAINTENANCE ....................................................................... 43<br />
9.3 E-TICKETING OPERATIONS .......................................................................................................................... 43<br />
10 ANNEXURES ....................................................................................................................................... 45<br />
10.1 ANNEXURE 1: LIST OF CIRCLES .................................................................................................................... 45<br />
10.2 ANNEXURE 2: VISITOR HISTORY TO THE MONUMENTS .................................................................................... 46<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 1
Request for Proposal for establishing e-Governance Systems<br />
A & P Accounts and Pay<br />
List <strong>of</strong> Abbreviations<br />
ADG Additional Director General<br />
AMC Annual Maintenance Contract<br />
ASI <strong>Archaeological</strong> <strong>Survey</strong> <strong>of</strong> <strong>India</strong><br />
BE Budget Estimate<br />
BPEL Business Process Execution Language<br />
CAG Comptroller and Audit General<br />
CDDO Cheque Drawing and Disbursing Officer<br />
CDO Cheque Drawing Officer<br />
CGF Central Government Fund<br />
COTS Commercial Off the Shelf<br />
DDO Drawing and Disbursing Officer<br />
FRS Functional Requirement Specifications<br />
FTP Full Technical Proposal<br />
HLD High Level Design<br />
IEEE Institute <strong>of</strong> Electrical and Electronics Engineers<br />
IMAP Internet Message Access Protocol<br />
ISO International Standards Organization<br />
LLD Low Level Design<br />
MIME Multipurpose Internet Mail Extensions<br />
NIC National Informatics Centre<br />
NISG National Institute for Smart Government<br />
NOC No Objection Certificate<br />
PAO Pay and Account Offices<br />
PKI Public Key Infrastructure<br />
PMU <strong>Project</strong> Management Unit<br />
PoS Point <strong>of</strong> Sale<br />
RFP Request for Proposal<br />
SI System Integrator<br />
SLA Service Level Agreement<br />
SPOC Single Point <strong>of</strong> Contact<br />
SRS S<strong>of</strong>tware Requirement Specifications<br />
VPN Virtual Private Network<br />
WFMC Workflow Management Coalition<br />
SMTP Simple Mail Transfer Protocol<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 2
Request for Proposal for establishing e-Governance Systems<br />
About this Request for Proposal<br />
This document constitutes the Request for Proposal (RFP) for selection <strong>of</strong> System Integrators (SI) by<br />
<strong>Archaeological</strong> <strong>Survey</strong> <strong>of</strong> <strong>India</strong> (ASI). This RFP has been prepared to invite bidders to submit their<br />
proposals for services to assist in the development, automation and implementation <strong>of</strong> an egovernance<br />
system for ASI.<br />
Information used for the preparation <strong>of</strong> this RFP has been made available from relevant and<br />
published sources <strong>of</strong> information. Nonetheless, bidders are required to make their informed<br />
evaluation and decision based on their judgments.<br />
This RFP document contains the entire information that constitutes the requirement as proposed by<br />
ASI in order for qualified bidders to submit their proposals. Any queries or clarifications must be<br />
submitted in the prescribed format and will be addressed to all bidders simultaneously.<br />
This RFP also includes a standard Letter <strong>of</strong> Invitation, Standard Information to SIs, Terms <strong>of</strong><br />
Reference, and General Conditions <strong>of</strong> Contract.<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 3
Request for Proposal for establishing e-Governance Systems<br />
Disclaimer<br />
The information contained in this Request for Proposal document (“RFP”) or subsequently provided to Bidders,<br />
whether verbally or in documentary or any other form by or on behalf <strong>of</strong> the <strong>Archaeological</strong> <strong>Survey</strong> <strong>of</strong> <strong>India</strong>,<br />
Government <strong>of</strong> <strong>India</strong> (“ASI”) or any <strong>of</strong> its employees or advisers, is provided to Bidders on the Terms and<br />
Conditions set out in this RFP and such other terms and conditions subject to which such information is<br />
provided.<br />
This RFP is not an agreement and is neither an <strong>of</strong>fer nor invitation by ASI to the prospective Bidders or any<br />
other person. The purpose <strong>of</strong> this RFP is to provide interested parties with information that may be useful to<br />
them in the formulation <strong>of</strong> their Proposals pursuant to this RFP.<br />
This RFP may not be appropriate for all companies, and it is not possible for ASI, its employees or advisers to<br />
consider the objectives, technical expertise and particular needs <strong>of</strong> each party who reads or uses this RFP. The<br />
assumptions, assessments, statements and information contained in this RFP, may not be complete, accurate,<br />
adequate or correct. Each biddershould therefore conduct its own investigations and analysis and should<br />
check the accuracy, adequacy, correctness, reliability and completeness <strong>of</strong> the assumptions, assessments and<br />
information contained in this RFP and obtain independent advice from appropriate sources.<br />
Information provided in this RFP to the Bidders is on a wide range <strong>of</strong> matters, some <strong>of</strong> which depend upon<br />
interpretation <strong>of</strong> facts. The information given is not an exhaustive account <strong>of</strong> requirements and should not be<br />
regarded as a complete or authoritative statement <strong>of</strong> facts. The specifications laid out in this RFP are indicated<br />
as the minimum requirements whereas the bidders are expected to focus on the objectives <strong>of</strong> the project and<br />
formulate their solution <strong>of</strong>ferings in a manner that enables achieving those objectives in letter as well as spirit.<br />
ASI accepts no responsibility for the accuracy or otherwise for any interpretation or opinion expressed herein.<br />
ASI, its employees and advisers make no representation or warranty and shall have no liability to any person<br />
including any Bidderunder any law, statute, rules or regulations or tort, principles <strong>of</strong> restitution or unjust<br />
enrichment or otherwise for any loss, damages, cost or expense which may arise from or be incurred or<br />
suffered on account <strong>of</strong> anything contained in this RFP or otherwise, including the accuracy, adequacy,<br />
correctness, reliability or completeness <strong>of</strong> the RFP and any assessment, assumption, statement or information<br />
contained therein or deemed to form part <strong>of</strong> this RFP or arising in any way in this Selection Process.<br />
ASI also accepts no liability <strong>of</strong> any nature whether resulting from negligence or otherwise however caused<br />
arising from reliance <strong>of</strong> any Bidderupon the statements contained in this RFP.<br />
ASI may in its absolute discretion, but without being under any obligation to do so, update, amend or<br />
supplement the information, assessment or assumption contained in this RFP.<br />
The issue <strong>of</strong> this RFP does not imply that ASI is bound to select an Bidder or to appoint the Selected Bidder, as<br />
the case may be, for the e-governance project. ASI reserves the right to reject all or any <strong>of</strong> the Proposals<br />
without assigning any reasons whatsoever.<br />
The Bidder shall bear all its costs associated with or relating to the preparation and submission <strong>of</strong> its Proposal<br />
including but not limited to preparation, copying, postage, delivery fees, expenses associated with any<br />
demonstrations or presentations which may be required by ASI or any other costs incurred in connection with<br />
or relating to its Proposal. All such costs and expenses will remain with the Bidder and ASI shall not be liable in<br />
any manner whatsoever for the same or for any other costs or other expenses incurred by an Bidder in<br />
preparation or submission <strong>of</strong> the Proposal, regardless <strong>of</strong> the conduct or outcome <strong>of</strong> the Selection Process.<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 4
Request for Proposal for establishing e-Governance Systems<br />
Contact Persons<br />
National institute <strong>of</strong> Smart Government (NISG) has been appointed as the Advisor to assist ASI in the<br />
preparation <strong>of</strong> this RFP, and the review <strong>of</strong> proposals received, and the selection <strong>of</strong> the eligible SI. All<br />
communication with regard to this RFP must be directed solely to the person and the address<br />
mentioned below. Any communication with a person other than the one mentioned below, would<br />
not be entertained and could result in the Application being considered as non-responsive.<br />
Table 1 Contact Details<br />
Contact Person Mr. B.B. Samaddar<br />
Address for Communication and Submission <strong>of</strong> bid Director – Administration<br />
<strong>Archaeological</strong> <strong>Survey</strong> <strong>of</strong> <strong>India</strong><br />
Janpath, New Delhi - 110011<br />
Phone: +91-11-23018614<br />
Fax: +91-11- 23010789<br />
websiteasi@gmail.com<br />
Bid document availability Bid document can be downloaded from ASI<br />
website :www.asi.nic.in<br />
: www.nisg.org<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 5
Request for Proposal for establishing e-Governance Systems<br />
Important Dates<br />
Following are the key dates for submission and selection process. Address for communication,<br />
collection and submission <strong>of</strong> bid forms are as given earlier.<br />
Table 2: Important Dates<br />
Release <strong>of</strong> RFP (Request for Proposal) Wednesday, 9-Nov-11<br />
Last date for submission <strong>of</strong> clarifications by bidders Wednesday, 16-Nov-11<br />
Pre-Bid Conference Friday, 18-Nov-11<br />
Response to bidder queries Monday, 21-Nov-11<br />
Last date for submission <strong>of</strong> Bids Monday, 12-Dec-11<br />
Pre Qualification Bid opening Monday, 12-Dec-11<br />
Date for opening <strong>of</strong> Technical Bids for qualified bidders Monday, 19-Dec-11<br />
Date for Technical Presentations or Pro<strong>of</strong> <strong>of</strong> Concept Monday, 26-Dec-11<br />
Date for opening <strong>of</strong> Commercial Bids for qualified bidders Monday, 2-Jan-12<br />
Award <strong>of</strong> Contract Monday, 16-Jan-12<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 6
Request for Proposal for establishing e-Governance Systems<br />
[insert: Location and Date]<br />
Dear [insert: Name <strong>of</strong> SI]:<br />
Dear Mr/Ms<br />
Request for Proposal<br />
The Archeological <strong>Survey</strong> <strong>of</strong> <strong>India</strong> (ASI) invites proposals to provide the following services:<br />
Development <strong>of</strong> automation systems as a part <strong>of</strong> the e-governance initiative <strong>of</strong> Archeological<br />
<strong>Survey</strong> <strong>of</strong> <strong>India</strong> (ASI) to include e-mailing systems, finance and budgeting systems, and eticketing<br />
solutions.<br />
This RFP has been addressed to the following shortlisted SIs:<br />
[Insert: List <strong>of</strong> Shortlisted SIs]<br />
ASI invites eligible System Integrators (SI) to indicate their interest in providing the services.<br />
Interested SIs must provide information indicating that they are qualified to perform the services<br />
(brochures, description <strong>of</strong> similar assignments, experience in similar conditions, availability <strong>of</strong><br />
appropriate skills among staff, etc.). SIs may associate to enhance their qualifications.<br />
An SI will be selected in accordance with the procedures set out in Volume 2 <strong>of</strong> this document.<br />
Interested SIs may obtain further information at the address mentioned below from 9:00 a.m. to<br />
6:00 p.m.<br />
Request for Proposal must be submittedto the address mentioned below by [insert date].<br />
It is not permissible to transfer this invitation to any other company.<br />
A company will be selected on the basis <strong>of</strong> evaluation <strong>of</strong> Quality <strong>of</strong> the proposal, as described in this<br />
RFP, in accordance with the rules set forth in the Guidelines.<br />
The RFP includes the following documents:<br />
• Volume 1: <strong>Project</strong> <strong>Requirements</strong><br />
• Volume 2: Commercial and bidding terms<br />
• Volume 3: Contractual and legal specifications<br />
Yours sincerely<br />
Archeological <strong>Survey</strong> <strong>of</strong> <strong>India</strong><br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 7
Request for Proposal for establishing e-Governance Systems<br />
1 Introduction and Background<br />
The <strong>Archaeological</strong> <strong>Survey</strong> <strong>of</strong> <strong>India</strong> (ASI), is a well established organization for archaeological<br />
research under the Ministry <strong>of</strong> Culture, and plays a significant role in protecting the cultural heritage<br />
<strong>of</strong> the Country. Conservation <strong>of</strong> ancient monuments, archaeological sites and excavations remains<br />
<strong>of</strong> national importance and are the prime concerns <strong>of</strong> the ASI.<br />
Established in 1861, over the years, ASI’s scope has expanded to a large number <strong>of</strong> fields such as<br />
preservation, conservation, architectural studies, epigraphy, horticultural and environmental upgradation<br />
and underwater archaeology. ASI regulates all archaeological activities in the country as<br />
per the provisions <strong>of</strong> the Ancient Monuments and <strong>Archaeological</strong> Sites and Remains Act, 1958. ASI<br />
also regulates Antiquities and Art Treasure Act, 1972. At present, ASI protects 3,675 monuments<br />
including 18 World Heritage Cultural Properties besides, and also maintains 41 museums around the<br />
country.<br />
ASI has now envisioned the development <strong>of</strong> an integrated IT enabled e-governance system across<br />
the departments in ASI in order to ensure transparent, easy, efficient and accurate availability <strong>of</strong><br />
information, and facilitation <strong>of</strong> transactions.<br />
With anintent <strong>of</strong> providing a robust system, ASI has decided to revamp its current systems and core<br />
functions through e-governance solutions by leveraging Information and Communication Technology<br />
across various departments in the organization. In this context, ASI has engaged National Institute<br />
for Smart Government (NISG) for consulting services, which includea detailed study <strong>of</strong> existing ASI<br />
operations and to propose feasible solutions that can be adopted by ASI in the near future.The<br />
entire project is divided into three phases:<br />
Phase I: Consulting and RFP formulation (by NISG)<br />
Phase II: Implementation <strong>of</strong> <strong>Project</strong> (by SI)<br />
Phase III: <strong>Project</strong> Monitoring and Review by PMU to be established by ASI<br />
As a part <strong>of</strong> the first phase, ASI is floating this RFP to receive responses from eligible bidders, and<br />
evaluation and selection <strong>of</strong> the most appropriate SI.<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 8
Request for Proposal for establishing e-Governance Systems<br />
2 About Archeological <strong>Survey</strong> <strong>of</strong> <strong>India</strong><br />
ASI is divided into 24 Circles (refer Annexure1 for the Circle Details) for the maintenance <strong>of</strong> ancient<br />
monuments, archaeological sites which remains <strong>of</strong> national importance. ASI carries out elaborate<br />
surveys <strong>of</strong> antiquarian remains in the country and protects monuments and sites. The Organization<br />
has a large work force comprising <strong>of</strong> trained archaeologists, conservators, epigraphist, architects and<br />
scientists for conducting archaeological research projects through its Circles, Museums, Excavation<br />
Branches, Prehistory Branch, Epigraphy Branches, Science Branch, Horticulture Branch, Building<br />
<strong>Survey</strong> <strong>Project</strong>, Temple <strong>Survey</strong> <strong>Project</strong>s and Underwater Archaeology Wing.<br />
The Circles carry out archaeological fieldwork, research activities and implement various activities<br />
which include:<br />
Extensive survey <strong>of</strong> antiquarian remains in villages <strong>of</strong> <strong>India</strong>.<br />
Exploration <strong>of</strong> archaeological sites and documentation <strong>of</strong> sculptures.<br />
Excavation <strong>of</strong> archaeological sites.<br />
Conservation and day-to-day maintenance <strong>of</strong> protected monuments.<br />
Providing basic facilities at the monuments for tourists.<br />
Issuing <strong>of</strong> NOC for any sort <strong>of</strong> construction, additions and alterations to existing structures or<br />
new constructions within regulated area <strong>of</strong> the protected monuments.<br />
Issuing permission for filming, photography and cultural programs at the protected monuments.<br />
Organizing public awareness programs on various occasions like Word Heritage Day, World<br />
Heritage Week, Museum Day and other important occasions.<br />
Registration <strong>of</strong> antiquities and issuing non-antiquity certificates.<br />
Interaction with various universities and research institutions.<br />
Currently there are 116 ticketed monuments that exist in the 24 Circles. Based on available<br />
information for the year 2009, approximately 32 million visitors have visited these monuments. The<br />
visitor history for these monuments is provided in Annexure 2.<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 9
Request for Proposal for establishing e-Governance Systems<br />
3 Current Status and Vision for e-Governance<br />
<strong>Project</strong> Vision<br />
ASI proposes e-Governance initiative to harness the power <strong>of</strong> ICT Platform for its vision<br />
”To ensure transparent, easy, efficient and accurate availability <strong>of</strong> information and facilitation <strong>of</strong><br />
transactions”<br />
In order to streamline its processes and increase efficiency and effectiveness <strong>of</strong> services, ASI has<br />
undertaken a comprehensive exercise to implement ICT based e-Governance across all the<br />
departments <strong>of</strong> the organization. The ICT based e-Governance is also aimed to bring in transparency<br />
and sustainability <strong>of</strong> the processes and systems.<br />
<strong>Project</strong> Objectives<br />
The key objectives <strong>of</strong> this e-governance initiative are:<br />
Design and implement processes and applications that help ASI achieve the project vision<br />
To increase the efficiency and better monitoring and administration for effective decision<br />
making<br />
Developing a single and integrated view <strong>of</strong> ASI’s information system across all departments<br />
and <strong>of</strong>fices<br />
Standards based approach to enable integration<br />
The following arekey components which would constitute envisioned e-governance ecosystem:<br />
<strong>Archaeological</strong>Data Management: ASI has vast amounts <strong>of</strong> data that has be processed and<br />
managed. Over the years, Data Management will acquire significance since huge amounts <strong>of</strong><br />
data are required to be acquired, digitized and maintained<br />
Electronic Communication: Proper communication between various departments plays a vital<br />
role in effective running <strong>of</strong> the organization. Communication continues to be mainly through<br />
paper, and no coherent means <strong>of</strong> faster electronic communication exist today, slowing down the<br />
process and ease <strong>of</strong> decision making and information dissemination.<br />
Computerized Financial Planning and Budgeting Systems: Budget planning and controls remain<br />
a vital part <strong>of</strong> the entire financial planning and accounts functions <strong>of</strong> ASI.While adequate<br />
processes exist, the planning, deployment and monitoring <strong>of</strong> funds remains a paper based<br />
system, lending it to inordinate delays in data collection, and decision making.<br />
Computerized system for management <strong>of</strong> Conservation & Excavation Works including various<br />
aspects <strong>of</strong> planning, approving, notification and monitoring with seamless integration <strong>of</strong> Funds<br />
management system.<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 10
Request for Proposal for establishing e-Governance Systems<br />
ASI is interested in automating all its functions, and as a part <strong>of</strong> this process, has identified three<br />
prioritizedmodules <strong>of</strong> Electronic Communication, E-ticketing solutions, and Finance and Budgeting<br />
Systems as the areas to be automated. These will eventually be integrated with other systems that<br />
are proposed to be set up.<br />
The sections below detail the current state assessment <strong>of</strong> the processes being followed:<br />
3.1 Electronic Communication<br />
3.1.1 ASI has no common platform for messaging.Most <strong>of</strong> the communications is paper<br />
based. Although an email system hosted by NIC exists, it is not extensively used.<br />
Currently, ASI staff mainly use public email accounts such as Gmail, Yahoo, etc. for<br />
communication. Even where information is transmitted through emails, documents<br />
which are not received in physical format are not considered as authentic.<br />
3.2 E-Ticketing<br />
3.2.1 ASI currently has multiple means <strong>of</strong> issuing tickets for monuments, most <strong>of</strong> which are<br />
PoS based systems.Ticket issuance currently has the following typical characteristics:<br />
3.2.1.1 Tickets are typically printed centrally at <strong>India</strong> Security Press, Nashik, and<br />
issued to each circle based on indents received at the Headquarters.<br />
3.2.1.2 At each monument, the ticket issuing counters are usually separate from the<br />
ticket checking locations.<br />
3.2.1.3 Many monuments have multiple ticketing counters and multiple ticket<br />
checking entrances. A visitor could purchase a ticket from one counter and<br />
decide to enter from any <strong>of</strong> the ticket checking entrances, and vice versa.<br />
3.2.1.4 Tickets could be issued by multiple ticket issuers for the same monument,<br />
each <strong>of</strong> which could be a valid ticket format.<br />
3.2.1.5 Group bookings are possible, whereby a visitor could be issued multiple tickets<br />
for the same monument, each ticket being used for a separate visitor. A<br />
purchaser <strong>of</strong> ticket may therefore not necessarily be the end user <strong>of</strong> the ticket.<br />
3.2.1.6 Some tickets are available which provide a visitor access to multiple<br />
monuments on the same ticket.<br />
3.2.1.7 Usually, the ticket checking staff either collect the ticket altogether, or tear<br />
and retain a counterfoil with the stub being returned to the visitor.<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 11
Request for Proposal for establishing e-Governance Systems<br />
3.2.1.8 No mechanism exists to identify a ticket with a ticket holder either at the<br />
issuing point or at the checking point.<br />
3.2.1.9 The ticket issuers as well as the ticket checkers are typically Class IV<br />
employees <strong>of</strong> ASI who are expected to perform this function in addition to<br />
their other routine functions. In many cases, this is not their primary job.<br />
3.2.1.10 There are no fool-pro<strong>of</strong> mechanisms to ensure that only ticket holders enter a<br />
monument site. Likewise, there is no tracking mechanism to see whether<br />
every issued ticket is used at a monument site.<br />
3.2.1.11 The reconciliation <strong>of</strong> payments for tickets to issuance <strong>of</strong> tickets is currently<br />
manual. In many instances, registers are maintained to tally the amounts.<br />
Payments are not recorded in a system, and all deposits are made manually at<br />
the end <strong>of</strong> the day, at the local branch <strong>of</strong> the bank.<br />
3.2.1.12 In some cases, receipts are split between ASI and the local civic body with<br />
separate submissions to each parties’ banks.<br />
3.3 Financial Planning and Budgeting Systems<br />
3.3.1 The Financial Planning and Budgeting systems currently in place are largely<br />
manual. Some <strong>of</strong> the reports are prepared in MS Excel for further collation and<br />
reporting. However, the process is laborious and manual. The key components <strong>of</strong><br />
the finance and budgeting process are as follows:<br />
3.3.2 Budget: Every year ASI submits Budget Estimate (BE) to the Ministry <strong>of</strong> Culture.<br />
The Circle Officer prepares Budget Estimatesthat are further broken down into<br />
plan and non-plan expenditure. Based on the BE and Last Expenditure Statement,<br />
the Ministry <strong>of</strong> Culture allocates funds for the current financial year to ASI. This<br />
fund is directly deposited to the bank <strong>of</strong> the concerned <strong>of</strong>fice.<br />
3.3.3 At the same time, the details <strong>of</strong> the fund allocation will be communicated to ASI<br />
Head Office. ASI Head Office in turn, communicates this information to the Branch<br />
Offices. Each <strong>of</strong>fice has one account (a/c number) with the bank. The booking<br />
amount is available in the respective account only during the current financial year.<br />
3.3.4 The ASI Head Office has the right to reallocate / shuffle funds between the Major<br />
Heads / Minor Heads / Sub Heads / Offices during the current financial year.<br />
3.3.5 Expenses:The expenses are maintained Major Head-wise, Minor Head-wise, Sub<br />
Head-wise and Detail Head-wise.The bill is prepared by Cashier and submitted to<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 12
Request for Proposal for establishing e-Governance Systems<br />
the Drawing and Disbursing Officer (DDO). There are approximately 120 DDO<br />
<strong>of</strong>fices all across the country. The DDO scrutinizes and approves the bill which is<br />
then forwarded to Cheque Drawing Officer (CDO) who sanctions and issues the<br />
Cheque against the bill. The Cheque is forwarded to the Cashier through the DDO.<br />
Cheques for third parties are handed over to the company / person.<br />
3.3.6 There are two Pay and Accounts Offices (PAO) working at ASI. One <strong>of</strong> the <strong>of</strong>fices<br />
islocated in Delhi and the other one is at Hyderabad. The <strong>of</strong>fice <strong>of</strong> the DDO and<br />
CDO may be located at different places. DDOs in the North <strong>of</strong> <strong>India</strong> sending the<br />
letter <strong>of</strong> account (periodical expense details) to PAO at Delhi while their<br />
counterparts in the South send the letter <strong>of</strong> account to Hyderabad.<br />
3.3.7 The DDO, CDO and PAO try to maintain the account for the expenses not to exceed<br />
the limit under each Head. All <strong>of</strong>fices submit Expenditure Statements periodically<br />
in prescribed formats.<br />
3.3.8 Revenue:Revenue yielding from ticketing, book publishing, etc. are collected by<br />
the cashier / counter clerk and deposited in the bank on the next working day.<br />
Revenue Accounting System encompasses various stages from recording the<br />
initial transactions in challans to the preparation <strong>of</strong> Annual Accounts. The<br />
monthly accounts are compiled by the Circle Offices on the basis <strong>of</strong> challans<br />
submitted by the Bank to ASI, and submitted to Principal Accounts Office. The<br />
Principal Accounts Office consolidates the Accounts received from all the Circle<br />
Offices and sends them to the Office <strong>of</strong> Controller General <strong>of</strong> Accounts.<br />
3.3.9 The overall financial planning process is described through this flow-chart:<br />
Individual<br />
Bill<br />
Preperation<br />
by Cashier<br />
Cheque<br />
If 3 rd Party<br />
Cheque<br />
Yes<br />
Cash<br />
Reaches to<br />
Concern Office /<br />
Person<br />
No<br />
Cash<br />
Bill<br />
Cash<br />
Checks Fund availability<br />
and approval <strong>of</strong> D.D.O.<br />
BANKS<br />
Is It Direct Cr.<br />
Ind. a/c/?<br />
EXPENDITURE PROCES<br />
Individual a/c<br />
Cheque<br />
Checks Fund availability<br />
and approval <strong>of</strong> C.D.O.<br />
If bill a amount exceeds<br />
the limit <strong>of</strong> D.D.O.<br />
Approval <strong>of</strong><br />
P.A.O.<br />
Expense<br />
Details<br />
Booking /<br />
accounting Head<br />
wise expenses<br />
details<br />
Bidders are required to make their own assessment as to the correctness or completeness <strong>of</strong> the<br />
above shown financial accounting process.<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 13<br />
Period Expense Statement<br />
ASI HQ
Request for Proposal for establishing e-Governance Systems<br />
4 <strong>Project</strong> Vision and Phases<br />
4.1.1 ASI has planned for a phased implementation <strong>of</strong> e-governance initiatives across the<br />
Country. All e-governance initiatives have been categorized into 3 broad phases,<br />
each <strong>of</strong> which would be implemented in tandem, in order to achieve the overall<br />
objective <strong>of</strong> setting up an integrated e-governance mechanism.<br />
4.1.2 This RFP is mainly intended to elicit responses on the three areas <strong>of</strong> electronic<br />
communication, accounting, finance and budgeting systems, and e-ticketing<br />
solutions. ASI is currently conducting a separate initiative through a National<br />
Mission on Monuments and Antiquities for the creation <strong>of</strong> a comprehensive record<br />
in the form <strong>of</strong> database <strong>of</strong> archaeological resources in terms <strong>of</strong> built heritage, sites<br />
and antiquities that can be referred.<br />
4.1.3 For the e-ticketing solution, a staggeredimplementation is proposed at a select<br />
number <strong>of</strong> locations which would be followed by a larger geographical roll-out<br />
across the entire country. (Refer the scope <strong>of</strong> work for more details)<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 14
Request for Proposal for establishing e-Governance Systems<br />
5 Scope <strong>of</strong> Work for the System Integrator<br />
5.1.1 The Scope <strong>of</strong> Work for the e-governance systems proposed through this RFP<br />
requires the simultaneous solution design, project planning, process mapping,<br />
possible pro<strong>of</strong> <strong>of</strong> concept, system development, acceptance, documentation, and<br />
user training. A generic description <strong>of</strong> the requirements in each <strong>of</strong> these phases is<br />
as follows:<br />
5.2 Phase 1: <strong>Project</strong> Planning Process<br />
5.2.1 The implementation <strong>of</strong> the project modules shall be completed within 12 months<br />
from the date <strong>of</strong> the selection <strong>of</strong> the SI in order to ensure smooth implementation,<br />
a robust project planning process is expected to be set up by the SI. This would<br />
include dovetailing the three Modules required to be implemented by the SI,<br />
ensuring location-wise roll-outs being provided for, migration plans, and overall<br />
planning to ensure objectives <strong>of</strong> ASI are achieved. The project plan would be<br />
submitted to ASI for their approval, and would be the basis for continuous<br />
evaluation and monitoring <strong>of</strong> project health.<br />
5.2.2 For planning purposes, the SI would be expected to implement a project planning<br />
tool which would also enable review and reporting to ASI.<br />
5.3 Phase 2: <strong>Requirements</strong> Analysis<br />
5.3.1 This is the initial phase in the development <strong>of</strong> the project. The analysis part<br />
includes complete understanding <strong>of</strong> the project, gathering its requirements, logical<br />
dividing <strong>of</strong> the components involved and deciding the modules to which it is being<br />
split into. The timeline required for each module also needs to be defined in this<br />
phase. The gathering <strong>of</strong> requirements also includes gathering database table<br />
information. SI shall gather and prepare a S<strong>of</strong>tware <strong>Requirements</strong> Specifications<br />
(SRS) document based on the project requirements in a comprehensive manner. It<br />
is expected that SI shall make its own assessment in consultation with ASI and its<br />
representatives.<br />
5.3.2 By the end <strong>of</strong> this phase, documentation needs to be completed for the following:<br />
5.3.2.1 All clarifications that arise in the requirements analysis need to be<br />
documented. The answers that are obtained also need to be<br />
documented in this phase.<br />
5.3.2.2 <strong>Requirements</strong> specification shall contain all the gathered<br />
requirements that need to be well documented.By the end <strong>of</strong> this<br />
phaseSI would need to obtain a final sign-<strong>of</strong>f from ASI on the<br />
requirements gathered and SRS before proceeding with design and<br />
development <strong>of</strong> the solution.<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 15
Request for Proposal for establishing e-Governance Systems<br />
It must be noted that the requirements and specifications provided as a part <strong>of</strong> this RFP are intended<br />
to describe salient aspects <strong>of</strong> the SI’s scope <strong>of</strong> work and provide sufficient understanding to the<br />
bidders for preparing proposals and should not be considered as exhaustive. The requirements will<br />
have to be detailed further as a part <strong>of</strong> SRS preparation.<br />
5.4 Phase 3: Solution Design<br />
5.4.1 The selected SI is required to study the existing systems and recommend the most<br />
suitable solution, taking into account the current state <strong>of</strong> automation <strong>of</strong> ASI and its<br />
future vision. This would, inter alia, entail the following:<br />
A review <strong>of</strong> existing systems<br />
Review <strong>of</strong> potential future technological changes, and their impact on any<br />
possible solution<br />
Examination <strong>of</strong> best possible alternative designs<br />
Preparation <strong>of</strong> a solutions document<br />
5.4.2 The database design which includes the structure <strong>of</strong> tables and also normalization<br />
<strong>of</strong> tables need to be prepared. The flow chart that shows involvement <strong>of</strong> tables<br />
and the integrity constraints on them also needs to be specified. All the database<br />
schema/tables should be created in this phase.<br />
5.4.3 The architectural design <strong>of</strong> the system and the way various systems/modules<br />
interact with each other need to be documented.After the detailed planning the<br />
initial pseudo-code and all possible test cases <strong>of</strong> various modules including<br />
designing <strong>of</strong> test strategy and test plan that need to be fulfilled should be<br />
documented. SI shall also be responsible for conducting the unit testing,<br />
integration testing, load testing and performance testing.<br />
5.5 Phase 4: System Development<br />
5.5.1 The SI shall be expected to develop some <strong>of</strong> the systems, or as necessary, s<strong>of</strong>tware<br />
or tools which could help in connecting <strong>of</strong>f-the-shelf third party s<strong>of</strong>tware that are<br />
proposed to be implemented. Where possible, the SI would be expected to use<br />
existing and tested code, in order to optimize the development process.<br />
This phase includes code development for the project.<br />
5.6 Phase 5: Solution Prototype<br />
5.6.1 The SI will be required to demonstrate a prototype prior to a full implementation,<br />
especially for solutions that require custom development for implementation at<br />
ASI locations. Every prototype must be demonstrated and approved by ASI prior to<br />
its implementation. The prototype phase would be used to evaluate whether the<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 16
Request for Proposal for establishing e-Governance Systems<br />
proposed solution meets all the requirements <strong>of</strong> the project. For proposed<br />
solutions which are implemented using <strong>of</strong>f-the-shelf solutions available from<br />
reputed vendors, a prototype may not be required.<br />
5.7 Phase 6: Entry <strong>of</strong> Historical Data<br />
5.7.1 SI shall be responsible for digitization and migration <strong>of</strong> data for financial planning<br />
and budgeting module from existing data sources to the ASI’s application being<br />
developed as a part <strong>of</strong> this project, to provide for availability <strong>of</strong> all data for the<br />
current financial year.<br />
5.8 Phase 7: Testing and Acceptance<br />
During this phase, SI shall conduct various types <strong>of</strong> testing including:<br />
5.8.1 Application Functional Testing<strong>of</strong> the e‐governance systems shall be carried out to<br />
validate whether the application meets the specified functional requirements<br />
covering the work flows, navigations, and business and data Validation rules for<br />
the defined user categories with access rights. The functional testing should be<br />
done following black box approach and using end‐to‐end user scenarios.<br />
5.8.2 Application Usability Testing shall include systematic observation under controlled<br />
conditions to determine how well users can use the application. The proposed<br />
systems are likely to be used by users <strong>of</strong> different levels <strong>of</strong> computer knowledge.<br />
Usability testing will ensure that the all types <strong>of</strong> users are comfortable to use the<br />
system. This shall be done by using defined international standards which<br />
recommend extensive user interaction and analysis <strong>of</strong> userbehavior for a defined<br />
task.<br />
5.8.1 Performance Testing <strong>of</strong> the system shall be done to ensure that system is capable<br />
<strong>of</strong> handling defined user as well as transactional load. The performance testing <strong>of</strong><br />
the e‐governance system will include measuring the response time <strong>of</strong> the system<br />
for defined scenarios. Also the manner/ trend in which performance changes with<br />
load will determine the scalability <strong>of</strong> the e‐governance systems.<br />
5.8.2 Application Security Testing conducted to unearth various application security<br />
vulnerabilities, weaknesses and concerns related to Data /Input Validation,<br />
Authentication, Authorization /Access Control, Session Management, Error<br />
Handling, Use <strong>of</strong> Cryptography, etc. Typical issues which may be discovered in an<br />
application security testing include Cross‐site scripting, Broken ACLs/Weak<br />
passwords, Weak session management, Buffer overflows, Forceful browsing,<br />
Form/hidden field manipulation, Command injection, SQL injection, Cookie<br />
poisoning, Insecure use <strong>of</strong> cryptography, Mis‐configurations, Well‐known platform<br />
vulnerabilities, Errors triggering sensitive information leak etc.<br />
5.8.3 Penetration Testing shall be done remotely from public domain (Internet) and also<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 17
Request for Proposal for establishing e-Governance Systems<br />
can be done from internal network to find out exploitable vulnerabilities. A series<br />
<strong>of</strong> tests should be conducted such as information gathering from public domain,<br />
port scanning, system fingerprinting, service probing, vulnerability scanning,<br />
manual testing, password cracking etc. using state‐<strong>of</strong>‐the‐art tools (commercial<br />
and open source) and other techniques shall be used with the objective <strong>of</strong><br />
unearthing vulnerabilities and weaknesses <strong>of</strong> the overall e‐governance systems and<br />
its underlying IT infrastructure.<br />
5.8.4 The test cases which were earlier designed during planning phase need to be<br />
executed in this phase. This phase includes Unit testing, Integration testing, and<br />
also testing for security. The SI should ensure that:<br />
The test results are documented<br />
Code review checklistsare filled up and the code is reviewed and verified. This<br />
ensures that all the coding conventions are followed correctly.<br />
Test cases and the results need to be documented and demonstrated.<br />
5.8.5 ASI may decide to appoint a third party audit agency to conduct an audit <strong>of</strong> the<br />
solution to review all aspects <strong>of</strong> the project and certify compliance with RFP before<br />
the system is rolled out. SI shall provide all necessary support, including setting up<br />
the required test environment, making seating arrangements and providing<br />
suitable access to computer & peripherals, to the agency for conducting<br />
acceptance testing.<br />
5.9 Phase 8: Documentation<br />
5.9.1 The SI is expected to deliver complete user documentation in the form <strong>of</strong><br />
electronic documents to enable users to understand and use the systems. The<br />
documents shall include user manual, administration manual, security manual,<br />
application support guide that would contain, inter alia, the screenshots and<br />
explanation indicating how the tool/s<strong>of</strong>tware is used and how the solution has<br />
been implemented. The entire documentation shall be as per industry best<br />
practices and acceptable standards (e.g. IEEE/ISO specifications for<br />
documentation).<br />
5.10 Phase 9: User Training, Operations, and Maintenance<br />
5.10.1 The SI is expected to provide extensive user training post implementation.<br />
5.10.2 Maintenance (AMC) : SI shall be fully responsible for maintenance <strong>of</strong> the ASI’s<br />
application, data center and other IT related infrastructure being established by SI<br />
as a part <strong>of</strong> this project. SI shall also deploy adequate staff for the preventive<br />
maintenance on a regular basis or a pre-defined frequency as mutually decided<br />
between ASI and the SI.<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 18
Request for Proposal for establishing e-Governance Systems<br />
5.10.3 In the case <strong>of</strong> the e-ticketing solution, the SI would be required to handle the<br />
ticketing solution by providing adequate manpower during the first six months<br />
post-implementation.<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 19
Request for Proposal for establishing e-Governance Systems<br />
6 Implementation model<br />
In the case <strong>of</strong> the e-ticketing solution, the SI would be required to handle the ticketing solution by<br />
providing adequate manpower during the first six months post-implementation. At the end <strong>of</strong> this<br />
period, ASI would decide whether to continue with the SIs staff on a new contract, or hire fresh<br />
persons who would provide the ticketing solution. However such a model will allow ASI to address<br />
important factors such as ASI’s ownership <strong>of</strong> the e-governance solution and to benefit from<br />
specialized expertise <strong>of</strong> private sector.<br />
In any event, the SI would be responsible for both training as well as ensuring that the persons who<br />
are recruited for this purpose are adequately trained, as a part <strong>of</strong> the capacity building<br />
requirements.<br />
The following responsibility matrix depicts the broad aspects <strong>of</strong> the implementation model:<br />
Sl.No. Aspect<br />
1. Implementation,<br />
deployment and operation<br />
<strong>of</strong> the project<br />
2. Testing <strong>of</strong> application<br />
modules<br />
3. Ownership <strong>of</strong> all IT<br />
infrastructure, application,<br />
system s<strong>of</strong>tware and all<br />
related components<br />
4. Audit& Certification <strong>of</strong> the<br />
application prior to go-live<br />
Responsibility /Ownership<br />
SI ASI<br />
Yes -<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 20<br />
Yes<br />
Server Side<br />
Client Side<br />
5. Program Governance Yes (through the Program<br />
Manager)<br />
6. Procurement and setup <strong>of</strong><br />
client end hardware,<br />
s<strong>of</strong>tware and LAN<br />
- Yes (through a third party<br />
audit agency)<br />
Yes<br />
Yes (through a PMU)
Request for Proposal for establishing e-Governance Systems<br />
7 Key Deliverables<br />
The details with regard to the key deliverables<strong>of</strong> electronic communication systems, e-ticketing<br />
solutions and computerized financial planning and budgeting solutions, the following section<br />
provides greater details about each <strong>of</strong> the modules.<br />
7.1 E-Governance <strong>Project</strong> Application Development and Infrastructure Deployment<br />
The Key Deliverables consist <strong>of</strong> the following:<br />
7.1.1 E-Governance <strong>Project</strong> Application Development<br />
i. Requirement gathering and Study <strong>of</strong> existing applications<br />
ii. The SI will be required to carry out a preliminary study <strong>of</strong> the requirements, before<br />
drafting the systems requirements and specifications<br />
iii. System Design and preparation <strong>of</strong> S<strong>of</strong>tware <strong>Requirements</strong> Specifications<br />
iv. The System design and SRS shall contain the objectives and scope <strong>of</strong> the system, the<br />
various levels <strong>of</strong> requirements, the process model, data model, data dictionary, etc<br />
v. Creation and maintenance <strong>of</strong> <strong>Requirements</strong> Traceability Matrix<br />
vi. Development <strong>of</strong> Prototype and Functional acceptance on Prototype<br />
vii. Development <strong>of</strong> High Level Design (HLD)<br />
viii. Develop a logical view <strong>of</strong> the solution to meet the user requirements, comprising <strong>of</strong><br />
functional architecture <strong>of</strong> the application and the changes/new database design.<br />
ix. Development <strong>of</strong> Detailed Design (Low Level Design – LLD)<br />
x. Creation <strong>of</strong> Test Plans based on the FRS (Functional Requirement Specifications) and<br />
SRS documents<br />
xi. Development <strong>of</strong> User Acceptance Test Plans<br />
xii. Full-Scale Development / Procurement, Implementation, Customization <strong>of</strong> S<strong>of</strong>tware<br />
Applications<br />
xiii. Data Migration from legacy applications<br />
xiv. Development <strong>of</strong> Testing and User Acceptance<br />
7.1.2 E-Governance <strong>Project</strong> Application related trainings<br />
i. Training Need Analysis<br />
ii. Training Content Development<br />
iii. Conducting Training<br />
iv. Conducting Executive Workshops<br />
v. Evaluating Training Feedback and tuning training content / methodology<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 21
Request for Proposal for establishing e-Governance Systems<br />
7.2 E-Governance <strong>Project</strong> Application and Infrastructure Maintenance<br />
The key deliverables consist <strong>of</strong> the following:<br />
7.2.1 E-Governance <strong>Project</strong> Application Maintenance<br />
i. System Administration and AMC (Annual Maintenance Contract) administration<br />
ii. Monitoring, maintenance and management <strong>of</strong> all IT applications<br />
iii. Performance Management and tuning <strong>of</strong> the applications, Infrastructure and<br />
environment<br />
iv. Development / customization / fixes <strong>of</strong> additional requirements, change requests and<br />
incidents reported by ASI users.<br />
7.2.2 IT infrastructure management<br />
i. Supply, Installation, Integration and Commissioning <strong>of</strong> enabling infrastructure<br />
comprising <strong>of</strong> Servers.<br />
ii. Complete management <strong>of</strong> enabling infrastructure <strong>of</strong> Servers, Storage and Security<br />
equipment along with associated peripherals, accessories and services at sites.<br />
iii. Incident Management, Problem management, Root Cause Analysis (RCA), Business<br />
continuity management, availability management, backup management, security<br />
management, disaster recovery etc.<br />
7.2.3 Technical Support and Helpdesk Service<br />
i. Provision <strong>of</strong> On-site technical support<br />
7.3 E- Ticketing Operations<br />
7.3.1 The SI is required to operate the manned e-ticketing solution for a minimum period<br />
<strong>of</strong> 6 months from the date <strong>of</strong> Go Live. Such operations will be required across all<br />
the 10 proposed monuments where e-ticketing is proposed in the pilot program.<br />
7.3.2 During this period, SI will be required to train existing staff at the counters, if<br />
required, with the primary responsibility for ticket issuance with the SI.<br />
7.3.3 At the end <strong>of</strong> the six month period, or any time during this period, ASI may decide<br />
to retain the existing ticketing staff <strong>of</strong> the SI for a limited period <strong>of</strong> time in order to<br />
transition to the new staff, and subsequently either request for a contract<br />
extension <strong>of</strong> the SI, or call for new staffing at the ticket counters. In such an event,<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 22
Request for Proposal for establishing e-Governance Systems<br />
the SI will be responsible for training and handholding <strong>of</strong> this solution.<br />
7.3.4 The responsibility for management <strong>of</strong> the hardware, the s<strong>of</strong>tware and the<br />
infrastructure would also be with the SI.<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 23
Request for Proposal for establishing e-Governance Systems<br />
8 Functional <strong>Requirements</strong><br />
The e-governance project application development and infrastructure deployment is required across<br />
three Modules: Electronic Communication Systems, E-ticketing Solutions, and Financial Planning and<br />
Budgeting Systems. The functional requirement for each <strong>of</strong> these systems is detailed below:<br />
8.1.1 Electronic Communication Systems<br />
8.1.1.1 Functional requirements<br />
Electronic Communication solutions have to fulfill the basic<br />
capability <strong>of</strong> messaging solution with good backup solutions, security<br />
solutions, administrator solutions, archiving solution, with efficient<br />
anti spam and antivirus solution. It should also contain feature rich<br />
messaging solutions. The messaging solution should be reliable,<br />
efficient and scalable. E-mailing shall be the main communication<br />
tool for the various departments within ASI.<br />
The solution will be hosted by the SI either out <strong>of</strong> a third party<br />
solution or out <strong>of</strong> its own servers. In any event, the solution must be<br />
secure, and must contain adequate features to prevent loss <strong>of</strong><br />
information, leakage <strong>of</strong> confidential information, and fraud.<br />
The main functional requirements are as follows:<br />
1. Client side requirements:<br />
Client/Server based solution: A process running on the client and an<br />
associated process running on the server system which does not<br />
require that the client establish a remote file system on the server.<br />
The client and server communicate using a mail access protocol<br />
(e.g., IMAP) instead <strong>of</strong> a file sharing access protocol in order to<br />
maximize efficient communication between the client and server<br />
and to minimize system demand on the client, server, and the<br />
network between them.<br />
Client configuration which supports multiple users in public access<br />
environment. Individual users mail should be the same (same<br />
interface, same configuration, same mail) from any machine used to<br />
access that mail.<br />
Should support access <strong>of</strong> email from various interfaces like email<br />
client (e.g. Outlook); browser (web access) or mobile phones (using<br />
Activesync/ IMAP etc.) without any additional third party<br />
components.<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 24
Request for Proposal for establishing e-Governance Systems<br />
Should use standard operating system network s<strong>of</strong>tware (standard<br />
TCP/IP protocol implementations) for each client platform<br />
Quality <strong>of</strong> the user interface must include:<br />
o Functionality, flexibility, and ease <strong>of</strong> use<br />
o Minimal training requirements for end users<br />
o Spell checking<br />
o Drag and drop enclosures<br />
Standard mail functions must include:<br />
o Printing capabilities<br />
o Auto-response features for vacation periods, including the<br />
ability to retain mail received during this period<br />
o Aut<strong>of</strong>orwarding<br />
Reasonably effective authentication for outgoing mail.<br />
Client mailbox management tools which include the ability to search<br />
and browse stored messages.<br />
User can change his/her own password.<br />
Reasonable network performance with minimal network impact.<br />
This should include reasonable performance when accessed<br />
remotely.<br />
Reasonable use <strong>of</strong> resources, such as memory and disk space, on<br />
different platforms.<br />
Ability to download email and enclosures to workstation or hard<br />
disks.<br />
Should have capability for filtering/scripting/rules-based mail<br />
handling, e.g., ability to easily filter incoming mail to separate<br />
mailboxes by subject or by sender.<br />
Should have capability for return receipt (delivery notification<br />
options should be available, e.g., delivery, open, etc. on the same<br />
system.<br />
Should permit recall <strong>of</strong> sent but unopened messages on local<br />
system.<br />
2. Server side requirements:<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 25
Request for Proposal for establishing e-Governance Systems<br />
Should accommodate accounts for all employees at ASI (total =<br />
2,000).<br />
Should have the capability to be scaled up to support 10,000 users.<br />
Should have efficient administrative tools for handling large<br />
numbers <strong>of</strong> accounts (e.g., automated account generation, mass<br />
account terminations, ability to customize tools).<br />
Should have features and options which enhance system reliability.<br />
Must be able to backup and restore system data.<br />
Mail/mailboxes are stored and managed on separate storage like<br />
DAS/ NAS for fault tolerance and availability.<br />
Tool to transfer stored messages from current email systems to the<br />
new system.<br />
Limits by user ID on server storage space; ability to monitor amount<br />
<strong>of</strong> storage used by individual users.<br />
Audit trail. Ability to audit administrative tasks, standard flow <strong>of</strong><br />
email, patterns <strong>of</strong> connections, records <strong>of</strong> mail transmissions.<br />
Facilities for investigation <strong>of</strong> connections and mailbox contents<br />
when appropriate.<br />
Tools to limit or manage message size to avoid catastrophic system<br />
impact.<br />
Aliases (nicknames), user/administrator created mailing lists, and<br />
automated mailing lists are supported on the server.<br />
Speed - minimal time needed to establish connection and rapid<br />
processing for all mail operations.<br />
Minimal impact on system resources with standard email gateways.<br />
Reasonable recovery from lost connections, requiring no<br />
intervention on server and minimal work loss on client end.<br />
Ability to send email from within other standard s<strong>of</strong>tware.<br />
Ability to use a centralized LDAP based directory service like Active<br />
Directory for identity storage and authentication.<br />
Should be able to be installed on a Virtual Server environment.<br />
8.1.1.2 Technical requirements<br />
The core technical requirements for an electronic communication<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 26
Request for Proposal for establishing e-Governance Systems<br />
solution are as follows:<br />
Enable the deployment <strong>of</strong> the solution with multiple interfaces<br />
including mixed PCs, mobile and web.<br />
Minimum storage for emails to be provided on each desktop.<br />
Automatic password expiry and renewal.<br />
Periodic back-up <strong>of</strong> e-mails preferably through the deployment<br />
<strong>of</strong> an exchange server.<br />
Multiple browser support including Internet Explorer, Google<br />
Chrome, Mozilla Firefox, etc.<br />
Multiple Operating System support on client, including MS<br />
Windows, and other OS.<br />
8.1.1.3 In addition, the following Protocols are preferred:<br />
TCP/IP. Transport Control Protocol/Internet Protocol. IPV6<br />
compatibility is desired.<br />
Open standards, including generally accepted Internet protocols,<br />
that allows for interoperability <strong>of</strong> various messaging<br />
components. For example, such a scheme allows for different<br />
clients, exchanging mail between systems, etc.<br />
SMTP(ESMTP). Simple Mail Transport Protocol, and Extended<br />
Simple Mail Transport Protocol. The standard way <strong>of</strong> sending<br />
and receiving email between computer systems on the Internet.<br />
Client authentication based on directory service. User has to log<br />
on with a unique user ID and password to use mail.<br />
MIME Support. Multipurpose Internet Mail Extensions is a<br />
standardized way <strong>of</strong> attaching to an email message documents<br />
that were created in other programs, so that the document is<br />
received in the same format that it was sent.<br />
IMAP Version 4. The advantage <strong>of</strong> the IMAP protocol is that it<br />
allows email to be stored and managed on the server, rather<br />
than the client, which facilitates users accessing mail from<br />
multiple locations.<br />
Encrypted client authentication. No clear text passwords are<br />
sent across any networks.<br />
8.1.1.4 Non-functional requirements (Operational requirements):The<br />
solution should be deployed by the SI for each staff member at ASI,<br />
currently estimated at about 5,000 persons. Initial set up would<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 27
Request for Proposal for establishing e-Governance Systems<br />
include the creation <strong>of</strong> user accounts, the creation <strong>of</strong><br />
administrator(s), the set-up <strong>of</strong> address book, the set up <strong>of</strong> initial<br />
work flows as defined by current processes, and initial training and<br />
familiarization.<br />
8.1.1.5 Interfacing requirements:Ability to interface with work flow<br />
automation tools using electronic communication. It should be<br />
possible to provide interfacing with electronic archiving solutions,<br />
financial reporting and budgeting solutions; in other words all<br />
business applications envisaged in this tender should be able to<br />
communicate using the messaging backbone.<br />
8.1.1.6 Business model:The electronic communication solution will be<br />
owned by ASI and deployed by the SI. The SI may deploy a COTS<br />
(Commercial <strong>of</strong>f the Shelf) solution, which is customized for use for<br />
ASI. In the event <strong>of</strong> a COTS solution being deployed, the licenses will<br />
be with ASI.<br />
The servers must be dedicated hosted servers, provided by the SI,<br />
with access to ASI administrators. The SI must ensure that the<br />
servers are set up as secure servers in line with the e-governance<br />
security standards framework.<br />
The SI will also assess the requirement for local desktops and any<br />
other peripherals, including networking, switches, routers, internet<br />
connectivity, printers, and scanners, at each location, and procure<br />
and deploy them. These will be owned by ASI. An indicative Bill <strong>of</strong><br />
Materialis provided in Annexure 3 to enable the SI in preparing their<br />
bid documents.<br />
8.1.1.7 Implementation model:The entire implementation would consist <strong>of</strong><br />
acquisition <strong>of</strong> a proven electronic communication s<strong>of</strong>tware, and<br />
customization to the needs <strong>of</strong> ASI. Implementation is expected to be<br />
completed within 30 days from the date <strong>of</strong> selection <strong>of</strong> the SI.<br />
8.1.2 E-ticketing Solution<br />
8.1.2.1 Functional <strong>Requirements</strong>:The proposed e-ticketing solution will<br />
meet the requirements <strong>of</strong> online booking by tourists and providing<br />
them ease <strong>of</strong> convenience. The e-ticketing solution will also<br />
integrate with Point <strong>of</strong> Sale (PoS) solutions which will be integrated<br />
so as to create an instantaneous record <strong>of</strong> tickets issued, and<br />
ensuring monitoring <strong>of</strong> the tourist traffic. The key functionalities <strong>of</strong><br />
an e-ticketing solution include:<br />
Issuance <strong>of</strong> secure, identifiable and authenticated electronic tickets<br />
Provision for booking tickets electronically on the web<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 28
Request for Proposal for establishing e-Governance Systems<br />
Provision for multiple payment options through cash, credit or debit<br />
cards, using various payment methods such as online payments,<br />
payment at unmanned or manned ticket dispending counters, or<br />
payments through agents. This should include the establishment <strong>of</strong><br />
secure payment gateways as required.<br />
Generation <strong>of</strong> printed tickets at the convenience <strong>of</strong> the visitor<br />
Verification <strong>of</strong> tickets at the ticket checking counters at monument<br />
sites.<br />
Recording and reconciliation <strong>of</strong> tickets issued, and collections made<br />
against the tickets on a periodic basis<br />
Integration with existing websites <strong>of</strong> ASI with capabilities for<br />
possible future integration with websites <strong>of</strong> travel and tourist sites.<br />
Generation <strong>of</strong> reports including ticket use and usage status, nonissue,<br />
or incomplete transactions, etc.<br />
Ability to provide a contact center interface integrated with the eticketing<br />
solution to handle queries.<br />
In order to meet these requirements, an e-ticketing solution customized<br />
to meet the convenience <strong>of</strong> foreigners and <strong>India</strong>n tourists have to be<br />
developed. The e-ticketing solution must provide for the following<br />
components:<br />
1. A web ticketing solution which could enable prospective tourists to<br />
pre-book their tickets even when outside <strong>India</strong>. The solution should<br />
provide a method to authenticate foreign tourists from domestic<br />
tourists for differential ticket rates.<br />
2. An e-ticketing solution which would replace the current manual<br />
ticketing solutions available at the monuments. The solution would<br />
require the provision <strong>of</strong> computers, provision <strong>of</strong> back-up power,<br />
provision <strong>of</strong> ticket printing and issuing options.<br />
Each <strong>of</strong> these solutions should have a common back-end and integrate<br />
with a common solution. Further, the ticket available for verification at<br />
the Monument gates should have a common and easily recognizable<br />
format.<br />
8.1.2.2 Technical requirements:The e-ticketing solution will provide for the<br />
following technical requirements:<br />
Browser support on multiple browsers for external users.<br />
An interactive and easy to use GUI interface for <strong>of</strong>ficials.<br />
An integrated interface for the contact center interface.<br />
Remote server based system connected through web. For PoS<br />
locations, the solution should support low bandwidth and dial up<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 29
Request for Proposal for establishing e-Governance Systems<br />
connectivity. In certain cases, there might not be connectivity<br />
available always, hence the proposed solution should have ability to<br />
also work <strong>of</strong>fline and synch data as and when connectivity becomes<br />
available.<br />
For PoS locations, the solution should also support batch processing<br />
and uploads, as a contingency arrangement.<br />
Secure browsing using appropriate encryption solutions with digital<br />
signature for authentication. The application shall support advanced<br />
authentication techniques along with username and password, such<br />
as PKI with X.509 certificates or higher, wherever required.<br />
Secure electronic payment gateways integrated with the e-ticketing<br />
solution, which are enabled for most commonly used electronic<br />
payment options, including direct payment through bank accounts,<br />
credit and debit cards<br />
8.1.2.3 Non-functional requirements (Operational requirements):The eticketing<br />
solution should be built on scalable hardware and<br />
commercially available CRM and Portal solutions so that scalability<br />
can be achieved, in terms <strong>of</strong> the volume <strong>of</strong> users and services it can<br />
support concurrently, therefore it must have capabilities to operate<br />
with an estimated daily peak load <strong>of</strong> up to 300,000 purchases per<br />
day. The web-ticketing solutions must be able to authenticate<br />
whether the purchaser is <strong>India</strong>n or foreign and should issue tickets<br />
accordingly.<br />
The PoS component <strong>of</strong> the solution should consist <strong>of</strong> a manned<br />
counter, where tickets are issued by an issuer based on information<br />
provided verbally by a purchaser. Adequate authentication methods<br />
must be built in to prevent revenue leakages. At the PoS, tickets<br />
would be printed and issued by the ticket issuer. Payments would be<br />
accepted through cash in <strong>India</strong>n currency only, or credit cards.<br />
Power and internet connectivity: The PoS solutions would have<br />
adequate provision for back-up power to enable uninterrupted<br />
functioning for at least 8 hours in a day. Also, the solution should be<br />
able to dispense tickets even without internet connectivity, with a<br />
feature to store information locally and upload to the centralized<br />
database on availability <strong>of</strong> internet connection.<br />
8.1.2.4 Interfacing requirements:The e-ticketing solution should interface<br />
with the multiple payment gateways authorized by ASI. The solution<br />
shall support card payments using all the popular debit and credit<br />
cards (Visa, Master Card etc.) and Direct Debit. The solution must<br />
also have interface with electronic card reading solutions such as<br />
barcodes, or magnetic cards.<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 30
Request for Proposal for establishing e-Governance Systems<br />
The proposed solution will also interface with financial planning and<br />
budgeting system.<br />
8.1.2.5 Business model:The e-ticketing solution will be hosted on a third<br />
party secured server, which will be for dedicated use by ASI based on<br />
the recommendation <strong>of</strong> the SI – the costs related to the server are<br />
part <strong>of</strong> the financial proposal to be provided by the SI. The third<br />
party solutions such as payment gateways will be procured by the SI;<br />
the transaction costs related to payments will be borne directly by<br />
ASI. All collections through the e-ticketing solution will directly be<br />
credited into ASI designated bank accounts.<br />
The SI will assess, recommend and procure the hardware at PoS site,<br />
including, but not limited to computers, networking, printers, and<br />
other peripherals. These will be owned by ASI.An indicative Bill <strong>of</strong><br />
Material is provided in Annexure 3 to enable the SI in preparing their<br />
bid documents.<br />
The SI will also procure the s<strong>of</strong>tware at PoS site which could include<br />
payment gateway interfaces, web ticketing services, and card<br />
reading s<strong>of</strong>tware. These would be part <strong>of</strong> the solution to be<br />
provided by the SI. If the S<strong>of</strong>tware is procured as a COTS solution,<br />
the license would be assigned to ASI. If the solution is a proprietary<br />
solution developed by the SI, the code for the s<strong>of</strong>tware must be<br />
made available to ASI.<br />
8.1.2.6 Implementation model:ASI has identified 116 monuments to<br />
implement e-ticketing solution; System Integrators will be required<br />
to conduct a phase-wise implementation <strong>of</strong> the e-ticketing solution.<br />
staggered implementationshall be conducted in select 10<br />
monuments which are <strong>of</strong> significance but not necessarily the highest<br />
traffic monuments. The proposed monuments where this staggered<br />
implementation shall be initiated are as follows:<br />
Circle Name <strong>of</strong> the Monument<br />
Agra Circle Taj Mahal, Agra<br />
Agra Circle Agra Fort<br />
Agra Circle Fatehpur Sikri Fort<br />
Agra Circle Sikandra<br />
Agra Circle Itimad-ud-Daula<br />
Aurangabad Circle Ajanta and Ellora<br />
Bhubaneswar Circle Sun Temple, Konark<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 31
Request for Proposal for establishing e-Governance Systems<br />
Chennai Circle Group <strong>of</strong> Monuments,Mamallapuram<br />
Delhi Circle Qutub Minar, New Delhi<br />
Patna Circle Nalanda Excavated Site<br />
Once successfully deployed, these solutions are proposed to be<br />
replicated across all the other identified monuments.<br />
It is expected that at the end <strong>of</strong> the project phase, the solution will<br />
be evaluated to determine whether any changes are required to be<br />
made to the solution, and the same solution, with modifications, if<br />
any, is expected to be rolled out across the rest <strong>of</strong> the monuments.<br />
This proposed roll-out is not a part <strong>of</strong> this RFP.<br />
8.1.3 Financial Planning and Budgeting System<br />
ASI currently manages its financial planning and budgeting systems manually.<br />
While the existing processes are robust, the fact that they are completely manually<br />
makes the systems cumbersome, and error prone. Additionally, the time taken to<br />
compile accounts, and reconciliation takes significant time and effort. The current<br />
accounting systems are single entry. The accounting books consist <strong>of</strong> cash register,<br />
check register, budget register, and payable register. Budget allocations are<br />
committed once a year. Revisions, if any, to the budget, are also done once a year,<br />
and funds could be reallocated. Unutilized funds during a year lapse, and revert to<br />
the CGF.<br />
8.1.3.1 Functional <strong>Requirements</strong>:The key functionalities <strong>of</strong> the proposed<br />
Financial Planning and Budgeting System include the following:<br />
Ability to record information relating to the budgets and budget<br />
allocations across various heads by the Accounts and Pay (A&P)<br />
department. The information should also be recorded at circle<br />
level, against allocated budgets. These should include plan and<br />
non-plan expenditures.The proposed system should be workflow<br />
based and web-enabled / online system. Further,<br />
o Electronic clearance/ online payment systemsshould be<br />
introduced wherever possible.<br />
o As far as possible, all reconciliation systems should<br />
online and real time system.<br />
Ability to record information related to release <strong>of</strong> payments by<br />
CDDOs<br />
Ability to reconcile payments against budgets<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 32
Request for Proposal for establishing e-Governance Systems<br />
Online reporting <strong>of</strong> financial transactions, including variances,<br />
under, and over-utilization <strong>of</strong> budgets, performance tracking and<br />
dashboarding for easy decision making at central level.<br />
Accounts / budgets will also cover the various departments at<br />
ASI such as, Conservation, Museums, etc. Provisions are<br />
required to integrate this for future Information System needs<br />
Interfaces and application logic is required to render the<br />
accounts in a manner and format compatible with and compliant<br />
to the requirements <strong>of</strong> the Comptroller and Audit General (CAG).<br />
CAG compliance requirements will be provided during SRS.<br />
The key functional requirements would include:<br />
Core Financial System Management Function<br />
General Ledger Management Function<br />
Funds Management Function<br />
Payment Management Function<br />
Receivables Management Function<br />
Cost Management Function<br />
Reporting Function<br />
The SI is expected to prepare a detailed FRS initially, in order to<br />
ensure that all specifications are accurately captured.<br />
8.1.3.2 Technical <strong>Requirements</strong>:The technical requirements <strong>of</strong> the solution<br />
must include:<br />
Solution must be web enabled, and developed/customized on<br />
COTS application platforms with ample flexibility <strong>of</strong><br />
customization based on ASI’s needs.<br />
Solution must use standard database.<br />
The solution must be on a dedicated server which is located at<br />
SIs premises.<br />
The detailed technical requirements are as follows:<br />
8.1.3.3 General Design/ Architecture:<br />
Core financial function should be modular in design.<br />
Should be built based on open system architecture.<br />
Should be easily customizable to accommodate changes in laws,<br />
regulations, best practices and new technology.<br />
Should have internal transaction processing controls , including the<br />
capability in the event <strong>of</strong> system failure, to automatically:<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 33
Request for Proposal for establishing e-Governance Systems<br />
o Roll Back option for incomplete transactions<br />
o Restore the system to its last consistent state before the<br />
failure occurred<br />
o Reapply all incomplete transactions previously submitted by<br />
the user<br />
Internal database consistency during all online and batch<br />
operations.<br />
Fully documented restart capabilities for online and batch<br />
processing capabilities.<br />
System include anintegrated relational, structured<br />
querylanguagecompliant database<br />
Should be capable <strong>of</strong> simultaneously process online transactions and<br />
transactions submitted via system interface.<br />
8.1.3.4 Infrastructure:<br />
Should utilize transaction control/Internet communications protocol<br />
for application, database, and workstation connectivity.<br />
Should support report spooling capability to enable online viewing,<br />
reprinting, and permanent archiving <strong>of</strong> requested reports.<br />
8.1.3.5 User interfaces:<br />
Should support consistent, Windows-compatible, online user<br />
interface to all modules and integrated subsystems.<br />
Should provide for common graphical interfaces such asmouseactivated<br />
icons, buttons, scroll bars, drop-down lists, check boxes,<br />
menu bars, text boxes, tool tips, resizable windows, andcut, copy,<br />
and paste functions<br />
Should reduce the amount <strong>of</strong> direct keying required to initiate<br />
transaction processing, such asthe use <strong>of</strong> default values, look-up<br />
tables, automatic data recall, single-function windows (e.g., one<br />
input screen per transaction), the ability to pass common data from<br />
screen to screen, highlighting <strong>of</strong> required fields, auto tabs, function<br />
keys (e.g., to retrieve previous data, invoke help facility, suspend<br />
transaction, or clear screen), disabling <strong>of</strong> non-supported function<br />
keys, menu mode and an expert mode <strong>of</strong> screen navigation, the<br />
ability to retrieve suspended transactions by user, document, circle,<br />
project, etc., transaction entry undo/redo, context-sensitive online<br />
help, andthe ability to select records from a listby scrolling or by<br />
typing in only part <strong>of</strong> an entry.<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 34
Request for Proposal for establishing e-Governance Systems<br />
Should support desktop integration with other common workstation<br />
applications used for word processing, spreadsheets, data<br />
management, and graphics.<br />
8.1.3.6 Workflow/messaging:<br />
Workflow management shall allow configuration <strong>of</strong> various<br />
processes and management <strong>of</strong> multi stage process workflow.<br />
Should have workflow management capability, including generation<br />
and routing <strong>of</strong> internal forms, reports, and other financial<br />
documents, for online approval or subsequent processing.<br />
Should enableauthorized users to define workflowprocesses and<br />
business rules, includingapproval levels, and to modify<br />
workflow(e.g., assigning a proxy approvingauthority).<br />
Ability to establish multiple levels <strong>of</strong>document approvals based on<br />
user-definedcriteria, including amounts, types <strong>of</strong>items purchased,<br />
and document types.<br />
The workflow should be able to send notifications when manual<br />
intervention is required in a process<br />
Aninternal calendar or user-defined routingtables to generate rulebased<br />
or exceptionreports to support the generation <strong>of</strong>workflow<br />
messages.<br />
Ability to track approvals online bytransaction, including the time,<br />
date, andapproving party.<br />
Thecapability to automatically generateelectronic routing and status<br />
messages toindividuals or groups.<br />
Workflow design to consider W3C standards.<br />
The workflow should interface with email system supporting SMTP<br />
for sending out notifications.<br />
8.1.3.7 Document Management:<br />
Should supportOpen Document Management<br />
Architecturestandards.<br />
Should provide thecapability to electronically image, index,store,<br />
and facilitate quick retrieval<strong>of</strong> document referenceMaterial.<br />
The solution should have the ability to expire and retire content.<br />
Should incorporate a file tracking system to be able to store, and<br />
retrieve indexed documents.<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 35
Request for Proposal for establishing e-Governance Systems<br />
System should allow the user to assign a note/annotation to a<br />
document.<br />
The solution should have the ability to migrate web-based content<br />
to a records-management system.<br />
System should allow the support <strong>of</strong> multiple, simultaneous indexing<br />
sessions. System performance should not degrade due to multiple<br />
indexing sessions.<br />
The solution should have the ability to search for objects by free text<br />
/ metadata / content attributes.<br />
The solution should have the ability to maintain and access previous<br />
versions <strong>of</strong> content when updated or changed(archiving and<br />
rollback).<br />
Should notify theuser <strong>of</strong> the presence <strong>of</strong> associateddocument<br />
images and allow an on-screendisplay <strong>of</strong> this material.<br />
The solution should allow users to upload multiple files at the same<br />
time.<br />
The solution should allow 'Drag-and drop' to upload multiple files.<br />
The solution should support WebDAV for <strong>of</strong>fice suite integration.<br />
The solution should allow multi-user, real-time editing on a<br />
document.<br />
The solution should support check In/check Out capabilities.<br />
The solution should support Web <strong>of</strong>fice (browser only) document<br />
version control, audit trails, visual version comparison, check in/out,<br />
per document access controls.<br />
The solution should also support document linking capabilities<br />
(static, dynamic, and/or other).<br />
The solution should have the ability to have the same repository<br />
used to store and manage documents also used for collaborative<br />
projects/objects.<br />
The solution should have the ability to have threaded discussions<br />
around documents/content.<br />
The solution should allow users to set up collaborative workspaces.<br />
Ability to search structured and unstructured information<br />
repositories, such as documents, images, audio and video.<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 36
Request for Proposal for establishing e-Governance Systems<br />
Support structured searches driven by metadata.<br />
Ability to perform searches across multiple indexes.<br />
Should support attachment search.<br />
Should be able to support search on multiple repositories such as<br />
web sites, file shares, Messaging System and other data repositories.<br />
8.1.3.8 Operations and Computer Performance:<br />
System should be capable <strong>of</strong> process scheduling that enablesthe<br />
operator to initiate, monitor, and stopscheduled processes, such as<br />
onlineavailability, batch jobs, and systemmaintenance.<br />
System should provideonline status messages indicating job<br />
ortransaction type and name, when requestedprocessing starts and<br />
completes, and systemerrors.<br />
System should allow reportsto be produced in the background<br />
whileother system processing takes place.<br />
System should provide thesystem administrator the ability to<br />
controlthe archiving process, including archiving criteria such as<br />
date,accounting period, closed items, andvendors inactive for a<br />
specific time period.<br />
System should provide theability to selectively retrieve archived<br />
databased on user-defined criteria such as date,accounting period,<br />
circle, or project.<br />
System should maintain andreport on productivity statistics<br />
aboutapplication usage.<br />
System must provide audittrails to identify changes made to<br />
systemparameters and tables that would affect theprocessing or<br />
reprocessing <strong>of</strong> any financialtransactions.<br />
System must providecomputing performance metrics, forplatforms<br />
and systems environments onwhich the application is certified to<br />
run, including transaction processing throughputcapacity,expected<br />
workstation client response, time by transaction type,data storage<br />
capacity, andlimitations on concurrent userconnectivity.<br />
System should maintain thecurrent and historical financialdata.<br />
Should supportconcurrent access to functional modules for multiple<br />
user communities.<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 37
Request for Proposal for establishing e-Governance Systems<br />
System should have the capability to process batched<br />
transactionsduring online hours and accept onlinetransactions from<br />
interfacing systems withno online performance degradation.<br />
8.1.3.9 Non-functional <strong>Requirements</strong> (Operational requirements):The<br />
solution must be built with a client-server module which permits<br />
entries by users at multiple locations with a review and acceptance<br />
feature. Each client would be enabled to make entries in ‘<strong>of</strong>f-line’<br />
mode which could be uploaded to the Server through batch<br />
processing when connected. Data would require to be periodically<br />
backed up on secure servers.<br />
8.1.3.10 Interfacing <strong>Requirements</strong>:The system should have capabilities for<br />
data to move effectivelybetween the core financial system and<br />
otherfinancial applications, which could include<br />
a. an application program interface (API)to accept and process<br />
financial datagenerated by external and otherinternal<br />
applications and<br />
b. the ability to export data required by other government<br />
systems<br />
the API should support the receipt and continued processing <strong>of</strong><br />
transactions for all core accounting components as well as project<br />
information updates.<br />
The API suspense process must include the ability to<br />
a. view, update, or delete suspended transactions and<br />
b. automatically reprocess suspended transactions.<br />
Should generate transaction editing error records in a standard<br />
format defined by the Circle Office for return to the originating<br />
feeder application.<br />
Should support XML-based specifications for the exchange <strong>of</strong><br />
financial data, such as Extensible Business Reporting Language.<br />
8.1.3.11 Business Model:The solution will be owned by ASI and will be set up<br />
on a server at ASI’s headquarters. Clients will be connected to the<br />
server through internet. The solution, the data and the hardware<br />
will all be owned by ASI with support being provided by the SI. The SI<br />
will assess the requirement <strong>of</strong> additional hardware including<br />
desktops, printers, scanners and network and internet connectivity,<br />
and procure and deploy them. These will be owned by ASI.<br />
8.1.3.12 Implementation Model:The entire implementation would consist <strong>of</strong><br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 38
Request for Proposal for establishing e-Governance Systems<br />
8.2 System Security <strong>Requirements</strong><br />
development <strong>of</strong> a system based on previously developed<br />
government accounts s<strong>of</strong>tware, and customization to the needs <strong>of</strong><br />
ASI. Implementation is expected to be completed within 6 months<br />
from the date <strong>of</strong> selection <strong>of</strong> the SI.<br />
It is expected that the solution implemented by the SI will be run in<br />
parallel with the existing systems for a period <strong>of</strong> at least 6 months in<br />
order to ensure that the output is the same in either case. The SI<br />
will also be required to migrate data from the existing systems to the<br />
new systems.<br />
8.2.1 Security features should be compliant withthe e-Governance Security Standards<br />
Framework.<br />
8.2.2 All systems should have integrated security features that areconfigurable by the<br />
system administrator tocontrol access to the application, functionalmodules,<br />
transactions, and data.<br />
8.2.3 Public key verificationmethods should be followed for verifying that the contents<br />
<strong>of</strong> a document have not been tampered with, and allowing the receiver to confirm<br />
the identity <strong>of</strong> the sender.<br />
8.2.4 The applications should require theuse <strong>of</strong> unique user IDs and passwords<br />
forauthentication purposes.<br />
8.2.5 The application should allow for the following:<br />
a. the enforcement <strong>of</strong> password standards<br />
b. the establishment <strong>of</strong> a specified periodfor password expiration, and<br />
c. the prohibition <strong>of</strong> recent passwordreuse<br />
8.2.6 System administrator should be able to define functional access rights and data<br />
access rights byassigned user ID, functional role, andowner organization.<br />
8.2.7 The systems should permit thesystem administrator to assign multiplelevels <strong>of</strong><br />
approval to a single user.<br />
8.2.8 System administrator should be able to restrict access tosensitive data elementsby<br />
named user, groups <strong>of</strong> users, orfunctional role.<br />
8.2.9 System should have audit logging capability to record accessactivity, including the<br />
following:<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 39
Request for Proposal for establishing e-Governance Systems<br />
a. all log-in/log-out attempts by user andworkstation;<br />
b. user-submitted transactions;<br />
c. initiated processes;<br />
d. system override events; and<br />
e. direct additions, changes, or deletionsto application-maintained data<br />
8.2.10 System should provide theability to query the audit log by type <strong>of</strong>access, date and<br />
time stamp range, user ID,or terminal ID.<br />
8.3 Governance Structure<br />
8.3.1 Overall responsibility for the implementation <strong>of</strong> all three modules will remain with<br />
the SI. Supervision and reporting during implementation will be to NISG. <strong>Project</strong><br />
progress review and monitoring will be the responsibility <strong>of</strong> NISG during project<br />
implementation phase. ASI will appoint a Single Point <strong>of</strong> Contact (SPOC) for IT<br />
Administration. Escalation <strong>of</strong> all issues related to the three modules will be<br />
through this SPOC, who will also be responsible for reviewing the SLAs being met.<br />
8.3.2 The e-ticketing solution will be owned by ASI and developed, operated and<br />
maintained by the SI. The SI will be responsible for end-to-end deployment<br />
including ticket issuance, verification, collections and deposit with ASI’s bankers on<br />
a daily basis, in line with current practices. The SIs staff will be directly responsible<br />
to the respective Circle Heads in each <strong>of</strong> the Circles where the PoS are located.<br />
For the project implementation phase, supervision and reporting during<br />
implementation will be to NISG. <strong>Project</strong> progress review and monitoring will be<br />
the responsibility <strong>of</strong> NISG during project implementation phase. ASI will appoint a<br />
SPOC for IT Administration. Escalation <strong>of</strong> all issues related to e-ticketing solution<br />
will be through this SPOC, who will also be responsible for reviewing the SLAs being<br />
met.<br />
8.4 Documentation Standards and <strong>Requirements</strong><br />
8.4.1 Documentation: Documentation must include complete installation, operating,<br />
and systemmaintenance documentation covering thefollowing:<br />
product installation and configurationsteps;<br />
application access procedures;<br />
user screen layout and content;<br />
transaction entry procedures;<br />
batch job setup, processing, andrecovery/restart procedures;<br />
error codes with full descriptions andrecovery steps;<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 40
Request for Proposal for establishing e-Governance Systems<br />
standard report layout and content;<br />
internal processing controls;<br />
application security;<br />
operating specifications and systemflowcharts;<br />
database entity relationships, tableformats, and data elementdescriptions; and<br />
program module descriptions<br />
9 Service Level Agreements<br />
Service Levels will include Availability measurements and Performance parameters. The Vendor<br />
shall provide Availability Report on a monthly basis and a review shall be conducted based on this<br />
report. A monthly report shall be provided to the ASI at the end <strong>of</strong> every month containing the<br />
summary <strong>of</strong> all incidents reported and associated Vendor performance measurement for that<br />
period.<br />
Performance measurements would be accessed through audits or reports, as appropriate to be<br />
provided by the Vendor e.g. utilization reports, response time measurements reports, etc. The tools<br />
to perform the audit will need to be provided by the Vendor. Audits will normally be done on<br />
regular basis or as required by ASI and will be performed by ASI or ASI appointed third party<br />
agencies.<br />
The following SLAs apply to the proposed solutions for each <strong>of</strong> the three deliverables.<br />
9.1 S<strong>of</strong>tware Application Development and Deployment<br />
Table 3: SLA requirements for Application Development and Infrastructure Deployment<br />
Service Level<br />
Description<br />
Measurement Minimum<br />
Service Level<br />
Gap Resolution All gaps observed in the functional<br />
specifications, current system<br />
study, training, business process reengineering,<br />
parameterization,<br />
testing and Launch<br />
Implementation shall be resolved<br />
within defined and mutually agreed<br />
time frames.<br />
Bug Reporting The Bidder shall ensure that all<br />
bugs reported by the users / testing<br />
team will be duly logged and<br />
Cost Reference<br />
98% S<strong>of</strong>tware<br />
Applications,<br />
Customization,<br />
Implementation<br />
97% Implementation<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 41
Request for Proposal for establishing e-Governance Systems<br />
Service Level<br />
Description<br />
Measurement Minimum<br />
Service Level<br />
assigned a unique ID for reference<br />
purposes.<br />
Bug Resolution The Bidder shall ensure that all<br />
bugs reported by the users / testing<br />
team will be duly resolved<br />
maximum within 3 calendar days.<br />
Modification/<br />
Enhancements<br />
resolution<br />
System Response<br />
Time<br />
System Response<br />
Time<br />
Disaster Recovery<br />
Site Availability<br />
The Bidder shall ensure that all<br />
modifications, enhancements<br />
reported by the ASI will be duly<br />
sized, agreed with the ASI and<br />
resolved as per the agreed<br />
timeframes<br />
End to end response time should be<br />
2 seconds (end user to core<br />
application and back)<br />
Support concurrent users as<br />
specified for each module<br />
Business operations to resume<br />
fromDisaster Recovery Site within<br />
60 minutes <strong>of</strong> the Data Server<br />
failing.<br />
Backup Success Rate Backup success rate for the<br />
Comprehensive Insurance Solution,<br />
other 3rd party solutions/Support<br />
applications and delivery channels.<br />
S<strong>of</strong>tware Service<br />
Requests<br />
IT Policies &<br />
Procedures<br />
Management<br />
Percentage <strong>of</strong> S<strong>of</strong>tware Service<br />
Requests concluded (patches, bug<br />
fixes, errors) within defined<br />
response resolution window.<br />
Compliance <strong>of</strong> the IT infrastructure<br />
to the ASI’s Policies & Procedures<br />
Cost Reference<br />
99.9% Implementation,<br />
S<strong>of</strong>tware<br />
Applications,<br />
Customization<br />
98% Implementation,<br />
S<strong>of</strong>tware<br />
Applications,<br />
Customization<br />
96.9% S<strong>of</strong>tware<br />
Applications,<br />
Database, Security<br />
Components,<br />
96% S<strong>of</strong>tware application<br />
for Internet costs for<br />
Internet, Security<br />
Components.<br />
98% S<strong>of</strong>tware<br />
Applications<br />
98% S<strong>of</strong>tware<br />
Applications<br />
98% S<strong>of</strong>tware<br />
Applications<br />
98% Network & Security<br />
Components, Facility<br />
Management<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 42
Request for Proposal for establishing e-Governance Systems<br />
Service Level<br />
Description<br />
Incident<br />
Management<br />
Computer downtime<br />
at PoS<br />
Measurement Minimum<br />
Service Level<br />
Cost Reference<br />
Percentage <strong>of</strong> incidents escalated 96.9% S<strong>of</strong>tware<br />
Applications<br />
Percentage <strong>of</strong> time that the<br />
computers functioning at the PoS<br />
either due to computer, internet, or<br />
power failure<br />
9.2 S<strong>of</strong>tware Application and Infrastructure Maintenance<br />
Table 4: SLA requirements for S<strong>of</strong>tware Application and infrastructure Maintenance<br />
ServiceLevelDescription Measurement Minimum<br />
ServiceLevel<br />
Application Down time Each planned down - time for<br />
application, database and<br />
operating system will not be<br />
more than 4 hours. This activity<br />
will not be carried out during<br />
business hours. However, such<br />
activities which require more<br />
than 4 hours or required to be<br />
carried out during business<br />
hours will be scheduled in<br />
consultation with the ASI. In<br />
case the downtime exceeds the<br />
planned hours the additional<br />
time taken for servicing will be<br />
considered for infrastructure or<br />
system downtime as per<br />
availability measurements table.<br />
Critical site<br />
infrastructure<br />
components<br />
9.3 E-ticketing Operations<br />
Availability <strong>of</strong> the critical site<br />
infrastructure components at<br />
all the implementation sites<br />
shall be at least<br />
Table 5: SLA requirements for e-ticketing Operations<br />
99% Hardware for Ticket<br />
Counters at PoS<br />
Cost Reference<br />
98% Application<br />
Hosting<br />
99% Hardware<br />
maintenance<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 43
Request for Proposal for establishing e-Governance Systems<br />
ServiceLevelDescription Measurement Minimum<br />
Service<br />
PoS Counter operations Percentage <strong>of</strong> time for which the PoS<br />
is not functioning to required timings<br />
Level<br />
Cost Reference<br />
95% PoS Counter<br />
Operations<br />
If service level for any <strong>of</strong> the metrics is measured and scored at a level lower than the expected<br />
in two months consecutively then ASI shall have the right to invoke penalty <strong>of</strong> 3% <strong>of</strong> total<br />
monthly amount payable to SI for a score <strong>of</strong> 100%.<br />
In case <strong>of</strong> a continued breach in the SLA beyond two months, ASI shall have the right to invoke<br />
penalty <strong>of</strong> 10% <strong>of</strong> total monthly amount payable to SI for a score <strong>of</strong> 100%.<br />
In case <strong>of</strong> two or more breaches in a month or breach <strong>of</strong> a particular SLA metric consecutively in<br />
two quarters, ASI shall have the right to invoke full PBG and/ or call for termination <strong>of</strong> contract.<br />
Penalty shall be adjusted to the final monthly amount payable to SI basis actual scores.<br />
If the overall penalty applicable in any month during the currency <strong>of</strong> the contract exceeds 20%;<br />
then ASI shall have the right to terminate the contract.<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 44
Request for Proposal for establishing e-Governance Systems<br />
10 Annexures<br />
10.1 Annexure 1: List <strong>of</strong> Circles<br />
Agra Aurangabad Bangalore<br />
Bhopal Bhubaneswar Chandigarh<br />
Chennai Dehradun Delhi<br />
Dharwad Goa Guwahati<br />
Hyderabad Jaipur Kolkata<br />
Lucknow Mumbai Patna<br />
Raipur Ranchi Shimla<br />
Srinagar Thrissur Vadodara<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 45
Request for Proposal for establishing e-Governance Systems<br />
10.2 Annexure 2: Visitor History to the Monuments<br />
Monument Name 2007 2008 2009<br />
Taj Mahal 3,210,190 3,226,843 3,077,114<br />
Agra Fort 1,534,703 1,675,507 1,713,006<br />
Fatehpur Sikri 461,672 483,725 453,988<br />
Akbar's Tomb 347,393 334,305 335,974<br />
Mariam's Tomb, Agra 9,473 12,291 10,054<br />
Itimad-ud-Daula, Agra 102,550 104,518 97,651<br />
Ram Bagh, Agra 35,040 32,406 27,623<br />
Mahtab Bagh, Agra 22,149 22,096 32,152<br />
Ajanta Caves 335,866 319,427 370,982<br />
Ellora 471,772 592,661 757,787<br />
Pandavlena Caves, Pathardi 112,676 103,192 108,131<br />
Daulatabad Fort 301,523 447,943 402,299<br />
Bibi-Ka-Maqbara, Aurangabad 893,121 983,867 1,033,185<br />
Aurangabad Caves 37,773 39,362 37,679<br />
Elephanta Caves, Gharaphuri, Mumbai 254,557 256,966 318,820<br />
Kanheri Caves, Mumbai (Suburban) 82,201 107,096 110,462<br />
Karla Caves, Karla 94,863 77,826 112,140<br />
Caves, Temples & Inscription, Junnar 254,071 302,793 323,893<br />
Raigad Fort 81,055 414,442 170,054<br />
Shaniwarwada, Pune 314,200 329,932 382,577<br />
Hirakota Old Fort, Alibagh 35,273 43,000 57,023<br />
Old Fort Sholapur 19,593 36,994 25,435<br />
Caves, Temples & Inscription, Bhaja 24,606 22,127 25,023<br />
AgaKhan Palace, Pune 77,338 129,698 90,957<br />
Group <strong>of</strong> Monuments, Hampi, Distt. Bellary 343,505 512,158 439,333<br />
Daria Daaulat Bagh,Srirangapatnam 706,015 731,472 804,434<br />
Keshva Temple, Somnathpura 141,209 145,736 176,399<br />
Tipu Sultan Palace, Bangalore 119,851 108,086 117,756<br />
Chitradurga Fort, Chitradurga 208,826 210,635 256,008<br />
Bellary Fort, Bellary 10,074 7,700 7,235<br />
Vihal Temple Venkatatapuram - 272,205 -<br />
Zanana Enclosure, Kamalapur - 239,953 -<br />
Western Group <strong>of</strong> Temples, Khajuraho 278,651 290,527 294,363<br />
Shahi Quila at Burthanpur 50,922 54,744 67,183<br />
Bagh Caves, Bagh 15,692 20,987 22,779<br />
Royal Complex, Mandu 161,751 198,821 242,655<br />
Rani Roopmati Pavilion, Mandu 159,704 206,067 252,693<br />
Hoshang Shah's Tomb Mandu 89,826 117,758 139,554<br />
Bhojshala Dhar Moula Mosque 13,572 - 14,393<br />
Bhuddhist Monuments at Sanchi 127,766 151,936 172,869<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 46
Request for Proposal for establishing e-Governance Systems<br />
Monument Name 2007 2008 2009<br />
Gwalior Fort, Gwalior 168,978 213,672 212,988<br />
Sun Temple, Konark 1,357,390 1,480,149 1,746,609<br />
Raja Rani Temple, Bhubaneswar 25,619 47,097 28,127<br />
Udaigiri & Kandagiri Caves 265,521 291,526 362,802<br />
Excavated Site, Ratnagiri 16,051 8,728 22,762<br />
Excavated Site, Lalitagiri 7,027 - 10,091<br />
Sheikh Chillis Tomb Thanesar 44,146 59,788 135,180<br />
Suraj Kund Monastery, Lakarpur 24,295 13,228 36,761<br />
Group <strong>of</strong> Monuments,Mamallapuram 873,055 277,683 1,013,889<br />
Rajgiri & Krishangiri Fort, Gingee 160,889 162,231 175,161<br />
Fort Dindigul 38,894 39,563 39,734<br />
Muvar Koil Kalumbalur 548 386 476<br />
Rock Cut-Jain Temple, Sittanvasal 15,322 14,660 13,894<br />
Natural Cavem, Eladipattanam 14,428 10,721 13,720<br />
Fort Thirumayan 39,500 40,289 58,756<br />
St. George Fort, Gennai 30,327 - 33,936<br />
Jantar Mantar 277,978 269,598 317,434<br />
Rahim-Khane-Khanam Tomb, Delhi 5,688 7,976 8,878<br />
Purana Quila 599,780 586,931 630,095<br />
Sultangahri Tomb 582 350 241<br />
Tughluqabad Fort 15,031 16,966 24,661<br />
Kotla Feroz Shah 55,892 51,657 55,742<br />
Safdarjung Tomb 112,722 59,416 53,358<br />
Red Fort 2,219,376 2,330,315 2,498,058<br />
Humayun's Tomb 440,952 483,310 478,768<br />
Qutab Minar 2,301,904 2,398,877 2,373,300<br />
Durga Temple Complex, Aihole 181,732 189,732 193,125<br />
Jaina & Vaishnava Caves, Badami 299,881 309,580 361,023<br />
Group <strong>of</strong> Monuments (WH), Pattadakal 205,233 224,309 246,921<br />
Gol-Gumbaz, Bijapur 779,534 841,949 958,499<br />
Ibrahim Rouza, Bijapur 136,211 151,658 162,654<br />
Temple and Sculpture Shed, Lakkundi 8,645 9,919 12,457<br />
Ahom Raja's Palace, Gurgaon 8,615 266,649 35,106<br />
Karenghar Palace, Jaysagar 34,439 88,932 119,558<br />
Ranghar Pavillion, Jaysagar 12,627 32,213 53,450<br />
Vishudol, Joysagar 2,371 5,646 8,447<br />
Group <strong>of</strong> Maidan, Cheraideo 4,448 21,008 25,456<br />
Golkonda Fort, Golkonda 270,131 1,259,659 1,238,140<br />
Charminar, Hyderabad 296,472 1,413,473 1,329,058<br />
Fort, Raja & Rani Mahal Chandragiri 24,961 85,857 83,563<br />
Ruined Buddhist Stupa & Remains Amarvati 5,367 18,410 15,497<br />
Hill <strong>of</strong> Nagarjunakonda with ancient remains 30,086 116,993 77,522<br />
Group <strong>of</strong> Buddhist monuments, Guntupali 2,358 18,252 20,255<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 47
Request for Proposal for establishing e-Governance Systems<br />
Monument Name 2007 2008 2009<br />
Four Storeyed Rock-Cut Hindu Temple, Undavalli 8,365 29,329 38,906<br />
Warangal Fort, Warangal 4,631 92,000 151,973<br />
Deeg Palaces, Deeg 19,263 20,939 27,875<br />
Kumbhalgath Fort 97,672 116,374 152,057<br />
Chittaurgath Fort 317,857 334,298 362,996<br />
Kooch Bihar Palace 260,579 272,212 341,427<br />
Hazarduari Palace Museum Murshidabad 412,773 496,638 617,622<br />
Bishnupur Group <strong>of</strong> Temples 75,830 86,962 93,138<br />
Rani Jhansi Mahal, Jhansi 6,935 8,163 5,955<br />
Sahet <strong>of</strong> Shravasti Monument 86,804 84,674 69,924<br />
Rani Jhansi Kla, Jhansi 139,603 128,168 123,598<br />
Residency, Lucknow 146,496 139,846 133,601<br />
Site <strong>of</strong> Mayuran Palace, Kumarhar, Patna 53,719 76,032 91,088<br />
Ancient Remain, Vaishali 49,668 76,419 100,072<br />
Sarnath Excavated Site 221,460 238,874 250,258<br />
Jaunpur Fort 92,723 96,575 114,812<br />
Man Singh Observatory, Varanasi 2,700 3,353 5,027<br />
Nalanda Excavated Site 267,158 532,673 363,967<br />
Sasaram Shershah Suri Tomb 117,652 131,849 151,082<br />
Lort Cornwalls Tomb, Gazipur 5,209 6,345 9,127<br />
Excavated Site Vikramshila, Aritichak 19,830 18,323 31,841<br />
Laxman Temple, Sirpur 33,389 32,919 36,017<br />
Bekal Fort Pallikkare 146,567 173,894 59,528<br />
Mattancherry Palace Museum, Kochi - 319,263 92,115<br />
Sun Temple, Modhera 119,630 185,969 194,845<br />
Rani-ki-Vav, Patan 152,662 213,230 215,418<br />
Monuments at Champaner 82,829 89,397 101,150<br />
Buddhist Caves, Junagadh 47,636 57,299 51,125<br />
Ashokan Rock Edict, Junagadh 45,334 44,106 45,569<br />
Baba Pyare and Khapra Kodiya Caves, Junagadh 219 127 236<br />
Ram Nagar Palace, Ramnagar 1,940 2,000 2,580<br />
Group <strong>of</strong> Temple, Kiramchi 854 793 1,424<br />
Avanti Swami Temple, A antipura 7,322 6,153 7,817<br />
Leh Palace, Leh 3,287 4,696 8,760<br />
Kangra Fort, Kangra 48,344 47,618 54,004<br />
Rock Cut Caves, Masoor 11,705 11,703 14,578<br />
Total Tourists 26,064,673 31,466,371 32,489,327<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 48
Request for Proposal for establishing e-Governance Systems<br />
10.3 Annexure 3: Indicative Bill <strong>of</strong> Materials<br />
Sl.<br />
No.<br />
Modules Hardware –<br />
Server side<br />
1 Electronic<br />
Communication<br />
Hosted<br />
Server based<br />
on technical<br />
specifications<br />
Location Hardware- client<br />
side<br />
At vendor<br />
location<br />
Minimum<br />
Quantity<br />
Maximum<br />
Quantity<br />
Networking 1 24 24 Circle<br />
Offices<br />
Desktop<br />
Computers with<br />
monitors<br />
Scanner-cumprinter<br />
Modem and Switch 1 24<br />
24 24 x 10 24 Circle<br />
Offices<br />
24 24 24 Circle<br />
Offices<br />
Location S<strong>of</strong>tware Ownership<br />
and payments<br />
Third party<br />
s<strong>of</strong>tware<br />
licenses<br />
Server<br />
ownership<br />
with SI.<br />
Client Side<br />
Hardware and<br />
peripherals to<br />
be procured by<br />
SI based on<br />
specifications<br />
by SI and<br />
owned by ASI.<br />
Third party<br />
licenses to be<br />
procured by SI<br />
in the name <strong>of</strong><br />
ASI<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 49
Request for Proposal for establishing e-Governance Systems<br />
Sl.<br />
No.<br />
Modules Hardware –<br />
Server side<br />
2 E-ticketing<br />
solution<br />
Hosted<br />
Server(s)<br />
based on<br />
technical<br />
specifications<br />
Location Hardware- client<br />
side<br />
At vendor<br />
location<br />
Minimum<br />
Quantity<br />
Maximum<br />
Quantity<br />
Networking 10 10 10<br />
Monuments<br />
Desktop<br />
Computers with<br />
monitors<br />
10 x 2 10 x 3 10<br />
Monuments<br />
Printers 10 x 1 10 x 1 10<br />
Monuments<br />
Modem and Switch 10 x 1 10 x 1 10<br />
Monuments<br />
UPS for Back-up<br />
power<br />
10 x 1 10 x 1 10<br />
Monuments<br />
Location S<strong>of</strong>tware Ownership<br />
and payments<br />
Customized<br />
s<strong>of</strong>tware, and<br />
where<br />
applicable,<br />
third party<br />
licenses.<br />
Server<br />
ownership<br />
with SI.<br />
Hardware and<br />
peripherals to<br />
be procured by<br />
SI based on<br />
specifications<br />
by SI and<br />
owned by ASI.<br />
Source code <strong>of</strong><br />
s<strong>of</strong>tware, and<br />
licenses, if any,<br />
to be owned<br />
by ASI. Refer<br />
RFP Volume 3.<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 50
Request for Proposal for establishing e-Governance Systems<br />
Sl.<br />
No.<br />
Modules Hardware –<br />
Server side<br />
3 Financial<br />
planning and<br />
Budgeting<br />
Solution<br />
Hosted<br />
Server based<br />
on technical<br />
specifications<br />
Location Hardware- client<br />
side<br />
At vendor<br />
location<br />
Minimum<br />
Quantity<br />
Maximum<br />
Quantity<br />
Networking 24 x 1 (120+24) x 2 24 Circles<br />
and 120<br />
locations<br />
Scanner-cumprinter<br />
Desktop<br />
Computers with<br />
monitors<br />
24 x 1 (120+24) x 2 24 Circles<br />
and 120<br />
locations<br />
24 x 1 (120+24) x 2 24 Circles<br />
and 120<br />
locations<br />
Location S<strong>of</strong>tware Ownership<br />
and payments<br />
Customized<br />
s<strong>of</strong>tware, and<br />
where<br />
applicable,<br />
third party<br />
licenses.<br />
Server<br />
ownership<br />
with SI.<br />
Hardware and<br />
peripherals to<br />
be procured by<br />
SI based on<br />
specifications<br />
by SI and<br />
owned by ASI.<br />
Source code <strong>of</strong><br />
s<strong>of</strong>tware, and<br />
licenses, if any,<br />
to be owned<br />
by ASI. Refer<br />
RFP Volume 3.<br />
RFP Volume 1:<strong>Project</strong> <strong>Requirements</strong> P a g e | 51
Request for Proposal<br />
For establishing e-Governance Systems<br />
For<br />
<strong>Archaeological</strong> <strong>Survey</strong> <strong>of</strong> <strong>India</strong><br />
Commercial and Bidding Terms<br />
November 2011
Request for Proposal for establishing e-Governance Systems<br />
Volume 2: Commercial and Bidding Terms<br />
1 INTRODUCTION ..................................................................................................................... 4<br />
1.1 PARTICULARS OF RFP .................................................................................................................... 4<br />
2 SCOPE OF WORK FOR IMPLEMENTATION AGENCY (SI) ........................................................... 5<br />
2.1 OVERVIEW OF SCOPE OF WORK ....................................................................................................... 5<br />
3 CONSTITUTION OF THE TEAM ................................................................................................ 6<br />
4 PROJECT IMPLEMENTATION ................................................................................................ 14<br />
4.1 APPROACH & METHODOLOGY FOR IMPLEMENTATION OF TECHNICAL SOLUTION ................................... 14<br />
4.2 PROJECT TIMELINES ..................................................................................................................... 15<br />
5 IMPLEMENTATION MODEL .................................................................................................. 19<br />
5.1 OPERATION MODEL .................................................................................................................... 19<br />
6 PAYMENT TERMS & SCHEDULE ............................................................................................ 20<br />
6.1 PAYMENT TERMS ........................................................................................................................ 20<br />
6.2 PAYMENT SCHEDULE ................................................................................................................... 20<br />
7 BIDDING PROCESS DETAILS .................................................................................................. 22<br />
7.1 BIDDING SCHEDULE ..................................................................................................................... 22<br />
7.2 GENERAL INSTRUCTION TO BIDDERS ............................................................................................... 23<br />
7.3 BID SUBMISSION INSTRUCTIONS .................................................................................................... 29<br />
7.4 CLARIFICATION ON RFP DOCUMENT .............................................................................................. 32<br />
7.5 BID OPENING & EVALUATION PROCESS .......................................................................................... 33<br />
8 AWARD OF CONTRACT ........................................................................................................ 38<br />
8.1 POST QUALIFICATION AND AWARD CRITERIA ................................................................................... 38<br />
8.2 PURCHASER'S RIGHT TO VARY SCOPE OF CONTRACT ......................................................................... 38<br />
8.3 PURCHASER'S RIGHT TO ACCEPT AND REJECT BIDS............................................................................ 38<br />
8.4 NOTIFICATION OF AWARD ............................................................................................................ 39<br />
8.5 NEGOTIATIONS WITH THE SUCCESSFUL BIDDER ................................................................................. 39<br />
8.6 SIGNING OF CONTRACT ................................................................................................................ 39<br />
8.7 PERFORMANCE SECURITY ............................................................................................................. 39<br />
9 ANNEXURE 1: BID FORMATS ................................................................................................ 40<br />
9.1 COVER LETTER ............................................................................................................................ 40<br />
9.2 PRE QUALIFICATION .................................................................................................................... 43<br />
9.3 TECHNICAL BID FORMATS ............................................................................................................. 48<br />
9.4 COMMERCIAL BID ....................................................................................................................... 54<br />
10 ANNEXURE 2: PRE-QUALIFICATION AND TECHNICAL BID EVALUATION CRITERIA ................. 58<br />
10.1 PRE-QUALIFICATION EVALUATION CRITERIA .................................................................................... 58<br />
10.2 EVALUATION OF TECHNICAL BIDS ................................................................................................... 60<br />
11 ANNEXURE 3: STATEMENT OF DEVIATION FORMAT ............................................................. 61<br />
11.1 STATEMENT OF DEVIATIONS FROM SCHEDULE OF REQUIREMENTS ....................................................... 61<br />
12 ANNEXURE 4: REQUEST FOR CLARIFICATION FORMAT ......................................................... 62<br />
12.1 FORMAT FOR CLARIFICATIONS ....................................................................................................... 62<br />
12.2 CLARIFICATION ON RFP DOCUMENT .............................................................................................. 63<br />
RFP Volume 2: Commercial and Bidding Terms Page 1
Request for Proposal for establishing e-Governance Systems<br />
RFP Volume 2: Commercial and Bidding Terms Page 2
Request for Proposal for establishing e-Governance Systems<br />
A & P Accounts and Pay<br />
List <strong>of</strong> Abbreviations<br />
ADG Additional Director General<br />
AMC Annual Maintenance Contract<br />
ASI <strong>Archaeological</strong> <strong>Survey</strong> <strong>of</strong> <strong>India</strong><br />
BE Budget Estimate<br />
CDDO Cheque Drawing and Disbursing Officer<br />
CDO Cheque Drawing Officer<br />
CGF Central Government Fund<br />
COTS Commercial Off the Shelf<br />
DDO Drawing and Disbursing Officer<br />
FRS Functional Requirement Specifications<br />
FTP Full Technical Proposal<br />
HLD High Level Design<br />
IMAP Internet Message Access Protocol<br />
ISO International Standards Organization<br />
LLD Low Level Design<br />
MIME Multipurpose Internet Mail Extensions<br />
NIC National Informatics Centre<br />
NISG National Institute for Smart Government<br />
NOC No Objection Certificate<br />
PAO Pay and Account Offices<br />
PKI Public Key Infrastructure<br />
PoS Point <strong>of</strong> Sale<br />
RFP Request for Proposal<br />
SI System Integrator<br />
SLA Service Level Agreement<br />
SPOC Single Point <strong>of</strong> Contact<br />
SRS S<strong>of</strong>tware Requirement Specifications<br />
VPN Virtual Private Network<br />
SMTP Simple Mail Transfer Protocol<br />
RFP Volume 2: Commercial and Bidding Terms Page 3
Request for Proposal for establishing e-Governance Systems<br />
1 Introduction<br />
1.1 Particulars <strong>of</strong> RFP<br />
1.1.1 This invitation to Tender is for “Establishing e-Governance Systems”for <strong>Archaeological</strong><br />
<strong>Survey</strong> <strong>of</strong> <strong>India</strong> (ASI).<br />
1.1.2 Bidders are advised to study the RFP Document carefully. Submission <strong>of</strong> Tender shall be<br />
deemed to have been done after careful study and examination <strong>of</strong> the Tender Document<br />
with full understanding <strong>of</strong> its implications. Sealed <strong>of</strong>fers prepared in accordance with the<br />
procedures enumerated in Section 8.3 should be submitted to the Director – Administration,<br />
at ASI, not later than the date and time laid down, at his/her address given in the Section<br />
8.1.2.<br />
1.1.3 The tender document can be obtained during working hours on all working days at the <strong>of</strong>fice<br />
address (as prescribed in Section 8.1.2) from the start date <strong>of</strong> sale <strong>of</strong> tender till the last date.<br />
The tender document can also be downloaded from ASI website (www.asi.nic.in).<br />
1.1.4 Tender fee <strong>of</strong> ` 10,000 (Rupees Ten Thousand Only) has to be paid at the time <strong>of</strong> purchasing<br />
the tender from the <strong>of</strong>fice address or if the document is downloaded, should be submitted<br />
along with the Bid Security at the time <strong>of</strong> Bid Submission. Tender fee should be in form <strong>of</strong><br />
Demand Draft drawn in favor <strong>of</strong> “Director – Administration, <strong>Archaeological</strong> <strong>Survey</strong> <strong>of</strong><br />
<strong>India</strong>”payable at New Delhi. Tender fee submitted by the bidder shall be non-refundable.<br />
1.1.5 This Tender document is not transferable.<br />
1.1.6 Bid Security<br />
All bids must be accompanied by Bid Security <strong>of</strong> ` 10,00,000 (Rupees Ten Lakhs Only).Bid<br />
Security is to be submitted in the form <strong>of</strong> Demand Draft issued valid for at least 180 days<br />
from the date <strong>of</strong> opening <strong>of</strong> Technical Bid. The Demand Draft should be in favor <strong>of</strong> “Director<br />
– Administration, <strong>Archaeological</strong> <strong>Survey</strong> <strong>of</strong> <strong>India</strong>” and payable at New Delhi.<br />
RFP Volume 2: Commercial and Bidding Terms Page 4
Request for Proposal for establishing e-Governance Systems<br />
2 Scope <strong>of</strong> Work for Implementation Agency (SI)<br />
2.1 Overview <strong>of</strong> Scope <strong>of</strong> Work<br />
The Scope <strong>of</strong> Work for the e-governance systems proposed through this RFP requires the following:<br />
1. Electronic Communication Solutions Module<br />
2. E-ticketing Solutions Module<br />
3. Financial Planning and budgeting Solutions Module<br />
For details, please refer to Volume 1 on <strong>Project</strong> <strong>Requirements</strong>.<br />
Each <strong>of</strong> the three modules would entail the phases <strong>of</strong>:<br />
<strong>Project</strong> Planning Process<br />
<strong>Requirements</strong> Analysis<br />
Solution Design<br />
System Development<br />
Solution Prototype, where required<br />
Entry <strong>of</strong> Historical Data<br />
Testing and Acceptance<br />
Documentation<br />
User Training, Operations and Maintenance<br />
RFP Volume 2: Commercial and Bidding Terms Page 5
Request for Proposal for establishing e-Governance Systems<br />
3 Constitution <strong>of</strong> the Team<br />
3.1 Overview<br />
3.1.1 Given the scale <strong>of</strong> the project, it is required that bidder proposes personnel that<br />
are highly dedicated and experienced in their fields.<br />
3.1.2 Bidder must note the minimum requisite positions which shall be used for<br />
technical evaluation are given below.<br />
3.1.3 Bidder is required to make an independent evaluation <strong>of</strong> all positions that are<br />
3.2 Team Structure<br />
<strong>Project</strong> Management Team<br />
required to be filled in order to meet the requirements <strong>of</strong> the project.<br />
Electronic<br />
Communication<br />
Module<br />
E-ticketing Module Financial Planning<br />
and Budgeting<br />
Module<br />
ProgramManager One Program Manager with at least 10-12 years <strong>of</strong> experience in<br />
similar implementations.<br />
<strong>Project</strong> Manager One <strong>Project</strong><br />
Manager with at<br />
least 10 years<br />
experience with email<br />
implementations.<br />
<strong>Project</strong> Implementation Team<br />
Business Analyst At least 8 years<br />
experience<br />
Solution Architect (Infrastructure and<br />
Hardware)<br />
Solution Architect (Network and<br />
Security)<br />
Solution Architect<br />
(Application/S<strong>of</strong>tware)<br />
Operations Team<br />
One <strong>Project</strong><br />
Manager with at<br />
least 10 years<br />
experience, with at<br />
least one e-ticketing<br />
implementation.<br />
At least 8 years<br />
experience<br />
Not required At least 5 years<br />
experience<br />
At least 5 years<br />
experience<br />
At least 5 years<br />
experience<br />
Not required At least 5 years<br />
experience<br />
Module Leader - post implementation One person with at least 6-8 years experience<br />
One <strong>Project</strong><br />
Manager with at<br />
least 10 years<br />
experience, with at<br />
least one Finance<br />
and Accounts<br />
s<strong>of</strong>tware module<br />
implementation.<br />
At least 8 years<br />
experience<br />
At least 5 years<br />
experience<br />
At least 5 years<br />
experience<br />
At least 5 years<br />
experience<br />
RFP Volume 2: Commercial and Bidding Terms Page 6
Request for Proposal for establishing e-Governance Systems<br />
3.3 Personnel Pr<strong>of</strong>ile<br />
The required pr<strong>of</strong>ile <strong>of</strong> the personnel mentioned above is as follows:<br />
3.3.1 Program Manager<br />
3.3.1.1 Pr<strong>of</strong>ile<br />
3.3.2 <strong>Project</strong> Manager<br />
(S)He must have a minimum <strong>of</strong> 10-12 years experience in IT with a<br />
minimum <strong>of</strong> 8 years in Program Management.<br />
(S)He must preferably have qualifications in <strong>Project</strong> Management<br />
(e.g., PMP certified).<br />
(S)He should have extensive experience and proven expertise in<br />
managing similar multi module contracts <strong>of</strong> this type and<br />
complexity.<br />
3.3.1.2 Responsibility<br />
(S)He should be responsible for organizing, planning, directing, and<br />
coordinating the overall program effort.<br />
(S)He should be responsible for allocating resources to the project<br />
modules.<br />
3.3.2.1 Pr<strong>of</strong>ile<br />
(S)He should be responsible for conflict management, issue and<br />
dispute resolution.<br />
(S)He should participate in all fortnightly / monthly project<br />
meetings and project review meetings.<br />
(S)He should review quality <strong>of</strong> project deliverables to ensure<br />
compliance with the agreed quality measures and standards.<br />
(S)He should ensure compliance with the Terms and Conditions <strong>of</strong><br />
the Contract and NDA signed with ASI.<br />
(S)He must have a graduation degree in Engineering.<br />
(S)He must have a minimum <strong>of</strong> 10 years experience in IT with<br />
minimum 5 years in senior managerial positions.<br />
(S)He must have PMP or an equivalent certification.<br />
3.3.2.2 Responsibility<br />
RFP Volume 2: Commercial and Bidding Terms Page 7
Request for Proposal for establishing e-Governance Systems<br />
3.3.3 Business Analyst<br />
(S)He should be responsible for the overall module performance<br />
for the entire duration <strong>of</strong> the contract and should be dedicated to<br />
this project for the entire duration <strong>of</strong> this contract.<br />
(S)He should be responsible for organizing, planning, directing, and<br />
coordinating the module effort.<br />
(S)He should participate in the Module related meetings.<br />
(S)He should be responsible for managing the module team<br />
resources and ensuring their optimum allocation.<br />
(S)He should review the integration test plan for completeness and<br />
correctness.<br />
3.3.3.1 Pr<strong>of</strong>ile<br />
(S)He should manage integration testing along with Solution<br />
Architect (S<strong>of</strong>tware) and Testing Engineers.<br />
(S)He should prepare Performance Test Plan which would specify<br />
the business transactions that would be tested for performance.<br />
(S)He should be responsible for organizing, planning, directing, and<br />
coordinating the efforts for the module.<br />
(S)He should have a thorough understanding and knowledge <strong>of</strong> the<br />
principles and methodologies associated with program<br />
management, vendor management, quality assurance metrics and<br />
techniques, and configuration management tools.<br />
(S)He must have an overall IT experience <strong>of</strong> not less than 8 years<br />
as Business Analyst in IT industry.<br />
(S)He shall be atleast a B Tech or B.E or have a Masters degree in<br />
Business Administration<br />
3.3.3.2 Responsibility<br />
(S)He should be the key resource for studying all redesigned<br />
workflows/ processes and identifying the critical workflows for the<br />
envisaged solution.<br />
RFP Volume 2: Commercial and Bidding Terms Page 8
Request for Proposal for establishing e-Governance Systems<br />
(S)He should lead the requirement gathering exercise by<br />
conducting meetings with the various process owners and the<br />
<strong>Project</strong> Management Team.<br />
(S)He should have the ability to intelligently probe department<br />
personnel and study the processes to understand the challenges<br />
that need to be addressed through the application<br />
(S)He should work in collaboration with the <strong>Project</strong> Manager to<br />
ensure that the gathered requirements are in line with the <strong>Project</strong><br />
Vision.<br />
(S)He should be able to identify the use cases for all processes<br />
(S)He should be most visible in the initial requirement gathering<br />
stage <strong>of</strong> the project<br />
3.3.4 Solution Architect (Infrastructure and Hardware)<br />
3.3.4.1 Pr<strong>of</strong>ile<br />
(S)He must have a minimum <strong>of</strong> 5 years experience in designing and<br />
implementation <strong>of</strong> similar infrastructure.<br />
(S)He must be qualified as a B.E., or M.C.A from a reputed<br />
university.<br />
3.3.4.2 Responsibility<br />
The Infrastructure Architect should have the capability to design<br />
platform solutions to support applications, including their<br />
integration with database, network, and storage solutions.<br />
(S)He should possess extensive detailed working knowledge and<br />
acumen in the enterprise architecture best practices, including, but<br />
not limited to, logical and physical data architectures, network<br />
communications, operating systems, applications, data base<br />
servers, application servers, web servers, server consolidation,<br />
server performance, middleware, etc.<br />
(S)He should have the ability to address specialized and complex<br />
infrastructure architectural issues. (S)He should have extensive<br />
experience in infrastructure architecture discipline(s) <strong>of</strong> similar<br />
complexity as described in the RFP.<br />
RFP Volume 2: Commercial and Bidding Terms Page 9
Request for Proposal for establishing e-Governance Systems<br />
3.3.5 Solution Architect (Network & Security)<br />
3.3.5.1 Pr<strong>of</strong>ile<br />
(S)He should have extensive experience in Implementation specific<br />
network architectures <strong>of</strong> similar complexity as described in the<br />
RFP.<br />
(S)He should be BE/B.Tech and preferably M.Tech<br />
Diploma / Relevant certification in networking would be preferred.<br />
(S)He should have a minimum <strong>of</strong> 5 years experience in designing<br />
and implementation <strong>of</strong> similar network infrastructure.<br />
3.3.5.2 Responsibility<br />
The Solution Architect should have the capability to address key<br />
security and privacy requirements <strong>of</strong> the network. (S)He should<br />
implement using appropriate technologies and thereby design<br />
secure network solutions.<br />
(S)He should have specialization on a range <strong>of</strong> solutions, including,<br />
but not limited to, making appropriate use <strong>of</strong> Public Key<br />
Infrastructure (PKI), intrusion detection / prevention, Virtual<br />
Private Network (VPN), single sign-on, firewalls, and all elements <strong>of</strong><br />
network-level security.<br />
(S)He should possess extensive knowledge and experience in<br />
network technology, network design, operations, encryption,<br />
information access, and authentication processes.<br />
(S)He should provide solutions to complex security-related<br />
architectural issues.<br />
3.3.6 Solution Architect (Application / S<strong>of</strong>tware)<br />
3.3.6.1 Pr<strong>of</strong>ile<br />
(S)He must have a graduation degree in Engineering with MCA or<br />
M. Tech.<br />
(S)He must have a minimum 5 years experience in Solution Design<br />
3.3.6.2 Responsibility<br />
(S)He should be responsible for creating or selecting the most<br />
appropriate architecture for a system (or systems), such that it<br />
RFP Volume 2: Commercial and Bidding Terms Page 10
Request for Proposal for establishing e-Governance Systems<br />
suits the business needs, satisfies user requirements, and achieves<br />
the desired results under given constraints.<br />
(S)He should create Overall technical design (System Design<br />
Document - SDD) <strong>of</strong> the system consisting <strong>of</strong> project standards, the<br />
functional design and the database design.<br />
(S)He should facilitate High level planning for the development -<br />
overall steps for creation <strong>of</strong> the solution (Low Level Design – LLD)<br />
from the blueprints.<br />
(S)He should develop integration test cases and include these in<br />
integration test plan. These test cases should focus primarily on<br />
testing the interfaces <strong>of</strong> the modules. Each test case should be<br />
described along with the input and output data, and the results<br />
expected after each test case.<br />
(S)He should have a thorough understanding <strong>of</strong> the technical and<br />
quality standards and ensure adherence to those in order to<br />
maximize the future investment value and minimizing costs.<br />
(S)He should be most visible during the requirements and design<br />
stages <strong>of</strong> a project lifecycle, but should proactively monitor the<br />
adherence <strong>of</strong> the implementation to the chosen architecture<br />
during all iterations.<br />
3.3.7 Module Leader - Post Implementation<br />
3.3.7.1 Pr<strong>of</strong>ile<br />
(S)He should have an experience <strong>of</strong> over 6-8 years in the<br />
application falling under the module and at least 5 years <strong>of</strong> team<br />
leader experience <strong>of</strong> application maintenance and management<br />
(S)He must be qualified as a B.E./B.Tech, M.C.A, M.E./M.Tech from<br />
a reputed university.<br />
3.3.7.2 Responsibility<br />
(S)He should be responsible for planning and scheduling <strong>of</strong> the<br />
module related activities along with <strong>Project</strong> Manager.<br />
(S)He should have a thorough understanding <strong>of</strong> the complexity <strong>of</strong><br />
the module to be implemented along with the dependencies on<br />
other modules.<br />
RFP Volume 2: Commercial and Bidding Terms Page 11
Request for Proposal for establishing e-Governance Systems<br />
(S)He should manage the flow <strong>of</strong> work within the team and ensure<br />
optimum allocation <strong>of</strong> work amongst team members.<br />
(S)He should be responsible for controlling the overall maintenance<br />
<strong>of</strong> the applications in the module.<br />
(S)He should coordinate with ASI team for regular updates on the<br />
application<br />
3.4 General instructions for proposing the team<br />
(S)He should coordinate with the relevant Programmers, Business<br />
Analysts and Testing Engineers for Unit & System Testing.<br />
(S)He should be able to assist ASI personnel in ensuring proper<br />
maintenance and regular backup <strong>of</strong> application data<br />
(S)He should have an understanding <strong>of</strong> all the applications and<br />
business requirements <strong>of</strong> the module.<br />
3.4.1 Bidder should provide adequate number <strong>of</strong> personnel each responsible for a<br />
specific role within the system. Bidder must provide clear definition <strong>of</strong> the role<br />
and responsibility <strong>of</strong> each individual personnel.<br />
3.4.2 Bidder should have a defined hierarchy and reporting structure for various teams<br />
that would be part <strong>of</strong> the project.<br />
3.4.3 Bidder should ensure that all the personnel identified for this project have high<br />
level <strong>of</strong> integrity. Bidder should undertake necessary due diligence to ensure that<br />
the personnel have high standard <strong>of</strong> trustworthiness. Bidder should obtain an<br />
undertaking from each <strong>of</strong> the personnel assigned and the same should be<br />
submitted to ASIas and when demanded by ASI. Any information needed for this<br />
activity by ASI should be provided immediately by Bidder.<br />
3.4.4 Bidder must ensure that the minimum number and type <strong>of</strong> Key Personnel are<br />
proposed, failing which the proposal would be considered as non-responsive.<br />
Bidder can provide additional manpower on the basis <strong>of</strong> their estimate <strong>of</strong> effort<br />
required to complete the terms <strong>of</strong> reference given in the RFP.<br />
3.4.5 Bidder can <strong>of</strong>fer more than one key personnel for a role to improve the quality <strong>of</strong><br />
key personnel keeping in mind the terms <strong>of</strong> reference given in the RFP.<br />
3.5 Expected effort from Key Personnel deployed by Bidder<br />
RFP Volume 2: Commercial and Bidding Terms Page 12
Request for Proposal for establishing e-Governance Systems<br />
Sr. No. Role<br />
Number <strong>of</strong><br />
personnel<br />
Minimum number <strong>of</strong> person-months<br />
expected<br />
1. Program Manager 1 At least 1 full day per month<br />
2. <strong>Project</strong> Manager 3* Full time till project implementation<br />
3. Solution Architect<br />
(S<strong>of</strong>tware)<br />
4. Solution Architect<br />
(Infrastructure and<br />
Hardware)<br />
5. Solution Architect<br />
(Network & Security)<br />
At least 1 full day per week post go-live<br />
during contract period<br />
2* 6 person-months per person<br />
2* 6 person months per person<br />
3* 6 person months per person for e-<br />
ticketing and Financial Planning and<br />
Budgeting, and 1 person month for<br />
Electronic Communication<br />
6. Business Analyst 3 6 person months per person for e-<br />
ticketing and Financial Planning and<br />
Budgeting, and 1 person month for<br />
Electronic Communication<br />
* Roles could be combined across modules, provided the Bidder can ensure adequate availability as<br />
required for implementation.<br />
RFP Volume 2: Commercial and Bidding Terms Page 13
Request for Proposal for establishing e-Governance Systems<br />
4 <strong>Project</strong> Implementation<br />
4.1 Approach & Methodology for Implementation <strong>of</strong> Technical Solution<br />
The implementation <strong>of</strong> the Modules would be in four phases. These phases are based on<br />
the criticality <strong>of</strong> the solutions to be provided by the Bidder. Approach for Implementation<br />
<strong>of</strong> technical Solution is provided below for better understanding <strong>of</strong> the Bidder.<br />
The application architecture has been classified based on the criticality <strong>of</strong> the functions<br />
into the following four phases <strong>of</strong> Go-Live with the corresponding tentative timelines:<br />
Sr.<br />
No.<br />
GO-Live phases Application modules Go-live timeline<br />
1 Go-Live<br />
(Module1)<br />
2 Go-Live<br />
(Module 2)<br />
3 Go-Live<br />
(Module 3)<br />
4 Go-Live<br />
(Counter Management)<br />
Electronic Communication Module T + 8 weeks<br />
E-ticketing Module T + 20 weeks<br />
Financial Planning and Budgeting<br />
Module<br />
T + 16 weeks<br />
E-ticketing Counter Management T + 22 weeks<br />
Bidders are advised to study the implementation approach carefully and propose the<br />
technical solution based on the implementation approach. It is expected that for “go-live”<br />
<strong>of</strong> each phase, Bidder would provide application prototype (if required), use cases,<br />
application hosting, and training to ASI’s personnel.<br />
All the modules presented above are defined in Volume 1 <strong>of</strong> this RFP document.<br />
Strategy for IT infrastructure for end-user:The SI will assess existing IT infrastructure,<br />
procure, deploy and maintain the necessary hardware, networking and peripherals in order<br />
to meet the project requirements.An indicative Bill <strong>of</strong> Materials has been provided in RFP<br />
Volume 1, Annexure 3 These will be owned by ASI.<br />
RFP Volume 2: Commercial and Bidding Terms Page 14
Request for Proposal for establishing e-Governance Systems<br />
4.2 <strong>Project</strong> Timelines<br />
Bidder is expected to follow the schedule as mentioned in the table below. Each <strong>of</strong> the milestones should be accompanied with a presentation on the<br />
deliverables by the bidder, related to that milestone. The submission <strong>of</strong> deliverable will be deemed complete after the submission <strong>of</strong> the hard / s<strong>of</strong>t copy <strong>of</strong><br />
the deliverable and the presentation by the bidder.<br />
The “Expected Date <strong>of</strong> Completion” as mentioned in the table below is the date by which the deliverable shall be submitted to the ASI. The Bidder shall<br />
ensure that the deliverable is accepted by the ASI as per schedule mentioned in the table below post review.<br />
Table 1: Timelines and Deliverables <strong>of</strong> the <strong>Project</strong><br />
Sr.<br />
No.<br />
1. <strong>Project</strong> Planning and submission<br />
<strong>of</strong> project plan<br />
2. Requirement study gathering and<br />
review <strong>of</strong> existing applications<br />
3. Preparation <strong>of</strong> S<strong>of</strong>tware<br />
<strong>Requirements</strong> Specification,<br />
Item Expected Date <strong>of</strong><br />
Submission from ‘T’<br />
Final<br />
acceptance<br />
post review<br />
T + 1 weeks Within 1 week<br />
post review<br />
T + 1 weeks for Electronic<br />
Communication Module<br />
T + 2 weeks for E-ticketing<br />
and Financial Planning and<br />
Budgeting Modules<br />
T + 1 week for Electronic<br />
Communication Module<br />
Payment<br />
Milestone<br />
RFP Volume 2: Commercial and Bidding Terms Page 15<br />
Deliverables<br />
[M0] <strong>Project</strong> Management services and<br />
Preparation <strong>of</strong> <strong>Project</strong> Plan<br />
Within 1 week None<br />
<strong>Project</strong> Management, Configuration<br />
Management and Issue Tracker tools<br />
<strong>Project</strong> performance reports formats<br />
Within 2 weeks System Requirement Specifications (SRS)<br />
Document (including customizations, if
Request for Proposal for establishing e-Governance Systems<br />
Sr.<br />
No.<br />
Item Expected Date <strong>of</strong><br />
Submission from ‘T’<br />
System design T + 3 weeks for E-ticketing<br />
and Financial Planning and<br />
Budgeting Modules<br />
4. Training for Go-Live for Electronic<br />
Communication Module<br />
5. Go-Live for Electronic<br />
Communication Module<br />
6. Preparation <strong>of</strong> User Acceptance<br />
test cases and test plan for<br />
Modules 2 and 3<br />
7. Commissioning <strong>of</strong> environment<br />
for Prototype Development for eticketing<br />
Module<br />
8. Sign-<strong>of</strong>f from stakeholders after<br />
Prototype demonstration<br />
9. Data Migration Plan for Financial<br />
Planning and Budgeting Module<br />
10. Procurement and deployment <strong>of</strong><br />
datacenter and IT infrastructure<br />
11. Preparation for User Acceptance<br />
Test for Financial Planning and<br />
Budgeting Module<br />
Final<br />
acceptance<br />
post review<br />
Payment<br />
Milestone<br />
RFP Volume 2: Commercial and Bidding Terms Page 16<br />
any)<br />
Deliverables<br />
System Design document (SDD)<br />
T+ 3 weeks Within 1 week Evaluating Training Feedback and<br />
training content / methodology<br />
T + 6 weeks Within 2 week [M 1] Roll-out checklist and plan<br />
T + 6 weeks Within 2 weeks User Acceptance Test Cases<br />
T + 6 weeks Within 2 weeks<br />
post review<br />
User Acceptance Plan<br />
Development <strong>of</strong> Prototype and Functional<br />
acceptance on Prototype<br />
T + 8 weeks Within 1 week Workshop for review and sign-<strong>of</strong>f<br />
T + 12 weeks Within 1 week Detailed Plan for Data Migration<br />
T + 14 weeks Within 2 weeks Certifications <strong>of</strong> deployment completion<br />
at each site given to bidder by concerned<br />
ASI <strong>of</strong>ficial / third party<br />
T + 12 weeks Within 1 week User Acceptance Test Cases<br />
User Acceptance Plan
Request for Proposal for establishing e-Governance Systems<br />
Sr.<br />
No.<br />
12. Data Migration for Financial<br />
Planning and Budgeting Module<br />
13. Training for Go-Live for Financial<br />
Planning and Budgeting Module<br />
14. User Acceptance Testing before<br />
Go-Live for Financial Planning<br />
and Budgeting Module<br />
15. Go-Live for Financial Planning<br />
and Budgeting Module<br />
16. Transition <strong>of</strong> existing ticketing<br />
Counters at each <strong>of</strong> the 10 pilot<br />
ASI monuments<br />
17. Preparation for User Acceptance<br />
Test for e-ticketing Module<br />
18. Training for Go-Live fore-ticketing<br />
Module<br />
19. User Acceptance Testing before<br />
for e-ticketing Module<br />
Item Expected Date <strong>of</strong><br />
Submission from ‘T’<br />
Final<br />
acceptance<br />
post review<br />
Payment<br />
Milestone<br />
RFP Volume 2: Commercial and Bidding Terms Page 17<br />
Deliverables<br />
T + 14 weeks Within 1 week Data Migration Completion Report<br />
T + 15 weeks<br />
T + 14 weeks Within 1 week<br />
post review<br />
Within 1 week Evaluating Training Feedback and<br />
tuning training content / methodology<br />
Testing report with fail / pass results<br />
and plan to fix the defects<br />
Test cases<br />
T + 16 weeks Within 2 week [M 2] Roll-out checklist and plan<br />
T + 18 weeks Within 1 week Transition completion report<br />
T + 16 weeks Within 1 week User Acceptance Test Cases<br />
T + 16 weeks for eticketing<br />
Module<br />
T + 16 weeks Within 1 week<br />
post review<br />
User Acceptance Plan<br />
Within 1 week Evaluating Training Feedback and<br />
tuning training content / methodology<br />
Testing report with fail / pass results<br />
and plan to fix the defects<br />
Test cases<br />
20. Go-Livefor e-ticketing Module T + 18 weeks Within 2 week [M 3] Roll-out checklist and plan<br />
21. Transition <strong>of</strong> Counters T + 20 weeks Within 2 weeks Transition completion report
Request for Proposal for establishing e-Governance Systems<br />
Sr.<br />
No.<br />
22. Training for e-ticketing counter<br />
Management<br />
Item Expected Date <strong>of</strong><br />
Submission from ‘T’<br />
Final<br />
acceptance<br />
post review<br />
Payment<br />
Milestone<br />
RFP Volume 2: Commercial and Bidding Terms Page 18<br />
Deliverables<br />
T + 20 weeks Within 1 week Evaluating Training Feedback and<br />
tuning training content / methodology<br />
Till end <strong>of</strong> Contract period NA installments,<br />
Quarterly performance appraisal<br />
reports<br />
For each year <strong>of</strong> support and<br />
based on the<br />
SLAs<br />
maintenance phase:<br />
Monthly log <strong>of</strong> service calls and<br />
problem resolution reports for Helpdesk<br />
23. Operation <strong>of</strong> the Counters 6 months NA Equated<br />
quarterly<br />
24. Maintenance and Technical<br />
Support for all the Systems<br />
T indicates the project kick-<strong>of</strong>f date<br />
Quarterly Performance Monitoring<br />
Reports for the system<br />
Updated system design documents,<br />
specifications for every change request<br />
Latest source code, application<br />
deployment files, configuration files for<br />
entire solution<br />
Updated user manuals, administration<br />
manuals, training manuals etc<br />
S<strong>of</strong>tware change logs
Request for Proposal for establishing e-Governance Systems<br />
5 Implementation Model<br />
5.1 Operation Model<br />
SI will propose an operation model commensurate with the requirements <strong>of</strong> ASI. It is proposed that<br />
the SI will take into consideration the following objectives <strong>of</strong> ASI:<br />
1. Enhancement <strong>of</strong> service delivery with respect to customer interface<br />
2. Increased efficiency <strong>of</strong> internal communication<br />
3. Reduced effort and time for generating financial reports<br />
For specific operations models for each <strong>of</strong> the modules, refer to Volume 1 <strong>of</strong> the RFP.<br />
RFP Volume 2: Commercial and Bidding Terms Page 19
Request for Proposal for establishing e-Governance Systems<br />
6 Payment Terms & Schedule<br />
6.1 Payment Terms<br />
6.1.1 ASI shall make payments to the Bidder at the times and in the manner set out in the Payment<br />
schedule as specified in Section 7.2 below. ASI will make all efforts to make payments to the<br />
Bidder within 30 days <strong>of</strong> receipt <strong>of</strong> invoice(s) and all necessary supporting documents.<br />
6.1.2 All payments agreed to be made by ASI to the Bidder in accordance with the Bid shall be<br />
inclusive <strong>of</strong> all statutory levies, duties, taxes and other charges whenever levied/applicable, if<br />
any, and ASI shall not be liable to pay any such levies/ other charges under or in relation to<br />
this Contract and/or the Services.<br />
6.1.3 No invoice for extra work/ change order on account <strong>of</strong> change order will be submitted by the<br />
Bidder unless said extra work /change order has been authorized/approved by the ASI in<br />
writing in accordance with Change Control Schedule.<br />
6.1.4 Contract would be signed for 3 years. Based on the performance <strong>of</strong> the Implementation<br />
Agency, ASI may decide to extend the period <strong>of</strong> contract by 2 years.Contract rates for the<br />
extended 2 years would be based on the rates <strong>of</strong> AMC for 3 rd year and would be negotiable<br />
between the Bidder and the ASI. ASI is not bound to extend the contract period by two<br />
years.<br />
6.1.5 Bidder needs to provide rationale for the commercial quotes provided. ASI holds the right to<br />
ask for an explanation <strong>of</strong> the rationale from the Bidder<br />
6.1.6 In the event <strong>of</strong> ASI noticing at any time that any amount has been disbursed wrongly to the<br />
Bidder or any other amount is due from the Bidder to the ASI, the ASI may without prejudice<br />
to its rights recover such amounts by other means after notifying the Bidder or deduct such<br />
amount from any payment falling due to the Bidder. The details <strong>of</strong> such recovery, if any, will<br />
be intimated to the Bidder. The Bidder shall receive the payment <strong>of</strong> undisputed amount<br />
under subsequent invoice for any amount that has been omitted in previous invoice by<br />
mistake on the part <strong>of</strong> the ASI or the Bidder.<br />
6.1.7 All payments to the Bidder shall be subject to the deductions <strong>of</strong> tax at source under Income<br />
Tax Act and other taxes, and deductions as provided for under any law, rule or regulation. All<br />
costs, damages or expenses which ASI may have paid or incurred, for which under the<br />
provisions <strong>of</strong> the Contract, the Bidder is liable, the same shall be deducted by ASI from any<br />
dues to the Bidder. All payments to the Bidder shall be made after making necessary<br />
deductions as per terms <strong>of</strong> the Contract and recoveries towards facilities, if any, provided by<br />
the ASI to the Bidder on chargeable basis.<br />
6.2 Payment Schedule<br />
Total Contract Value is the total value mentioned by the Bidder in Section 10.4.2 in this<br />
volume <strong>of</strong> RFP.<br />
RFP Volume 2: Commercial and Bidding Terms Page 20
Request for Proposal for establishing e-Governance Systems<br />
S.<br />
No.<br />
<strong>Project</strong> Milestone<br />
1. Commencement <strong>of</strong> the project 10%<br />
2.<br />
3.<br />
4.<br />
5.<br />
Acceptance <strong>of</strong> System - Solution Go-Live<br />
Module 1<br />
Acceptance <strong>of</strong> System - Solution Go-Live<br />
Module 2<br />
Acceptance <strong>of</strong> System – Solution Go-Live<br />
Module 3<br />
Total Operation & Maintenance Support<br />
Post Implementation Phase including:<br />
<strong>Project</strong> Management<br />
Technical Support & Helpdesk<br />
Operations <strong>of</strong> -POS Counters and Call<br />
Center<br />
A Year 2 Operation & Maintenance Support<br />
B Year 3 Operation & Maintenance Support<br />
Payment (percentage <strong>of</strong> total<br />
Contract value)<br />
RFP Volume 2: Commercial and Bidding Terms Page 21<br />
10%<br />
20%<br />
20%<br />
40%<br />
Operation & maintenance cost<br />
would be paid in equated<br />
quarterly installments <strong>of</strong> each<br />
year’s payout as mentioned<br />
below<br />
5% <strong>of</strong> total contract value<br />
would be paid per quarter<br />
(5%*4=20% <strong>of</strong> total annual<br />
contract value would be paid in<br />
year 2)<br />
5% <strong>of</strong> total contract value<br />
would be paid per quarter<br />
(5%*4=20% <strong>of</strong> total annual<br />
contract value would be paid in<br />
year 3)
Request for Proposal for establishing e-Governance Systems<br />
7 Bidding Process Details<br />
7.1 Bidding Schedule<br />
7.1.1 Name <strong>of</strong> the Purchaser:<br />
<strong>Archaeological</strong> <strong>Survey</strong> <strong>of</strong> <strong>India</strong><br />
7.1.2 Addressee and Address at which RFPs to be submitted:<br />
Director – Administration<br />
<strong>Archaeological</strong> <strong>Survey</strong> <strong>of</strong> <strong>India</strong><br />
Janpath, New Delhi - 110011<br />
Phone: +91-11-23018614<br />
Fax: +91-11- 23010789<br />
websiteasi@gmail.com<br />
7.1.3 Latest time and date for receipt <strong>of</strong> RFP<br />
On or before 1500 hours on Monday, 12 December 2011<br />
7.1.4 Date till which the response to the RFP should be valid:<br />
7.1.5 Important dates:<br />
180 days from the date <strong>of</strong> opening <strong>of</strong> the Technical Bids<br />
The following table provides information regarding the important dates <strong>of</strong> the bid<br />
process for this RFP:<br />
RFP Volume 2: Commercial and Bidding Terms Page 22
Request for Proposal for establishing e-Governance Systems<br />
Activity Date<br />
Release <strong>of</strong> RFP (Request for Proposal) Wednesday, 9-Nov-11<br />
Last date for submission <strong>of</strong> clarifications by bidders Wednesday, 16-Nov-11<br />
Pre-Bid Conference Saturday, 19-Nov-11<br />
Response to bidder queries Monday, 21-Nov-11<br />
Last date for submission <strong>of</strong> Bids Monday, 12-Dec-11<br />
Pre Qualification Bid opening Monday, 12-Dec-11<br />
Date for opening <strong>of</strong> Technical Bids for qualified bidders Monday, 19-Dec-11<br />
Date for Technical Presentations or Pro<strong>of</strong> <strong>of</strong> Concept Monday, 26-Dec-11<br />
Date for opening <strong>of</strong> Commercial Bids for qualified bidders Monday, 2-Jan-12<br />
Award <strong>of</strong> Contract Monday, 16-Jan-12<br />
7.1.6 Bidders must note that bids received after due date and time shall be rejected. The bids shall<br />
be submitted in the sealed box kept in the <strong>of</strong>fice <strong>of</strong> the ADG at the address mentioned in<br />
Section 8.1.2 above.<br />
7.2 General Instruction to Bidders<br />
7.2.1 Cost <strong>of</strong> Bidding Process<br />
7.2.1.1 The Bidder shall bear all costs associated with the preparation and<br />
submission <strong>of</strong> its bid, including cost <strong>of</strong> presentation for the purposes <strong>of</strong><br />
clarification <strong>of</strong> the bid, if so desired by ASI.<br />
7.2.1.2 ASI will in no case be responsible or liable for the above mentioned costs,<br />
7.2.2 Bid Prices<br />
regardless <strong>of</strong> the conduct or outcome <strong>of</strong> the Tendering process.<br />
7.2.2.1 The Bidder shall indicate in the pr<strong>of</strong>orma prescribed at Section 10.4.2 <strong>of</strong><br />
Volume 2, the unit rates and total Bid Prices <strong>of</strong> the goods and services, it<br />
proposes to provide under the Contract. Prices should be shown separately<br />
for each item as detailed in Bid Documents.<br />
7.2.2.2 In absence <strong>of</strong> information as requested in Section 8.2.2.1 above, a bid shall<br />
be considered incomplete and summarily rejected.<br />
7.2.2.3 The Bidder shall prepare the bid based on details provided in the RFP<br />
documents. The Bidder shall carry out all the tasks in accordance with the<br />
RFP Volume 2: Commercial and Bidding Terms Page 23
Request for Proposal for establishing e-Governance Systems<br />
requirement <strong>of</strong> the RFP documents and it shall be the responsibility <strong>of</strong> the<br />
Bidder to fully meet all the requirements <strong>of</strong> the RFP documents.<br />
7.2.2.4 The Bidder as part <strong>of</strong> its Commercial Bid should account for all out <strong>of</strong> pocket<br />
and other expenses that the Bidder shall incur during the contract period.<br />
7.2.2.5 It is mandatory that Unit rates should be indicated in the Table as per the<br />
7.2.3 Firm Prices<br />
pr<strong>of</strong>orma prescribed at Section 10.4.2 <strong>of</strong> Volume 2 <strong>of</strong> this RFP. This may be<br />
used by ASI for any changes to scope.<br />
7.2.3.1 Prices quoted must be firm and final and shall remain constant throughout<br />
the period <strong>of</strong> the contract and shall not be subject to any upward<br />
modifications, on any account whatsoever. The Bidder shall, therefore,<br />
indicate the prices in Section 10.4.2 <strong>of</strong> Volume 2 enclosed with the Bid. The<br />
Bid Prices shall be indicated in <strong>India</strong>n Rupees (INR) only.<br />
7.2.3.2 The Commercial bid should clearly indicate the price to be charged without<br />
any qualifications whatsoever and should include all taxes (sales, service,<br />
etc.), duties (excise & customs, etc), Octroi, fees, levies, works contract tax<br />
and other charges as may be applicable in relation to the activities proposed<br />
to be carried out. It is mandatory that such charges wherever<br />
applicable/payable should be indicated separately in Section 10.4.2 <strong>of</strong><br />
Volume 2.<br />
7.2.3.3 A proposal submitted with an adjustable price quotation or conditional<br />
7.2.4 Discount<br />
proposal shall be treated as non-responsive and the bid shall be rejected<br />
summarily.<br />
7.2.4.1 The Bidders are advised not to indicate any separate discount. Discount, if<br />
7.2.5 Bidder Authorization<br />
any, should be merged with the quoted prices. Discount <strong>of</strong> any type,<br />
indicated separately, will not be taken into account for evaluation purpose.<br />
RFP Volume 2: Commercial and Bidding Terms Page 24
Request for Proposal for establishing e-Governance Systems<br />
7.2.5.1 The "Bidder" shall mean the one who has signed the RFP Form. The Bidder<br />
may be either the Principal Officeror his/her duly Authorized Representative,<br />
in which case he/she shall submit a power <strong>of</strong> attorney with the RFP<br />
response. All certificates and documents (including any clarifications sought<br />
and any subsequent correspondences) received hereby, shall, as far as<br />
possible, be furnished and signed by the representative.<br />
7.2.5.2 It is further clarified that the individual signing the tender or other<br />
documents in connection with the RFP must certify whether he/she signs as :<br />
Constituted attorney <strong>of</strong> the firm, if it is a company<br />
RFP Volume 2: Commercial and Bidding Terms Page 25<br />
OR<br />
The Principal <strong>of</strong>ficer or his/her duly Authorized Representative <strong>of</strong> the Bidder<br />
7.2.5.3 The authorization shall be indicated by power-<strong>of</strong>-attorney accompanying the<br />
bid.<br />
7.2.6 Particulars for Bid Security<br />
7.2.6.1 The Bidder shall furnish, as part <strong>of</strong> its bid, a bid security <strong>of</strong> the amount<br />
mentioned in Section 1.1.6 <strong>of</strong> this volume <strong>of</strong> RFP.<br />
7.2.6.2 The bid security is required to protect ASI against the risk <strong>of</strong> Bidder’s conduct<br />
which would warrant the security's forfeiture, pursuant to Section 8.2.6.7<br />
7.2.6.3 The bid security shall be denominated in <strong>India</strong>n Rupees, and shall be in the<br />
form <strong>of</strong> a demand draft issued by a Nationalized / Scheduled Bank<br />
7.2.6.4 No Bidder is exempted from furnishing <strong>of</strong> bid security.<br />
7.2.6.5 Unsuccessful Bidder’s bid security will be discharged/ returned after award<br />
<strong>of</strong> contract to the successful Bidder. No interest will be paid by ASI on the<br />
Bid security amount.<br />
7.2.6.6 The successful Bidder’s bid security will be discharged upon the Bidder<br />
executing the Contract, pursuant to Section 9.6 <strong>of</strong> Volume 2 <strong>of</strong> this RFP and
Request for Proposal for establishing e-Governance Systems<br />
furnishing the performance security, pursuant to Section 9.7 <strong>of</strong> Volume 2 <strong>of</strong><br />
this RFP.<br />
7.2.6.7 The bid security may be forfeited:<br />
a. if a Bidder withdraws its bid during the period <strong>of</strong> bid validity specified by the<br />
Bidder in the Bid; or<br />
7.2.7 Period <strong>of</strong> Validity <strong>of</strong> Bids<br />
b. in the case <strong>of</strong> a successful Bidder, if the Bidder fails:<br />
to sign the Contract or<br />
to furnish performance security in accordance<br />
7.2.7.1 Bids shall remain valid for period as stated in Section 8.1.4 <strong>of</strong> Volume 2 <strong>of</strong><br />
this RFP. A bid valid for a shorter period shall be rejected by ASI as non-<br />
responsive and shall not be taken up for evaluation purposes.<br />
7.2.7.2 ASI may request the Bidder(s) for an extension <strong>of</strong> the period <strong>of</strong> validity. The<br />
7.2.8 Revelation <strong>of</strong> Prices<br />
request and the responses thereto shall be made in writing (or by e-mail or<br />
fax). The validity <strong>of</strong> bid security provided under Section 1.1 in Volume 2 <strong>of</strong><br />
this RFP shall also be suitably extended.<br />
7.2.8.1 Prices in any form or by any reason before opening the Commercial Bid<br />
should not be revealed. If price change is envisaged due to any clarification,<br />
revised Bids in a separate sealed cover can be called from all the Bidders by<br />
ASI.<br />
7.2.9 Terms and Conditions <strong>of</strong> Bidders<br />
7.2.9.1 Printed terms and conditions (General Conditions) <strong>of</strong> the Bidder will not be<br />
considered as forming part <strong>of</strong> their Bids. In case terms and conditions <strong>of</strong> the<br />
contract applicable to this Invitation to bid are not acceptable to any Bidder,<br />
he should clearly specify deviation in his Technical Bid, Section 12, Annexure<br />
3 <strong>of</strong> Volume 2 <strong>of</strong> this RFP. Similarly in case the Services being <strong>of</strong>fered have<br />
RFP Volume 2: Commercial and Bidding Terms Page 26
Request for Proposal for establishing e-Governance Systems<br />
deviations from the requirements/specifications laid down in this RFP, the<br />
Bidder shall describe in what respects and to what extent the Services being<br />
<strong>of</strong>fered differ/deviate from the requirements, even though the deviations<br />
may not be very material. The Bidder must state categorically whether or<br />
not his <strong>of</strong>fer conforms to RFP requirements / specifications and indicate<br />
deviations, if any, in his Technical Bid (Section 12, Annexure 3 <strong>of</strong> Volume 2 <strong>of</strong><br />
this RFP).<br />
7.2.9.2 Any deviations / assumptions mentioned elsewhere in the Bid, other than<br />
the formats (Section 12, Annexure 3 <strong>of</strong> this volume) will not be considered<br />
by ASI.<br />
7.2.10 Local Conditions<br />
7.2.10.1 It will be imperative on each Bidder to fully acquaint himself with the local<br />
conditions and factors at the respective locations, sites and <strong>of</strong>fices which<br />
would have any effect on the performance <strong>of</strong> the contract and / or the cost.<br />
7.2.10.2 The Bidder is expected to obtain for himself on his own responsibility all<br />
information that may be necessary for preparing the bid and entering into<br />
contract. Obtaining such information shall be at Bidder’s own cost.<br />
7.2.10.3 Failure to obtain the information necessary for preparing the bid and/or<br />
failure to perform activities that may be necessary for designing an optimal<br />
solution before entering into contract will in no way relieve the successful<br />
Bidder from performing any work in accordance with the contract entered<br />
into.<br />
7.2.10.4 It will be imperative for each Bidder to fully inform themselves <strong>of</strong> all legal<br />
conditions and factors which may have any effect on the execution <strong>of</strong> the<br />
contract as described in the bidding documents.<br />
7.2.10.5 It is the responsibility <strong>of</strong> the Bidder that such factors have properly been<br />
investigated and considered while submitting the bid proposals and that no<br />
claim whatsoever including those for financial adjustment to the contract<br />
awarded under the bidding documents will be entertained by ASI and that<br />
neither any change in the time schedule <strong>of</strong> the contract nor any financial<br />
RFP Volume 2: Commercial and Bidding Terms Page 27
Request for Proposal for establishing e-Governance Systems<br />
adjustments arising there<strong>of</strong> shall be permitted by ASI on account <strong>of</strong> failure <strong>of</strong><br />
the Bidder to appraise themselves <strong>of</strong> local laws and conditions.<br />
7.2.11 Last Date for Receipt <strong>of</strong> Bids<br />
7.2.11.1 Bids will be received by ASI at the address specified under Section 8.1.2 not<br />
later than the time and date specified in Section 8.1.3. In the event <strong>of</strong> the<br />
specified date for the receipt <strong>of</strong> Bids being declared a holiday for ASI, the<br />
Bids will be received up to the appointed time on the next working day.<br />
7.2.11.2 ASI may, at its discretion, extend the last date for the receipt <strong>of</strong> bids by<br />
7.2.12 Late Bids<br />
amending the RFP Document, in which case all rights and obligations <strong>of</strong> ASI<br />
and Bidders previously subject to the last date will thereafter be subject to<br />
the last date as extended.<br />
7.2.12.1 Any bid received by ASI after the last date for receipt <strong>of</strong> bids prescribed by<br />
ASI will be rejected and/or returned unopened to the Bidder.<br />
7.2.13 Modification and Withdrawal <strong>of</strong> Bids<br />
7.2.13.1 No bid may be altered / modified subsequent to the closing time and date<br />
for submission <strong>of</strong> bids. Unsolicited correspondences from Bidders will not be<br />
considered.<br />
7.2.13.2 No bid may be withdrawn in the interval between the last date for receipt <strong>of</strong><br />
bids and the expiry <strong>of</strong> the bid validity period specified by the Bidder in the<br />
Bid. Withdrawal <strong>of</strong> a bid during this interval may result in the Bidder’s<br />
forfeiture <strong>of</strong> its bid security.<br />
RFP Volume 2: Commercial and Bidding Terms Page 28
Request for Proposal for establishing e-Governance Systems<br />
7.2.14 Address for Correspondence<br />
7.2.14.1 The Bidder has designated the <strong>of</strong>ficial mailing address, place and fax number<br />
7.2.15 Contacting ASI<br />
stated in Section 8.1.2. All correspondence shall be sent by ASI on this<br />
address only.<br />
7.2.15.1 No Bidder shall contact ASI on any matter relating to its bid, from the time <strong>of</strong><br />
the bid opening to the time the Contract is awarded.<br />
7.2.15.2 Any effort by a Bidder to influence ASI’s bid evaluation, bid comparison or<br />
7.3 Bid Submission Instructions<br />
contract award decisions may result in the rejection <strong>of</strong> the Bidder’s bid.<br />
7.3.1 Procedure for Submission <strong>of</strong> Bids<br />
7.3.1.1 Prequalification Bid (1 hard copy) in one separate cover.<br />
7.3.1.2 Technical Bid (1 hard copy) in one separate cover.<br />
7.3.1.3 Commercial Bid (1 hard copy) in one separate cover<br />
7.3.1.4 Each <strong>of</strong> the Prequalification Bid, Technical Bid and Commercial Bid <strong>of</strong> the RFP<br />
should be covered in separate sealed covers super scribing “Pre Qualification<br />
Bid”, "Technical Bid" and “Commercial Bid” respectively. Please Note that<br />
Prices should not be indicated in the Pre Qualification Bid or Technical Bid<br />
and should only be indicated in the Commercial Bid.<br />
7.3.1.5 The Prequalification and Technical Bid should be duly initialed by Authorized<br />
Signatory and stamped with correct name <strong>of</strong> the Bidder’s<br />
company/organization.<br />
7.3.1.6 The cover containing Prequalification Bid, Technical Bid and Commercial Bid<br />
as mentioned in clause 8.3.1.4 above should be put in another single sealed<br />
envelope clearly marked “Selection <strong>of</strong> Implementation Agency for ASI e-<br />
Governance <strong>Project</strong>”. This envelope is to be superscribed with RFP Number,<br />
Due Date and the wordings “DO NOT OPEN BEFORE 1500 hours on 12<br />
RFP Volume 2: Commercial and Bidding Terms Page 29
Request for Proposal for establishing e-Governance Systems<br />
December 2011”. Same details are to be marked on the covers <strong>of</strong> the<br />
Prequalification, Technical Bids and Commercial Bid also.<br />
7.3.1.7 The cover thus prepared, encapsulating the three bids as mentioned above,<br />
should also indicate clearly the name, address and telephone number <strong>of</strong> the<br />
Bidder.<br />
7.3.1.8 The bids received after the due date and time shall be summarily rejected<br />
and returned to the Bidder declaring as “Late submission” and the same shall<br />
not be opened.<br />
7.3.1.9 Each copy <strong>of</strong> the RFP should be a complete document and should be bound<br />
as a volume. The document should be page numbered and appropriately<br />
flagged and must contain the list <strong>of</strong> contents with page numbers.Different<br />
copies must be bound separately. If not properly bounded the ASI shall not<br />
be in any way responsible for loss <strong>of</strong> sheets due to inadvertent opening <strong>of</strong><br />
the document at any stage and that affecting the prospects <strong>of</strong> the Bidder<br />
during the evaluation due to loss <strong>of</strong> these documents.<br />
7.3.1.10 As part <strong>of</strong> the bid, Bidder should also provide the pre qualification, technical<br />
and commercial bid in editable s<strong>of</strong>t copy format, in the form <strong>of</strong> a non-re-<br />
writeable CD–R (Compact Disc) as follows:<br />
One CD containing the pre qualification bid - The CD containing pre<br />
qualification should be sealed along with the hard copy <strong>of</strong> the ‘Original’<br />
copy <strong>of</strong> the pre qualification bid<br />
One CD containing the technical bid - The CD containing technical bid<br />
should be sealed along with the hard copy <strong>of</strong> the ‘Original’ copy <strong>of</strong> the<br />
technical bid.<br />
One CD containing the commercial bid - The CD containing commercial<br />
bid should be sealed along with the hard copy <strong>of</strong> the ‘Original’ copy <strong>of</strong><br />
the commercial bid.<br />
All CDs submitted by the Bidder must be in sealed covers.The sealed<br />
covers as well as the CD media must be duly signed by the Bidder using<br />
a “Permanent Pen/Marker”, should be super scribed with “Pre<br />
RFP Volume 2: Commercial and Bidding Terms Page 30
Request for Proposal for establishing e-Governance Systems<br />
7.3.2 Language <strong>of</strong> Bids<br />
Qualification Bid” / “Technical Bid” / “Commercial Bid” (as the case may<br />
be) and should bear the name <strong>of</strong> the Bidder.<br />
Bidder must ensure that the information furnished by him in respective<br />
CDs is identical to that submitted by him in the original paper bid<br />
document. In case <strong>of</strong> any discrepancy observed by ASI in the contents<br />
<strong>of</strong> the CDs and original paper bid documents, the information furnished<br />
on original paper bid document will prevail over the s<strong>of</strong>t copy.<br />
Bidder must ensure that Technical Bid CD do not contain any<br />
Commercial items / prices.<br />
7.3.2.1 The Bids prepared by the Bidder and all correspondence and documents<br />
relating to the bids exchanged by the Bidder and ASI, shall be written in<br />
English language.<br />
7.3.3 Documents Comprising the Bids<br />
7.3.3.1 The bid prepared by the Bidder shall comprise <strong>of</strong> the following components:<br />
A. Pre Qualification Bid - The Prequalification shall comprise <strong>of</strong> the following:<br />
Section 10.1 - Covering Letter<br />
Section 10.2 – Prequalification Formats along with supporting documents<br />
Bid Security (Demand Draft)<br />
RFP document fees (Demand Draft)<br />
Power <strong>of</strong> Attorney executed by the Bidder in favor <strong>of</strong> the Principal Officer or<br />
the duly Authorized Representative, certifying him/her as an authorized<br />
signatory for the purpose <strong>of</strong> this RFP<br />
B. Technical Bid - The Technical Bid shall comprise <strong>of</strong> the following:<br />
Section 10.3 – Technical Formats<br />
Section 10.3.1 – Technical Bid Letter<br />
RFP Volume 2: Commercial and Bidding Terms Page 31
Request for Proposal for establishing e-Governance Systems<br />
Section 12 – Statement <strong>of</strong> Deviations<br />
C. Commercial Bid - The Commercial Bid shall comprise <strong>of</strong> the following:<br />
7.3.4 Format and Signing <strong>of</strong> Bid<br />
Section 10.4.1 - Commercial Bid Letter<br />
Section 10.4.2 - Breakdown <strong>of</strong> cost components<br />
7.3.4.1 The Bidder shall prepare one copy <strong>of</strong> the Bid.<br />
7.3.4.2 The original and all copies <strong>of</strong> the bid shall be typed or written in indelible ink.<br />
All pages <strong>of</strong> the ‘Original’ bid document shall be initialed and stamped by the<br />
person or persons signing the bid.<br />
7.3.4.3 The bid shall contain no interlineations, erasures or overwriting except as<br />
necessary to correct errors made by the Bidder, in which case such<br />
corrections shall be initialed by the person or persons signing the bid.<br />
7.3.4.4 The Bidder shall duly sign and seal its bid with the exact name <strong>of</strong> the<br />
firm/company to whom the contract is to be issued.<br />
7.3.4.5 The Bidder shall seal and mark the original and each copy <strong>of</strong> the Bid.<br />
7.3.4.6 If the outer cover <strong>of</strong> the bid is not sealed and marked as required by Section<br />
8.3.1, ASI will assume no responsibility for the bid's misplacement or<br />
premature opening.<br />
7.4 Clarification on RFP Document<br />
7.4.1.1 Bidder requiring any clarification on the RFP Document may submit his<br />
queries, in writing, at ASI's mailing address and as per schedule indicated in<br />
Section 8.1. The queries must be submitted in Micros<strong>of</strong>t Excel format as<br />
provided in Section 13.1.<br />
7.4.1.2 The Bidders shall bear in mind that their bids with any Technical or<br />
Commercial deviations will not be accepted. Thus, any issues / queries<br />
regarding Contract terms and conditions, Scope <strong>of</strong> Work, minimum<br />
requirements for Hardware infrastructure, essential features <strong>of</strong> the<br />
RFP Volume 2: Commercial and Bidding Terms Page 32
Request for Proposal for establishing e-Governance Systems<br />
application / components and minimum staffing requirements etc, should be<br />
either clarified before bid submission or submitted to ASI in writing as per<br />
the schedule indicated in Section 8.1.<br />
7.4.1.3 ASI will respond in writing, to any request for clarification to queries on the<br />
RFP Document, received not later than the dates prescribed by ASI in Section<br />
8.1.3 <strong>of</strong> this RFP document. Written copies <strong>of</strong> ASI's response (including the<br />
query but without identifying the source <strong>of</strong> inquiry) would be put up on the<br />
ASI website. Bidders are advised to keep browsing the information posted<br />
on the website.<br />
7.5 Bid Opening & Evaluation Process<br />
7.5.1 Opening <strong>of</strong> Bids by Purchaser<br />
7.5.1.1 ASI will open the Pre-Qualification and Technical Bids at the schedule given,<br />
in the presence <strong>of</strong> the representatives <strong>of</strong> the Bidders who choose to attend,<br />
at the time, date and place, as mentioned in Section 8.1.5 <strong>of</strong> this document.<br />
7.5.1.2 The Bidders' names, modifications, bid withdrawals and the presence or<br />
7.5.2 Evaluation <strong>of</strong> Bids<br />
absence <strong>of</strong> the requisite Bid Security and such other details as ASI, at its<br />
discretion, may consider appropriate will be announced at the bid opening.<br />
7.5.2.1 The selected Bidder must possess the requisite experience, strength and<br />
capabilities in providing the solution, equipment and services necessary to<br />
meet ASI’s requirements, as described in the RFP Document. The Bidder<br />
must possess the technical know-how and the financial wherewithal that<br />
would be required to successfully perform activities as per the Scope <strong>of</strong><br />
Work in Section 2 <strong>of</strong> the RFP for the entire period <strong>of</strong> the contract. The<br />
Bidder’s bid must be complete in all respect and covering the entire scope <strong>of</strong><br />
work as stipulated in the RFP document.<br />
7.5.2.2 The evaluation process <strong>of</strong> the RFP proposed to be adopted by ASI is<br />
indicated under this Clause. The purpose <strong>of</strong> this Clause is only to provide the<br />
Bidders an idea <strong>of</strong> the evaluation process that ASI may adopt.<br />
RFP Volume 2: Commercial and Bidding Terms Page 33
Request for Proposal for establishing e-Governance Systems<br />
7.5.3 Preliminary Examination<br />
7.5.3.1 ASI will examine the bids to determine whether they are complete, whether<br />
the bid format conforms to the RFP requirements, whether any<br />
computational errors have been made, whether required RFP fees and bid<br />
security has been furnished, whether the documents have been properly<br />
signed, and whether the bids are generally in order.<br />
7.5.3.2 ASI may waive any nonconformity or irregularity in a bid which does not<br />
constitute a material deviation according to ASI.<br />
7.5.4 Clarification from the Bidder<br />
7.5.4.1 When deemed necessary, during the tendering process, ASI may seek<br />
clarifications on any aspect from any or all the Bidders. However, that would<br />
not entitle the Bidder to change or cause any change in the substance <strong>of</strong> the<br />
RFP submitted or price quoted.<br />
7.5.4.2 During the tendering process, the Bidders will make Technical presentations<br />
to ASI on experience, proposed project staff experience and proposed<br />
project approach and methodology. Purchaser expects that the Bidder’s<br />
<strong>Project</strong> Manager and other key personnel named in the proposal will take an<br />
active and leading role in these presentations.<br />
7.5.4.3 Bidders may also be required to demonstrate the features <strong>of</strong> the proposed<br />
products, if needed, or demonstrate pro<strong>of</strong> <strong>of</strong> concept.<br />
7.5.5 Evaluation <strong>of</strong> Prequalification Bid<br />
7.5.5.1 In this part, the technical bid will be reviewed for determining the eligibility<br />
<strong>of</strong> the Bidder for the <strong>Project</strong>.<br />
7.5.5.2 This will be the first stage <strong>of</strong> the evaluation by ASI.<br />
7.5.5.3 Bidder needs to provide satisfactory documents against the Pre Qualification<br />
criteria stated in Section 10.2.2 to clear the pre qualification stage.<br />
7.5.6 Evaluation <strong>of</strong> Technical Bids<br />
RFP Volume 2: Commercial and Bidding Terms Page 34
Request for Proposal for establishing e-Governance Systems<br />
7.5.6.1 In this part, the technical bid will be reviewed for determining the eligibility<br />
<strong>of</strong> the Bidder for the <strong>Project</strong> and to ascertain Compliance <strong>of</strong> the Technical<br />
bids with the RFP terms and conditions, technical requirements and scope <strong>of</strong><br />
work as defined in this RFP.<br />
7.5.6.2 This shall be the second stage <strong>of</strong> the evaluation by ASI. Only those Bidders<br />
who cross the threshold level <strong>of</strong> Technical Evaluation indicated below and<br />
adhere to ASI’s technical requirements shall be considered for commercial<br />
evaluation.<br />
7.5.6.3 In case <strong>of</strong> no response by the Bidder to any <strong>of</strong> the requirements with regard<br />
to the contents <strong>of</strong> the Technical Bid, he shall not be assigned any marks for<br />
the same.<br />
7.5.6.4 Technical bid <strong>of</strong> the bidder shall be opened and evaluated for acceptability <strong>of</strong><br />
Techno-functional requirements, deviations and technical suitability.<br />
Bidders shall respond to the requirements as explained in Section 11.2 <strong>of</strong><br />
Volume 2 <strong>of</strong> RFP for their evaluation with regard to experience and<br />
qualification. Also, Bidder shall refer and respond to ALL technical<br />
requirements as mentioned in the RFP document. The evaluation process<br />
would also include a presentation <strong>of</strong> technical proposal by the Bidder.<br />
7.5.6.5 In order to qualify technically, a proposal must secure a minimum <strong>of</strong> 70% <strong>of</strong><br />
total marks after summing up. The Bidder would be technically evaluated<br />
out <strong>of</strong> 100 marks.Only those proposals which have a minimum score <strong>of</strong> 70%<br />
<strong>of</strong> total marks will be considered for opening <strong>of</strong> their Commercial Bid and<br />
evaluation there<strong>of</strong>.<br />
7.5.6.6 Detailed technical evaluation criteria are provided in Section 11.2 <strong>of</strong> the<br />
Volume 2 <strong>of</strong> this RFP.<br />
7.5.7 Evaluation <strong>of</strong> Commercial Bids<br />
7.5.7.1 ASI will open the Commercial Bids <strong>of</strong> only Technically Qualified Bidders, in<br />
the presence <strong>of</strong> the representatives <strong>of</strong> the Bidderwho choose to attend, at<br />
the time, date and place, as decided by ASI.<br />
RFP Volume 2: Commercial and Bidding Terms Page 35
Request for Proposal for establishing e-Governance Systems<br />
7.5.7.2 The commercial bids shall be evaluated by ASI for completeness and<br />
accuracy. Arithmetical errors will be rectified on the following basis. If there<br />
is a discrepancy between the unit price and the total price that is obtained<br />
by multiplying the unit price and quantity, the unit price shall prevail and the<br />
total price shall be corrected. If there is a discrepancy between words and<br />
figures, the amount in words will prevail.<br />
7.5.7.3 The Bid having the Lowest Commercial Quote shall be termed as the Lowest<br />
7.5.8 Rejection Criteria<br />
Evaluated Bid. The technically qualified Bidder with the lowest commercial<br />
quote, termed as L1, will be considered as best evaluated Bid.<br />
7.5.8.1 Besides other conditions and terms highlighted in the RFP document, bids<br />
may be rejected under following circumstances:<br />
7.5.8.2 General Rejection Criteria<br />
Bids submitted without or improper Bid Security or tender fees<br />
Bids received through non-prescribed modes such as Fax/ e-Mail.<br />
Bids not bounded appropriately e.g. in the form <strong>of</strong> loose papers.<br />
Bids which do not confirm unconditional validity <strong>of</strong> the bid as prescribed in the<br />
RFP.<br />
If the information provided by the Bidder is found to be incorrect / misleading<br />
at any stage / time during the Tendering Process.<br />
Any effort on the part <strong>of</strong> a Bidder to influence ASI’s bid evaluation, bid<br />
comparison or contract award decisions.<br />
Bids received by ASI after the last date for receipt <strong>of</strong> bids prescribed by ASI,<br />
pursuant to Section 8.1.3.<br />
Bids without signature <strong>of</strong> duly authorized person(s) on all pages <strong>of</strong> bid<br />
documents<br />
Bids without power <strong>of</strong> authorization and any other document consisting <strong>of</strong><br />
adequate pro<strong>of</strong> <strong>of</strong> the ability <strong>of</strong> the signatory to bind the Bidder.<br />
7.5.8.3 Technical Rejection Criteria<br />
Technical Bid containing commercial details.<br />
Revelation <strong>of</strong> Prices in any form or in bids other than Commercial or by any<br />
reason before opening the Commercial Bid.<br />
RFP Volume 2: Commercial and Bidding Terms Page 36
Request for Proposal for establishing e-Governance Systems<br />
Failure to furnish all information required by the RFP Document or submission<br />
<strong>of</strong> a bid not substantially responsive to the RFP Document in every respect.<br />
Bidders not responding to the complete scope <strong>of</strong> Work as indicated in the RFP<br />
documents, addendum (if any) and any subsequent information given to the<br />
Bidder.<br />
If the bid does not confirm to the timelines indicated in the bid.<br />
7.5.8.4 Commercial Rejection Criteria<br />
Incomplete price bid<br />
Price Bids that do not conform to the RFP’s price bid format.<br />
If there is an arithmetic discrepancy in the commercial bid calculations ASI shall<br />
rectify the same. If the Bidder does not accept the correction <strong>of</strong> the errors, its<br />
bid may be rejected.<br />
RFP Volume 2: Commercial and Bidding Terms Page 37
Request for Proposal for establishing e-Governance Systems<br />
8 Award <strong>of</strong> Contract<br />
8.1 Post Qualification and Award Criteria<br />
8.1.1 ASI will determine to its satisfaction whether the Bidder selected as having submitted the<br />
best evaluated bid is qualified to satisfactorily perform the Contract.<br />
8.1.2 This determination will take into account the Bidder's financial, technical, implementation<br />
and post-implementation strengths and capabilities. It will also include examination <strong>of</strong> the<br />
documentary evidence submitted by the Bidder as part <strong>of</strong> the bid and any other<br />
information as ASI deems necessary and appropriate.<br />
8.1.3 An affirmative determination will be a prerequisite for award <strong>of</strong> the Contract to the Bidder.<br />
A negative determination will result in rejection <strong>of</strong> the Bidder's bid, in which event; ASI will<br />
proceed to the next lowest commercial bid to make a similar determination <strong>of</strong> that Bidder's<br />
capabilities to perform satisfactorily.<br />
8.1.4 ASI is not bound to accept the best evaluated bid or any bid and reserves the right to accept<br />
any bid, wholly or in part.<br />
8.2 Purchaser's Right to Vary Scope <strong>of</strong> Contract<br />
8.2.1 ASI may at any time, by a written order given to the Bidder, make changes within the<br />
quantities, specifications, services or scope <strong>of</strong> the Contract as specified.<br />
8.2.2 If any such change causes an increase or decrease in the cost <strong>of</strong>, or the time required for<br />
the Bidder’s performance <strong>of</strong> any part <strong>of</strong> the work under the Contract, whether changed or<br />
not changed by the order, an equitable adjustment shall be made in the Contract Price or<br />
time schedule, or both, and the Contract shall accordingly be amended.<br />
8.3 Purchaser's Right to Accept and Reject Bids<br />
8.3.1 ASI reserves the right to accept any bid, and to annul the RFP process and reject all bids at<br />
any time prior to award <strong>of</strong> Contract, without thereby incurring any liability to the affected<br />
Bidder or Bidders or any obligation to inform the affected Bidder or Bidders <strong>of</strong> the grounds<br />
for ASI's action.<br />
8.3.2 ASI reserves the right to negotiate the commercials with the selected Bidder and seek<br />
revised commercial bid.<br />
RFP Volume 2: Commercial and Bidding Terms Page 38
Request for Proposal for establishing e-Governance Systems<br />
8.4 Notification <strong>of</strong> Award<br />
8.4.1 Prior to the expiration <strong>of</strong> the period <strong>of</strong> bid validity, pursuant to Section 8.1.6 ASI will notify<br />
the successful Bidder in writing that its bid has been accepted. The Bidder shall provide his<br />
acceptance within 3 working days <strong>of</strong> such notification.<br />
8.4.2 Upon the successful Bidder's furnishing <strong>of</strong> performance security pursuant to Section 9.7,<br />
ASI may notify each unsuccessful Bidder and will discharge their EMD, pursuant to Section<br />
8.2.6.5<br />
8.5 Negotiations with the successful Bidder<br />
8.5.1 If required, negotiations will be held at the date, time and address intimated to the<br />
qualified and selected Bidder. Representatives conducting negotiations on behalf <strong>of</strong> the<br />
Bidder must have written authority to negotiate and conclude a Contract.<br />
8.6 Signing <strong>of</strong> Contract<br />
8.6.1 After completing negotiations ASI shall issue a Letter <strong>of</strong> Intent to the selected Bidder and<br />
promptly notify all other Bidders who have submitted proposals about the decision taken.<br />
8.6.2 The Bidder will sign the contract within 15 working days <strong>of</strong> submission <strong>of</strong> Performance Bank<br />
Guarantee.<br />
8.7 Performance Security<br />
8.7.1 Within 15 working days <strong>of</strong> the receipt <strong>of</strong> notification <strong>of</strong> award from ASI, the successful<br />
Bidder shall furnish the performance security <strong>of</strong> 10% <strong>of</strong> total contract value in accordance<br />
with the Contractual & Legal Specification in the form <strong>of</strong> a Bank Guarantee.<br />
8.7.2 Failure <strong>of</strong> the successful Bidder to comply with the requirement <strong>of</strong> Section 9.7.1 shall<br />
constitute sufficient grounds for the annulment <strong>of</strong> the award and forfeiture <strong>of</strong> the bid<br />
security, in which event ASI may award the Contract to the next best evaluated bidder or<br />
call for new bids.<br />
8.7.3 The Bank Guarantee shall be valid for 180 days more than the period <strong>of</strong> the contract.<br />
RFP Volume 2: Commercial and Bidding Terms Page 39
Request for Proposal for establishing e-Governance Systems<br />
9 Annexure 1: Bid Formats<br />
9.1 Cover Letter<br />
Date: dd/mm/yyyy<br />
To<br />
Director – Administration<br />
<strong>Archaeological</strong> <strong>Survey</strong> <strong>of</strong> <strong>India</strong><br />
Janpath, New Delhi –110011<br />
Sir,<br />
*on the Bidder’s Letterhead+<br />
Subject: Selection <strong>of</strong> Implementation Agency for E-Governance <strong>Project</strong>, ASI<br />
Reference: RFP No: _____________________________ Dated _______________<br />
With reference to your Request for Proposal for “Selection <strong>of</strong> Implementation agency for E-<br />
Governance <strong>Project</strong>”, we hereby submit our Pre-Qualification Proposal, Technical Proposal<br />
and Commercial Proposal for the same.<br />
We hereby declare that:<br />
a. We <strong>of</strong>fer to supply equipments and provide services at the prices and rates mentioned in the<br />
attached commercial proposal<br />
b. We have not been banned or blacklisted by ASI.<br />
c. We have never been declared to be a willful defaulter by any Bank<br />
d. We or any person on our behalf will not engage in any corrupt, fraudulent or coercive practices<br />
to influence the Bidding Process.<br />
e. We hereby acknowledge and accept that ASI has the discretion to change or modify criteria as it<br />
deems appropriate while short listing <strong>of</strong> Agency for providing services.<br />
f. We have enclosed Demand Draft <strong>of</strong> `10,00,000/- in favor <strong>of</strong> ‘Director – Administration ,<br />
<strong>Archaeological</strong> <strong>Survey</strong> <strong>of</strong> <strong>India</strong>’ as Bid Security, which is valid for 180 days from the opening <strong>of</strong><br />
the Technical Bid.<br />
RFP Volume 2: Commercial and Bidding Terms Page 40
Request for Proposal for establishing e-Governance Systems<br />
g. We hereby declare that all information and details furnished by us in the Proposal are true and<br />
correct, and all documents accompanying such application are true copies <strong>of</strong> their respective<br />
originals.<br />
h. We agree to abide by our <strong>of</strong>fer for a period <strong>of</strong> 180 days from the date <strong>of</strong> opening <strong>of</strong> technical bid<br />
prescribed by ASI and that we shall remain bound by a communication <strong>of</strong> acceptance within that<br />
time.<br />
i. We have carefully read and understood the terms and conditions <strong>of</strong> the RFP and the conditions<br />
<strong>of</strong> the contract applicable to the RFP. We do hereby undertake to provision as per these terms<br />
and conditions.<br />
j. In the event <strong>of</strong> acceptance <strong>of</strong> our bid, we do hereby undertake-<br />
1. To supply the products and commence services as stipulated in the schedule <strong>of</strong> delivery<br />
forming a part <strong>of</strong> the attached proposal.<br />
2. To undertake the project services for a period <strong>of</strong> 3 years from the date <strong>of</strong> signing <strong>of</strong> the<br />
contract.<br />
3. We affirm that the prices quoted are inclusive <strong>of</strong> delivery, commissioning, training, and<br />
providing facility management and inclusive <strong>of</strong> all out <strong>of</strong> pocket expenses, taxes, levies<br />
discounts etc.<br />
k. We do hereby undertake, that, until a formal contract is prepared and executed, this proposal,<br />
together with your written acceptance there<strong>of</strong> and notification <strong>of</strong> award <strong>of</strong> contract, shall<br />
constitute a binding contract between us.<br />
l. We understand that the amount furnished by us as Bid security may be encashed under<br />
conditions enumerated in the RFP<br />
m. We understand that the ASI may cancel the bidding process at any time and that ASI is not<br />
bound to accept any bid that it may receive, without incurring any liability towards the bidder.<br />
In case <strong>of</strong> any clarifications please contact ___________________ email at<br />
_______________<br />
_________________________________________<br />
Signature <strong>of</strong> Authorized Signatory (with <strong>of</strong>ficial seal)<br />
Date ____________<br />
Name ____________<br />
Designation ____________<br />
Address ____________<br />
Telephone ____________<br />
Fax ____________<br />
E-mail address ____________<br />
RFP Volume 2: Commercial and Bidding Terms Page 41
Request for Proposal for establishing e-Governance Systems<br />
RFP Volume 2: Commercial and Bidding Terms Page 42
Request for Proposal for establishing e-Governance Systems<br />
9.2 Pre Qualification<br />
9.2.1 Pre- qualification Letter<br />
To<br />
Director – Administration<br />
<strong>Archaeological</strong> <strong>Survey</strong> <strong>of</strong> <strong>India</strong><br />
Janpath, New Delhi – 110011<br />
Sir,<br />
Subject: Selection <strong>of</strong> Implementation Agency for e-Governance project for ASI<br />
Reference: RFP No: Dated <br />
We, the undersigned Bidder, having read and examined in detail all the RFP document in<br />
respect <strong>of</strong> Selection <strong>of</strong> Implementation Agency for e-Governance <strong>Project</strong> for ASI, do hereby<br />
propose to provide the services as specified in the RFP no.<br />
_______________________________ Dated ______________.<br />
We are hereby submitting our Pre-Qualification Bid (one original and two copies), which<br />
includes the following:<br />
Supporting Information for Pre-Qualification Conditions<br />
Bid Security <strong>of</strong> the prescribed amount and validity<br />
RFP document fees as prescribed<br />
Power <strong>of</strong> Attorney in favor <strong>of</strong> the authorized signatory<br />
We hereby declare that all the information and statements made in the Pre-Qualification<br />
related documents are true and accept that any misinterpretation contained in it may lead<br />
to our disqualification.<br />
We also agree to hold in trust any Confidential Information received by us as part <strong>of</strong> the<br />
tendering process, we shall maintain strict confidentiality in respect <strong>of</strong> such Confidential<br />
Information and in no event a degree <strong>of</strong> confidentiality less than we use to protect our own<br />
confidential and proprietary information.<br />
RFP Volume 2: Commercial and Bidding Terms Page 43
Request for Proposal for establishing e-Governance Systems<br />
Yours sincerely,<br />
Bidder<br />
Authorised Signatory<br />
Name<br />
Designation:<br />
Company Seal<br />
RFP Volume 2: Commercial and Bidding Terms Page 44
Request for Proposal for establishing e-Governance Systems<br />
9.2.2 Supporting Information for Pre-Qualification Conditions<br />
The Bidder is required to fill relevant information in each <strong>of</strong> the formats given below. The<br />
pre-qualification bid must contain documentary evidences and supporting information to<br />
enable Purchaser to evaluate the eligibility <strong>of</strong> the Bidder without ambiguity.<br />
S.No. Particulars<br />
Bidder Details<br />
1. Name <strong>of</strong> the company / firm<br />
2. Mailing address in <strong>India</strong><br />
3. Telephone number<br />
4. Fax number<br />
5. E-mail address<br />
6. Name and designation <strong>of</strong> the<br />
authorized person<br />
7. Year <strong>of</strong> establishment and<br />
constitution <strong>of</strong> organization<br />
8. Whether the Firm / Company has<br />
1.<br />
any widely accepted certification.<br />
Minimum Criteria Type <strong>of</strong> Documentary Evidence<br />
Provided<br />
Bidder Pre Qualification<br />
Bidder should be in<br />
operation in <strong>India</strong> in IT/ITeS<br />
for a period <strong>of</strong> at least 5<br />
years as on 31-03-11<br />
Evidence<br />
Annexed at<br />
Page No.<br />
RFP Volume 2: Commercial and Bidding Terms Page 45
Request for Proposal for establishing e-Governance Systems<br />
2.<br />
3.<br />
4.<br />
5.<br />
6.<br />
Minimum Criteria Type <strong>of</strong> Documentary Evidence<br />
Provided<br />
Bidder should have annual<br />
turnover <strong>of</strong> minimum `100<br />
Crores in each <strong>of</strong> last three<br />
financial year (ending 31st<br />
March 2011) accruing from<br />
System Integration<br />
(including supply <strong>of</strong><br />
hardware servers,<br />
components, devices, etc),<br />
development <strong>of</strong> IT<br />
applications areas and<br />
Application Maintenance<br />
services.<br />
Bidder should be a pr<strong>of</strong>it<br />
making entity in last<br />
financial year (2010-11)<br />
Bidder should have at least<br />
250 full time s<strong>of</strong>tware<br />
pr<strong>of</strong>essionals on its rolls<br />
Bidder should have<br />
experience <strong>of</strong> handling at<br />
least 2 assignments in <strong>India</strong><br />
as Finance and Accounts<br />
S<strong>of</strong>tware implementation<br />
and at least 1 assignment in<br />
e-ticketing solutions in the<br />
last 3 years.<br />
Bidder should have<br />
experience <strong>of</strong> handling at<br />
least one assignment the<br />
value <strong>of</strong> which should be at<br />
Year Bidder’s turn<br />
over<br />
2010 – 11<br />
2009 – 10<br />
2008 – 09<br />
Audited Financial Statements<br />
Certificate from the Company<br />
<strong>Project</strong> Completion Certificate<br />
Evidence<br />
Annexed at<br />
Page No.<br />
RFP Volume 2: Commercial and Bidding Terms Page 46
Request for Proposal for establishing e-Governance Systems<br />
7.<br />
8.<br />
9.<br />
10.<br />
Minimum Criteria Type <strong>of</strong> Documentary Evidence<br />
Provided<br />
least ` 10 Crores (`Ten<br />
Crores).<br />
Bidder should have<br />
certification <strong>of</strong><br />
a. ISO 9001:2000 and<br />
b. CMMi Level 3 or above<br />
Bidder should submit RFP<br />
fees <strong>of</strong> Rs 10,000 (Rupees<br />
Ten Thousand) in form <strong>of</strong><br />
Demand Draft (DD)<br />
Bidder should submit<br />
Earnest Money Deposit<br />
(EMD) <strong>of</strong> `10,00,000<br />
(Rupees Ten Lakh only) in<br />
the form <strong>of</strong> a Demand Draft<br />
(DD)<br />
Power <strong>of</strong> Attorney<br />
executed by the Bidder in<br />
favor <strong>of</strong> the Principal<br />
Officer or the duly<br />
Authorized Representative<br />
should be attached<br />
Bidder<br />
Authorised Signatory<br />
Name<br />
Designation:<br />
Company Seal<br />
DD Number:<br />
DD Date:<br />
Issuing Authority / Bank:<br />
DD Number:<br />
DD Date:<br />
Issuing Authority / Bank:<br />
Evidence<br />
Annexed at<br />
Page No.<br />
RFP Volume 2: Commercial and Bidding Terms Page 47
Request for Proposal for establishing e-Governance Systems<br />
9.3 Technical Bid Formats<br />
9.3.1 Technical Bid Letter<br />
To<br />
Director – Administration<br />
<strong>Archaeological</strong> <strong>Survey</strong> <strong>of</strong> <strong>India</strong><br />
Janpath, New Delhi – 110011<br />
Sir,<br />
Subject: Selection <strong>of</strong> Implementation Agency for e-Governance <strong>Project</strong>, ASI<br />
Reference: RFP No: _____________________________ Dated ______________<br />
Sir,<br />
We, the undersigned Bidder, having read and examined in detail the entire RFP document in<br />
respect <strong>of</strong> Selection <strong>of</strong> Implementation Agency for E-Governance <strong>Project</strong>, ASI, do hereby<br />
propose to provide the services as specified in the RFP No.<br />
_____________________________ Dated ______________.<br />
1. Deviations<br />
We declare that all the services shall be performed strictly in accordance with the RFP<br />
documents except for the variations and deviations, all <strong>of</strong> which have been detailed out<br />
exhaustively in the following statements, irrespective <strong>of</strong> whatever has been stated to the<br />
contrary anywhere else in our RFP:<br />
(a) Statement <strong>of</strong> Deviations Format as per Section 12 Annexure 3 <strong>of</strong> the Volume 2 <strong>of</strong> RFP<br />
document<br />
Further we agree that additional conditions, if any, found in the RFP documents, other than<br />
those stated in deviation schedule, shall not be given effect to.<br />
2. Qualifying Data<br />
RFP Volume 2: Commercial and Bidding Terms Page 48
Request for Proposal for establishing e-Governance Systems<br />
We confirm having submitted the information as required by you as Prequalification Criteria.<br />
In case you require any other further information/documentary pro<strong>of</strong> in this regard before<br />
evaluation <strong>of</strong> our bid, we agree to furnish the same in time to your satisfaction.<br />
We hereby declare that our bid is made in good faith, without collusion or fraud and the<br />
information contained in the bid is true and correct to the best <strong>of</strong> our knowledge and belief.<br />
We understand that our bid is binding on us and that you are not bound to accept bid you<br />
receive.<br />
Thanking you.<br />
Yours faithfully<br />
Bidder<br />
Authorized Signatory<br />
Name<br />
Designation<br />
Company Seal<br />
RFP Volume 2: Commercial and Bidding Terms Page 49
Request for Proposal for establishing e-Governance Systems<br />
9.3.2 Credential Format<br />
Credentials are required in the prescribed format for each <strong>of</strong> the following:<br />
1. At least one engagement as System Integrator for managing large visitor inflow with requirements on a<br />
scale comparable to ASI.<br />
2. At least 2 engagements for Finance and Accounts s<strong>of</strong>tware implementations.<br />
3. Prior experience <strong>of</strong> working with as System Integrator in <strong>India</strong> with project value more than `10 crores<br />
(excluding supply <strong>of</strong> hardware servers, components, devices etc) each in past 3 years<br />
4. Prior experience <strong>of</strong> handling at least one engagements for manning customer facing counter operations.<br />
Agency shall have an experience <strong>of</strong> handling customer facing transactions. Bidder shall submit Published<br />
document by previous client for these engagements<br />
S. No. Items Details<br />
General Information<br />
1. Customer Name<br />
2.<br />
<strong>Project</strong> Details<br />
Name <strong>of</strong> the contact person and<br />
contact details for the client <strong>of</strong> the<br />
assignment<br />
3. <strong>Project</strong> Title<br />
4. Start Date / End Date<br />
5. Date <strong>of</strong> Go-Live<br />
6. Total Cost <strong>of</strong> the project<br />
7.<br />
8.<br />
9.<br />
10.<br />
Current Status (Live / completed / on-<br />
going / terminated / suspended)<br />
Pr<strong>of</strong>essional Staff Provided by your<br />
Company<br />
Size <strong>of</strong> the project<br />
Please indicate the current or the latest<br />
AMC period with the client (From Month<br />
–Year to Month-Year)<br />
Please indicate whether the client is<br />
currently using the implemented solution<br />
11. Number <strong>of</strong> total users and concurrent Total users<br />
RFP Volume 2: Commercial and Bidding Terms Page 50
Request for Proposal for establishing e-Governance Systems<br />
12.<br />
13.<br />
users <strong>of</strong> the solution at the client<br />
location(s):<br />
Hardware (give brief details covering<br />
Server, Processor configuration (SMP<br />
or Cluster), storage technology (SAN<br />
or internal disks with RAID) etc<br />
Security features implemented -<br />
Password-based / Role-based / Digital<br />
certificates / signature, encryption,<br />
public key system, LDAP server, single<br />
sign-on etc.<br />
14. Training responsibilities <strong>of</strong> Bidder<br />
15.<br />
Any other information to be shared<br />
with ASI<br />
Enclosures Required<br />
Enclosure A:<br />
Narrative Description <strong>of</strong> the <strong>Project</strong><br />
Enclosure B:<br />
Concurrent users<br />
Detailed Description <strong>of</strong> actual services provided by your company:<br />
RFP Volume 2: Commercial and Bidding Terms Page 51
Request for Proposal for establishing e-Governance Systems<br />
9.3.3 Overview <strong>of</strong> Proposed Solution<br />
Please provide relevant details on Solutions & Services specific to Bidder’s proposal under<br />
below mentioned Headings. The list is indicative and can be populated with other relevant<br />
headings.<br />
1. Solution Architecture<br />
a. Capabilities <strong>of</strong> the proposed tools to address the functional requirements<br />
b. Testing approach<br />
c. Risk Management Plan<br />
d. Application Security Architecture<br />
e. Disaster Recovery approach<br />
2. Network Solution / Architecture<br />
3. Hardware Solution / Architecture<br />
4. Service Approach for Facility Management Service, POS Staff, Help Desk<br />
5. Training Approach<br />
6. Work Plan and Staffing Schedule<br />
7. Functional Requirement Specification<br />
Any other response to the Schedule would be treated as Requirement Not Met.<br />
8. Technical Requirement Specification<br />
Any other response to the Schedule would be treated as Requirement Not Met.<br />
A Detailed <strong>Project</strong> Plan covering break-up <strong>of</strong> each phase into the key activities, along with the start<br />
and end dates must be provided as per format given below.<br />
9.3.4 Detailed Work plan and Staffing Plan<br />
The Bidder shall provide a detailed project plan with timelines, resource allocation,<br />
milestones etc. in Micros<strong>of</strong>t <strong>Project</strong> format for carrying out the scope <strong>of</strong> work activities. The<br />
project plan should clearly indicate the deliverables at each milestone in the project. The<br />
Approach and Methodology should capture, in detail, all the activities enlisted in the project<br />
plan.<br />
RFP Volume 2: Commercial and Bidding Terms Page 52
Request for Proposal for establishing e-Governance Systems<br />
9.3.5 Manpower details<br />
Note: For the Key Personnel (refer Section 3, Volume 2 <strong>of</strong> this RFP), it is mandatory to<br />
provide name <strong>of</strong> proposed resource along with details desired as per format given below. It<br />
is mandatory that the resource proposed for the key position should not change in the first<br />
six months <strong>of</strong> the project. For all other categories <strong>of</strong> resources, except the Key Personnel,<br />
the details <strong>of</strong> proposed resources may be furnished by the Bidder at the time <strong>of</strong> contract<br />
finalization.<br />
9.3.6 Pr<strong>of</strong>ile <strong>of</strong> Personnel<br />
Note: Bidder must note that CV should not be more than 2 pages<br />
<br />
1. Proposed position<br />
/ role<br />
2 Designation<br />
3 Date <strong>of</strong> Birth<br />
4 Nationality<br />
5 Education<br />
6 Employment<br />
Record<br />
7 Relevant<br />
Experience<br />
(Starting with present position and last two firms, list in reverse order)<br />
(Give an outline on the experience most pertinent to tasks mentioned in<br />
the project. Describe degree <strong>of</strong> responsibility held on these relevant<br />
assignments – Up to half <strong>of</strong> a page).<br />
8 Certification I, the undersigned, certify that to the best <strong>of</strong> my knowledge and belief,<br />
this bio-data correctly describes me, my qualifications and my experience.<br />
Date:<br />
Place Signature <strong>of</strong> the Candidate<br />
RFP Volume 2: Commercial and Bidding Terms Page 53
Request for Proposal for establishing e-Governance Systems<br />
9.4 Commercial Bid<br />
9.4.1 Commercial Bid Letter<br />
To<br />
Director – Administration<br />
<strong>Archaeological</strong> <strong>Survey</strong> <strong>of</strong> <strong>India</strong><br />
Janpath, New Delhi – 110011<br />
Sir,<br />
Subject: Selection <strong>of</strong> Implementation Agency for E-Governance <strong>Project</strong>, ASI<br />
Reference: RFP No: __________________________ Dated _______________<br />
Sir,<br />
We, the undersigned Bidder, having read and examined in detail the entire RFP document in<br />
respect <strong>of</strong> Selection <strong>of</strong> Implementation Agency for E-Governance <strong>Project</strong>, ASI, do hereby<br />
propose to provide the services as specified in the RFP No. ______________________<br />
Dated _________________.<br />
1. PRICE AND VALIDITY<br />
All the prices mentioned in our RFP are in accordance with the terms as specified in the RFP<br />
documents. All the prices and other terms and conditions <strong>of</strong> this RFP are valid for a period <strong>of</strong><br />
180 calendar days from the date <strong>of</strong> opening <strong>of</strong> the technical bids.<br />
2. We have studied the relevant clause(s) in <strong>India</strong>n Tax Laws and hereby declare that if any taxes,<br />
surcharge, Pr<strong>of</strong>essional and any other corporate Tax in altercated under the laws, we shall pay<br />
the same.<br />
3. UNIT RATES<br />
We have indicated in the relevant schedules enclosed, the unit rates for the purpose <strong>of</strong> on<br />
account <strong>of</strong> payment as well as for price adjustment in case <strong>of</strong> any increase to / decrease<br />
from the scope <strong>of</strong> work under the contract.<br />
4. BID PRICING<br />
RFP Volume 2: Commercial and Bidding Terms Page 54
Request for Proposal for establishing e-Governance Systems<br />
We further confirm that the prices stated in our bid are in accordance with RFP.<br />
5. QUALIFYING DATA<br />
We confirm having submitted the information as required by you in your Instruction to<br />
Bidders. In case you require any other further information/documentary pro<strong>of</strong> in this regard<br />
before evaluation <strong>of</strong> our bid, we agree to furnish the same in time to your satisfaction.<br />
6. BID PRICE<br />
We declare that our bid prices are for the entire scope <strong>of</strong> the work as specified in the Scope<br />
<strong>of</strong> Work and bid documents. These prices are attached with our bid as part <strong>of</strong> the bid.<br />
7. PERFORMANCE BANK GUARANTEE<br />
We hereby declare that in case the contract is awarded to us, we shall submit the<br />
Performance Bank Guarantee within 15 working days <strong>of</strong> award notification.<br />
8. We hereby declare that our bid is made in good faith, without collusion or fraud and the<br />
information contained in the bid is true and correct to the best <strong>of</strong> our knowledge and belief.<br />
9. We understand that our bid is binding on us DURING THE VALIDITY PERIOD OR THE EXTENSIONS<br />
THEREOF and that you are not bound to accept a Bid you receive.<br />
10. We confirm that no deviations are attached here with this commercial <strong>of</strong>fer.<br />
Thanking you,<br />
Yours faithfully,<br />
(Signature <strong>of</strong> the Bidder)<br />
Printed Name<br />
Designation<br />
Seal:<br />
Date:<br />
Place:<br />
Business Address:<br />
RFP Volume 2: Commercial and Bidding Terms Page 55
Request for Proposal for establishing e-Governance Systems<br />
Sr.<br />
No<br />
9.4.2 Breakdown <strong>of</strong> Cost Components<br />
Item Description Unit Price (A)<br />
1. Hardware for Ticket Counters at PoS – at 10 sites Per site<br />
2. COTS S<strong>of</strong>tware Licenses (Perpetual) Per license<br />
3.<br />
3 a<br />
3 b<br />
3 c<br />
Implementation and Rollout (including one year warranty<br />
and server side hardware)<br />
- Electronic Communication Solution Module<br />
- E-ticketing Solution Module<br />
- Financial Planning and Budgeting Solutions Module<br />
4. Application Hosting<br />
4 a<br />
4 b<br />
4 c<br />
- Electronic Communication Solution Module<br />
- E-ticketing Solution Module<br />
- Financial Planning and Budgeting Solutions Module<br />
Blended person-<br />
month rate<br />
5. AMC for each module for 2 years, post warranty For 1 year<br />
RFP Volume 2: Commercial and Bidding Terms Page 56<br />
Total Base Price<br />
(B)<br />
Total <strong>of</strong> Taxes,<br />
Duties & Levies<br />
(C)<br />
(All Prices in <strong>India</strong>n Rupees)<br />
Total Price<br />
D=B+C
Request for Proposal for establishing e-Governance Systems<br />
Sr.<br />
No<br />
6 a<br />
6 b<br />
6 c<br />
Item Description Unit Price (A)<br />
- Electronic Communication Solution Module<br />
- E-ticketing Solution Module<br />
- Financial Planning and Budgeting Solutions Module<br />
6. PoS Counter Operating Costs<br />
Per person-month per<br />
RFP Volume 2: Commercial and Bidding Terms Page 57<br />
POS<br />
Total Base Price<br />
(B)<br />
Total <strong>of</strong> Taxes,<br />
Duties & Levies<br />
Total Capital Contract Value TOTAL<br />
Amount in Words (……………………………………………………………………….)<br />
Note:<br />
(C)<br />
Total Price<br />
SI is required to make his own Bill <strong>of</strong> Material Assessment. An indicative Bill <strong>of</strong> Materials is provided in RFP volume 1, Annexure 3. SI is required to<br />
provide an undertaking for the Bill <strong>of</strong> Materials along with the Bid.<br />
SI should provide all prices, quantities as per the prescribed format under this Section. SI should not leave any field blank. In case the field is not<br />
applicable, SI must indicate “0” (Zero) in all such fields.<br />
It is mandatory to provide breakup <strong>of</strong> all Taxes, Duties and Levies wherever applicable and/or payable.<br />
ASI may, at its discretion, decide to procure items mentioned in the Bill <strong>of</strong> Materials directly.<br />
ASI reserves the right to ask the SI to submit pro<strong>of</strong> <strong>of</strong> payment against any <strong>of</strong> the taxes, duties, levies indicated.<br />
ASI shall take into account all Taxes, Duties & Levies for the purpose <strong>of</strong> Evaluation.<br />
D=B+C
Request for Proposal for establishing e-Governance Systems<br />
10 Annexure 2: Pre-Qualification and Technical Bid Evaluation<br />
Criteria<br />
10.1 Pre-Qualification Evaluation Criteria<br />
Pre Qualification Condition Documentary Pro<strong>of</strong> Require<br />
General for Bidder<br />
1. Bidder should be in operation in <strong>India</strong> in IT for a period<br />
<strong>of</strong> at least 5 years as on 31-03-11<br />
2. Bidder should have annual turnover <strong>of</strong> minimum ` 100<br />
crores in each <strong>of</strong> last three financial year (ending 31st<br />
March 2011) accruing from System Integration (including<br />
supply <strong>of</strong> hardware servers, components, devices, etc),<br />
development <strong>of</strong> IT applications areas and Application<br />
Maintenance services. The revenues <strong>of</strong> subsidiaries will<br />
not be considered for this purpose.<br />
3. Bidder should be a pr<strong>of</strong>it making entity in last three<br />
financial years<br />
4. Bidder should have experience <strong>of</strong> developing s<strong>of</strong>tware<br />
assignments in <strong>India</strong> with at least 2 assignments as<br />
Finance and Accounts s<strong>of</strong>tware Implementer and at least<br />
1 assignment in e-ticketing solutions. One <strong>of</strong> the<br />
enterprises must be in Government/PSU.<br />
5. Bidder should have certification <strong>of</strong>:<br />
a. ISO 9001:2000 and<br />
b. CMMi Level 3 or more<br />
Certificate <strong>of</strong> Incorporation<br />
issued by the Registrar <strong>of</strong><br />
Companies<br />
Duly certified statement from<br />
their appointed statutory<br />
auditor for the years 2008-09,<br />
2009-10 and 2010-11<br />
indicating the amount <strong>of</strong><br />
turnover during these years<br />
Duly certified statement from<br />
their appointed statutory<br />
auditor for the years 2008-09,<br />
2009-10 and 2010-11<br />
indicating pr<strong>of</strong>it during these<br />
years<br />
Purchase Order / Work Order /<br />
Completion certificate from<br />
client. The last three years will<br />
comprise <strong>of</strong> periods counted<br />
from 2008-09 onward<br />
Completion Certificate would<br />
be preferred.<br />
Copy <strong>of</strong> valid certificate issued<br />
to Bidder by respective<br />
agencies<br />
RFP Volume 2: Commercial and Bidding Terms Page 58
Request for Proposal for establishing e-Governance Systems<br />
Pre Qualification Condition Documentary Pro<strong>of</strong> Require<br />
6. Bidder should have at least 250 full time s<strong>of</strong>tware<br />
pr<strong>of</strong>essionals on its rolls<br />
7. Bidder should submit RFP fees <strong>of</strong> `10,000 (Rupees Ten<br />
Thousand) in form <strong>of</strong> Demand Draft (DD)<br />
8. Bidder should submit Earnest Money Deposit (EMD) <strong>of</strong><br />
`10,00,000 (Rupees Ten Lakhs only) in the form <strong>of</strong> a<br />
Demand Draft (DD)<br />
Certificate by the Statutory<br />
Auditor or Company Secretary<br />
<strong>of</strong> the firm<br />
Demand Draft drawn in favor<br />
<strong>of</strong> “Director – Administration,<br />
<strong>Archaeological</strong> <strong>Survey</strong> <strong>of</strong> <strong>India</strong>”<br />
from a Scheduled Bank<br />
payable at New Delhi.<br />
Demand Draft drawn in favor<br />
<strong>of</strong> “Director – Administration,<br />
<strong>Archaeological</strong> <strong>Survey</strong> <strong>of</strong> <strong>India</strong>”<br />
from a Scheduled Bank payable<br />
at New Delhi.<br />
RFP Volume 2: Commercial and Bidding Terms Page 59
Request for Proposal for establishing e-Governance Systems<br />
10.2 Evaluation <strong>of</strong> Technical Bids<br />
The evaluation <strong>of</strong> the technical bids will be based on the following parametsrs:<br />
Technical Evaluation Parameter<br />
Understanding <strong>of</strong> RFP and Approach for implementation<br />
Qualifying<br />
Marks<br />
Understanding <strong>of</strong> <strong>Requirements</strong> 5<br />
Adequacy <strong>of</strong> work plan 5<br />
Solution Proposed for ASI 25<br />
Proposed solution and the methodology for each <strong>of</strong> the Application systems<br />
including compliance to Functional Requirement Specification<br />
10<br />
Proposed quality <strong>of</strong> Hardware and Hosting solution<br />
5<br />
Plan for (a) training, (b) Deployment across locations, (c) resource (operator)<br />
ramp-up for additional counters in future.<br />
Assessment <strong>of</strong> Manpower plan for Ticketing Counters<br />
<strong>Project</strong> Plan 10<br />
Adequacy <strong>of</strong> plan 5<br />
Provisions for contingencies 5<br />
Manpower Proposed 30<br />
Program Manager 9<br />
Experience 5<br />
Qualifications 4<br />
Solution Architect (S<strong>of</strong>tware) 7<br />
Experience 4<br />
Qualifications 3<br />
Solution Architect (Infrastructure and Hardware) 7<br />
Experience 4<br />
Qualifications 3<br />
Solution Architect (Network and Security) 7<br />
Experience 4<br />
Qualifications 3<br />
POC for e-ticketing Module 25<br />
Technical quality <strong>of</strong> the POC 15<br />
Modules and required customization 5<br />
Previous installations 5<br />
Total Marks 100<br />
RFP Volume 2: Commercial and Bidding Terms Page 60<br />
10<br />
5<br />
5
Request for Proposal for establishing e-Governance Systems<br />
11 Annexure 3: Statement <strong>of</strong> Deviation Format<br />
11.1 Statement <strong>of</strong> deviations from Schedule <strong>of</strong> <strong>Requirements</strong><br />
S.No.<br />
Dear Sirs,<br />
Following are the Technical deviations and variations from the requirements and documents for<br />
“E-Governance <strong>Project</strong> for <strong>Archaeological</strong> <strong>Survey</strong> <strong>of</strong> <strong>India</strong>” against RFP No.<br />
________________________ Dated ______________. These deviations and variations are<br />
exhaustive. Except these deviations and variations, the entire work shall be performed as per<br />
your requirements and documents.<br />
Bidders may please note that, compliance to a Clause and a Sub-Clause would mean complete<br />
compliance to all the other Sections within those Clauses and Sub-Clauses.<br />
Deviation in Scope <strong>of</strong> Work<br />
Tenderer:<br />
Section<br />
No.<br />
Clause No. Page No.<br />
Signature ------------------------<br />
Name ------------------------<br />
Address ------------------------<br />
Company ------------------------<br />
Date ------------------------<br />
Statement <strong>of</strong><br />
deviations and<br />
variations.<br />
Remarks<br />
RFP Volume 2: Commercial and Bidding Terms Page 61
Request for Proposal for establishing e-Governance Systems<br />
12 Annexure 4: Request for Clarification Format<br />
12.1 Format for clarifications<br />
Bidder requiring any clarification on the RFP Document may submit his queries, in writing, at the ASI's<br />
mailing address and as per schedule indicated in Section 8.1.2. The queries must be submitted in<br />
Micros<strong>of</strong>t Excel format as follows:<br />
Sr. No. Volume No. Section No. & Page No. Clause in RFP Clarification Sought<br />
RFP Volume 2: Commercial and Bidding Terms Page 62
Request for Proposal for establishing e-Governance Systems<br />
12.2 Clarification on RFP Document<br />
12.2.1 The Bidders shall bear in mind that their bids with any Technical or Commercial deviations<br />
will not be accepted, Thus, any issues / queries regarding Contract terms and conditions,<br />
Scope <strong>of</strong> Work, minimum requirements for Hardware infrastructure, essential features <strong>of</strong> the<br />
COTS products / components and minimum staffing requirements etc, should be either<br />
clarified before bid submission or submitted to the ASI in writing as per the schedule<br />
indicated in Clause 7.2.<br />
12.2.2 The ASI will respond in writing, to any request for clarification to queries on the RFP<br />
Document, received not later than the dates prescribed by the ASI in Clause 7.2 <strong>of</strong> this RFP<br />
document. Written copies <strong>of</strong> the ASI's response (including the query but without identifying<br />
the source <strong>of</strong> inquiry) would be put up on the www.ASI.nic.in website. Bidders are advised to<br />
keep browsing the information posted on the website.<br />
RFP Volume 2: Commercial and Bidding Terms Page 63
Request for Proposal<br />
For establishing e-Governance Systems<br />
For<br />
<strong>Archaeological</strong> <strong>Survey</strong> <strong>of</strong> <strong>India</strong><br />
Draft Legal Contract<br />
October 2011
Request for Proposal for establishing e-Governance Systems<br />
Volume 3: Draft Legal Contract<br />
1 INTRODUCTION .................................................................. ERROR! BOOKMARK NOT DEFINED.<br />
1.1 PARTICULARS OF RFP ........................................................... ERROR! BOOKMARK NOT DEFINED.<br />
2 SCOPE OF WORK FOR IMPLEMENTATION AGENCY (SI) ........ ERROR! BOOKMARK NOT DEFINED.<br />
2.1 OVERVIEW OF SCOPE OF WORK .............................................. ERROR! BOOKMARK NOT DEFINED.<br />
3 CONSTITUTION OF THE TEAM ............................................. ERROR! BOOKMARK NOT DEFINED.<br />
4 PROJECT IMPLEMENTATION ............................................... ERROR! BOOKMARK NOT DEFINED.<br />
4.1 APPROACH & METHODOLOGY FOR IMPLEMENTATION OF TECHNICAL SOLUTIONERROR! BOOKMARK NOT DEFINED.<br />
4.2 PROJECT TIMELINES .............................................................. ERROR! BOOKMARK NOT DEFINED.<br />
5 IMPLEMENTATION MODEL ................................................. ERROR! BOOKMARK NOT DEFINED.<br />
5.1 OPERATION MODEL ............................................................. ERROR! BOOKMARK NOT DEFINED.<br />
6 PAYMENT TERMS & SCHEDULE ........................................... ERROR! BOOKMARK NOT DEFINED.<br />
6.1 PAYMENT TERMS ................................................................. ERROR! BOOKMARK NOT DEFINED.<br />
6.2 PAYMENT SCHEDULE ............................................................ ERROR! BOOKMARK NOT DEFINED.<br />
7 BIDDING PROCESS DETAILS ................................................. ERROR! BOOKMARK NOT DEFINED.<br />
7.1 BIDDING SCHEDULE .............................................................. ERROR! BOOKMARK NOT DEFINED.<br />
7.2 GENERAL INSTRUCTION TO BIDDERS ........................................ ERROR! BOOKMARK NOT DEFINED.<br />
7.3 BID SUBMISSION INSTRUCTIONS ............................................. ERROR! BOOKMARK NOT DEFINED.<br />
7.4 CLARIFICATION ON RFP DOCUMENT ....................................... ERROR! BOOKMARK NOT DEFINED.<br />
7.5 BID OPENING & EVALUATION PROCESS ................................... ERROR! BOOKMARK NOT DEFINED.<br />
8 AWARD OF CONTRACT ....................................................... ERROR! BOOKMARK NOT DEFINED.<br />
8.1 POST QUALIFICATION AND AWARD CRITERIA ............................ ERROR! BOOKMARK NOT DEFINED.<br />
8.2 PURCHASER'S RIGHT TO VARY SCOPE OF CONTRACT .................. ERROR! BOOKMARK NOT DEFINED.<br />
8.3 PURCHASER'S RIGHT TO ACCEPT AND REJECT BIDS..................... ERROR! BOOKMARK NOT DEFINED.<br />
8.4 NOTIFICATION OF AWARD ..................................................... ERROR! BOOKMARK NOT DEFINED.<br />
8.5 NEGOTIATIONS WITH THE SUCCESSFUL BIDDER .......................... ERROR! BOOKMARK NOT DEFINED.<br />
8.6 SIGNING OF CONTRACT ......................................................... ERROR! BOOKMARK NOT DEFINED.<br />
8.7 PERFORMANCE SECURITY ...................................................... ERROR! BOOKMARK NOT DEFINED.<br />
9 ANNEXURE 1: BID FORMATS ............................................... ERROR! BOOKMARK NOT DEFINED.<br />
9.1 COVER LETTER ..................................................................... ERROR! BOOKMARK NOT DEFINED.<br />
9.2 PRE QUALIFICATION ............................................................. ERROR! BOOKMARK NOT DEFINED.<br />
9.3 TECHNICAL BID FORMATS ...................................................... ERROR! BOOKMARK NOT DEFINED.<br />
9.4 COMMERCIAL BID ................................................................ ERROR! BOOKMARK NOT DEFINED.<br />
10 ANNEXURE 2: PRE-QUALIFICATION AND TECHNICAL BID EVALUATION CRITERIAERROR! BOOKMARK NOT DEFIN<br />
10.1 PRE-QUALIFICATION EVALUATION CRITERIA ............................. ERROR! BOOKMARK NOT DEFINED.<br />
10.2 EVALUATION OF TECHNICAL BIDS ............................................ ERROR! BOOKMARK NOT DEFINED.<br />
11 ANNEXURE 3: STATEMENT OF DEVIATION FORMAT ............ ERROR! BOOKMARK NOT DEFINED.<br />
11.1 STATEMENT OF DEVIATIONS FROM SCHEDULE OF REQUIREMENTS ERROR! BOOKMARK NOT DEFINED.<br />
12 ANNEXURE 4: REQUEST FOR CLARIFICATION FORMAT ........ ERROR! BOOKMARK NOT DEFINED.<br />
12.1 FORMAT FOR CLARIFICATIONS ................................................ ERROR! BOOKMARK NOT DEFINED.<br />
12.2 CLARIFICATION ON RFP DOCUMENT ....................................... ERROR! BOOKMARK NOT DEFINED.<br />
RFP Volume 3: Draft Legal Contract Page 1
Request for Proposal for establishing e-Governance Systems<br />
A & P Accounts and Pay<br />
List <strong>of</strong> Abbreviations<br />
ADG Additional Director General<br />
AMC Annual Maintenance Contract<br />
ASI <strong>Archaeological</strong> <strong>Survey</strong> <strong>of</strong> <strong>India</strong><br />
BE Budget Estimate<br />
CDDO Cheque Drawing and Disbursing Officer<br />
CDO Cheque Drawing Officer<br />
CGF Central Government Fund<br />
COTS Commercial Off the Shelf<br />
DDO Drawing and Disbursing Officer<br />
FRS Functional Requirement Specifications<br />
FTP Full Technical Proposal<br />
HLD High Level Design<br />
IMAP Internet Message Access Protocol<br />
ISO International Standards Organization<br />
LLD Low Level Design<br />
MIME Multipurpose Internet Mail Extensions<br />
NIC National Informatics Centre<br />
NISG National Institute for Smart Government<br />
NOC No Objection Certificate<br />
PAO Pay and Account Offices<br />
PKI Public Key Infrastructure<br />
PoS Point <strong>of</strong> Sale<br />
RFP Request for Proposal<br />
SI System Integrator<br />
SLA Service Level Agreement<br />
SPOC Single Point <strong>of</strong> Contact<br />
SRS S<strong>of</strong>tware Requirement Specifications<br />
VPN Virtual Private Network<br />
SMTP Simple Mail Transfer Protocol<br />
RFP Volume 3: Draft Legal Contract Page 2
Request for Proposal for establishing e-Governance Systems<br />
1.1 DRAFT CONTRACT<br />
Draft Contract between the<br />
<br />
Government <strong>of</strong> <strong>India</strong><br />
and<br />
(Name <strong>of</strong> the Company)<br />
for<br />
PROVIDING THE SYSTEM INTEGRATION SERVICES FOR THE IMPLEMENTATION OF E-GOVERNANCE<br />
SOLUTION AT ASI<br />
Contract No dated <br />
Contract Number <br />
THIS CONTRACT is made on this <strong>of</strong>,, by and between:<br />
(i) The President <strong>of</strong> <strong>India</strong>, through the represented by<br />
AND<br />
_______________ (hereinafter called as the “BUYER”, which expression unless repugnant to<br />
the context or meaning there<strong>of</strong>, shall mean and include its successors or nominees or<br />
assignees or legal representative) <strong>of</strong> the FIRST PART;<br />
(ii) a company registered under the Companies Act, 1956 represented<br />
by and in the business <strong>of</strong> system integration (hereinafter called as<br />
“System Integrator” or “SI”, which expression unless repugnant to the context or meaning<br />
there<strong>of</strong>, shall mean and include its successors or permitted assigns ).<br />
( BUYER and SI are collectively referred to as the “Parties” and individually as a “Party”)<br />
WHEREAS<br />
RECITALS<br />
A. The BUYER intends to procure System Integration Services, Operations & Maintenance <strong>of</strong> E-<br />
governance solution on a turnkey basis (hereinafter called as “<strong>Project</strong>”) for selected<br />
locations <strong>of</strong> <strong>Archaeological</strong> <strong>Survey</strong> <strong>of</strong> <strong>India</strong> (ASI).<br />
B. The BUYER carried out selection process for selecting a suitable system integrator for<br />
implementing the <strong>Project</strong>, through the process <strong>of</strong> competitive bidding,pursuant to the “RFP”<br />
(as defined hereinafter);<br />
C. SI has been selected as the successful bidder to implement the <strong>Project</strong> on the basis <strong>of</strong> the<br />
proposal no. ------ dated -------- submitted by SI (“Proposal”).<br />
RFP Volume 3: Draft Legal Contract Page 3
Request for Proposal for establishing e-Governance Systems<br />
D. The BUYER has agreed to accord SI, the right to implement the <strong>Project</strong> on the terms and<br />
conditions set forth below.<br />
E. SI in pursuance <strong>of</strong> its Proposal undertakes to implement the <strong>Project</strong> on the terms and<br />
conditions set forth below.<br />
NOW THEREFORE, IN THE TERMS AND CONDITIONS OF THIS INDENTURE ARE SET OUT HEREIN<br />
UNDER, the Parties have agreed to enter into this Contract to govern the way in which the SI<br />
shall implement and execute the <strong>Project</strong> under this Contract and define the roles and<br />
responsibilities <strong>of</strong> the BUYER and SI.<br />
RFP Volume 3: Draft Legal Contract Page 4
Request for Proposal for establishing e-Governance Systems<br />
2 Article 1: Definitions And Interpretations<br />
1.1. Definitions:In this Contract, unless the context otherwise requires<br />
(1) “Annual Maintenance Contract” (AMC) means the following services to be provided<br />
by SI.<br />
(i) Warranty Services<br />
(ii) Technical Support and help desk services<br />
for the application, data center and other IT related infrastructure<br />
(2) “Applicable Laws” includes all applicable statutes, enactments, acts <strong>of</strong> legislature or<br />
parliament laws, ordinances, rules, by-laws, regulations, notifications, guidelines,<br />
policies, directions, directives and orders <strong>of</strong> any Governmental authority, tribunal,<br />
board, court or other quasi judicial authority<br />
(3) “ASI Area” means portion(s) <strong>of</strong> the Data Center, Disaster Recovery Center,<br />
Deployment and Implementation Sites that are made available to SI for the<br />
placement <strong>of</strong> IT infrastructure, and solutions.<br />
(4) “Availability and Performance Report” means the report on the Service Levels<br />
measured for the defined period.<br />
(5) “Business Hours” would invariably mean 9:00am to 6:00pm on all working days.<br />
Business hours at Implementation Sites may vary as per local orders.<br />
(6) “Conditions Precedent” shall have the meaning assigned to it in Article 2.2 here<strong>of</strong>.<br />
(7) “Contract” means this contract together with all the Schedules and shall include any<br />
modifications, alterations, additions or deletions thereto agreed between the Parties<br />
in writing after the date here<strong>of</strong> in terms <strong>of</strong> this contract. In the event <strong>of</strong> a conflict<br />
between this contract and the Schedules, the terms <strong>of</strong> the Contract shall prevail.<br />
(8) “Confidential Information” means all information as defined in the Article 17.<br />
(9) “Customization” means the process <strong>of</strong> making Modifications, Enhancements,<br />
developing interfaces and making changes to the s<strong>of</strong>tware including but not limited<br />
to Electronic Communication, E-ticketing and Financial Planning and Budgeting<br />
Modules, Help Desk s<strong>of</strong>tware, s<strong>of</strong>tware for access to historical data, Security<br />
applications and products, backup s<strong>of</strong>tware and applications, hardware and network<br />
control and the monitoring s<strong>of</strong>tware to be implemented by SI to meet the<br />
requirements <strong>of</strong> the BUYER as specified in Article 3 and system requirement<br />
specifications study to be performed by SI.<br />
RFP Volume 3: Draft Legal Contract Page 5
Request for Proposal for establishing e-Governance Systems<br />
(10) “Data” shall mean any record <strong>of</strong> any matter or thing tangible or intangible, factual,<br />
fictitious or imaginary, hypothetical or abstract, known or unknown, accurate or<br />
inaccurate and includes any thought, form or substance, or knowledge proposition<br />
or opinion supplied or recorded by man or machine and prepared, stored or<br />
transmitted in computer readable form and shall include information.<br />
(11) “DataCenter” or “(DC)” means the primary centre where Data, s<strong>of</strong>tware, computer<br />
systems and associated components, such as telecommunication and storage<br />
systems, redundant or backup power supplies, redundant data communications,<br />
environment controls and security devices are housed and operated from.<br />
(12) “Data Migration” means moving <strong>of</strong> Data from existing manual systems or existing<br />
automated systems to the new E-governance solution.<br />
(13) “Deliverables” means the business designs, the process documentations, the<br />
hardware, the solutions, the training materials, etc agreed to be delivered by SI as<br />
defined in Article 3 in pursuance <strong>of</strong> the Contract.<br />
(14) “Development Site” means the site that is provided to SI by the BUYER where SI<br />
would perform the activities related to the <strong>Project</strong>.<br />
(15) “Disaster Recovery Centre” or “DRC” means the centre that is designed to act as the<br />
DataCenter on occurrence <strong>of</strong> a disaster / non-functioning <strong>of</strong> the primary DC.<br />
(16) “Documentation” shall mean the explanatory electronic or paper documents and<br />
notes referring to the installation, configuration, customization, maintenance and<br />
use <strong>of</strong> the Licensed S<strong>of</strong>tware.<br />
(17) “Effective Date <strong>of</strong> Contract” or “Effective Date” means the date on which this<br />
Contract is signed by both the Parties.<br />
(18) “Effective Date <strong>of</strong> <strong>Project</strong> Commencement” means the date on which the<br />
Conditions Precedent have been satisfied by SI or waived by the BUYER. For<br />
calculation <strong>of</strong> all project schedules/delays etc, this date will be taken into account as<br />
the date <strong>of</strong> commencement <strong>of</strong> the <strong>Project</strong>.<br />
(19) “End Users” means the users who use the s<strong>of</strong>tware and services.<br />
(20) “Enhancement” means incorporation <strong>of</strong> new modules, etc made to the Licensed<br />
S<strong>of</strong>tware by SI, so as to support new technologies, functionalities and upgrades.<br />
(21) “Equipment” means the computer hardware, network, peripherals, and other<br />
tangible equipments supplied for the <strong>Project</strong>, pursuant to the Contract.<br />
(22) “E-governance solution” means the three modules related to electronic<br />
communication solutions, e-ticketing solutions, and Finance and budgeting solutions<br />
proposed by BUYER to meet the functional and technical requirements <strong>of</strong> the<br />
BUYER. This includes all the standard modules <strong>of</strong> the E-governance solution as well<br />
RFP Volume 3: Draft Legal Contract Page 6
Request for Proposal for establishing e-Governance Systems<br />
as the third party tools, databases, and middleware s<strong>of</strong>tware bundled with the E-<br />
governance solution to make it work as a complete solution.<br />
(23) “Executive Committee” shall be the committee constituted by ASI to take up the<br />
project <strong>of</strong> implementation <strong>of</strong> E-governance solution at ASI.<br />
(24) “Go-Live” or “Go Live” means commissioning and integration <strong>of</strong> all the hardware<br />
including Data Center, Disaster Recovery Center, the networks, the client side<br />
computing devices and all the s<strong>of</strong>tware applications, including the E-governance<br />
solutions configured, customized and used successfully by all the intended users <strong>of</strong><br />
the BUYER for successfully executing all the intended transactions as mentioned in<br />
the Article 3 at mutually agreeable levels<br />
(25) “Handholding” means the support provided by SI that includes but not limited to<br />
the onsite support at the Implementation sites, DataCenter,<br />
DisasterRecoveryCenter, Help Desk, support for the implemented s<strong>of</strong>tware, users <strong>of</strong><br />
the system and maintenance <strong>of</strong> the related information technology infrastructure.<br />
(26) “Help Desk” means the facility setup by SI at selected locations that provides<br />
support through personnel or telephonic or any other means for issues faced by End<br />
Users.<br />
(27) “Implementation Services” means the services required to be delivered by SI to the<br />
BUYER for successful and comprehensive implementation <strong>of</strong> E-governance solution<br />
for the BUYER as per the requirements detailed in Article 3.<br />
(28) “Implementation Site” means any locations <strong>of</strong> the BUYER where E-governance<br />
solution is implemented.<br />
(29) “Information” shall mean any Data after being processed for the purpose <strong>of</strong> being<br />
applied or supplied in response to a given requirement and other statement or<br />
record made by man or machine and capable <strong>of</strong> being perceived by the human<br />
senses.<br />
(30) “Intellectual Property Rights" means rights as defined in the Article 14.<br />
(31) “Licensed S<strong>of</strong>tware” shall mean ……..…. as specified in Schedule III <strong>of</strong> this Contract.<br />
(32) “Modification” means any change effected to fix bugs and program s<strong>of</strong>tware<br />
defects, errors, minor customization, incorporation <strong>of</strong> minor new features etc in the<br />
Licensed Electronic Communication, E-ticketing, and Finance and Budgeting<br />
Solutions by SI, so as to make it functionally complete.<br />
(33) “Material Adverse Effect” means material adverse effect on (a) the ability <strong>of</strong> SI to<br />
perform/discharge any <strong>of</strong> its duties/obligations under and in accordance with the<br />
provisions <strong>of</strong> this Contract and/or (b) the legal validity, binding nature or<br />
enforceability <strong>of</strong> this Contract.<br />
RFP Volume 3: Draft Legal Contract Page 7
Request for Proposal for establishing e-Governance Systems<br />
(34) “Network” means the physical medium through which Data is transferred from<br />
source to destination.<br />
(35) “New Version” means a version <strong>of</strong> Licensed S<strong>of</strong>tware or hardware released as “New<br />
Version” by the OEM.<br />
(36) “OEM” or “Original Equipment Manufacturer” means the original manufacturer <strong>of</strong><br />
the s<strong>of</strong>tware or hardware that owns the original Intellectual Property rights to the<br />
s<strong>of</strong>tware or hardware to be used in the <strong>Project</strong> and to which the BUYER has been<br />
granted license to use.<br />
(37) “Operations and Maintenance Services” or “O&M” includes the activities covered<br />
during the period from “Go Live” till the expiry or termination <strong>of</strong> the Contract. Some<br />
<strong>of</strong> the key activities in this stage include but are not limited to the warranty for<br />
equipments, ATS for s<strong>of</strong>tware, handholding for the implemented s<strong>of</strong>tware solution,<br />
supporting the End Users in using the new system, maintenance <strong>of</strong> the entire<br />
Information Technology infrastructure, New Versions, Helpdesk services and AMC.<br />
(38) “Operative Period <strong>of</strong> Contract” or “Term”means the period <strong>of</strong> the Contract<br />
commencing from the Effective Date <strong>of</strong> <strong>Project</strong> Commencement and continuing till<br />
the last day <strong>of</strong> Operations and Maintenance Service, or the date <strong>of</strong> termination, in<br />
case <strong>of</strong> earlier termination <strong>of</strong> the Contract.<br />
(39) “<strong>Project</strong>” means the entire set <strong>of</strong> activities that include “System Integration<br />
Services” and “Operations & Maintenance Services”.<br />
(40) “<strong>Project</strong> Assets” means the assets (including hardware and s<strong>of</strong>tware), other than ASI<br />
Supplied Equipment, supplied for the purpose <strong>of</strong> the <strong>Project</strong>, pursuant to this<br />
Contract.<br />
(41) “<strong>Project</strong> Site” means all the sites that include Development Site, Implementation<br />
Sites, DataCenter and DisasterRecoveryCenter.<br />
(42) “Request for Proposal (RFP)” means the documents containing the general,<br />
technical, functional, commercial and legal specifications for the implementation <strong>of</strong><br />
the <strong>Project</strong> issued in different parts and as different Appendices and Annexure and<br />
includes the clarifications, explanations, minutes <strong>of</strong> the meetings and amendments<br />
issued from time to time during the bidding process.<br />
(43) "Replacement SI" means any third party that the BUYER may appoint to replace SI<br />
on or before the expiry <strong>of</strong> the Operative Period <strong>of</strong> Contract or on termination <strong>of</strong> this<br />
Contract to undertake the <strong>Project</strong> or part or extension there<strong>of</strong>.<br />
(44) "Service Level" means the level <strong>of</strong> service and the completeness <strong>of</strong> the services<br />
delivered, and other performance criteria which will apply to the services as set out<br />
in Article 3.<br />
RFP Volume 3: Draft Legal Contract Page 8
Request for Proposal for establishing e-Governance Systems<br />
(45) “SI Assets for Own Use” or “SI Assets” means assets other than the <strong>Project</strong> Assets<br />
including but not limited to the computer hardware, s<strong>of</strong>tware, Network<br />
components, power supply and other tangible equipment used by SI for the <strong>Project</strong>.<br />
(46) “Source Code” means the human-readable version <strong>of</strong> the Licensed S<strong>of</strong>tware made<br />
up <strong>of</strong> the source program containing computer instructions and Data definitions,<br />
which cannot be executed on a computer processor without compilation or<br />
conversion into binary language.<br />
(47) “System Integration Services or “SIS” includes the activities till Go Live. These<br />
include but are not limited to Integration & Commissioning <strong>of</strong> hardware<br />
configuration, Customization and implementation <strong>of</strong> all the s<strong>of</strong>tware including the<br />
Electronic Communication, E-ticketing, and Finance and Budgeting Solutions; Data<br />
Migration and training.<br />
(48) “Third Party Systems” means systems or any part there<strong>of</strong> for which the Intellectual<br />
Property Rights are owned by a third party and the BUYER has been granted a<br />
license to use.<br />
(49) “Updates” means but is not limited to a minor change, Modification, customization<br />
made to the Licensed S<strong>of</strong>tware by SI or OEM so as to incorporate ‘bug fixes’, or<br />
improve the existing technology, features or functionality.<br />
(50) “Working Day” means any day on which any <strong>of</strong> the unit <strong>of</strong> ASI will be functioning.<br />
The BUYER will provide list <strong>of</strong> its scheduled holidays.<br />
1.2. Interpretations. In this Contract, unless the context otherwise requires:-<br />
(1) Any reference to a statutory provision and shall include such provision as from time<br />
to time modified or re-enacted or consolidated so far as such modification or re-<br />
enactment or consolidation applies or is capable <strong>of</strong> applying to any transactions<br />
entered into hereunder.<br />
(2) The words importing singular shall include plural and vice versa, and words denoting<br />
natural person shall include partnerships, firms, companies, corporations, joint<br />
ventures, trusts, associations, organizations, executors, administrators, successors,<br />
agents, substitutes and any permitted assignees or other entities (whether or not<br />
having a separate legal entity). A reference to a group <strong>of</strong> persons is a reference to<br />
all <strong>of</strong> them collectively, to any two or more <strong>of</strong> them collectively and to each <strong>of</strong> them<br />
individually. Reference to a Party or the Parties is a reference to a party or to the<br />
parties to this Contract unless otherwise stated.<br />
(3) Unless otherwise expressly stated, the words "herein", "here<strong>of</strong>", "hereunder" and<br />
similar words refer to this Contract as a whole and not to any particular Article or<br />
Schedule. The term Articles, refers to Articles <strong>of</strong> this Contract. The words "in writing"<br />
RFP Volume 3: Draft Legal Contract Page 9
Request for Proposal for establishing e-Governance Systems<br />
and "written" mean "in documented form", whether electronic or hard copy, unless<br />
otherwise stated. Any reference to attorneys' fees shall include fees <strong>of</strong> the<br />
pr<strong>of</strong>essional assistants <strong>of</strong> such attorneys.<br />
(4) The headings and use <strong>of</strong> bold type in this Contract are for convenience only and shall<br />
not affect the interpretation <strong>of</strong> any provision <strong>of</strong> this Contract. The table <strong>of</strong> contents<br />
and any headings in this Contract are for ease <strong>of</strong> reference only and shall not affect<br />
the construction or interpretation <strong>of</strong> this Contract.<br />
(5) References to “installation” include investigation, design, engineering, procurement,<br />
delivery, transportation, installation, processing, fabrication, testing, commissioning<br />
and other activities incidental to the construction.<br />
(6) Any reference to any period <strong>of</strong> time shall mean a reference to that according to<br />
<strong>India</strong>n standard time.<br />
(7) Any reference to day shall mean a reference to <strong>India</strong>n calendar day.<br />
(8) Any reference to month shall mean a reference to <strong>India</strong>n calendar month<br />
(9) Any reference at any time to any Contract, deed, instrument, license or document <strong>of</strong><br />
any description shall be construed as reference to that Contract, deed, instrument,<br />
license or other document as amended, varied, supplemented, modified or<br />
innovated at the time <strong>of</strong> such reference.<br />
(10) Any Contract, consent, approval, authorization, notice, communication, information<br />
or report required under or pursuant to this Contract from or by any Party or the<br />
independent engineer and/or a statutory auditor and/or any other authority shall be<br />
valid and effectual only if it is in writing under the hands <strong>of</strong> duly authorized<br />
representative <strong>of</strong> such Party or the independent engineer and/or statutory auditor<br />
or any other authority, as the case may be, in this behalf and not otherwise.<br />
(11) Unless otherwise stated, any reference to any period commencing “from” a<br />
specified day or date and “till” or “until” a specified day or date shall include both<br />
such days or dates.<br />
(12) Unless otherwise specified, any interest to be calculated and payable under this<br />
Contract shall accrue on an Annual basis and from the respective due dates as<br />
provided for in this Contract.<br />
(13) A reference to an article, clause, section, schedule, annexure or appendix is a<br />
reference to an article, clause, section, schedule, annexure or appendix to this<br />
Contract unless otherwise stated and references to this Contract include any recital,<br />
schedule, annexure or appendix to this Contract.<br />
(14) A word denoting a gender includes all genders.<br />
RFP Volume 3: Draft Legal Contract Page 10
Request for Proposal for establishing e-Governance Systems<br />
(15) A reference to knowledge <strong>of</strong> a person includes information that a reasonable person<br />
in the circumstances <strong>of</strong> that person would have known by reasonable inquiry.<br />
(16) In interpreting this Contract no rule <strong>of</strong> construction applies to the disadvantage <strong>of</strong> a<br />
party because that party or its legal advisor was responsible for the preparation <strong>of</strong><br />
this Contract or any part <strong>of</strong> it.<br />
1.3. Measurements and Arithmetic Conventions. All measurements and calculations shall be in<br />
metric system and calculations done to 2 decimal places, with the third digit <strong>of</strong> 5 or above<br />
being rounded up and below 5 being rounded down.<br />
1.4. Ambiguities and Discrepancies. In case <strong>of</strong> ambiguities or discrepancies within this<br />
Contract, the following shall apply:-<br />
(1) Between two Articles <strong>of</strong> this Contract, the provisions <strong>of</strong> specific Articles relevant to<br />
the issue under consideration shall prevail over those in other Articles.<br />
(2) Between the dimension scaled from the design and drawings and its specific written<br />
dimension, the latter shall prevail.<br />
(3) Between any value written in numerals and that in words, the latter shall prevail;<br />
and<br />
(4) Between the provisions <strong>of</strong> this Contract and any other documents forming part <strong>of</strong><br />
this Contract, the former shall prevail.<br />
RFP Volume 3: Draft Legal Contract Page 11
Request for Proposal for establishing e-Governance Systems<br />
3 Article 2: Structure<br />
2.1. Overview. This Contract shall operate as a legally binding contract for the <strong>Project</strong> specifying<br />
the master terms which apply to the Parties under this Contract, including but not limited to<br />
terms in relation to implementation <strong>of</strong> Electronic Communication, E-ticketing, and Finance<br />
and Budgeting Solutions, integration <strong>of</strong> the solution components, training <strong>of</strong> the users and<br />
subsequently operate and maintain the system with commitment for delivering the goods<br />
and services specified under this Contract in accordance with roles and responsibilities set<br />
for the herein for maximum total consideration <strong>of</strong> Rs. , inclusive <strong>of</strong><br />
all taxes, levies, cess and any other statutory dues.<br />
(1) This Contract constitutes the entire understanding between the Parties regarding<br />
the <strong>Project</strong> and supersedes or supplements all previous written and/or oral<br />
representations and/or arrangements regarding the same. If there is any aspect <strong>of</strong><br />
the <strong>Project</strong> not covered by any <strong>of</strong> the provisions <strong>of</strong> this Contract, then and only in<br />
that event, reference may be made by the Parties to the bid documents, inter alia<br />
including the clauses and materials <strong>of</strong> all the specifications, terms and conditions <strong>of</strong><br />
RFP issued by the BUYER and also including the addendums, clarifications given in<br />
writing in the pre-bid meetings and the submissions <strong>of</strong> SI and the bid submitted by SI<br />
but not otherwise. In case <strong>of</strong> any contradictions in the terms <strong>of</strong> this Contract and any<br />
such other bid documents as referred to above, the terms <strong>of</strong> this Contract shall<br />
prevail.<br />
(2) This Contract shall include all the commitments made by SI through the response to<br />
the RFP, duly signed by the authorised signatory <strong>of</strong> SI.<br />
(3) There are two distinct stages during which the Contract will be in force. The nature<br />
<strong>of</strong> work, the commitment and the interpretation <strong>of</strong> the Contract will be based on<br />
the context <strong>of</strong> these two stages. Both these stages together comprise the <strong>Project</strong> :-<br />
(i) System Integration Services (SIS) Stage.<br />
(ii) Operations and Maintenance Services stage.<br />
(4) While the SIS stage will be executed in a project mode with emphasis on the supply<br />
2.2. Conditions Precedent.<br />
<strong>of</strong> the <strong>Project</strong> Assets, installing, commissioning and implementing them, etc. as per<br />
the technical and functional specifications, the Operations and Maintenance<br />
Services stage will be driven by definition <strong>of</strong> services, the Service Levels, the<br />
measurement <strong>of</strong> Service Levels, penalties for non conformance to services, etc.<br />
RFP Volume 3: Draft Legal Contract Page 12
Request for Proposal for establishing e-Governance Systems<br />
(1) Subject to express terms to the contrary, the rights and obligations under this<br />
Contract shall be effective (at any point <strong>of</strong> time during the course <strong>of</strong> the Contract)<br />
only upon fulfilment <strong>of</strong> all the conditions precedent (“Conditions Precedent”) set<br />
out in this Article 2.2 (a). SI shall:-<br />
(i) Provide the “Performance Bank Guarantee” (as defined in Article 2.6 here<strong>of</strong>)<br />
to the BUYER as specified in the RFP document.<br />
(ii) Provide the BUYER, the certified true copies <strong>of</strong> its constitutional documents<br />
and board resolutions authorizing the execution, delivery and performance <strong>of</strong><br />
this Contract with the BUYER.<br />
However, the BUYER may at any time at its sole discretion waive fully or partially any<br />
<strong>of</strong> the Conditions Precedent.<br />
(2) Non-fulfilment <strong>of</strong> Conditions Precedent.<br />
(i) Subject to Article 2 (b) (iv) below, in the event that any <strong>of</strong> the Conditions<br />
Precedent has not been fulfilled within fifteen days <strong>of</strong> the Effective Date and the<br />
same has not been waived by the BUYER fully or partially, this Contract shall<br />
stand terminated as <strong>of</strong> that date.<br />
(ii) In the event <strong>of</strong> termination <strong>of</strong> the Contract on account <strong>of</strong> non-fulfillment <strong>of</strong><br />
Conditions Precedent, the BUYER shall not be liable in any manner whatsoever<br />
to SI and SI shall forthwith forfeit the money deposited by Buyer under RFP<br />
(“Earnest Money Deposit”). Such termination and forfeitures shall be without<br />
prejudice or other rights <strong>of</strong> the BUYER under law or Contract.<br />
(iii) In the event that vacant possession <strong>of</strong> any <strong>of</strong> the <strong>Project</strong> facilities and/or<br />
equipment has been delivered to SI prior to the fulfillment in fulfillment <strong>of</strong> the<br />
Conditions Precedent, then on termination <strong>of</strong> this Contract such possession shall<br />
immediately revert to the BUYER free and clear from any encumbrances or<br />
claims.<br />
2.3. Entire Agreement.<br />
(iv) Instead <strong>of</strong> terminating this Contract as provided in Article 2.2 (b)(i) above, the<br />
Parties may mutually agree in writing to extend the time for fulfilling the<br />
Conditions Precedent and the Term. It is further clarified that any such extension<br />
<strong>of</strong> time shall be subject to imposition <strong>of</strong> penalties on SI linked to the delay in<br />
fulfilling the Conditions Precedent.<br />
(1) This Contract shall constitute the entire agreement amongst the Parties hereto in<br />
respect <strong>of</strong> the subject matter here<strong>of</strong>.<br />
(2) This Contract, including all documents incorporated herein by reference, constitutes the<br />
complete and final agreement between the BUYER and SI with respect to the subject<br />
matter here<strong>of</strong>, and supersedes all prior or contemporaneous negotiations, written or<br />
RFP Volume 3: Draft Legal Contract Page 13
Request for Proposal for establishing e-Governance Systems<br />
oral understandings and agreements, between the Parties regarding such subject<br />
matter.<br />
(3) This Contract may be executed in two or more counterparts, each <strong>of</strong> which will be<br />
deemed an original, but all <strong>of</strong> which together shall constitute one and the same<br />
instrument.<br />
(4) It is the obligation <strong>of</strong> SI to inform OEMs in respect <strong>of</strong> their respective obligations to SI<br />
and in turn to ASI under the Contract and to ensure that they agree and commit to due<br />
discharge <strong>of</strong> their obligations under the relevant terms and conditions <strong>of</strong> this Contract.<br />
2.4. Severability. If any provision <strong>of</strong> the Contract, or any part there<strong>of</strong>, shall be found by any court<br />
or administrative body <strong>of</strong> competent jurisdiction to be illegal, invalid or unenforceable, the<br />
illegality, invalidity or unenforceability <strong>of</strong> such provision or part provision shall not affect the<br />
other provisions <strong>of</strong> the Contract or the remainder <strong>of</strong> the provisions in question which shall<br />
remain in full force and effect. The Parties shall negotiate in good faith in order to agree to<br />
substitute for any illegal, invalid or unenforceable provision a valid and enforceable<br />
provision, which achieves to the greatest extent possible the economic, legal and<br />
commercial objectives <strong>of</strong> the illegal, invalid or unenforceable provision or part provision.<br />
2.5. Additional work. The BUYER has the option to avail the services <strong>of</strong> SI for carrying out any<br />
extension or changes in scope <strong>of</strong> work, as a part <strong>of</strong> the <strong>Project</strong>, provided the prices for the<br />
same has been obtained already in the bidding process leading to this Contract in the<br />
Schedule I. All such additional work will be initiated using the change control procedures<br />
listed in the Schedule II.<br />
2.6. Bank guarantee.SI warrants to provideBank guarantee for the Contract as a whole, valued at<br />
10% <strong>of</strong> value <strong>of</strong> the Contract valid for the Operative Period <strong>of</strong> Contract. (“Performance Bank<br />
Guarantee”) or (“PBG)”):<br />
2.7. Extension <strong>of</strong> the Contract. The BUYER has the option to extend the Contract on expiry, to<br />
avail the services <strong>of</strong> SI for specific work or continuation <strong>of</strong> the work carried out during the<br />
Operative Period <strong>of</strong> Contract. All the general terms and conditions other than the scope <strong>of</strong><br />
work as listed in Article 3 <strong>of</strong> this Contract will be in force during the extended period <strong>of</strong> the<br />
Contract. The new scope <strong>of</strong> work for the extension period will be defined through the<br />
change control procedure mentioned in Schedule II.<br />
2.8. Amendment. No provisions <strong>of</strong> this Contract shall be changed or modified in any way<br />
(including this provision) either in whole or in part except by an instrument in writing made<br />
after the Effective Date <strong>of</strong> Contract and signed by both Parties and which expressly states to<br />
amend this Contract.<br />
RFP Volume 3: Draft Legal Contract Page 14
Request for Proposal for establishing e-Governance Systems<br />
4 Article 3: Scope <strong>of</strong> the <strong>Project</strong><br />
Scope <strong>of</strong> the project is detailed in Volume I <strong>of</strong> the RFP document.<br />
3.1. Interpretation <strong>of</strong> the Scope <strong>of</strong> Work.<br />
(1) The BUYER retains the right <strong>of</strong> the final say in the interpretation <strong>of</strong> the scope <strong>of</strong> the<br />
<strong>Project</strong>. The possible variations to the processes during the Business Design phase<br />
from the way they are specified in the Schedule III should not be considered as<br />
deviations or extensions to the original process specifications.<br />
(2) The performance <strong>of</strong> the ultimate system can be achieved by different combinations<br />
<strong>of</strong> the Equipments and Network components. The final acceptance <strong>of</strong> the integrated<br />
solution and infrastructure components should be as per the performance<br />
requirements and will be the determining factor but not the specifications <strong>of</strong> the<br />
infrastructure alone.<br />
RFP Volume 3: Draft Legal Contract Page 15
Request for Proposal for establishing e-Governance Systems<br />
4.1. Terms <strong>of</strong> Payment.<br />
5 Article 4 : Payment Terms<br />
(1) In consideration <strong>of</strong> the <strong>Project</strong> and subject to the provisions <strong>of</strong> this Contract, the BUYER<br />
shall pay SI for the services rendered in pursuance <strong>of</strong> this Contract, in accordance with<br />
the Schedule IV to this Contract.<br />
(2) Except as otherwise provided for herein or as agreed between the Parties in writing, the<br />
BUYER shall not be required to make any payments in respect <strong>of</strong> the services other than<br />
those covered by the terms <strong>of</strong> payment, as stated in the Schedule IV.<br />
4.2. Invoicing and Settlement.<br />
(1) In respect <strong>of</strong> its remuneration for the <strong>Project</strong> SI shall be eligible to receive payments in<br />
accordance with the Schedule IV.<br />
(i) The BUYER shall be invoiced by SI for the <strong>Project</strong>. Generally and unless otherwise<br />
agreed in writing between the Parties or expressly set out in the Contract SI shall<br />
raise an invoice as per the terms <strong>of</strong> payment as stated in Schedule IV.<br />
(ii) The invoices will be accepted by the BUYER for payment only if the or the designated representative <strong>of</strong> the issues an acceptance certificate that the respective<br />
milestones and the Deliverables <strong>of</strong> those milestones are accepted.<br />
(iii) Any invoice presented in accordance with this Article shall be in a form agreeable by<br />
the BUYER.<br />
(2) Invoices shall be accurate and all adjustments to or changes in the terms <strong>of</strong> payment as<br />
stated in the Schedule IV shall be applied to the next payment invoice.<br />
(3) The BUYER shall be entitled to process the payment <strong>of</strong> any invoice raised by SI or part <strong>of</strong><br />
it only after the acceptance certificate for the Deliverables is issued by the . Any exercise by the BUYER under this<br />
Article shall not entitle SI to delay or withhold provision <strong>of</strong> the <strong>Project</strong>.<br />
(4) SI shall pay all their sub-contractors in a timely fashion in accordance with a mechanism,<br />
which will not prejudice the objective <strong>of</strong> the <strong>Project</strong>.<br />
4.3. Payment <strong>of</strong> Tax / Tax Considerations.<br />
(1) The BUYER shall be entitled to deduct tax (at source) from the amounts due and payable<br />
to SI, wherever applicable. SI shall pay for all other taxes in connection with this<br />
Contract, and any other including, but not limited to, property, sales, use, excise duty,<br />
value-added goods and services, consumption and other similar taxes or duties.<br />
RFP Volume 3: Draft Legal Contract Page 16
Request for Proposal for establishing e-Governance Systems<br />
(2) The BUYER or its associated entity shall provide SI with the statement <strong>of</strong> tax receipt <strong>of</strong><br />
any taxes deducted at source on payments under this Contract. SI agrees to reimburse<br />
and do not hold the BUYER accountable from any deficiency (including penalties and<br />
interest) relating to taxes that are its responsibility under this paragraph. For purposes<br />
<strong>of</strong> this Contract, taxes shall include taxes incurred on transactions between and among<br />
the BUYER, SI and any third party subcontractors.<br />
(3) In the event <strong>of</strong> any increase or decrease <strong>of</strong> the rate <strong>of</strong> taxes due to any statutory<br />
notification/s during the term <strong>of</strong> the Contract, the consequential effect shall be to the<br />
account <strong>of</strong> SI.<br />
(4) The Parties shall cooperate to enable each Party to accurately determine its own tax<br />
liability and to minimize such liability to the extent legally permissible. In connection<br />
therewith, the Parties shall provide each other with (i) any resale certificates, (ii) any<br />
relevant information regarding use <strong>of</strong> out-<strong>of</strong>-state materials, equipment or services and<br />
(iii) any exemption certificates or information reasonably requested by the other Party.<br />
4.4. Liquidated Damages. In the event <strong>of</strong> SI's failure to submit the Bonds, Guarantees and<br />
Documents, supply the <strong>Project</strong> Assets and conduct trials, installation <strong>of</strong> equipment and<br />
training as per Schedule III specified in this Contract, the BUYER may at his discretion<br />
withhold any payment until the completion <strong>of</strong> the Contract. The BUYER may also deduct<br />
from SI as agreed, liquidated damages to the sum <strong>of</strong> 0.5% <strong>of</strong> the Contract price <strong>of</strong> the<br />
delayed/undelivered stores/ services mentioned above for every week <strong>of</strong> delay or part <strong>of</strong> a<br />
week, subject to the maximum value <strong>of</strong> the Liquidated Damages being not higher than 5% <strong>of</strong><br />
the value <strong>of</strong> delayed stores. This right to claim any liquidated damages shall be without<br />
prejudice to other rights and remedies available to BUYER under the Contract and/or law.<br />
RFP Volume 3: Draft Legal Contract Page 17
Request for Proposal for establishing e-Governance Systems<br />
6 Article 5: Representation and Warranties<br />
5.1. Representations and Warranties and Covenants <strong>of</strong> SI. SI represents and warrants and<br />
covenants to the BUYER that:<br />
(1) It is duly organised, validly existing and in good standing under the laws <strong>of</strong> <strong>India</strong> and<br />
hereby expressly and irrevocably waives any immunity in any jurisdiction in respect<br />
<strong>of</strong> this Contract or matters arising thereunder including any obligation, liability or<br />
responsibility hereunder.<br />
(2) It has full power and authority to execute, deliver and perform its obligations under<br />
this Contract.<br />
(3) It has taken all necessary action to authorise the execution, delivery and<br />
performance <strong>of</strong> this Contract.<br />
(4) This Contract constitutes the legal, valid and binding obligation <strong>of</strong> SI, enforceable<br />
against it in accordance with the terms here<strong>of</strong>.<br />
(5) There are no actions, suits or proceedings pending or to its best knowledge,<br />
threatened against or affecting it before any court, administrative body or arbitral<br />
tribunal which might materially and adversely affect its ability to meet or perform<br />
any <strong>of</strong> its obligations under this Contract.<br />
(6) It has the financial standing and capacity to undertake the <strong>Project</strong> in accordance<br />
with the terms <strong>of</strong> this Contract.<br />
(7) The execution, delivery and performance <strong>of</strong> this Contract will not conflict with,<br />
result in the breach <strong>of</strong>, constitute a default under, or accelerate performance<br />
required by any <strong>of</strong> the terms <strong>of</strong> its memorandum <strong>of</strong> association and articles <strong>of</strong><br />
association or any Applicable Laws or any covenant, Contract, agreement,<br />
arrangement, understanding, decree or order to which it is a Party or by which it or<br />
any <strong>of</strong> its properties or assets is bound or affected.<br />
(8) It has no knowledge <strong>of</strong> any violation or default with respect to any order, writ,<br />
injunction or decree <strong>of</strong> any court or any legally binding order <strong>of</strong> any Government<br />
authority which may result in any Material Adverse Effect on its ability to perform its<br />
obligations under this Contract and no fact or circumstance exists which may give<br />
rise to such proceedings that would adversely affect the performance <strong>of</strong> its<br />
obligations under this Contract.<br />
(9) It has complied with Applicable Laws in all material respects and has not been<br />
subject to any fines, penalties, injunctive relief or any other civil or criminal liabilities<br />
RFP Volume 3: Draft Legal Contract Page 18
Request for Proposal for establishing e-Governance Systems<br />
which in the aggregate have or may have a Material Adverse Effect on its ability to<br />
perform its obligations under this Contract.<br />
(10) All its rights and interests in the <strong>Project</strong>/<strong>Project</strong> Assets that are to be transferred to<br />
the BUYER, pursuant to this Contract shall pass to and vest in the BUYER or its<br />
nominee on the Transfer Date free and clear <strong>of</strong> all liens, claims and encumbrances,<br />
without any further act or deed on its part or that <strong>of</strong> the BUYER, and that none <strong>of</strong><br />
the <strong>Project</strong> Assets that are acquired by the BUYER shall be acquired by it, subject to<br />
any agreement under which a security interest or other lien or encumbrance is<br />
retained by any person, save and except as expressly provided in this Contract. The<br />
expression “Transfer Date” shall mean date on which the <strong>Project</strong> Assets or any part<br />
there<strong>of</strong> are transferred to the BUYER or its nominee, pursuant to the Contract, on<br />
Go Live coming into effect or on termination <strong>of</strong> the Contract, if such termination<br />
happens prior to Go-Live.<br />
(11) No representation or warranty by it contained herein or in any other document<br />
furnished by it to the BUYER including the Proposal or to any Government Authority<br />
contains or will contain any untrue or misleading statement <strong>of</strong> material fact or omits<br />
or will omit to state a material fact necessary to make such representation or<br />
warranty not misleading.<br />
(12) No sums, in cash or kind, have been paid or will be paid, by it or on its behalf, to any<br />
person by way <strong>of</strong> fees, commission or otherwise for securing the Contract or<br />
entering into this Contract or for influencing or attempting to influence any <strong>of</strong>ficer<br />
or employee <strong>of</strong> the BUYER in connection therewith.<br />
(13) Agrees that the execution, delivery and performance by it <strong>of</strong> this Contract and all<br />
other agreements, Contracts, documents and writings relating to this Contract<br />
constitute private and commercial acts and not public or governmental acts.<br />
(14) Consents generally in respect <strong>of</strong> the enforcement <strong>of</strong> any judgement against it in any<br />
proceedings in any jurisdiction to the giving <strong>of</strong> any relief or the issue <strong>of</strong> any process<br />
in connection with such proceedings.<br />
(15) Provide support in terms <strong>of</strong> warranty, technical support, and maintenance for a<br />
minimum period <strong>of</strong> three years for s<strong>of</strong>tware (E-governance solution and other<br />
applications) from the date <strong>of</strong> Go Live. The BUYER may, at its discretion, opt to<br />
extend the warranty, technical support and maintenance for an additional period <strong>of</strong><br />
two years.<br />
(16) Even after the mandatory warranty period, the SI agrees to give a commitment<br />
obtained from OEMs that they shall give at least two years notice to the ASI prior to<br />
closing the production line (or the support for the application) so as to enable a “Life<br />
Time Buy” <strong>of</strong> all spares before closure <strong>of</strong> the said production line or the particular<br />
version <strong>of</strong> the s<strong>of</strong>tware. SI shall intimate to BUYER all New Versions and<br />
RFP Volume 3: Draft Legal Contract Page 19
Request for Proposal for establishing e-Governance Systems<br />
Modifications carried out on the application and changes introduced to the s<strong>of</strong>tware<br />
during the period <strong>of</strong> support as mentioned above.<br />
5.2. Representations and Warranties <strong>of</strong> the BUYER. The BUYER represents and warrants to SI<br />
that :-<br />
(1) It has full power and authority to execute, deliver and perform its obligations under this<br />
Contract.<br />
(2) It has taken all necessary action to authorize the execution, delivery and performance <strong>of</strong><br />
this Contract.<br />
5.3. Warranties on the Supply and Services.<br />
(1) SI warrants that the <strong>Project</strong> Assets supplied under this Contract conform to technical<br />
specifications prescribed in RFP and shall perform according to the said technical<br />
specifications.<br />
(2) SI warrants that the <strong>Project</strong> Assets are new, non-refurbished, unused and recently<br />
manufactured; the <strong>Project</strong> Assets are <strong>of</strong> the latest version, at the time <strong>of</strong> delivery to<br />
the BUYER. They shall not be nearing end <strong>of</strong> sale/ end <strong>of</strong> support; and shall be<br />
supported by SI and respective OEM along with service and spares support to ensure<br />
its efficient and effective operation for the entire Operative Period <strong>of</strong> Contract.<br />
(3) SI warrants that the <strong>Project</strong> Assets supplied under this Contract shall be <strong>of</strong> the highest<br />
grade and quality and consistent with the established and accepted standards for<br />
materials <strong>of</strong> this type. The <strong>Project</strong> Assets shall be in full conformity with the<br />
specifications and shall operate properly and safely. All recent design improvements in<br />
<strong>Project</strong> Assets, unless provided otherwise in the Contract shall also be made available.<br />
(4) SI warrants that the <strong>Project</strong> Assets shall be free from all encumbrances and defects /<br />
faults arising from design, material, manufacture or workmanship or from any act or<br />
omission <strong>of</strong> SI, that may present a snag/fault, under normal use <strong>of</strong> the same.<br />
(5) SI warrants for a period <strong>of</strong> three years mandatory support and two years <strong>of</strong> optional<br />
support for the configured and customized E-governance solution, from the date <strong>of</strong><br />
expiry <strong>of</strong> Post Go-Live support; that the <strong>Project</strong> Assets and/or services supplied under<br />
this Contract and each component used in the manufacture there<strong>of</strong> shall be free from<br />
all types <strong>of</strong> defects / failures.<br />
(6) If within the period <strong>of</strong> warranty, the <strong>Project</strong> Assets are reported by the BUYER to have<br />
failed to perform as per the specifications, SI shall either replace or rectify the same<br />
free <strong>of</strong> charge or accept damages as per Service Levels and terms <strong>of</strong> damages<br />
contained in Schedule III. Warranty <strong>of</strong> such <strong>Project</strong> Asset would be extended by such<br />
duration. Record <strong>of</strong> the down time would be maintained by user in log book. Spares<br />
required for warranty repairs shall be maintained at the <strong>Project</strong> Site and provided free<br />
<strong>of</strong> cost by SI. SI also undertakes to diagnose, test, adjust, calibrate and repair / replace<br />
RFP Volume 3: Draft Legal Contract Page 20
Request for Proposal for establishing e-Governance Systems<br />
the <strong>Project</strong> Assets damaged or malfunctioning due to accidents by neglect or misuse<br />
by the operator or damage due to transportation <strong>of</strong> the <strong>Project</strong> Assets during the<br />
warranty period, at no cost to ASI or the BUYER.<br />
(7) SI hereby warrants that the warranty and technical support shall be provided and it<br />
will ensure the implementation <strong>of</strong> the necessary upgrades and patches <strong>of</strong> the New<br />
Versions <strong>of</strong> the <strong>Project</strong> Assets (for a period <strong>of</strong> one year years from the date <strong>of</strong> expiry <strong>of</strong><br />
Post Go-Live support for the Equipment and s<strong>of</strong>tware).<br />
(8) SI hereby warrants providing Handholding support to ensure the necessary bug fixes,<br />
configuration changes, and enhancements to the <strong>Project</strong> Assets.<br />
(9) In case the complete delivery <strong>of</strong> <strong>Project</strong> Assets is delayed beyond the period stipulated<br />
in this Contract, then SI undertakes that the warranty period for such <strong>Project</strong> Assets<br />
shall be extended to that extent.<br />
(10) SI hereby warrants that necessary service and repair back up during the warranty<br />
period <strong>of</strong> the Equipment shall be provided and it will ensure that the performance,<br />
availability, and other metrics for application (including OS) is as per Service Levels<br />
described in Schedule III.<br />
5.4. Insurance. SI warrants and represents that it shall maintain adequate standard forms <strong>of</strong><br />
comprehensive insurance including liability insurance, system and facility insurance and any<br />
other insurance for the personnel, assets, Data, s<strong>of</strong>tware, etc and further agrees to provide to<br />
the BUYER on request copies <strong>of</strong> such policy <strong>of</strong> insurance and evidence that the premiums have<br />
been paid. SI also warrants and represents that it shall keep all their respective directors,<br />
partners, advisers, agents, representatives and or employees adequately insured in respect <strong>of</strong><br />
business travel in <strong>India</strong> and further agrees to provide to the BUYER on request copies <strong>of</strong> such<br />
policy <strong>of</strong> insurance and evidence that the premiums have been paid.<br />
5.5. Disclosure. In the event that any occurrence or circumstance comes to the attention <strong>of</strong> either<br />
Party that renders any <strong>of</strong> its aforesaid representations or warranties untrue or incorrect, such<br />
Party shall immediately notify the other Party <strong>of</strong> the same. Such notification shall not have the<br />
effect <strong>of</strong> remedying any breach <strong>of</strong> the representation or warranty that has been found to be<br />
untrue or incorrect nor shall it adversely affect or waive any obligation <strong>of</strong> either Party under<br />
this Contract.<br />
RFP Volume 3: Draft Legal Contract Page 21
Request for Proposal for establishing e-Governance Systems<br />
6.1. Statutory Obligations.<br />
7 Article 6: Obligations, Compliance<br />
(1) The Contract shall be governed by and interpreted in accordance with the laws <strong>of</strong> the<br />
Republic <strong>of</strong> <strong>India</strong>.<br />
(2) The Parties agree that the rights and obligations under this Contract are recognized<br />
and performed in conformity with laws and legal procedures established in the<br />
country and no right under this Contract becomes enforceable and no obligation<br />
requires performance, if the enforcement <strong>of</strong> such right or the performance <strong>of</strong> such<br />
obligation violates any such laws and legal procedures established.<br />
(3) SI represents and warrants to the BUYER that at the date here<strong>of</strong> the entering into this<br />
Contract or the performance <strong>of</strong> obligations under this Contract will not conflict with or<br />
result in a breach <strong>of</strong> any <strong>of</strong> the terms, conditions or provisions <strong>of</strong> or constitute a<br />
default or require any consent under, any instrument or arrangement to which SI is a<br />
party or violate any other Applicable Laws or any writ, order, injunction or judgment<br />
by which SI is bound and notwithstanding Article 6.1 (a) as far as SI is aware, no<br />
provision <strong>of</strong> this Contract derogates from the statutory obligations <strong>of</strong> SI.<br />
6.2. Compliance with Laws.<br />
(1) Each Party to this Contract accepts that its individual conduct shall (to the extent<br />
applicable to it) at all times comply with all applicable laws, rules and regulations. For<br />
the avoidance <strong>of</strong> doubt the obligations <strong>of</strong> the Parties to this Contract are subject to their<br />
respective compliance with all applicable laws and regulations.<br />
(2) Compliance with all applicable laws: SI agrees and undertakes to observe, adhere to,<br />
abide by, comply with and notify the BUYER about all laws in force or as are or as made<br />
applicable in future, pertaining to or applicable to them, their business, their employees<br />
or their obligations towards them and all purposes <strong>of</strong> this Contract and shall indemnify,<br />
keep indemnified, hold harmless, defend and protect the BUYER and its<br />
employees/<strong>of</strong>ficers/staff/ personnel/representatives/ agents from any failure or<br />
omission on its part to do so and against all claims or demands <strong>of</strong> liability and all<br />
consequences that may occur or arise for any default or failure on its part to conform or<br />
comply with the above and all other statutory obligations arising there-from.<br />
(3) Compliance in obtaining approvals/permissions/licenses: SI shall promptly and timely<br />
obtain all such consents, permissions, approvals, licenses, etc., as may be necessary or<br />
required for any <strong>of</strong> the purposes <strong>of</strong> this Contract or for the conduct <strong>of</strong> its own business<br />
under any applicable Law, Government regulation/guidelines and shall keep the same<br />
RFP Volume 3: Draft Legal Contract Page 22
Request for Proposal for establishing e-Governance Systems<br />
valid and in force during the term <strong>of</strong> this Contract, and in the event <strong>of</strong> any failure or<br />
omission to do so, shall indemnify, keep indemnified, hold harmless, defend, protect and<br />
fully compensate the BUYER and its employees/ <strong>of</strong>ficers/ staff/ personnel/<br />
representatives/agents from and against all claims or demands <strong>of</strong> liability and all<br />
consequences that may occur or arise for any default or failure on its part to conform or<br />
comply with the above and all other statutory obligations arising there-from.<br />
RFP Volume 3: Draft Legal Contract Page 23
Request for Proposal for establishing e-Governance Systems<br />
8 Article 7: Force Majeure Events And Events Of Default<br />
7.1. Force Majeure Events.<br />
(1) The failure or delay <strong>of</strong> a Party (“Affected Party”) to perform any obligation under this<br />
Contract solely by reason <strong>of</strong> “Force Majeure” event shall not be deemed to be a breach<br />
<strong>of</strong> this Contract, provided, however, that the Affected Party so prevented from<br />
complying shall continue to take all actions within its power to comply as fully as<br />
possible herewith and to remove or remedy such cause with all reasonable dispatch.<br />
‘Force Majeure’ events are only those events which prevents or impedes the due<br />
performance <strong>of</strong> the Affected Party and which such Affected Party while observing due<br />
diligence is unable to avoid or overcome through its individual concerted effort. For the<br />
purpose <strong>of</strong> this Contract, Force Majeure event shall mean but not limited to acts <strong>of</strong> God<br />
not confined to the premises <strong>of</strong> the Affected Party, flood, drought, lightning or fire,<br />
earthquakes, strike, lock-outs beyond its control, labour disturbance not caused at the<br />
instance <strong>of</strong> the Affected Party, acts <strong>of</strong> government or other competent authority,<br />
“Change in Law”, war, terrorist activities, military operations, riots, epidemics, civil<br />
commotions etc. Notwithstanding anything contained herein, no failure, delay or other<br />
default <strong>of</strong> any contractor or sub-contractor to either Party shall entitle such Party to<br />
claim Force Majeure under this provision.<br />
(2) The Party seeking to rely on Force Majeure shall promptly, within 2 days, notify the<br />
other Party (“Non Affected Party”) <strong>of</strong> the occurrence <strong>of</strong> a Force Majeure event as a<br />
condition precedent to the availability <strong>of</strong> this defence with particulars detail in writing to<br />
the Non Affected Party and shall demonstrate that it has and is taking all reasonable<br />
measures to mitigate the events <strong>of</strong> Force Majeure. The Non Affected Party shall grant<br />
such postponement <strong>of</strong> the date <strong>of</strong> completion as may in all the circumstances be<br />
considered reasonable.<br />
(3) If any delay in the Affected Party’s performance caused by Force Majeure event exceeds<br />
ninety (90) days, the Non Affected Party may at its option terminate this Contract<br />
immediately.<br />
(4) Notwithstanding anything contained herein, the failure on the part <strong>of</strong> SI under the<br />
Contract to implement any disaster contingency planning and back-up and other data<br />
safeguards in accordance with the terms <strong>of</strong> the Contract against natural disaster, fire,<br />
sabotage or other similar occurrence shall not be an event <strong>of</strong> Force Majeure.<br />
(5) Notwithstanding the rights <strong>of</strong> SI during an event <strong>of</strong> Force Majeure, if it is essential for<br />
the BUYER to run its operations smoothly and uninterrupted, like in the case <strong>of</strong> war or<br />
external aggression, if the <strong>Project</strong> is under O&M Stage, the BUYER has the right to reject<br />
the notice <strong>of</strong> SI for a Force Majeure and request SI to provide the services required by<br />
RFP Volume 3: Draft Legal Contract Page 24
Request for Proposal for establishing e-Governance Systems<br />
the BUYER. However under these circumstances, it will be the responsibility <strong>of</strong> the<br />
BUYER to provide security to SI personnel on duty and be responsible and accountable<br />
for all the eventualities as per the Applicable Laws.<br />
(6) The expression “Change in Law” means any <strong>of</strong> the following events which have a<br />
Material Adverse Effect:<br />
(i) Adoption, promulgation, Modification, reinterpretation or repeal after the date <strong>of</strong><br />
this Contract by any Government Authority <strong>of</strong> any statute, rule, ordinance,<br />
regulation or order, treaty, convention, directive, guideline, policy having force <strong>of</strong><br />
law; or<br />
(ii) The imposition by any Government Authority <strong>of</strong> any material condition (other<br />
than a condition which has been imposed as a consequence <strong>of</strong> a violation by SI <strong>of</strong><br />
any Applicable Permit) in connection with the issuance, renewal or Modification <strong>of</strong><br />
any applicable permits after the date <strong>of</strong> this Contract which renders the<br />
performance by SI <strong>of</strong> any <strong>of</strong> the terms <strong>of</strong> this Contract impossible or unviable; or<br />
(iii) Any applicable permit previously granted, ceasing to remain in full force and effect<br />
for reasons other than breach/violation by or the negligence <strong>of</strong> SI or if granted for<br />
a limited period, being renewed on terms different from those previously<br />
stipulated.<br />
(iv) Provided any (i) imposition <strong>of</strong> new taxes, duties, cess and the like and/or the<br />
increase in taxes, duties, cess and the like effected from time to time by any<br />
Government Authority, and/or (ii) imposition <strong>of</strong> standards and condition <strong>of</strong><br />
operations, maintenance and safety arising out <strong>of</strong> a new or revised Environmental<br />
Law; and/or (iii) any rules or regulations stipulated by regulatory authority having<br />
jurisdiction over the <strong>Project</strong> in respect <strong>of</strong> the standards <strong>of</strong> service, testing,<br />
acceptance norms, shall not constitute a Change in Law.<br />
7.2. SI Event <strong>of</strong> Default. “SI Event <strong>of</strong> Default” means any <strong>of</strong> the following events unless<br />
such an event has occurred as a consequence <strong>of</strong> a Force Majeure Event :-<br />
(1) SI’s failure to perform or discharge any <strong>of</strong> its obligations in accordance with the<br />
provisions <strong>of</strong> this Contract.<br />
(2) The activities at any <strong>Project</strong> Site is abandoned by SI for a more than 7 (Seven) Days<br />
during the <strong>Project</strong>.<br />
(3) A delay <strong>of</strong> more than 180 (one hundred and eighty) days from any Milestone date in<br />
achieving any <strong>of</strong> the performance obligations set forth for the relevant Milestone<br />
Date.<br />
(4) Change in the structure <strong>of</strong> the project team, the “Key Personnel” by SI without<br />
written approval <strong>of</strong> the BUYER for the changes.<br />
RFP Volume 3: Draft Legal Contract Page 25
Request for Proposal for establishing e-Governance Systems<br />
(5) Inability to staff the <strong>Project</strong> with competent team in case any <strong>of</strong> the team members<br />
leave the <strong>Project</strong> either due to voluntary severance or disciplinary actions against<br />
them.<br />
(6) SI’s failure to perform or discharge any <strong>of</strong> its obligations under any other project<br />
contract, which has or is likely to affect the <strong>Project</strong>/ facilities and services related to<br />
the <strong>Project</strong>, materially.<br />
(7) Any representation made or warranties given by SI under this Contract is found to<br />
be false or misleading.<br />
(8) If SI has given false information in qualifying for the <strong>Project</strong> or getting selected or<br />
any information provided by the SI during the procurement process is found to be<br />
false.<br />
(9) Breach <strong>of</strong> any clause or part there<strong>of</strong> <strong>of</strong> the “Integrity Pact” signed by the Parties<br />
pursuant to the RFP.<br />
(10) Appointment <strong>of</strong> a provisional liquidator, administrator, trustee or receiver <strong>of</strong> the<br />
whole or substantially whole <strong>of</strong> the undertaking <strong>of</strong> SI by a court <strong>of</strong> competent<br />
jurisdiction in proceedings for winding up or any other legal proceedings.<br />
(11) Levy <strong>of</strong> an execution or restraint on SI’s assets which has or is likely to have Material<br />
Adverse Effect and/or affect the <strong>Project</strong>/ facilities and services related to the<br />
<strong>Project</strong>, materially and such execution or destraint remaining in force for a period<br />
exceeding 90 (ninety) Days.<br />
(12) The Performance Bank Guaranteeand any other securities required to be maintained<br />
under this Contract is not maintained in terms <strong>of</strong> the provisions here<strong>of</strong>.<br />
(13) SI abandons or expresses its intention to revoke/terminate this Contract without<br />
being entitled to do so as is expressly provided in the Contract.<br />
(14) Change in constitution/organization <strong>of</strong> SI which violates the short listing criteria used<br />
in EoI process.<br />
(15) Amalgamation <strong>of</strong> SI with any other company or reconstruction or transfer <strong>of</strong> the<br />
whole or part <strong>of</strong> the <strong>Project</strong> or the revenue earning parts <strong>of</strong> the <strong>Project</strong> [other than<br />
transfer <strong>of</strong> assets in the ordinary course <strong>of</strong> business] in contravention with the<br />
provisions <strong>of</strong> Article 2 here<strong>of</strong>; and<br />
(16) SI engages or knowingly allows any <strong>of</strong> its employees, agents, Contractor or<br />
representative to engage in any activity prohibited under this Contract and/or by<br />
law or which constitutes a breach <strong>of</strong> the Contract or breach <strong>of</strong> or an <strong>of</strong>fence under<br />
any law, in the course <strong>of</strong> any activity undertaken pursuant to this Contract.<br />
(17) SI suffers a change <strong>of</strong> control. For the purpose <strong>of</strong> this provision the change <strong>of</strong> control<br />
<strong>of</strong> SI would happen if:<br />
RFP Volume 3: Draft Legal Contract Page 26
Request for Proposal for establishing e-Governance Systems<br />
(i) the promoter group <strong>of</strong> SI ceases to control the board <strong>of</strong> directors <strong>of</strong> SI; or<br />
(ii) Any reduction in the cumulative shareholding <strong>of</strong> the promoter group <strong>of</strong> SI falls<br />
below 26% <strong>of</strong> the total paid up equity share capital <strong>of</strong> SI.<br />
Note: For this provision “Promoter group” shall mean <br />
7.3. The BUYER Events <strong>of</strong> Default.<br />
7.4. Parties Rights.<br />
(1) The BUYER’s failure to perform or discharge its obligations in accordance with the<br />
provisions <strong>of</strong> this Contract unless such failure has occurred as a consequence <strong>of</strong> any<br />
SI Event <strong>of</strong> Default or a Force Majeure Event.<br />
(2) Any representation made or warranties given by the BUYER under this Contract is<br />
found to be false or misleading<br />
(1) Upon the occurrence <strong>of</strong> SI’s Event <strong>of</strong> Default, the BUYER shall without prejudice to any<br />
other rights and remedies available to it under this Contract, be entitled to terminate<br />
this Contract.<br />
(2) Upon the occurrence <strong>of</strong> the BUYER Event <strong>of</strong> Default, SI shall without prejudice to any<br />
other rights and remedies available to it under this Contract, be entitled to terminate<br />
this Contract.<br />
(3) Consultation Notice. The non defaulting Party shall issue to the defaulting Party a notice<br />
in writing specifying in reasonable detail the underlying Event <strong>of</strong> Default(s) and<br />
proposing consultation amongst the Parties and the OEMs (if required) to consider<br />
possible measures <strong>of</strong> curing or otherwise dealing with the underlying Event <strong>of</strong> Default<br />
(“Consultation Notice”).<br />
RFP Volume 3: Draft Legal Contract Page 27
Request for Proposal for establishing e-Governance Systems<br />
7.5. Remedial Process.<br />
8.1 Following the issue <strong>of</strong> Consultation Notice by the non defaulting Party, within a period<br />
not exceeding 90 (ninety) Days or such extended period as the Parties may agree in<br />
writing (“Remedial Period”) the Parties shall, in consultation with the OEMs (if<br />
applicable) whose contracts are in vogue, endeavor to arrive at an agreement as to<br />
the manner <strong>of</strong> rectifying or remedying the underlying Event <strong>of</strong> Default.<br />
7.6. Obligations during Remedial Period.Except expressly provided otherwise in the<br />
Contract, during the Remedial Period, the Parties shall continue to perform their<br />
respective obligations under this Contract which can be performed, failing which the<br />
Party in breach shall compensate the other Party for any loss or damage occasioned<br />
or suffered on account <strong>of</strong> the underlying failure/breach.<br />
7.7. Revocation <strong>of</strong> Consultation Notice.If during the Remedial Period the underlying<br />
Event <strong>of</strong> Default is cured or waived or the Parties and the OEMs agree upon any <strong>of</strong><br />
the measures set out in this Article, the Consultation Notice shall be withdrawn in<br />
writing by the Party who has issued the same.<br />
7.8. Termination due to Events <strong>of</strong> Default.If before the expiry <strong>of</strong> the Remedial Period, the<br />
underlying Event <strong>of</strong> Default is neither cured nor waived the Party who has issued the<br />
Consultation Notice shall have the right to terminate this Contract, in which event,<br />
inter alia, the provisions <strong>of</strong> Article 9 and Schedules V and VIshall, to the extent<br />
expressly made applicable, apply<br />
7.9. Remedies Cumulative. The exercise <strong>of</strong> right by either Party to terminate this<br />
Contract, as provided herein, shall not preclude, such Party from availing any other<br />
rights or remedies that may be available to it under law or Contract. All remedies<br />
available to the Parties shall be cumulative and the exercise or failure there<strong>of</strong> <strong>of</strong> one<br />
or more remedies by any Party shall not limit or preclude the exercise <strong>of</strong> or constitute<br />
a waiver <strong>of</strong> any other remedies by such Party.<br />
RFP Volume 3: Draft Legal Contract Page 28
Request for Proposal for establishing e-Governance Systems<br />
8.1. Amicable Settlement.<br />
9 Article 8: Dispute Resolution<br />
(1) If any dispute or difference or claims <strong>of</strong> any kind arise between the BUYER and SI in<br />
connection with construction, interpretation or application <strong>of</strong> any terms and conditions<br />
or any matter or thing in any way connected with or in connection with or arising out <strong>of</strong><br />
this Contract, or the rights, duties or liabilities <strong>of</strong> any Party under this Contract, whether<br />
before or after the termination <strong>of</strong> this Contract, then the Parties shall meet together<br />
promptly, at the request <strong>of</strong> any Party, in an effort to resolve such dispute, difference or<br />
claim by discussion between them.<br />
(2) Any dispute arising out <strong>of</strong> or in connection with this Contract shall in the first instance be<br />
dealt with in accordance with the escalation mechanism as set out in the Schedule V.<br />
(3) Assistance <strong>of</strong> Experts. The Parties may, in appropriate cases agree to refer the matter to<br />
an Expert/s appointed by them with mutual consent. The cost <strong>of</strong> obtaining the service <strong>of</strong><br />
the Expert shall be shared equally.<br />
8.2. Arbitration. Any dispute or difference whatsoever arising between the parties to this<br />
Contract out <strong>of</strong> or relating to the construction, meaning, scope, operation or effect <strong>of</strong><br />
this Contract or the validity <strong>of</strong> the breach there<strong>of</strong>, which can not be resolved through<br />
the application <strong>of</strong> the provisions <strong>of</strong> Article 8.1 above, shall be taken to arbitration.<br />
8.3. Arbitrators.<br />
(1) Failing amicable settlement and/or settlement with the assistance <strong>of</strong> Expert appointed<br />
by the Parties by mutual consent, the dispute or differences or claims as the case may<br />
be, shall be finally settled by binding arbitration under the Arbitration and Conciliation<br />
Act, 1996.<br />
(2) The arbitration shall be by a panel <strong>of</strong> three Arbitrators, one to be appointed by each<br />
Party and the third, who shall act as presiding arbitrator, to be appointed by the two<br />
arbitrators appointed by the Parties.<br />
(3) The arbitration shall be invoked by one party issuing to the other a notice in writing<br />
invoking the arbitration and appointing an Arbitrator. Upon receipt <strong>of</strong> the notice, the<br />
other Party shall appoint the second Arbitrator. The two Arbitrators so appointed shall<br />
appoint the third Arbitrator who shall act as the ‘Presiding Arbitrator’. In the event <strong>of</strong> a<br />
vacancy caused in the <strong>of</strong>fice <strong>of</strong> the arbitrators, the Party which nominated such<br />
arbitrator shall be entitled to nominate another in his place and the arbitration<br />
proceedings shall continue from the stage they were left by the retiring arbitrator.<br />
(4) In the event <strong>of</strong> one <strong>of</strong> the Parties failing to appoint an arbitrator within thirty (30) days<br />
from the receipt <strong>of</strong> notice or if any <strong>of</strong> the Parties does not nominate another arbitrator<br />
RFP Volume 3: Draft Legal Contract Page 29
Request for Proposal for establishing e-Governance Systems<br />
within thirty (30) days <strong>of</strong> the place <strong>of</strong> arbitrator falling vacant, the appointment shall be<br />
made upon request <strong>of</strong> the other Party by the Chief Justice <strong>of</strong> the Andhra Pradesh High<br />
Court.<br />
(5) Both the Parties will make attempts to appoint arbitrators with background in<br />
Information Technology related activities, Information Technology related acts,<br />
understanding <strong>of</strong> the processes and activities <strong>of</strong> defence PSU organizations and an<br />
understanding <strong>of</strong> the s<strong>of</strong>tware applications.<br />
8.4. Place <strong>of</strong> Arbitration. Place <strong>of</strong> arbitration will be New Delhi, <strong>India</strong>.<br />
8.5. Language for Arbitration. The request for arbitration, answer to the request, terms<br />
<strong>of</strong> reference, any written submissions, any orders and rulings shall be in English and,<br />
if oral hearings take place, English shall be the language to be used in the hearings.<br />
8.6. Procedure. The procedure to be followed within the arbitration, including<br />
appointment <strong>of</strong> arbitrator/arbitral tribunal, the rules <strong>of</strong> evidence which are to apply<br />
shall be in accordance with the Arbitration and Conciliation Act, 1996.<br />
8.7. Enforcement <strong>of</strong> Award. Any decision or award resulting from arbitration shall<br />
be final and binding upon the Parties. The Parties hereto agree that the arbitral<br />
award may be enforced against the Parties to the arbitration proceeding or their<br />
assets wherever they may be found and that a judgment upon the arbitral award<br />
may be entered in any court having jurisdiction there<strong>of</strong>.<br />
8.8. Fees and Expenses.<br />
(1) The fees and expenses <strong>of</strong> the arbitrators and all other expenses <strong>of</strong> the arbitration shall<br />
be initially borne and paid equally by respective Parties subject to determination by the<br />
arbitrators.<br />
(2) The arbitrators may provide in the arbitral award for the reimbursement to the<br />
successful party <strong>of</strong> its costs and expenses in bringing or defending the arbitration claim,<br />
including legal fees and expenses incurred by the Party.<br />
8.9. Performance during Arbitration. Pending the submission <strong>of</strong> and/or decision on a<br />
dispute, difference or claim or until the arbitral award is made, the Parties shall<br />
continue to perform all <strong>of</strong> their obligations under this Contract without prejudice to a<br />
final adjustment in accordance with such award.<br />
RFP Volume 3: Draft Legal Contract Page 30
Request for Proposal for establishing e-Governance Systems<br />
10 Article 9: Termination And Transfer<br />
9.1. Termination Procedure. The Party entitled to terminate this Contract either on account<br />
<strong>of</strong> a Force Majeure Event or on account <strong>of</strong> an Event <strong>of</strong> Default shall do so by issue <strong>of</strong> a<br />
notice in writing as per Schedule V to the other Party. The Termination Notice shall be<br />
<strong>of</strong> not more than 30(thirty) days, (“Termination Period”) and at the expiry <strong>of</strong> the<br />
Termination Period, this Contract shall stand terminated without any further notice.<br />
9.2. Obligations during Termination Period. During Termination Period, SI shall, subject<br />
where applicable to the provisions <strong>of</strong> this Article, continue to perform such <strong>of</strong> their<br />
respective obligations under this Contract which are capable <strong>of</strong> being performed with<br />
the object, as far as possible, <strong>of</strong> ensuring continued availability <strong>of</strong> the <strong>Project</strong> team,<br />
<strong>Project</strong> Assets and services to the BUYER, failing which the SI shall compensate the<br />
BUYER for any loss or damage occasioned or suffered on account <strong>of</strong> the underlying<br />
failure/breach.<br />
9.3. Consequence <strong>of</strong> Termination.<br />
(1) The liability <strong>of</strong> BUYER in case <strong>of</strong> termination <strong>of</strong> the Contract initiated on account <strong>of</strong><br />
BUYER event <strong>of</strong> default or Force Majeure, shall be limited to full payments for<br />
Equipment, Systems, Licensed S<strong>of</strong>tware, up to the milestone immediately preceding the<br />
milestone SI would be working on at the time <strong>of</strong> termination.<br />
(2) In case <strong>of</strong> termination due to SI event <strong>of</strong> default, SI shall pay damages amounting to<br />
encashment <strong>of</strong> all bank guarantees by BUYER and all outstanding payments. Any<br />
additional expenditure arising from subsequent negotiations <strong>of</strong> the Contract with any<br />
other agency will also be SI’s liability. Final payment up to the last completed milestone<br />
will be after handing over the complete documentation and meeting all requirements as<br />
per the Contract to the satisfaction <strong>of</strong> BUYER.<br />
(3) In the event <strong>of</strong> a termination effected in pursuance <strong>of</strong> this Article, or expiry <strong>of</strong> this<br />
Contract, the relevant provisions <strong>of</strong> the Exit Management (Schedule VI) shall apply.<br />
9.4. Risk. Until transfer in accordance with the Contract, during the <strong>Project</strong>, the <strong>Project</strong><br />
Assets and OEM contracts shall remain at the sole risk <strong>of</strong> SI except for any loss or<br />
damage caused to or suffered by SI due to any act or omission or negligence on the<br />
part <strong>of</strong> the BUYER under this Contract.<br />
RFP Volume 3: Draft Legal Contract Page 31
Request for Proposal for establishing e-Governance Systems<br />
10.1. Undertaking by SI.<br />
11 Article 10: Use Of Undue Influence<br />
(1) SI undertakes that he has not given, <strong>of</strong>fered or promised to give, directly or indirectly<br />
any gift, consideration, reward, commission, fees brokerage or inducement to any<br />
person in service <strong>of</strong> the BUYER or otherwise in procuring the Contracts or forbearing to<br />
do or for having done or forborne to do any act in relation to the obtaining or execution<br />
<strong>of</strong> the Contract or any other agreement with the Government for showing or forbearing<br />
to show favour or disfavour to any person in relation to the Contract or any other<br />
agreement with the Government. Any breach <strong>of</strong> the aforesaid undertaking by SI or any<br />
one employed by it or acting on its behalf (whether with or without the knowledge <strong>of</strong><br />
SI) or the commission <strong>of</strong> any <strong>of</strong>fers by SI or anyone employed by it or acting on its<br />
behalf, as defined in Chapter IX <strong>of</strong> the <strong>India</strong>n Penal Code, 1860 or the Prevention <strong>of</strong><br />
Corruption Act, 1988 or any other acts/legislations enacted for the prevention <strong>of</strong><br />
corruption shall entitle the BUYER to forthwith terminate the Contract and all or any<br />
other contracts with SI and recover from SI the amount <strong>of</strong> any loss arising from such<br />
cancellation. The decision <strong>of</strong> the BUYER or his nominee to the effect that a breach <strong>of</strong> the<br />
undertaking had been committed shall be final and binding on SI.<br />
(2) Giving or <strong>of</strong>fering <strong>of</strong> any gift, bribe or inducement or any attempt at any such act on<br />
behalf <strong>of</strong> SI towards any <strong>of</strong>ficer/employee <strong>of</strong> the BUYER or to any other person in a<br />
position to influence any <strong>of</strong>ficer/employee <strong>of</strong> the BUYER for showing any favour in<br />
relation to this or any other Contract, shall render SI to such liability/ penalty as the<br />
BUYER may deem proper, including but not limited to termination <strong>of</strong> the Contract,<br />
imposition <strong>of</strong> penal damages, forfeiture <strong>of</strong> the Performance Bank Guarantee and seek<br />
immediate refund <strong>of</strong> the amounts paid by the BUYER.<br />
RFP Volume 3: Draft Legal Contract Page 32
Request for Proposal for establishing e-Governance Systems<br />
12 Article 11: Agents / Agency Commission<br />
11.1. Undertaking by SI. SI confirms and declares to the BUYER that it has not engaged<br />
any individual or firm, whether <strong>India</strong>n or foreign whatsoever, to intercede, facilitate<br />
or in any way to recommend to the Government <strong>of</strong> <strong>India</strong> or any <strong>of</strong> its functionaries,<br />
whether <strong>of</strong>ficially or un<strong>of</strong>ficially, to the award <strong>of</strong> the Contract to SI; nor has any<br />
amount been paid, promised or intended to be paid to any such individual or firm in<br />
respect <strong>of</strong> any such intercession, facilitation or recommendation. SI agrees that if it is<br />
established at any time to the satisfaction <strong>of</strong> the BUYER that the present declaration<br />
is in any way incorrect or if at a later stage it is discovered by the Buyer that SI has<br />
engaged any such individual/firm, and paid or intended to pay any amount, gift,<br />
reward, fees, commission or consideration to such person, party, firm or institution,<br />
whether before or after signing <strong>of</strong> this Contract, SI will be liable to refund that<br />
amount to the BUYER. SI will also be debarred from entering into any contract with<br />
the Government <strong>of</strong> <strong>India</strong> for a minimum period <strong>of</strong> five years. The BUYER will also<br />
have a right to consider cancellation <strong>of</strong> the Contract either wholly or in part, without<br />
any entitlement or compensation to SI who shall in such event be liable to refund all<br />
payments made by the BUYER in terms <strong>of</strong> the Contract along with interest at the rate<br />
<strong>of</strong> 2% per annum above LIBOR rate. The BUYER will also have the right to recover any<br />
such amount from any contracts concluded earlier with the Government <strong>of</strong> <strong>India</strong>.<br />
RFP Volume 3: Draft Legal Contract Page 33
Request for Proposal for establishing e-Governance Systems<br />
13 Article 12: Non Disclosure Of Contract Documents<br />
12.1. Undertaking by SI. Except as provided under the Contract, SI shall not disclose and<br />
cause other parties (connected with the <strong>Project</strong>, who have been disclosed the<br />
information on Contract as per the terms <strong>of</strong> the Contract) not to disclose the Contract<br />
or any provision, specification, plan, design, pattern, sample or information there<strong>of</strong><br />
to any third party, without prior written consent <strong>of</strong> the BUYER.<br />
RFP Volume 3: Draft Legal Contract Page 34
Request for Proposal for establishing e-Governance Systems<br />
14 Article 13: Assets And Third Party Contracts<br />
13.1. The Physical Assets <strong>of</strong> SI Prior to Go Live.<br />
(1) SI agrees to install and commission a development environment consisting <strong>of</strong> the<br />
hardware, Networks and s<strong>of</strong>tware at a mutually agreed <strong>Project</strong> Development Assets, big<br />
enough to organize the entire <strong>Project</strong> team pursuant to this Contract.<br />
(2) SI Assets for Own Use will be owned, operated and managed by SI.<br />
(3) SI is free to bring in and move out <strong>of</strong> ASI all SI Assets for Own Use by following the<br />
procedures listed below :-<br />
(i) The details <strong>of</strong> equipments required to be brought in/ taken out <strong>of</strong> the ASI Area,<br />
will be approved by an <strong>of</strong>ficial designated by the BUYER for the purpose.<br />
(ii) When the equipments have to be brought in to the ASI Area, a requisite<br />
permission will be sought and the equipments would move in on an approval slip<br />
signed by designated <strong>of</strong>ficial.<br />
(iii) When the equipments have to be taken out <strong>of</strong> the ASI Area, a gate pass will be<br />
prepared and signed by the SI delegated authority. A copy <strong>of</strong> signed gate pass will<br />
be deposited at the main gate.<br />
(iv) SI must adhere to the security regulations <strong>of</strong> the ASI in vogue.<br />
(4) SI will keep a register <strong>of</strong> all the Equipments brought into the ASI Area and inform BUYER<br />
<strong>of</strong> this movement.<br />
(5) It is the responsibility <strong>of</strong> SI to ensure the safety, security and upkeeping <strong>of</strong> the physical<br />
assets brought into the ASI Area.<br />
(6) The BUYER shall not be liable for the safety, security and upkeep <strong>of</strong> any <strong>of</strong> the assets <strong>of</strong><br />
SI.<br />
13.2. The <strong>Project</strong> Assets.<br />
(1) The physical/tangible/intangible assets, forming part <strong>of</strong> the “<strong>Project</strong> Assets”, shall be<br />
brought into ASI area by SI for the purpose <strong>of</strong> the <strong>Project</strong> and transferred to the BUYER,<br />
pursuant to this Contract.<br />
(2) The list <strong>of</strong> <strong>Project</strong> Assets is given in Schedule VII.<br />
(3) SI will keep a register <strong>of</strong> all the assets <strong>of</strong> the <strong>Project</strong> bought into the project site, with all<br />
the documents indicating the movement and ownership. This register will be<br />
countersigned by the BUYER representative<br />
(4) It is the responsibility <strong>of</strong> SI to ensure the safety <strong>of</strong> the <strong>Project</strong> Assets and insure these<br />
assets till transfer <strong>of</strong> ownership.<br />
RFP Volume 3: Draft Legal Contract Page 35
Request for Proposal for establishing e-Governance Systems<br />
(5) The ownership <strong>of</strong> all the <strong>Project</strong> Assets will be transferred to BUYER or its nominee, in<br />
the event <strong>of</strong> Go-Live coming into effect. Further in the event <strong>of</strong> termination <strong>of</strong> the<br />
Contract prior to Go-Live, the ownership <strong>of</strong> only such <strong>Project</strong> Assets shall be transferred<br />
to the BUYER or its nominee as the BUYER in its sole discretion may determine. The<br />
relevant provisions <strong>of</strong> Schedule VI would apply to any transfer <strong>of</strong> the <strong>Project</strong> Assets to<br />
the BUYER, pursuant to this Article.<br />
13.3. Transfer <strong>of</strong> <strong>Project</strong> Assets.<br />
(1) All the <strong>Project</strong> Assets shall be transferred to the BUYER at the end <strong>of</strong> the contract t or<br />
termination <strong>of</strong> the Contract prior to closing <strong>of</strong> the contract, without any liabilities.<br />
(2) The transfer <strong>of</strong> these assets means the BUYER will have the complete ownership <strong>of</strong><br />
these assets and will be responsible for safety <strong>of</strong> these assets and authority for usage.<br />
(3) However, SI will be responsible for maintaining <strong>Project</strong> Assets after “Go Live”, as per the<br />
warranty clauses and will be fully accountable for the warranty clauses.<br />
13.4. ASI Supplied Equipments.<br />
(1) ASI Supplied Equipments includes the <strong>of</strong>fice space, the physical assets associated with<br />
the <strong>of</strong>fice, power supply, power backup, client computing environment, belonging to<br />
BUYER and earmarked by BUYER for the purpose <strong>of</strong> the <strong>Project</strong> and used by SI for the<br />
<strong>Project</strong> are treated as the ASI assets for the <strong>Project</strong>.<br />
(2) The details <strong>of</strong> the assets earmarked by the BUYER for the purpose <strong>of</strong> the <strong>Project</strong> and<br />
used by SI shall be listed in a register duly signed by the representatives <strong>of</strong> SI and BUYER.<br />
(3) The ownership <strong>of</strong> ASI Supplied Equipmentslies with BUYER.<br />
(4) In normal circumstances the BUYER will not charge SI for using the ASI Supplied<br />
Equipments.<br />
(5) SI is responsible for ensuring that the ASI Supplied Equipments are used for the purpose<br />
<strong>of</strong> the <strong>Project</strong> only.<br />
(6) If SI is found to be using the ASI Supplied Equipmentsfor any other activity other than<br />
directly or indirectly related to the <strong>Project</strong>, the BUYER has the rights to initiate<br />
appropriate proceedings and claim reliefs (including damages) against SI for the misuse<br />
<strong>of</strong> the ASI Supplied Equipments.<br />
(7) The ASI Supplied Equipments shall not be transferred or moved by SI either within or<br />
outside the premises <strong>of</strong> ASI.<br />
13.5. Third Party Contracts.<br />
(1) The contracts executed by SI to procure any <strong>of</strong> the services or <strong>Project</strong> Assets to be used<br />
by SI in the <strong>Project</strong>, including but not limited to development tools, testing facilities,<br />
outsourcing contracts during the <strong>Project</strong> are to be treated as third party contracts.<br />
RFP Volume 3: Draft Legal Contract Page 36
Request for Proposal for establishing e-Governance Systems<br />
(2) The third party contracts are owned by SI and the liability for these contracts lies solely<br />
with SI.<br />
(3) The agreements with the OEMs for supply <strong>of</strong> goods and service including but not limited<br />
to hardware, Network components, E-governance solution applications & other<br />
s<strong>of</strong>tware applications, service contracts for warranty support, specialized services for<br />
audit/testing etc. will be assigned to the BUYER or its nominees and will indicate ASI<br />
units / echelons as “End Users” as per the Contract.<br />
(4) List <strong>of</strong> goods and services to be supplied by the OEM subject to Article 13.6 (a) is<br />
appended at Schedule VII.<br />
(5) SI will share these contracts and licenses in entirety with BUYER.<br />
(6) The BUYER will have the right to overrule any restrictive clauses or clauses limiting the<br />
ownership <strong>of</strong> these contracts.<br />
(7) In the event <strong>of</strong> termination <strong>of</strong> the Contract, SI shall transfer/assign or cause to be<br />
transferred/assigned to the BUYER or its nominee such third party contracts which are<br />
valid and subsisting and which the BUYER has chosen to take over at its sole discretion<br />
as per Schedule VI here<strong>of</strong>.<br />
RFP Volume 3: Draft Legal Contract Page 37
Request for Proposal for establishing e-Governance Systems<br />
14.1. Intellectual Property.<br />
15 Article 14: Intellectual Property<br />
(1) Pre-Existing Works The copyright and other intellectual property rights in any materials<br />
ors<strong>of</strong>tware (whether written or machine-readable) created by or licensed to SI priorto<br />
this Contract or outside this engagement and any subsequent Modifications to the same<br />
(“Pre-Existing Works”) will remain vested in SI or a third party. To the extent that pre-<br />
existingworks are embedded in any deliverable materials, the BUYER will have a license<br />
to use them in accordancewith the provisions below.<br />
(2) Other Deliverable Materials TheBUYER will own the copyright in all deliverable<br />
materials created under this Contract by SI.<br />
(3) SI agrees that ownership <strong>of</strong> all Intellectual Property Rights for any functional and<br />
technical process <strong>of</strong> ASI or information or materials or ASI Supplied Equipment provided<br />
to SI by the BUYER shall remain vested in the BUYER.<br />
(4) SI agrees that the BUYER shall own all Intellectual Property Rights in all <strong>Project</strong> Assets<br />
produced exclusively for the BUYER by SI pursuant to this Contract, including<br />
improvements that are developed by SI for the BUYER. SI shall execute necessary<br />
documents and instruments to perfect the ownership <strong>of</strong> ASI in respect <strong>of</strong> the aforesaid<br />
materials.<br />
(5) Notwithstanding any other provision <strong>of</strong> this Contract, SI will not be prevented or<br />
restricted by this Contract from using any technique, idea, concepts or know-how<br />
relatingto SI’s business activities. Nothing contained in this Contract shall restrict either<br />
Party from the use <strong>of</strong> any ideas, concepts, know-how, or techniques relating to data<br />
processing or Network management, which either Party, individually orjointly, develops<br />
or discloses under this Contract, except to the extent such use infringes any <strong>of</strong> either<br />
Party’s patent rights or copyrights. However, except for the licenses expressly granted<br />
by an agreement between the Parties to this Contract, neither this Contract nor any<br />
disclosure made hereunder grants any license to either Party under any patents or<br />
copyrights <strong>of</strong> the other Party.<br />
14.2. Infringement <strong>of</strong> Intellectual Property Rights:-<br />
(1) SI confirms that there shall be no infringement <strong>of</strong> any patent or intellectual & industrial<br />
property rights as per the applicable laws <strong>of</strong> relevant jurisdictions, having requisite<br />
competence, in respect <strong>of</strong> the <strong>Project</strong> Assets or any part there<strong>of</strong>, supplied under this<br />
Contract. SI shall indemnify the BUYER against all cost/claims/legal claims/liabilities<br />
arising from third party claim at any time on account <strong>of</strong> the infringement or<br />
unauthorised use <strong>of</strong> patent or intellectual & industrial property rights <strong>of</strong> any such<br />
RFP Volume 3: Draft Legal Contract Page 38
Request for Proposal for establishing e-Governance Systems<br />
parties, whether such claims arise in respect <strong>of</strong> manufacture or use. Without prejudice<br />
to the aforesaid indemnity, SI shall be responsible for the completion <strong>of</strong> the supplies<br />
including spares and uninterrupted use <strong>of</strong> such <strong>Project</strong> Asset or any part there<strong>of</strong> by the<br />
BUYER and persons authorised by the BUYER, irrespective <strong>of</strong> the fact <strong>of</strong> claims <strong>of</strong><br />
infringement <strong>of</strong> any or all the rights mentioned above.<br />
(2) If, as a result <strong>of</strong> such claim, the BUYER is injuncted from using such <strong>Project</strong> Asset or any<br />
part there<strong>of</strong> or is likely to be injuncted, SI, at its expense, shall (i) modify such <strong>Project</strong><br />
Asset (provided its functionality is not impaired) so that it is no longer infringing and<br />
obtains a certificate to the said effect from the party claiming infringement, (ii) replace<br />
such <strong>Project</strong> Asset with a functionally equivalent component <strong>of</strong> the same qulaity, or (iii)<br />
obtain the right for the BUYER to continue using such <strong>Project</strong> Assets.<br />
(3) For a third party product supplied by SI, SI shall pass on to BUYER all the indemnities<br />
<strong>of</strong>fered by the third party.<br />
14.3. Trademarks and Publicity. Neither Party may use the trademarks <strong>of</strong> the other Party<br />
without the prior written consent <strong>of</strong> the other Party. Except as required by law or the<br />
rules and regulations <strong>of</strong> each stock exchange upon which the securities <strong>of</strong> one <strong>of</strong> the<br />
Parties is listed, neither Party shall publish or permit to be published either along or in<br />
conjunction with any other person any press release, information, article,<br />
photograph, illustration or any other material <strong>of</strong> whatever kind relating to this<br />
Contract, or the business <strong>of</strong> the Parties without prior reference to and approval in<br />
writing from the other Party, such approval not to be unreasonably withheld or<br />
delayed.<br />
RFP Volume 3: Draft Legal Contract Page 39
Request for Proposal for establishing e-Governance Systems<br />
16 Article 15: Access To Book Of Accounts, Audit And Reporting<br />
15.1. Access to Book <strong>of</strong> Accounts, Audit and Reporting.<br />
(1) SI shall provide access to the auditors <strong>of</strong> the BUYER, or the authorised representatives <strong>of</strong><br />
the BUYER to the following or any such material required under circumstances, to<br />
determine compensation, payment <strong>of</strong> agent’s commission, unlawful payments,<br />
employment <strong>of</strong> suspected personnel for the <strong>Project</strong>, availability and grant <strong>of</strong> the<br />
authorisation to the authorized representatives <strong>of</strong> SI etc:-<br />
(i) Books <strong>of</strong> accounts.<br />
(ii) SI’s contracts.<br />
(iii) Recruitment and employment practices.<br />
(iv) <strong>Project</strong> loading practices and procedures.<br />
(v) The project management techniques and tools.<br />
(vi) The documentation standards.<br />
(vii) Statutory Books and Registers<br />
(2) SI should provide the BUYER or its authorized representatives necessary<br />
information/right to inspect the documents or information as per Schedule IX.<br />
RFP Volume 3: Draft Legal Contract Page 40
Request for Proposal for establishing e-Governance Systems<br />
16.1. Supervision and Management.<br />
17 Article 16: Personnel<br />
(1) Personnel assigned by SI to implement the <strong>Project</strong> shall be employees <strong>of</strong> SI, and<br />
under no circumstances will such personnel be considered employees <strong>of</strong> the BUYER.<br />
(2) SI agrees that no right <strong>of</strong> any employment with BUYER shall accrue or arise, by virtue<br />
<strong>of</strong> engagement <strong>of</strong> employees, agents, contractors, subcontractors etc. by SI,<br />
pursuant to this Contract.<br />
(3) All remuneration, claims, wages, dues <strong>of</strong> such employees, agents, contractors,<br />
subcontractors <strong>of</strong> SI is agreed to be paid by SI alone and the BUYER shall not have<br />
any direct or indirect liability or obligation, to pay any charges, claims or wages <strong>of</strong><br />
any <strong>of</strong> employee, agents, contractors, and subcontractors <strong>of</strong> SI.<br />
(4) SI has the responsibility for payment <strong>of</strong> such personnel's entire compensation,<br />
including salary, withholding <strong>of</strong> income taxes and other taxes as applicable, worker's<br />
compensation, employee and disability benefits and the like and shall be responsible<br />
for all employer obligations under all applicable laws<br />
(5) SI shall have the sole responsibility for supervision and control <strong>of</strong> its personnel and<br />
for ensuring that they carry out their assigned job in a pr<strong>of</strong>essional manner.<br />
(6) SI shall use its best efforts to ensure that sufficient SI personnel are employed to<br />
perform the services pursuant to the <strong>Project</strong>, and also that such personnel have<br />
appropriate qualifications to perform the services.<br />
(7) The BUYER has the right to seek replacement <strong>of</strong> any member <strong>of</strong> the <strong>Project</strong> team<br />
being deployed by SI or the subcontractor, based on the assessment <strong>of</strong> the BUYER<br />
that the person in question is incompetent to carry out the tasks expected <strong>of</strong><br />
him/her or found that person does not really possess the skills<br />
/experience/qualifications as projected in his/her pr<strong>of</strong>ile or on the ground <strong>of</strong><br />
security concerns or breach <strong>of</strong> ethics.<br />
(8) Except as stated in this Article, nothing in this Contract will limit the ability <strong>of</strong> SI to<br />
assign or reassign its employees; provided that SI shall be responsible, at its<br />
expense, for transferring all appropriate knowledge from personnel being replaced<br />
to their replacements. The BUYER shall have the right to review and approve SI's<br />
plan for any such knowledge transfer. SI shall maintain the same standards for skills<br />
and pr<strong>of</strong>essionalism among replacement personnel as in personnel being replaced.<br />
(9) In the event that the BUYER requests that any SI personnel be replaced, the<br />
substitution <strong>of</strong> such personnel shall be accomplished pursuant to a mutually agreed<br />
upon schedule but not later than 15 working days from the date <strong>of</strong> such requests.<br />
RFP Volume 3: Draft Legal Contract Page 41
Request for Proposal for establishing e-Governance Systems<br />
(10) The BUYER would like to identify as the “Key Personnel” those persons whose<br />
pr<strong>of</strong>iles were the basis for the evaluation <strong>of</strong> the competence <strong>of</strong> SI to carry out the<br />
implementation <strong>of</strong> the <strong>Project</strong> at the BUYER as listed in Schedule VIII. It is the<br />
responsibility <strong>of</strong> SI to deploy these resources either on a full time or part time basis<br />
for the activities they have been proposed to be deployed during the <strong>Project</strong> as per<br />
the response to the RFP submitted by SI.<br />
(11) In the event that the BUYER identifies any personnel <strong>of</strong> SI as Key Personnel, then SI<br />
shall not remove or replace such personnel without the prior written consent <strong>of</strong> the<br />
BUYER under the applicable section <strong>of</strong> this Contract.<br />
(12) Under exceptional circumstances when the Key Personnel are to be replaced or<br />
removed, SI shall put forward the pr<strong>of</strong>iles <strong>of</strong> personnel being proposed as<br />
replacements. These pr<strong>of</strong>iles should be either equivalent or better than the ones<br />
being replaced. However whether these pr<strong>of</strong>iles are better or equivalent to the ones<br />
being replaced will be decided by the BUYER or its authorised representative. The<br />
BUYER or its authorised representative will have the right to accept or reject these<br />
substitute pr<strong>of</strong>iles.<br />
(13) In the event that any Key Personnel is to be replaced for reasons not attributed to<br />
the BUYER the substitution <strong>of</strong> such personnel shall be accomplished pursuant to a<br />
mutually agreed upon schedule but not later than 7 working days from the date <strong>of</strong><br />
exit <strong>of</strong> such personnel.<br />
(14) In the event that the Key Personnel are to be replaced, it can be done only by<br />
following the procedure in Schedule VIII.<br />
(15) Each Party shall be responsible for the performance <strong>of</strong> all its obligations under this<br />
Contract and shall be liable for the acts and omissions <strong>of</strong> its employees and agents in<br />
connection therewith.<br />
(16) SI warrants that its personnel shall at all times comply with security regulations in<br />
effect from time to time at the BUYER premises and externally for materials<br />
belonging to the BUYER.<br />
(17) SI will comply with the directions issued from time to time by the BUYERand the<br />
standards related to the security and safety ins<strong>of</strong>ar as it applies to the personnel<br />
operating out <strong>of</strong> the BUYER premises.<br />
RFP Volume 3: Draft Legal Contract Page 42
Request for Proposal for establishing e-Governance Systems<br />
16.2. The Minimum Pr<strong>of</strong>iciency. The BUYER would like to identify as “Key Roles”, certain<br />
roles <strong>of</strong> the <strong>Project</strong> team being deployed by SI during the implementation <strong>of</strong> <strong>Project</strong><br />
as per Schedule VIII. These key roles are identified to be critical to the success <strong>of</strong> the<br />
<strong>Project</strong> and it is expected that these key roles will be staffed with personnel with<br />
adequate pr<strong>of</strong>iciency. The minimum pr<strong>of</strong>iciency in terms <strong>of</strong> expertise, skills and<br />
educational qualifications are listed in Schedule VIII.<br />
16.3. Clearance for Personnel.<br />
(1) In pursuance <strong>of</strong> the conditions in the the RFP, SI undertakes that all the personnel being<br />
deployed by SI for the <strong>Project</strong> are <strong>India</strong>n nationals.<br />
(2) It is the responsibility <strong>of</strong> SI to ensure that all the personnel deployed by SI for the <strong>Project</strong><br />
are not involved in any criminal or antinational activities.<br />
(3) SI should submit the police verification records <strong>of</strong> any <strong>of</strong> the personnel <strong>of</strong> SI/ Sub<br />
Contractors/ OEMs, if demanded by BUYER.<br />
16.4. Sub Contract Liabilities.Any sub contracting by SI shall be as per the terms <strong>of</strong> the<br />
Contract. It is understood by the Parties that SI shall be liable for any such<br />
subcontracting and further SI shall be the principal employer for all claims arising<br />
from the liabilities, statutory or otherwise, concerning the sub-contractors. SI<br />
undertakes to indemnify the BUYER or its nominated agencies from any claims on the<br />
grounds stated hereinabove.<br />
16.5. The OEM Personnel.<br />
(1) In pursuance <strong>of</strong> the commitment made in the RFP, SI undertakes to take the services <strong>of</strong><br />
experts from the OEM for the specific activities as listed in Schedule III.<br />
(2) The OEM personnel and the services rendered by them will be paid by SI<br />
(3) The OEM personnel will report directly to the BUYER on their work, observations and<br />
audit findings<br />
(4) Within the framework <strong>of</strong> this Contract, the BUYER will seek the deployment <strong>of</strong> the OEM<br />
personnel through SI.<br />
16.6. Liability for Actions <strong>of</strong> the Personnel.<br />
(1) SI agrees to be responsible for managing the activities <strong>of</strong> its personnel (including OEMs)<br />
and shall be accountable for both.<br />
(2) The SI agrees and shall be vicariously liable for any acts, deeds or things done by their<br />
employees, agents, contractors, subcontractors, etc., which is outside the scope <strong>of</strong><br />
power vested or instructions issued by the BUYER.<br />
RFP Volume 3: Draft Legal Contract Page 43
Request for Proposal for establishing e-Governance Systems<br />
(3) SI agrees and shall be the principal employer <strong>of</strong> the employees, agents, contractors,<br />
subcontractors, etc. engaged by SI and shall be vicariously liable for all the acts, deeds or<br />
things, whether the same is within the scope <strong>of</strong> instructions or outside the scope <strong>of</strong><br />
instructions set out in the Contract.<br />
(4) SI agrees to hold the BUYER, its successors, assignees, employees, representatives and<br />
administrators fully indemnified and harmless against loss or liability, claim actions or<br />
proceedings, if any, that may arise from whatsoever nature, caused to the BUYER<br />
through the action <strong>of</strong> its employees, agents, contractors, subcontractors, etc.<br />
(5) The BUYER agrees to inform SI, all breaches and claims <strong>of</strong> indemnification and agrees to<br />
grant SI sole authority to defend, manage, negotiate or settle such claims; and make<br />
available all reasonable assistance in defending the claims and the expenses <strong>of</strong> such<br />
activities are directly borne by SI.<br />
(6) The written demand by the BUYER as to the loss / damages stated in Articles 16.6() to (e)<br />
shall be final, conclusive and binding on SI and SI agrees and shall be liable to pay on<br />
demand the actual amount <strong>of</strong> such loss / damages caused to the BUYER.<br />
16.7. Personnel during Exit Management.<br />
(1) At any time during the exit management period, SI shall, subject to applicable laws,<br />
restraints and regulations (including in particular those relating to privacy) provide to<br />
the BUYER a list <strong>of</strong> all employees (with job titles) <strong>of</strong> SI dedicated to providing the services<br />
at the commencement <strong>of</strong> the exit management period.<br />
(2) If the termination happens and the exit management provisions need to be invoked<br />
during the SIS Stage, the BUYER will have the right to request the services <strong>of</strong> the Key<br />
Personnel <strong>of</strong> SI to facilitate transfer <strong>of</strong> knowledge to the BUYER or the Replacement SI as<br />
per the Schedule VI.<br />
(3) On the termination <strong>of</strong> the Contract during O&M Stage, the BUYER will have the right to<br />
identify SI personnel and demand their presence for knowledge transfer to the BUYER or<br />
the Replacement SI.<br />
(4) If the BUYER hires the services <strong>of</strong> another agency on the expiry <strong>of</strong> the Contract, or<br />
16.8. Non Hiring.<br />
before that, to carry out any next phase <strong>of</strong> the E-governance solution implementation<br />
and other applications, SI shall cooperate with the new agency in knowledge transfer<br />
and the BUYER shall have the right to demand the presence <strong>of</strong> the required personnel<br />
from SI for this purpose.<br />
(1) During the term <strong>of</strong> the Contract and for a period <strong>of</strong> one year thereafter, except as<br />
otherwise provided under this Contract, neither party shall (either directly or indirectly<br />
RFP Volume 3: Draft Legal Contract Page 44
Request for Proposal for establishing e-Governance Systems<br />
through a third party) employ, solicit to employ, cause to be solicited for the purpose <strong>of</strong><br />
employment or <strong>of</strong>fer employment to any employee/s or sub contractor/s <strong>of</strong> the other<br />
party, or aid any third person to do so, without the specific written consent <strong>of</strong> the other<br />
party.<br />
(2) The clause does not prevent hiring based on responses by employees to public<br />
advertisement on any media that are not specifically targeted at the other Party’s<br />
employees.<br />
RFP Volume 3: Draft Legal Contract Page 45
Request for Proposal for establishing e-Governance Systems<br />
18 Article 17: Information Security And Audit Rights<br />
17.1. Information Security.<br />
(1) SI shall also comply with the Information Technology security and standards policies in<br />
force from time to time at the <strong>Project</strong> Site <strong>of</strong> the BUYER and SI, and which the<br />
BUYERmakes SI aware in writing ins<strong>of</strong>ar as the same apply to the <strong>Project</strong>.<br />
(2) The Parties to the Contract shall use reasonable endeavours to report forthwith in<br />
writing to each other all identified attempts (whether successful or not) by unauthorized<br />
persons (including unauthorized persons who are employees <strong>of</strong> any Party) either to gain<br />
access to or interfere with the <strong>Project</strong>'s Data, facilities or Confidential Information.<br />
(3) SI shall, upon reasonable request by the BUYER participate in regular meetings when<br />
safety and Information Technology security matters are reviewed.<br />
(4) The Parties under the Contract shall promptly report in writing to each other any act or<br />
omission which they are aware that could have an adverse effect on the proper conduct<br />
<strong>of</strong> safety and information technology security at the <strong>Project</strong> Site.<br />
(5) The Parties acknowledge that high level <strong>of</strong> security needs to be maintained. All persons<br />
employed by SI for this Contract shall undergo verification as per regulations in force in<br />
ASI. SI undertakes to treat information passed on to them under this Contract as<br />
classified. Such information will not be communicated/published/advertised by SI to any<br />
person without the express permission <strong>of</strong> the BUYER. All persons working on this<br />
Contract shall be required to render a certificate that they have familiarized themselves<br />
with the provisions <strong>of</strong> The <strong>India</strong>n Official Secret Act 1927.<br />
(6) Any private, proprietary or classified information which has to be made available by the<br />
receiving party to a third party for the execution <strong>of</strong> this Contract, shall be submitted to<br />
such a third party with the same restrictions as included in this Article.<br />
(7) SI undertakes to meet the laid down security requirements/stipulations. All the matters<br />
related to the Contract will be treated as classified and highly confidential and shall not<br />
be communicated to anybody (except for the purpose <strong>of</strong> this Contract) or<br />
published/advertised without the consent <strong>of</strong> the BUYER.<br />
17.2. Confidential Information.<br />
(1) SI recognizes that during the term <strong>of</strong> the Contract, sensitive Data will be procured and<br />
made available to it, its sub contractors and agents and others working for or under SI.<br />
Further, SI also recognises that any improper and unauthorised disclosure or usage <strong>of</strong><br />
the <strong>Project</strong> Data by any such recipient may constitute a breach <strong>of</strong> applicable laws<br />
causing harm not only to BUYER but also the stakeholders whose data is used. SI, its<br />
subcontractors and agents shall demonstrate utmost care, sensitivity and strict<br />
RFP Volume 3: Draft Legal Contract Page 46
Request for Proposal for establishing e-Governance Systems<br />
confidentiality. Any breach <strong>of</strong> any confidentiality obligation set out in the Contract,<br />
including Articles will result in BUYER a right to seek injunctive relief and damages<br />
suffered or are reasonably likely to be suffered and the cost incurred to mitigate the<br />
implication <strong>of</strong> such disclosure or usage, from SI<br />
(2) “Confidential Information” means any and all information that is or has been received<br />
by either Party (the “Receiving Party”) from the other Party (the “Disclosing Party”) and<br />
that: (a) relates to the Disclosing Party; and (b) is designated by the Disclosing Party as<br />
being confidential or is disclosed in circumstances where the Receiving Party would<br />
reasonably understand that the disclosed information would be confidential or (c) is<br />
prepared or performed by or on behalf <strong>of</strong> the Disclosing Party by its employees, <strong>of</strong>ficers,<br />
directors, agents, representatives or consultants.<br />
(3) Without limiting the generality <strong>of</strong> the foregoing, Confidential Information shall mean<br />
and include any information, data, analysis, compilations, notes, extracts, materials,<br />
reports, drawings, designs, specifications, graphs, layouts, plans, charts, studies,<br />
memoranda or other documents, or materials relating to the Licensed S<strong>of</strong>tware, the<br />
modules, the Program Documentation, the Source Codes, the object codes and all<br />
Enhancements and Updates, services, systems processes, ideas, concepts, formulas,<br />
methods, know-how, trade secrets, designs, research, inventions, techniques, processes,<br />
algorithms, schematics, testing procedures, s<strong>of</strong>tware design and architecture, computer<br />
code, internal documentation, design and function specifications, product requirements,<br />
problem reports, analysis and performance information, business affairs, <strong>Project</strong>s,<br />
technology, finances (including revenue projections, cost summaries, pricing formulae),<br />
clientele, markets, marketing and sales programs, client and customer data, appraisal<br />
mechanisms, planning processes etc. or any existing or future plans, forecasts or<br />
strategies in respect there<strong>of</strong>.<br />
(4) “Confidential Materials” shall mean all tangible materials containing Confidential<br />
Information, including, without limitation, written or printed documents and computer<br />
disks or tapes, whether machine or user readable.<br />
17.3. Managing Confidential Information.<br />
(1) The Receiving Party agrees to regard, preserve and keep as secret and confidential<br />
all confidential information and materials <strong>of</strong> the Disclosing Party howsoever<br />
obtained and agrees that it shall not, without obtaining the written consent <strong>of</strong> the<br />
Disclosing Party :-<br />
(i) Disclose, transmit, reproduce or make available any such Confidential<br />
Information and materials to any person, firm, Company or any other entity<br />
other than its directors, partners, advisers, agents or employees, who need to<br />
know the same for the purposes <strong>of</strong> the <strong>Project</strong>. The Receiving Party agrees to be<br />
RFP Volume 3: Draft Legal Contract Page 47
Request for Proposal for establishing e-Governance Systems<br />
responsible for ensuring that the usage and confidentiality by its directors,<br />
partners, advisers, agents or employees is in accordance with the terms and<br />
conditions <strong>of</strong> this Contract; or<br />
(ii) Unless otherwise agreed herein, use any such Confidential Information and<br />
materials for its own benefit or the benefit <strong>of</strong> others or do anything prejudicial<br />
to the interests <strong>of</strong> the Disclosing Party or its customers or their projects.<br />
(2) In maintaining confidentiality hereunder, the Receiving Party on receiving the<br />
Confidential Information and materials agrees and warrants that it shall:<br />
i. Take at least the same degree <strong>of</strong> care in safeguarding such Confidential<br />
Information and materials as it takes for its own Confidential Information <strong>of</strong><br />
like importance and such degree <strong>of</strong> care shall be at least that which is<br />
reasonably calculated to prevent such inadvertent disclosure.<br />
ii. Keep the Confidential Information and materials and any copies there<strong>of</strong><br />
secure and in such a way so as to prevent unauthorized access by any third<br />
party.<br />
iii. Limit access to such Confidential Information and materials to those <strong>of</strong> its<br />
directors, partners, advisers, agents or employees who are directly involved<br />
in the consideration/evaluation <strong>of</strong> the Confidential Information and bind<br />
each <strong>of</strong> its directors, partners, advisers, agents or employees so involved to<br />
protect the Confidential Information and materials in the manner prescribed<br />
in this Contract; and<br />
iv. Upon discovery <strong>of</strong> any unauthorized disclosure or suspected unauthorized<br />
disclosure <strong>of</strong> Confidential Information, promptly inform the Disclosing Party<br />
<strong>of</strong> such disclosure in writing and immediately return to the Disclosing Party<br />
all such Information and materials, in whatsoever form, including any and all<br />
copies there<strong>of</strong>.<br />
(3) The Receiving Party who receives the Confidential Information and materials agrees<br />
that on a regular basis or in receipt <strong>of</strong> a written demand from the Disclosing Party or<br />
at the end <strong>of</strong> the contract period or on termination <strong>of</strong> contract:-<br />
i. Immediately return all Confidential Materials and all copies there<strong>of</strong> provided<br />
to, or produced by it or its advisers, as the case may be, which is in Receiving<br />
Party’s possession or under its custody and control;<br />
ii. Hand over all analyses, compilations, notes, studies, memoranda or other<br />
documents prepared by it or its associates to the extent that the same<br />
contain, reflect or derive from Confidential Information relating to the<br />
Disclosing Party.<br />
RFP Volume 3: Draft Legal Contract Page 48
Request for Proposal for establishing e-Governance Systems<br />
iii. Expunge any Confidential Information relating to the Disclosing Party or its<br />
projects from any computer, word processor or other device in its<br />
possession or under its custody and control; and<br />
iv. Furnish a certificate signed by its director or other responsible<br />
representative confirming that to the best <strong>of</strong> his/her knowledge,<br />
information and belief, having made all proper enquiries the requirements<br />
<strong>of</strong> this paragraph have been fully complied with.<br />
(4) The restrictions in this Article 17.3 shall not apply to:<br />
i. Any information that is publicly available at the time <strong>of</strong> its disclosure or<br />
becomes publicly available following disclosure (other than as a result <strong>of</strong><br />
disclosure by the Disclosing Party contrary to the terms <strong>of</strong> this Contract); or<br />
ii. Any disclosure required by law or by any court <strong>of</strong> competent jurisdiction, the<br />
rules and regulations <strong>of</strong> any recognised stock exchange or any enquiry or<br />
investigation by any governmental, statutory or regulatory body which is<br />
lawfully entitled to require any such disclosure provided that, so far as it is<br />
lawful and practical to do so prior to such disclosure, the Receiving Party<br />
shall promptly notify the Disclosing Party <strong>of</strong> such requirement with a view to<br />
providing the Disclosing Party an opportunity to obtain a protective order or<br />
to contest the disclosure or otherwise agree to the timing and content <strong>of</strong><br />
such disclosure; or<br />
iii. is identified in writing by the Discloser as no longer proprietary or<br />
confidential.<br />
(5) The Receiving Party agrees that its obligation under this Section with respect to<br />
confidentiality will survive the termination <strong>of</strong> this Contract<br />
(6) Confidential Information shall be and remain the property <strong>of</strong> the Discloser and<br />
nothing in this Article shall be construed to grant either Party any right or licence<br />
with respect to the other Party's Confidential Information otherwise than as is<br />
expressly set out in this Contract.<br />
(7) Both Parties agree that monetary damages would not be a sufficient remedy for any<br />
breach <strong>of</strong> this Article by the other Party and that the BUYER and Partner, as<br />
appropriate, shall be entitled to equitable relief, including injunction and specific<br />
performance as a remedy for any such breach. Such remedies shall not be deemed<br />
to be the exclusive remedies for a breach by a Party <strong>of</strong> this Article, but shall be in<br />
addition to all other remedies available at law or equity to the damaged Party.<br />
(8) In connection with the <strong>Project</strong> under this Contract, the BUYER may from time to<br />
time undertake one or more quality assessment reviews for the purpose <strong>of</strong><br />
improving quality <strong>of</strong> the E-governance solution implementation project. In order for<br />
RFP Volume 3: Draft Legal Contract Page 49
Request for Proposal for establishing e-Governance Systems<br />
such reviews to be frank and candid, for the greatest benefit to the BUYER and SI,<br />
they shall be kept confidential to the greatest extent possible. The Parties agree that<br />
any documentation created in connection with such quality assessment reviews<br />
shall be Confidential Information <strong>of</strong> the BUYER which is licensed to SI for any internal<br />
use except that in no event shall such documentation or the results <strong>of</strong> such reviews<br />
be discoverable or admissible (or used for any purpose) in any arbitration or legal<br />
proceedings against the BUYER related to this Contract or the <strong>Project</strong>.<br />
(9) SI agrees that all information processed, stored, or transmitted by SI equipment<br />
belongs to the BUYER. By having the responsibility to maintain the equipment, SI<br />
agrees not to acquire implicit access rights to the information or rights to<br />
redistribute the information.<br />
(10) SI understands and agrees that civil, criminal, or administrative penalties may apply<br />
for failure to protect information appropriately.<br />
17.4. Information Ownership<br />
(1) SI agrees that all information processed, stored, or transmitted by the <strong>Project</strong> Assets or<br />
SI Assets for Own Use belongs to the BUYER. By having the responsibility to maintain the<br />
equipment, SI agrees not to acquire implicit access rights to the information or rights to<br />
redistribute the information.<br />
(2) SI understands and agrees that civil, criminal, or administrative implications may arise<br />
for failure to protect information appropriately.<br />
(3) SI agrees that<br />
(i) All customers’, suppliers’, associated organisations and process related<br />
information <strong>of</strong> the BUYER is considered as sensitive and will be protected from<br />
unauthorized disclosure, modification or access.<br />
(ii) Any sensitive information <strong>of</strong> the BUYERwould be protected from unauthorized<br />
disclosure, modification or access.<br />
(iii) The type <strong>of</strong> sensitive information that will be found on the BUYER systems that<br />
SI agrees to support or have access to includes but is not limited to , process<br />
information, user rights, security features & guidelines, disaster management<br />
practices etc.<br />
17.5. Privacy and Security Safeguards.<br />
(1) SI agrees not to publish or disclose in any manner, under any circumstances the details<br />
<strong>of</strong> any security safeguards designed, developed, or implemented by SI under this<br />
Contract or existing at any <strong>of</strong> the BUYER locations.<br />
RFP Volume 3: Draft Legal Contract Page 50
Request for Proposal for establishing e-Governance Systems<br />
(2) SI agrees to develop procedures and implementation plans to ensure that IT resources<br />
(being used during the system integration phase or O&M phase) leaving the control <strong>of</strong><br />
the assigned user (such as being reassigned, removed for repair, replaced,or upgraded)<br />
are cleared <strong>of</strong> all the BUYER information, data and sensitive application s<strong>of</strong>tware.<br />
17.6. Access for Inspection<br />
(1) SI shall be obliged to extend all co-operation to the BUYER personnel or the experts<br />
appointed by the BUYER for purposes <strong>of</strong> verifying that the <strong>Project</strong> Systems and the<br />
<strong>Project</strong> Facilities and the activities within the project team are operated and maintained<br />
in compliance with Information Technology Security Policies <strong>of</strong> ASI.<br />
(2) Additionally, SI shall, upon prior intimation by the BUYER, provide the BUYER personnel<br />
or the authorized representatives <strong>of</strong> the BUYER access to the <strong>Project</strong> Assets/the <strong>Project</strong><br />
Facilities and documents for inspection and review <strong>of</strong> operations and also to ascertain<br />
compliance with any <strong>of</strong> the requirements under this Contract.<br />
(3) Without prejudice to the generality <strong>of</strong> this provision, it is agreed that SI shall in particular<br />
extend all co-operation to, and provide all information required by the Experts<br />
appointed by the BUYER for conducting a security audit and verifying that the<br />
<strong>Project</strong>/<strong>Project</strong> Facilities and Services are in strict compliance with the information<br />
security requirements.<br />
(4) These audits may include, but are not limited to, a review <strong>of</strong> access and authorization<br />
procedures, physical security controls, backup and recovery procedures, Network<br />
security controls and program change controls.<br />
(5) SI agrees to provide the BUYER access to various monitoring and performance<br />
measurement systems (both manual and automated). The BUYER has the right to get<br />
the monitoring and performance measurement systems (both manual and automated)<br />
audited without prior approval / notice to SI.<br />
(6) The audit, access, reporting and inspection rights <strong>of</strong> the BUYER under this Article shall be<br />
governed by Schedule IX <strong>of</strong> the Contract.<br />
RFP Volume 3: Draft Legal Contract Page 51
Request for Proposal for establishing e-Governance Systems<br />
19 Article 18: Indemnities, Limitations <strong>of</strong> Liabilities<br />
18.1. Third Party Claims.<br />
(1) SI undertakes to indemnify the BUYER from and against all losses, claims or damages on<br />
account <strong>of</strong> bodily injury, death or damage to tangible personal property arising in favour<br />
<strong>of</strong> any person, corporation or other entity (including the BUYER) attributable to SI’s<br />
performance under this Contract.<br />
(2) The indemnities set out in this Articles shall be subject to the following conditions :-<br />
(i) The BUYER, as promptly as practicable, informs SI in writing <strong>of</strong> the claim or<br />
proceedings and provides all relevant evidence, documentary or otherwise.<br />
(ii) The BUYER mayat its option (but shall not be obligated to), at the cost <strong>of</strong> SI, give SI<br />
all reasonable assistance in the defense <strong>of</strong> such claim including reasonable access<br />
to all relevant information, documentation and personnel provided that the<br />
BUYER may, at its sole cost and expense, reasonably participate, through its<br />
attorneys or otherwise, in such defense.<br />
(iii) If SI does not assume full control over the defense <strong>of</strong> a claim as provided in this<br />
Article, the BUYER may participate in such defense at cost and expense <strong>of</strong> SI.<br />
(iv) The BUYER shall not prejudice, pay or accept any proceedings or claim, or<br />
compromise any proceedings or claim, without the written consent <strong>of</strong> SI.<br />
(v) All settlements <strong>of</strong> claims subject to indemnification under this Article will: (i) be<br />
entered into only with the consent <strong>of</strong> the BUYER, which consent will not be<br />
unreasonably withheld and include an unconditional release to the BUYER from<br />
the claimant for all liability in respect <strong>of</strong> such claim; and (ii) include any<br />
appropriate confidentiality agreement prohibiting disclosure <strong>of</strong> the terms <strong>of</strong> such<br />
settlement.<br />
(vi) The BUYER shall account to SI for all awards, settlements, damages and costs (if<br />
18.2. Limitation <strong>of</strong> Liability.<br />
any) finally awarded in favor <strong>of</strong> the BUYER which are to be paid to it, in connection<br />
with any such claims or proceedings;<br />
(1) SI’s aggregate liability for actual direct damages shall be capped at *x]% <strong>of</strong> the value <strong>of</strong><br />
the Contract provided that this limit shall not apply to 1) the bodily injury (including<br />
death) and damage to real property and tangible personal property caused by SI's<br />
negligence and/or 2) the intellectual property infringement claims as per Article 14.<br />
(2) SI shall not in any event be liable for any indirect or consequential damages, or for loss<br />
<strong>of</strong> pr<strong>of</strong>it, business, revenue, goodwill, anticipated savings or Data, or third party claims<br />
RFP Volume 3: Draft Legal Contract Page 52
Request for Proposal for establishing e-Governance Systems<br />
except with respect to bodily injury (including death) and damage to real and tangible<br />
personal property.<br />
(3) Neither this Contract nor the services delivered by SI under this Contract grants or<br />
creates any rights, benefits, claims, obligations or causes <strong>of</strong> action in, to or on behalf <strong>of</strong><br />
any person or entity (including any third party) other than between the respective<br />
Parties to this Contract, as the case may be.<br />
(4) Title and Risk <strong>of</strong> Loss. SI shall bear the risk <strong>of</strong> loss on <strong>Project</strong> Assets, up to the time they<br />
are transferred and handed over to the BUYER - after which it shall stand transferred to<br />
the BUYER. SI shall arrange and pay for insurance to cover such item until it is<br />
transferred.<br />
RFP Volume 3: Draft Legal Contract Page 53
Request for Proposal for establishing e-Governance Systems<br />
19.1. Notices<br />
20 Article 19: Miscellaneous<br />
(1) Except as expressly otherwise provided in this Contract, any notice or other document,<br />
which may be given by either Party under the Contract, shall be given in writing in<br />
person or by pre-paid recorded delivery post or by facsimile transmission or by email.<br />
(2) All the notices will be initiated by the designated <strong>of</strong>ficers <strong>of</strong> the respective Parties :-<br />
(i) BUYER –.<br />
(ii) SI – <strong>Project</strong> Manager<br />
(iii) Buyer - <br />
(iv) SI – The nominated representative.<br />
NOTE: All the notices will be sent to the following “principal <strong>of</strong>ficers” <strong>of</strong> both Parties<br />
with a copy marked to the designated initiating <strong>of</strong>ficers <strong>of</strong> the other party.<br />
(3) In relation to a notice given under the Contract, any such notice or other document shall<br />
be addressed to the other Party's address as set out below:<br />
BUYER :<br />
Tel:<br />
Fax:<br />
SI: Address<br />
Tel:<br />
Fax:<br />
(4) Any notice or other document shall be deemed to have been given to the other Party<br />
(or, if relevant, its relevant associated company) when delivered (if delivered in person)<br />
between the hours <strong>of</strong> 9.00 am and 6.00 pm (or on the next working day thereafter if<br />
delivered outside such hours) at the address <strong>of</strong> the other Party set forth above or if sent<br />
by fax, provided the copy fax is accompanied by a confirmation <strong>of</strong> transmission between<br />
the hours <strong>of</strong> 9.00 am and 6.00 pm (or on the next working days thereafter if delivered<br />
outside such hours), and 7 working days from the date <strong>of</strong> posting (if by letter under<br />
Regd. AD)<br />
(5) Either Party to the Contract may change its address, telephone number, facsimile<br />
number and nominated contact for notification purposes by giving the other reasonable<br />
prior written notice <strong>of</strong> the new information and its effective date.<br />
19.2. Independent Contractors. Nothing in this Contract shall be construed as establishing<br />
or implying any partnership or joint venture between the Parties to this Contract and,<br />
RFP Volume 3: Draft Legal Contract Page 54
Request for Proposal for establishing e-Governance Systems<br />
except as expressly stated in this Contract, nothing in this Contract shall be deemed<br />
to constitute any Parties as the agent <strong>of</strong> any other Party or authorizes either Party<br />
(1) To incur any expenses on behalf <strong>of</strong> the other Party,<br />
(2) To enter into any engagement or make any representation or warranty on behalf <strong>of</strong> the<br />
other Party,<br />
(3) To pledge the credit <strong>of</strong> or otherwise bind or oblige the other Party,<br />
(4) To commit the other Party in any way whatsoever without in each case obtaining the<br />
other Party's prior written consent.<br />
19.3. Sub Contractors.SI shall not subcontract any work related to the following works<br />
pertaining to the implementation <strong>of</strong> the E-governance solution to be performed<br />
under this Contract without the BUYER’s prior written consent.<br />
(1) <strong>Project</strong> management for the implementation <strong>of</strong> the E-governance solution<br />
(2) Business design and process documentation<br />
(3) Configuration / customisation <strong>of</strong> the E-governance solution<br />
(4) Go Live <strong>of</strong> the solution<br />
19.4. Authority For Assignment<br />
(1) The BUYER may assign this Contract in whole or as part <strong>of</strong> a reorganization,<br />
restructuring, consolidation, merger, or as per the decisions <strong>of</strong> the Ministry <strong>of</strong> Culture,<br />
Government <strong>of</strong> <strong>India</strong>.<br />
(2) SI shall not assign the Contract or its rights or its duties under this Contract either in<br />
whole or in part without the prior written consent <strong>of</strong> the BUYER, and any attempted<br />
assignment or delegation without such consent will be void. It is understood that<br />
transfer <strong>of</strong> 25% or more voting share capital <strong>of</strong> SI by one transaction or a series <strong>of</strong><br />
transaction in favour <strong>of</strong> any person or a group persons shall inter-alia be considered and<br />
deemed to be an assignment/transfer <strong>of</strong> this Contract and shall require prior written<br />
consent <strong>of</strong> the BUYER.<br />
19.5. Specific Performance. SI acknowledges and agrees that the BUYER would suffer<br />
irreparable loss and damage in the event any <strong>of</strong> the provisions <strong>of</strong> this Contract are<br />
not performed in accordance with their specific terms or are otherwise breached.<br />
Accordingly, SI agrees that BUYER shall be entitled to an injunction or such other<br />
equitable relief without notice to SI to prevent any breach <strong>of</strong> the provisions <strong>of</strong> this<br />
Contract and to enforce this Contract specifically and the terms and provisions here<strong>of</strong><br />
in any action instituted in any court having jurisdiction over the Parties and the<br />
matter, in addition to any other remedy to which the BUYER may be entitled, at law<br />
or in equity.<br />
RFP Volume 3: Draft Legal Contract Page 55
Request for Proposal for establishing e-Governance Systems<br />
19.6. Waiver.No waiver <strong>of</strong> any provision <strong>of</strong> this Contract shall be effective unless set forth<br />
in a written instrument signed by the Party waiving such provision. No failure or<br />
delay by a Party in exercising any right, power or remedy under this Contract shall<br />
operate as a waiver there<strong>of</strong>, nor shall any single or partial exercise <strong>of</strong> the same<br />
preclude any further exercise there<strong>of</strong> or the exercise <strong>of</strong> any other right, power or<br />
remedy. Without limiting the foregoing, no waiver by a Party <strong>of</strong> any breach by any<br />
other Party <strong>of</strong> any provision here<strong>of</strong> shall be deemed to be a waiver <strong>of</strong> any subsequent<br />
breach <strong>of</strong> that or any other provision here<strong>of</strong>.<br />
19.7. Survival.The termination <strong>of</strong> this Contract shall in no event terminate or prejudice (a)<br />
any right or obligation arising out <strong>of</strong> or accruing under this Contract attributable to<br />
events or circumstances occurring prior to such termination; (b) the provisions <strong>of</strong> this<br />
Contract that by their nature are intended to survive the termination <strong>of</strong> this Contract,<br />
including without limitation the provisions dealing with the Representations and<br />
Warranties <strong>of</strong> the Parties, Termination, Confidentiality, Indemnity Arbitration, Non-<br />
Solicitation, Governing Law and Notice respectively.<br />
RFP Volume 3: Draft Legal Contract Page 56
Request for Proposal for establishing e-Governance Systems<br />
21 Schedule I: Costs And Pricing<br />
<br />
Table I - The costs and pricing for different work elements/services<br />
Table II – The unit rates for supplementary work / services/resources<br />
RFP Volume 3: Draft Legal Contract Page 57
Request for Proposal for establishing e-Governance Systems<br />
22 Schedule II: Change Control<br />
2.1. Purpose. This Schedule applies to and describes the procedure to be followed in the<br />
event <strong>of</strong> any proposed change to the scope <strong>of</strong> work. Such change shall include, but<br />
shall not be limited to, changes in the scope <strong>of</strong> services provided by SI, pursuant to<br />
this Contract, and changes to the terms <strong>of</strong> payment as stated in the Schedule IV. The<br />
BUYER and SI recognize that change is an inevitable part <strong>of</strong> delivering services and<br />
that a significant element <strong>of</strong> this change can be accomplished by re-organizing<br />
processes and responsibilities without a material effect on the cost. SI will endeavor,<br />
wherever reasonably practicable, to effect change without an increase in the terms <strong>of</strong><br />
payment as stated in the Schedule IV, and The BUYER will work with SI to ensure that<br />
all changes are discussed and managed in a constructive manner.<br />
2.2. Change Control Note (CCN).<br />
(1) Change requests in respect <strong>of</strong> the Contract, the scope <strong>of</strong> work, the Deliverables, the<br />
acceptance criteria for the Deliverables, the <strong>Project</strong> management, or the Operation and<br />
Maintenance and the Implementation Services will emanate from the Parties' respective<br />
relevant <strong>Project</strong> representatives who will be responsible for obtaining approval for the<br />
change and who will act as its sponsor throughout the change control process and will<br />
complete Part A <strong>of</strong> the CCN given under section 2.7. CCNs will be presented to the other<br />
Party's Programme Manager who will acknowledge receipt by signing the CCN.<br />
(2) SI and the BUYER, while preparing the CCN, shall consider the change in the context <strong>of</strong><br />
the following parameter, namely whether the change is beyond the scope <strong>of</strong> services<br />
pursuant to the Contract including ancillary and concomitant services required and as<br />
detailed in the RFP and is suggested and applicable only after the configuring, testing,<br />
commissioning and acceptance <strong>of</strong> the E-governance solution, as set out in this Contract.<br />
(3) It is hereby also clarified that the costs for the changes brought in after project sign-<strong>of</strong>f<br />
2.3. Quotation.<br />
will be calculated on the basis <strong>of</strong> implementation cost and blended man-month rate<br />
quoted by SI in its bid and estimated blended man-month effort to be submitted by SI<br />
prior to taking up the change control note and accepted by the BUYER.<br />
(1) SI shall assess the CCN and complete Part B <strong>of</strong> the CCN. In completing Part B <strong>of</strong> the CCN,<br />
SI shall provide as a minimum :-<br />
(i) A description <strong>of</strong> the change.<br />
RFP Volume 3: Draft Legal Contract Page 58
Request for Proposal for establishing e-Governance Systems<br />
(ii) A list <strong>of</strong> deliverables required for implementing the change. A timetable for<br />
implementation.<br />
(iii) An estimate <strong>of</strong> the timelines or effort <strong>of</strong> any proposed change.<br />
(iv) The unit <strong>of</strong> measure to cost the change (either the resource cost as indicated in<br />
the proposal or as a work element as mentioned in the proposal <strong>of</strong> SI).<br />
(v) Any relevant acceptance criteria.<br />
(vi) An assessment <strong>of</strong> the value <strong>of</strong> the proposed change.<br />
(vii) Material evidence to prove that the proposed change is not already covered<br />
within the scope <strong>of</strong> the <strong>Project</strong> and the implementation services.<br />
(viii) Description <strong>of</strong> the circumstances which influenced the origin <strong>of</strong> this change.<br />
(ix) Alternative options possible to address the change if any and the implications <strong>of</strong><br />
these alternative options.<br />
(2) Prior to submission <strong>of</strong> the completed CCN to the BUYER, or its nominated agencies, SI<br />
will undertake its own internal review <strong>of</strong> the proposal and obtain all necessary internal<br />
approvals. As a part <strong>of</strong> this internal review process, SI shall consider the materiality <strong>of</strong><br />
the proposed change in the context <strong>of</strong> the Contract, the scope <strong>of</strong> implementation<br />
services, the deliverables, the <strong>Project</strong> Management, Operation and Maintenance<br />
affected by the change and the total effect that may arise from implementation <strong>of</strong> the<br />
change.<br />
(3) Materiality criteria will be established by the BUYER and the SI's Programme Manager.<br />
Changes requiring no escalation <strong>of</strong> authority can be implemented. Discussion and<br />
Contract as to materiality will be held in accordance with the Schedule V.<br />
2.4. Costs.Each Party shall be responsible for its own costs incurred in the quotation,<br />
preparation <strong>of</strong> CCNs and in the completion <strong>of</strong> its obligations described in this process<br />
provided SI meets the obligations as set in the CCN. In the event SI is unable to meet<br />
the obligations as defined in the CCN then the cost <strong>of</strong> getting it done by third party<br />
will be borne by SI.<br />
2.5. Reporting. Change requests and CCNs will be reported monthly to each Party's<br />
Programme Managers who will prioritize and review progress.<br />
2.6. Obligations. SI shall be obliged to implement any proposed changes once the<br />
approval in accordance with clauses above has been given, with effect from the date<br />
agreed for implementation.<br />
2.7. Change Control Note.<br />
Change Control Note CCN Number:<br />
RFP Volume 3: Draft Legal Contract Page 59
Request for Proposal for establishing e-Governance Systems<br />
Part A: Initiation<br />
Title:<br />
Originator:<br />
Sponsor:<br />
Date <strong>of</strong> Initiation:<br />
Details <strong>of</strong> Proposed Change<br />
(To include reason for change and appropriate details/specifications. Identify any<br />
attachments as A1, A2, and A3 etc.)<br />
Authorized by THE<br />
BUYER<br />
Name:<br />
Signature:<br />
Received by the<br />
Operator<br />
Name:<br />
Signature:<br />
Date:<br />
Date:<br />
Change Control Note CCN Number:<br />
Part B : Evaluation<br />
(Identify any attachments as B1, B2, and B3 etc.)<br />
Changes to Services, charging structure, payment pr<strong>of</strong>ile, documentation, training, services<br />
and component working arrangements and any other contractual issue.<br />
RFP Volume 3: Draft Legal Contract Page 60
Request for Proposal for establishing e-Governance Systems<br />
Brief Description <strong>of</strong> Solution:<br />
Impact:<br />
Deliverables:<br />
Timetable:<br />
Charges for Implementation:<br />
(including a schedule <strong>of</strong> payments)<br />
Other Relevant Information:<br />
(including value-added and acceptance criteria)<br />
Authorized by the<br />
Operator<br />
Name:<br />
Signature:<br />
For the THE BUYER and its nominated<br />
agencies<br />
Date:<br />
For SI<br />
RFP Volume 3: Draft Legal Contract Page 61
Request for Proposal for establishing e-Governance Systems<br />
Signature Signature<br />
Name Name<br />
Title Title<br />
Date Date<br />
Change Control Note<br />
Part C : Authority to Proceed<br />
Implementation <strong>of</strong> this CCN as<br />
submitted in Part A, in accordance with<br />
Part B is: (tick as appropriate)<br />
Approved<br />
Rejected<br />
Requires Further Information (as<br />
follows, or as Attachment 1 etc.)<br />
For the THE BUYER and its nominated<br />
agencies<br />
CCN Number :<br />
For SI<br />
Signature Signature<br />
Name Name<br />
Title Title<br />
Date Date<br />
2.8. Amendment to the Contract.<br />
Amendment Note Amendment Number:<br />
Part A: Initiation<br />
RFP Volume 3: Draft Legal Contract Page 62
Request for Proposal for establishing e-Governance Systems<br />
Title:<br />
Originator:<br />
Date <strong>of</strong> Initiation:<br />
Details <strong>of</strong> Amendment<br />
(To include reason for amendment and appropriate details/specifications. Identify any<br />
attachments as A1, A2, and A3 etc.)<br />
The clause or<br />
schedule <strong>of</strong> the<br />
Contract (the original<br />
wording)<br />
The clause or<br />
schedule <strong>of</strong> the<br />
Contract – changed<br />
wording<br />
Validated by PM <strong>of</strong><br />
THE BUYER<br />
Name:<br />
Signature:<br />
Date:<br />
Validated by PM <strong>of</strong> SI Date:<br />
Name:<br />
Signature:<br />
Change Control Note<br />
Part C : Authority to Incorporate (tick as<br />
Amendment Number :<br />
RFP Volume 3: Draft Legal Contract Page 63
Request for Proposal for establishing e-Governance Systems<br />
appropriate)<br />
Approved<br />
Rejected<br />
Requires Further Information (as<br />
follows, or as Attachment 1 etc.)<br />
For the BUYER and its nominated agencies<br />
For the SI<br />
Signature Signature<br />
Name Name<br />
Title Title<br />
Date Date<br />
RFP Volume 3: Draft Legal Contract Page 64
Request for Proposal for establishing e-Governance Systems<br />
23 Schedule III: Specifications for Supply And Services<br />
<br />
RFP Volume 3: Draft Legal Contract Page 65
Request for Proposal for establishing e-Governance Systems<br />
24 Schedule IV: Terms <strong>of</strong> Payment Schedule<br />
<br />
RFP Volume 3: Draft Legal Contract Page 66
Request for Proposal for establishing e-Governance Systems<br />
25 Schedule V: Governance<br />
5.1. The Governance Structure and Governance Procedure.<br />
(1) There will be a <strong>Project</strong> Management Committee for managing the <strong>Project</strong>. The<br />
committee <strong>of</strong> the governance structure are duly constituted within seven days <strong>of</strong> signing<br />
the Contract:<br />
(2) The “<strong>Project</strong> Management Committee” will consist <strong>of</strong> :-<br />
(i) .<br />
(ii)<br />
(iii)<br />
(3) The principal <strong>of</strong>ficers: – and the Representative <strong>of</strong> SI will be<br />
“Principal Officers” with authority and responsibility for initiating actions for dispute<br />
resolution, overcoming the impact <strong>of</strong> events, facilitating consultation and initiating<br />
notices which will have impact on the continuity and content <strong>of</strong> the Contract.<br />
5.2. <strong>Project</strong> Manager.<br />
(1) The relationship under this Contract will be managed by the <strong>Project</strong> Managers appointed<br />
by each Party, who will provide the interface between the executive <strong>of</strong>ficers <strong>of</strong> the<br />
respective Parties.<br />
(2) In the case <strong>of</strong> the BUYER the <strong>Project</strong> Manager will be an individual who is appointed by<br />
. In the case <strong>of</strong> SI, the <strong>Project</strong> Manager will be an<br />
individual who is on the rolls <strong>of</strong> SI. In the event that either Party wishes to substitute its<br />
<strong>Project</strong> Manager, it will do so in manner in which the original appointment is made and<br />
notify the other Party <strong>of</strong> such substitution as soon as reasonably practicable but at the<br />
latest within fourteen days <strong>of</strong> the substitution.<br />
(3) The <strong>Project</strong> Managers shall have responsibility for maintaining the interface and<br />
communication between the Parties.<br />
(4) The Director BUYER.The Director from the BUYER will be single point <strong>of</strong> contact (SPOC)<br />
for SI. The responsibilities <strong>of</strong> Director (Buyer) include the following :-<br />
(i) Provide access to information required and available with BUYER for the<br />
engagement.<br />
(ii) Own <strong>Project</strong> Plan, <strong>Project</strong> Communication and Team Coordination.<br />
(iii) <strong>Project</strong> Reporting and Communication.<br />
(iv) <strong>Project</strong> issue resolution.<br />
(v) Initiate Change Control process, where required.<br />
(vi) Expedite approvals and clarifications raised by SI and the BUYER team.<br />
RFP Volume 3: Draft Legal Contract Page 67
Request for Proposal for establishing e-Governance Systems<br />
(vii) Provide access to physical resources as outlined above.<br />
(viii) Nominate specific executives from within the BUYER for the <strong>Project</strong> for a specific<br />
process and activity and responsibility.<br />
(ix) Coordinate with the BUYER Management on any specific aspects requiring their<br />
approval.<br />
(x) Initiating the notices as applicable.<br />
(5) The <strong>Project</strong> Manager SI. The <strong>Project</strong> Manager assumes overall responsibility for the<br />
assignment and ensures that all resources required are made available and the<br />
engagement is carried out according to agreed implementation plans. He/she shall<br />
function as the primary channel <strong>of</strong> communication for all the BUYER requirements to SI.<br />
The responsibilities <strong>of</strong> <strong>Project</strong> Manager include the following :-<br />
(i) Overall responsibility for operations <strong>of</strong> SI at the <strong>Project</strong> site.<br />
(ii) Lead the <strong>Project</strong> team <strong>of</strong> SI.<br />
(iii) Ensure successful completion <strong>of</strong> unit tests and integration tests for all<br />
development activity.<br />
(iv) Ensure that all phases <strong>of</strong> the development activity are duly signed <strong>of</strong>f by the<br />
BUYER.<br />
(v) He / She will handle all the issues at the BUYER relating to implementation project.<br />
(vi) Walk-through <strong>of</strong> Business Blue Print, ensure sign <strong>of</strong>f <strong>of</strong> detailed design and<br />
coordinate testing activities.<br />
(vii) <strong>Project</strong> Reporting and Communication.<br />
(viii) <strong>Project</strong> issue resolution.<br />
(ix) Initiating the notices as applicable.<br />
5.3. <strong>Project</strong> Management Committee.<br />
(1) <strong>Project</strong> Management Committee will meet formally on a periodical basis at a time and<br />
location (either physically at one place or through teleconferencing facility) to be agreed<br />
between them. These meetings will cover, as a minimum, the following agenda items :-<br />
(i) Consideration <strong>of</strong> monthly Performance Reports.<br />
(ii) Consideration <strong>of</strong> matters arising out <strong>of</strong> the Schedule II.<br />
(iii) Issues escalated in accordance with the escalation procedure as set out in the<br />
Schedule V.<br />
(iv) Matters to be brought before the <strong>Project</strong> Management Committee in accordance<br />
with the Contract and the Schedules.<br />
RFP Volume 3: Draft Legal Contract Page 68
Request for Proposal for establishing e-Governance Systems<br />
(v) Any matter brought before the <strong>Project</strong> Management Committee by SI or the<br />
BUYER under this Schedule.<br />
(vi) Any other issue which either Party wishes to add to the agenda.<br />
5.4. Purpose <strong>of</strong> Governance Procedures.The purpose <strong>of</strong> Governance procedure is to:-<br />
(1) Establish and maintain the formal and informal processes for managing the relationship<br />
between the BUYER and SI (including the outputs from other Schedules to this Contract).<br />
(2) Define the principles that both Parties wish to follow to ensure the delivery <strong>of</strong> the<br />
Services.<br />
(3) Ensure the continued alignment <strong>of</strong> the interests <strong>of</strong> the Parties.<br />
(4) Ensure that the relationship is maintained at the correct level within each Party.<br />
(5) Create the flexibility to revise and maintain the relationship and this Contract during the<br />
Term <strong>of</strong> the contract.<br />
(6) Set out the procedure for escalating disagreements and resolving disputes.<br />
(7) Enable Contract administration and performance management.<br />
5.5. Governance Procedures<br />
(1) The agenda for each meeting <strong>of</strong> the <strong>Project</strong> Management Committee, shall be set to<br />
reflect the discussion items referred to above and extraordinary items may be added<br />
either with the Contract <strong>of</strong> the Parties or at the request <strong>of</strong> either Party. Copies <strong>of</strong> the<br />
agenda for meetings <strong>of</strong> the Committees, along with relevant pre-reading material, shall<br />
be distributed at least one week in advance <strong>of</strong> the relevant meeting.<br />
(2) SI shall be responsible for bringing in the representatives <strong>of</strong> the OEMs, if requisitioned<br />
by the BUYER as special invitees to participate in the meetings <strong>of</strong> the <strong>Project</strong><br />
Management Committee, to discuss or resolve any issues arising out <strong>of</strong> or requiring the<br />
involvement <strong>of</strong> the OEMs in the <strong>Project</strong>.<br />
(3) All meetings and proceedings will be documented; such documents to be distributed to<br />
both Parties and copies shall be kept as a record. All actions, responsibilities and<br />
accountabilities arising out <strong>of</strong> any meeting shall be tracked and managed.<br />
(4) The Parties shall ensure as far as reasonably practicable that the <strong>Project</strong> Management<br />
Committee shall resolve the issues and resolve the objectives placed before them and<br />
those members representing that Party are empowered to make relevant decisions or<br />
have easy access to empowered individuals for decisions to be made to achieve this.<br />
(5) In the event that there is any material factor which affects the <strong>Project</strong> or the terms <strong>of</strong><br />
payment as stated in the Schedule IV, the Parties agree to discuss in the <strong>Project</strong><br />
Management Committee any appropriate amendment to the Contract or Statement <strong>of</strong><br />
Works including any variation to the terms <strong>of</strong> payment as stated in the Schedule IV. Any<br />
RFP Volume 3: Draft Legal Contract Page 69
Request for Proposal for establishing e-Governance Systems<br />
variation so agreed shall be put forward to the Executive Committee (EC) for approval<br />
and action.<br />
(6) Any amendments to the Contract or any supplements to be added to the Contract will<br />
be discussed by the <strong>Project</strong> Management Committee. These documents will become<br />
part <strong>of</strong> the Contract after being duly signed by the authorised representatives <strong>of</strong> the<br />
BUYER and SI.<br />
5.6. Escalation Procedures<br />
(1) Irrespective <strong>of</strong> the nature <strong>of</strong> disputes, events, and defaults, the notices for discussion or<br />
resolution will follow the escalation procedures.<br />
(2) The initiation <strong>of</strong> the escalation activities, other than the ones for termination and<br />
arbitration, will be from the <strong>Project</strong> Management Committee or its members.<br />
(3) The escalations will follow the guidelines listed for each type <strong>of</strong> notices.<br />
5.7. Procedure for Issuing Notices<br />
(1) Subject to the provisions here<strong>of</strong>, all notices hereunder shall be issued as per Article 19.1<br />
(Notices) <strong>of</strong> this Contract.<br />
(2) If the responding party fails to respond to the notice within 21 days <strong>of</strong> a notice, a<br />
maximum <strong>of</strong> one more notice to the same effect may be issued to the party.<br />
(3) If the responding party does not respond to two notices, it is treated as wilful violation<br />
<strong>of</strong> the Contract and the actions related to breach <strong>of</strong> Contract will come into force.<br />
5.8. Notices on Disputes<br />
(1) Either Party (“Claimant”) shall first submit any dispute or disagreement (dispute notice)<br />
between the Parties arising out <strong>of</strong> or relating to and/or in connection with this Contract<br />
which is not a material breach <strong>of</strong> this Contract (a "Disputed Matter") to the , with a copy to the other Party.<br />
(2) The dispute notices will be a written notice and shall be accompanied by :-<br />
(i) A statement by the Claimant describing the Disputed Matter in reasonable detail.<br />
(ii) Documentation, if any, supporting the Claimant's position on the Disputed Matter.<br />
(3) The other Party ("Respondent") shall have the right to respond to the Dispute Notice<br />
within 7 days after receipt <strong>of</strong> the Dispute Notice.<br />
(4) The two designated authorities from both the parties will resolve the dispute through<br />
mutual discussions<br />
(5) The minutes <strong>of</strong> the meeting <strong>of</strong> the proceedings <strong>of</strong> the committees will serve as the basis<br />
for action on disputes, withdrawal <strong>of</strong> notice, or taking matter to arbitration.<br />
RFP Volume 3: Draft Legal Contract Page 70
Request for Proposal for establishing e-Governance Systems<br />
5.9. Notice for Consultation<br />
(1) The Party shall submit a notice for consultation for an event <strong>of</strong> default to the , with a copy to the other Party,<br />
(2) The consultation notice will be accompanied by :-<br />
(i) Description <strong>of</strong> the event <strong>of</strong> default.<br />
(ii) The date and circumstances <strong>of</strong> default.<br />
(iii) Documentary evidence if any <strong>of</strong> the event <strong>of</strong> default.<br />
(3) The other Party ("Respondent") shall have the right to respond to the Consultation<br />
Notice within 7 days after receipt <strong>of</strong> the Consultation Notice.<br />
(4) The respective authorities will initiate the remedial process, with specific action and<br />
timelines for action (not exceeding 90 days) to rectify the event <strong>of</strong> default, through<br />
mutual discussions.<br />
(5) The minutes <strong>of</strong> the meeting <strong>of</strong> the proceedings <strong>of</strong> the committees will serve as the basis<br />
for action on consultation, withdrawal <strong>of</strong> notice or termination.<br />
5.10. Notice <strong>of</strong> an Event<br />
(1) The Affected Party shall give notice on the event to the other Party <strong>of</strong> the occurrence <strong>of</strong><br />
any event within 7 (seven) days after the Affected Party knew, or ought reasonably to<br />
have known, <strong>of</strong> its occurrence.<br />
(2) The Notice shall include details <strong>of</strong> :-<br />
(i) The nature, time <strong>of</strong> occurrence and extent <strong>of</strong> the Force Majeure Event with<br />
documentary evidence in respect there<strong>of</strong>.<br />
(ii) If the event is due to Change in Law, a certified copy <strong>of</strong> the changed law, the<br />
effective date <strong>of</strong> the law and a copy <strong>of</strong> the earlier law which was applicable when<br />
the Contract came into effect.<br />
(iii) If the event is due to Change in Law, the notice will also include the list <strong>of</strong> articles<br />
or part <strong>of</strong> the articles which will be impacted and suggestions if any for<br />
modification.<br />
(iv) Description <strong>of</strong> the adverse effect it has or is likely to have on the performance <strong>of</strong><br />
the party’s obligations under this Contract.<br />
(v) The duration or estimated duration and the effect or probable effect the Event has<br />
or will have on the Affected Party’s ability to perform its obligations or any <strong>of</strong><br />
them under this Contract.<br />
RFP Volume 3: Draft Legal Contract Page 71
Request for Proposal for establishing e-Governance Systems<br />
(vi) The measures which the Affected Party has taken or proposes to take, to alleviate<br />
the impact <strong>of</strong> the Event or to mitigate the damage; and<br />
(vii) Any other relevant information.<br />
(3) If the notice <strong>of</strong> an event is accepted by the other Party as valid, the two Principal Officers<br />
will initiate the actions required to be undertaken and the periodicity (at least once in a<br />
month) for the affected party to submit reports on the event to the other party.<br />
5.11. Notices on Arbitration and Termination<br />
(1) Notice for arbitration or termination will be issued when all the mechanisms <strong>of</strong> dispute<br />
resolution listed in the governance procedure have failed to resolve or overcome the<br />
event.<br />
(2) The minutes <strong>of</strong> the EC will be the basis for issuing arbitration and/or termination notices.<br />
(3) The arbitration and termination notices will include :-<br />
(i) The details <strong>of</strong> events, default or disputes leading to arbitration or termination.<br />
(ii) In case <strong>of</strong> termination, a deadline and a plan <strong>of</strong> action for exit management.<br />
5.12. Declaration <strong>of</strong> “Go- Live”.<br />
(1) The two <strong>Project</strong> Managers from the Buyer and SI, after satisfactory completion <strong>of</strong> all the<br />
activities as listed in the section on scope <strong>of</strong> SIS <strong>of</strong> the Article 3, and after scrutinizing all<br />
the inspection reports, audit findings, Contracts, licensing agreements etc. will initiate<br />
jointly the notice for declaring “Go Live”.<br />
(2) The “Go Live” notice is submitted to the “<strong>Project</strong> Management Committee” for action.<br />
(3) Within fifteen days <strong>of</strong> receiving the notice the <strong>Project</strong> ManagementCommittee will<br />
decide on the actions to be taken on “Go Live”.<br />
(4) If the project ManagementCommittee approves the Go-Live notice, the same is<br />
submitted to the EC.<br />
(5) The Go Live date comes into effect only when the EC approves the notice for Go Live.<br />
(6) In the event that any <strong>of</strong> the approving committees do not approve or suggest further<br />
action, the notices are reinitiated only after the recommended actions have been<br />
satisfactorily completed.<br />
RFP Volume 3: Draft Legal Contract Page 72
Request for Proposal for establishing e-Governance Systems<br />
6.1. Initiation.<br />
26 Schedule VI: Exit Management<br />
(1) This schedule sets out the provisions, which will apply on expiry or termination <strong>of</strong> the<br />
Contract, during the SIS Stage and O&M Stage <strong>of</strong> the <strong>Project</strong>.<br />
(2) In the case <strong>of</strong> termination <strong>of</strong> the Contract, the Parties shall agree at that time whether,<br />
and if so during what period, the provisions <strong>of</strong> this schedule shall apply.<br />
(3) In case <strong>of</strong> expiry <strong>of</strong> the Contract or part <strong>of</strong> the contracted service, the provisions <strong>of</strong> this<br />
schedule come into effect three months before the Contract for the particular service<br />
comes to an end.<br />
(4) However, if the BUYER, in the intervening period, invokes the provisions <strong>of</strong> the Contract<br />
and extends the term <strong>of</strong> the Contract for the particular service, the provisions <strong>of</strong> the<br />
schedule will not come into effect.<br />
(5) The Parties shall ensure that their respective associated entities carry out their<br />
respective obligations set out in this Schedule.<br />
6.2. Exit Management Plan.<br />
(1) On the initiation <strong>of</strong> the provisions <strong>of</strong> the exit management schedule by the BUYER, SI<br />
shall provide the BUYER with a recommended exit management plan which shall<br />
deal with at least the following aspects <strong>of</strong> exit management in relation to the<br />
Contract or the particular service <strong>of</strong> the Contract.<br />
(2) A detailed program <strong>of</strong> the transfer process that could be used in conjunction with a<br />
Replacement SI or the BUYER’s <strong>Project</strong> team including details <strong>of</strong> the means to be<br />
used to ensure continuing provision <strong>of</strong> the services throughout the transfer process<br />
or until the cessation <strong>of</strong> the services and <strong>of</strong> the management structure to be used<br />
during the transfer.<br />
(3) Plans for the communication with such <strong>of</strong> SI's , staff, suppliers, and any related third<br />
party as are necessary to avoid any material detrimental impact on <strong>Project</strong>’s<br />
operations as a result <strong>of</strong> undertaking the termination or expiry.<br />
(4) The proposed arrangements for the segregation <strong>of</strong> communication means<br />
(including but not limited to transfer <strong>of</strong> data in electronic forms, emails etc.) from<br />
the Networks employed by the BUYER and identification <strong>of</strong> specific security tasks<br />
necessary for ensuring this.<br />
(5) Plans for provision <strong>of</strong> contingent support to the BUYER and Replacement SI for a<br />
reasonable period after transfer.<br />
(6) The plan for settling the payments and claims pursuant to the Contract, if applicable.<br />
(7) The list <strong>of</strong> services to be rendered by SI, during the exit management period.<br />
RFP Volume 3: Draft Legal Contract Page 73
Request for Proposal for establishing e-Governance Systems<br />
(8) The acceptance mechanisms for successful completion <strong>of</strong> exit management.<br />
(9) Payments during the Exit Management period shall be made in accordance with the<br />
Schedule IV.<br />
(10) This Exit Management plan shall be furnished in writing to the BUYER within 7 days<br />
from the date on which the action for termination is initiated or ninety days prior to<br />
the date <strong>of</strong> expiry <strong>of</strong> the Contract.<br />
6.3. SI Obligations on Termination.On termination or expiry <strong>of</strong> the Contract, the<br />
obligations <strong>of</strong> the SI are listed below and these shall be applicable on the basis <strong>of</strong> the<br />
last milestone achieved by SI prior to termination :-<br />
(1) Hand over the possession <strong>of</strong> the Development Site, <strong>Project</strong> Assets, ASI Supplied<br />
Equipment and Documentation to the BUYER or its nominee.<br />
(2) Transfer all rights, titles and interests in such <strong>Project</strong> Assets (as the BUYER in its sole<br />
discretion may determine) to the BUYER or its nominee and transfer information which<br />
are required to be transferred to the BUYER in accordance with this Contract and<br />
execute such deeds and documents as may be necessary for the aforesaid purposes<br />
including completing all legal or other formalities required in this regard.<br />
(3) Hand over to the BUYER or its nominee all documents including, but not limited to,<br />
process specifications, testing specifications, test results, manuals and records relating<br />
to operation and maintenance <strong>of</strong> the s<strong>of</strong>tware and hardware.<br />
(4) Transfer/assign or cause to be transferred/assigned to the BUYER or its nominee any<br />
OEM contracts which are valid and subsisting and those OEM Contracts which the BUYER<br />
has chosen to take over, and, cancel or cause to be cancelled such OEM contracts which<br />
are not to be transferred/assigned to the BUYER or its nominee. For this purpose, SI shall<br />
ensure that all OEM Contracts are assignable in favor <strong>of</strong> the BUYER or its nominee<br />
without any further action on part <strong>of</strong> the respective counterparties. SI shall entirely at its<br />
cost, terminate all such OEM contracts which are not transferred/assigned and/or are<br />
not required to be transferred/assigned to the BUYER.<br />
(5) Transfer/assign all the warranties for the hardware and s<strong>of</strong>tware, in favour <strong>of</strong> the BUYER<br />
or its nominee, which are required by the BUYER to continue to operate or use, either<br />
during the SIS Stage or O&M Stage.<br />
(6) At its cost, remove within 90 (ninety) days from expiry <strong>of</strong> the Contract, from the <strong>Project</strong><br />
Site, any moveable assets that are not taken over by or not to be transferred to the<br />
BUYER in terms <strong>of</strong> the provisions <strong>of</strong> this Contract.<br />
(7) SI shall extend all support for the exit without service disruption as per the conditions<br />
under this Schedule.<br />
RFP Volume 3: Draft Legal Contract Page 74
Request for Proposal for establishing e-Governance Systems<br />
6.4. Confidential Information, Security and Data.SI will promptly on the commencement<br />
<strong>of</strong> the exit management period, hand over to the BUYER the following :-<br />
(1) Information relating to the current services rendered and customer satisfaction surveys<br />
and performance data relating to the performance <strong>of</strong> sub Contractors in relation to the<br />
services.<br />
(2) Documentation relating to <strong>Project</strong>’s Intellectual Property Rights.<br />
(3) The data belonging to the BUYER and Confidential Information.<br />
(4) All current and updated data <strong>of</strong> the <strong>Project</strong> as is reasonably required for purposes <strong>of</strong> the<br />
BUYER or its nominated agencies, transitioning the services to its Replacement SI in a<br />
readily available format nominated by the BUYER.<br />
(5) All other information (including, but not limited to, documents, records and Contracts)<br />
relating to the services reasonably necessary to enable the BUYER or its nominated<br />
agencies, or its Replacement SI to carry out due diligence in order to transition the<br />
provision <strong>of</strong> the services to the BUYER or its nominated agencies, or its Replacement SI<br />
(as the case may be).<br />
(6) Before the expiry <strong>of</strong> the exit management period, SI shall deliver to the BUYER; all new<br />
or up-dated materials from the categories set out in Article above and shall not retain<br />
any copies there<strong>of</strong>, except that SI shall be permitted to retain one copy <strong>of</strong> such materials<br />
for archival purposes only.<br />
(7) Before the expiry <strong>of</strong> the exit management period, unless otherwise provided under the<br />
Contract, the BUYER shall deliver to SI all forms <strong>of</strong> SI’s confidential information, which is<br />
in the possession or control <strong>of</strong> the BUYER or its users.<br />
6.5. Knowledge Transfer.<br />
(1) SI will undertake the following activities to ensure that the knowledge about the entire<br />
Information Technology system including, but not limited to, Data Centres, Disaster<br />
Recovery Centres, the Networks, the applications, customised solution, the design and<br />
operational characteristics <strong>of</strong> these systems are transferred to the Buyer Team or the<br />
Replacement SI. The activities will be aimed at :-<br />
(i) Knowledge transfer <strong>of</strong> operations.<br />
(ii) Knowledge transfer <strong>of</strong> technology<br />
(iii) Knowledge transfer <strong>of</strong> processes<br />
(2) Some <strong>of</strong> the key activities to be carried out by SI for knowledge transfer will be :-<br />
(i) Documents walk through to explain design and characteristics.<br />
(ii) The code walkthrough to explain the characteristics <strong>of</strong> the s<strong>of</strong>tware applications.<br />
RFP Volume 3: Draft Legal Contract Page 75
Request for Proposal for establishing e-Governance Systems<br />
(iii) Joint operations <strong>of</strong> key activities or services <strong>of</strong> help desk, Data Centre and DR<br />
centre operations.<br />
(iv) Briefing sessions on process and process documentation.<br />
(v) Walk through the logs <strong>of</strong> the bugs, the changes to the codes etc.<br />
(vi) Briefing sessions on applications, the way these are deployed and integrated.<br />
(3) Transfer technology and up-to-date know-how relating to operation and maintenance <strong>of</strong><br />
6.6. Employees.<br />
the s<strong>of</strong>tware and hardware.<br />
(1) Since the <strong>Project</strong> team <strong>of</strong> SI is critical for effective knowledge transfer and exit<br />
management, SI will comply with the obligations set out in Article 16.7 <strong>of</strong> the Contract<br />
and ensure the following during the exit management period :-<br />
(i) At least 75% <strong>of</strong> the key personnel as identified in the Schedule VIII are available for<br />
joint operations and knowledge transfer.<br />
(ii) At least 75% <strong>of</strong> the operations team is staffed with people with minimum<br />
pr<strong>of</strong>iciency as listed in the Schedule VIII.<br />
(2) Ensure that all the employees who worked on the <strong>Project</strong> have followed the clauses in<br />
the Article 14 and Article 17 <strong>of</strong> this Contract.<br />
(3) Ensure that the exiting employees have followed the security guidelines <strong>of</strong> the ASI<br />
premises.<br />
6.7. General Obligations <strong>of</strong> SI.<br />
(1) SI will involve the services <strong>of</strong> the OEMs as the case may be, for the purpose <strong>of</strong> executing<br />
the exit management plans, without any costs to the BUYER.<br />
(2) SI shall provide all such information as mentioned in the above clauses in order to affect<br />
as seamless a handover as practicable in the circumstances.<br />
(3) For the purposes <strong>of</strong> this Schedule, anything in the possession or control <strong>of</strong> SI, any<br />
associated entity, or is deemed to be in the possession or control <strong>of</strong> SI.<br />
(4) SI shall commit adequate resources to comply with its obligations under this Exit<br />
Management Schedule.<br />
(5) The task <strong>of</strong> SI with reference to the exit management is deemed to be complete only<br />
when the <strong>Project</strong> Manager SI <strong>of</strong> the BUYER issues a satisfactory completion certificate<br />
for the “exit management plan”.<br />
RFP Volume 3: Draft Legal Contract Page 76
Request for Proposal for establishing e-Governance Systems<br />
6.8. BUYER’s Obligations on Termination. On termination <strong>of</strong> the Contract, the BUYER’S<br />
obligations towards SI will be as follows:-<br />
(1) The BUYER confirms that the payment for the last milestone achieved by SI will be<br />
expedited subject to the set <strong>of</strong>f rights.<br />
(2) The BUYER shall extend all support for the knowledge transfer activities as per this<br />
Schedule VI.<br />
RFP Volume 3: Draft Legal Contract Page 77
Request for Proposal for establishing e-Governance Systems<br />
27 Schedule VII: List <strong>of</strong> Assets<br />
<br />
RFP Volume 3: Draft Legal Contract Page 78
Request for Proposal for establishing e-Governance Systems<br />
8.1. The List <strong>of</strong> Key Personnel.<br />
28 Schedule VIII: Personnel<br />
<br />
8.2. The Procedure for Replacing Key Personnel.<br />
(1) SI will give an advanced notice in writing <strong>of</strong> not less than four weeks on its intention to<br />
replace the core team member.<br />
(2) After getting the approval <strong>of</strong> the BUYER, SI will propose an equivalent pr<strong>of</strong>ile as<br />
replacement to the BUYER.<br />
(3) The BUYER or its authorized representative will evaluate the pr<strong>of</strong>ile and indicate the<br />
acceptance / rejection <strong>of</strong> the pr<strong>of</strong>ile. The BUYER may seek a personal interview <strong>of</strong> the<br />
person being proposed.<br />
(4) After getting the approval <strong>of</strong> the BUYER, SI will ensure that there will be sufficient time<br />
for the replacement person to work with the person being replaced, for transferring the<br />
project specific knowledge to him/her.<br />
(5) If the proposed pr<strong>of</strong>ile is rejected by the BUYER, SI will provide alternate pr<strong>of</strong>iles, till<br />
there is an acceptable pr<strong>of</strong>ile.<br />
(6) The costs associated with replacements like conducting interviews, travel costs <strong>of</strong> the<br />
replacement pr<strong>of</strong>ile will be completely borne by SI<br />
(7) The format for submitting the pr<strong>of</strong>iles <strong>of</strong> replacement for core team members should be<br />
as below:-<br />
RFP Volume 3: Draft Legal Contract Page 79
Request for Proposal for establishing e-Governance Systems<br />
Name <strong>of</strong> the person<br />
Role in the <strong>Project</strong><br />
Qualification<br />
Total number <strong>of</strong> years <strong>of</strong> experience<br />
Number <strong>of</strong> years with the current company (the bidder)<br />
Functional area / expertise<br />
Area <strong>of</strong> certification<br />
Number <strong>of</strong> complete life cycle implementations carried<br />
out<br />
The names <strong>of</strong> customers. (Please provide the relevant<br />
names)<br />
The functional areas /processes implemented<br />
RFP Volume 3: Draft Legal Contract Page 80
Request for Proposal for establishing e-Governance Systems<br />
29 Schedule IX: Audit, Access, And Reporting<br />
9.1. Purpose. This Schedule details the audit, access and reporting rights <strong>of</strong> the BUYER<br />
and respective obligations <strong>of</strong> SI under the Contract.<br />
9.2. Audit Notice and Timing.<br />
(1) As soon as reasonably practicable after the Effective Date, the Parties shall use their best<br />
endeavours to agree to a timetable for routine audits during the <strong>Project</strong>.Such time table<br />
may be reviewed every 3 months. During the Term, the BUYER or its nominated agencies<br />
shall conduct routine audits in accordance with such agreed timetable and shall not be<br />
required to give SI any further notice <strong>of</strong> carrying out such audits.<br />
(2) The BUYER may conduct non-timetabled (adhoc) audits at its own discretion if it<br />
reasonably believes that such non-timetabled audits are necessary as a result <strong>of</strong> an act<br />
<strong>of</strong> fraud by SI, a security violation, or breach <strong>of</strong> confidentiality obligations by SI, provided<br />
that the requirement for such an audit is notified in writing to SI a reasonable period<br />
time prior to the audit (taking into account the circumstances giving rise to the<br />
reasonable belief) stating in a reasonable level <strong>of</strong> detail the reasons for the requirement<br />
and the alleged facts on which the requirement is based. If SI considers that the non-<br />
timetabled audit was not appropriate, the matter shall be referred to the escalation<br />
procedure as set out in the Schedule V.<br />
(3) The frequency <strong>of</strong> audits shall be six (6) monthly, provided always thatthe BUYER or ASI<br />
shall endeavour to conduct such audits with the lowest levels <strong>of</strong> inconvenience and<br />
disturbance as practicable being caused to SI.<br />
(4) The audit and access rights contained shall survive the termination or expiration <strong>of</strong> the<br />
Contract for a period <strong>of</strong> twenty-four(24) months.<br />
9.3. Access. SI shall provide to the BUYER or its nominated agencies, or its or their<br />
authorised representatives, reasonable access to employees, subcontractors,<br />
suppliers, third party facilities, including leased premises, Data Recovery Centres,<br />
documents, records and systemsreasonably required for audit and shall provide all<br />
such persons with routine assistance in connection with the audits and inspections.<br />
The BUYER or its nominated agencies during the audit shall have the right to copy<br />
and retain copies <strong>of</strong> any relevant records. SI shall make every reasonable effort to co-<br />
operate with them in effecting the Audit.<br />
9.4. Audit Rights.<br />
(1) The BUYER shall have the right to audit and inspect suppliers, agents, third party<br />
facilities, including leased premises, Data recovery centres, documents, records,<br />
RFP Volume 3: Draft Legal Contract Page 81
Request for Proposal for establishing e-Governance Systems<br />
procedures and systems relating to the <strong>Project</strong>, but only to the extent that they relate to<br />
these , as shall be reasonably necessary to verify:-<br />
(i) The security, integrity and confidentiality availability <strong>of</strong> all the BUYER Data<br />
processed, held or conveyed by SI on behalf <strong>of</strong> the BUYER or its nominated<br />
agencies and its Usersand documentation related thereto;<br />
(ii) That SI has complied with the relevant technical standards, and has adequate<br />
internal controls in place; and<br />
(iii) The compliance <strong>of</strong> SI with any other obligation under the Contract.<br />
(iv) SI’s internal cost records shall be excluded for the purpose <strong>of</strong> audit<br />
(v) That the actual level <strong>of</strong> performance <strong>of</strong> the Services is the same as that specified in<br />
the Service Level Agreement<br />
9.5. Audit Rights <strong>of</strong> Sub-Contractors, Suppliers and Agents.<br />
(1) SI shall use reasonable endeavours to achieve the same audit and access provisions as<br />
defined in this Schedule with sub-Contractors, suppliers and agents who supply labour,<br />
services, materials in respect <strong>of</strong> the services. SI shall inform the BUYER, prior to<br />
concluding any sub-Contract or supply agreement, <strong>of</strong> any failure to achieve the same<br />
rights <strong>of</strong> audit and/or access.<br />
(2) Reporting.SI will provide reports to the BUYER regarding any specific aspects <strong>of</strong> the<br />
<strong>Project</strong> and in context <strong>of</strong> the audit and access information as required by the BUYER<br />
9.6. Action and Review.<br />
(1) Any change or amendment to the systems and procedures <strong>of</strong> SI, or sub-Contractors,<br />
where applicable, arising from the audit report shall be agreed within thirty (30)<br />
calendar days from the submission <strong>of</strong> the said report.<br />
(2) Any discrepancies identified by any audit pursuant to this Schedule shall be immediately<br />
notified to the who shall determine what action<br />
should be taken in respect <strong>of</strong> such discrepancies in accordance with the terms <strong>of</strong> the<br />
Contract.<br />
9.7. Records and Information. For the purposes <strong>of</strong> audit in accordance with this<br />
Schedule, SI shall maintain true and accurate records in connection with the<br />
provision <strong>of</strong> the services and SI shall handover all the relevant records and<br />
documents upon the termination or expiry <strong>of</strong> the Contract.<br />
RFP Volume 3: Draft Legal Contract Page 82