Seven <strong>Liebherr</strong> top-slewing cranes<br />
of the EC-H, EC-B and HC series<br />
used on the construction of the new<br />
Daimler-Benz museum in Stuttgart.<br />
<strong>Job</strong>- <strong>Job</strong>-<br />
<strong>Report</strong> <strong>Report</strong>
EC-H, EC-B and HC cranes at work<br />
on the Daimler-Benz museum.<br />
A total of seven powerful <strong>Liebherr</strong> top-slewing cranes<br />
of the EC-H, EC-B and HC series are working on the<br />
construction of the new Daimler-Benz museum in<br />
Stuttgart.<br />
Two cranes have extraordinarily high free-standing towers.<br />
The highest tower crane, a 256 HC, has a hook height<br />
of 85.8 m; the 280 EC-B 12 Litronic has a hook height of<br />
73.7 m. With their 65-metre and 45-metre-long jibs, these<br />
cranes can cover their entire operating areas without<br />
restriction at their respective vertical working levels.<br />
Large 550 EC-H 20 Litronic crane<br />
The large 550 EC-H 20 Litronic crane with a hook height of<br />
49 m is positioned in the centre. At a working radius<br />
of 41.5 m, this crane still has a maximum lifting capacity of<br />
18 t at the jib head and is used to transport heavy steel<br />
and precast concrete sections.<br />
<strong>Liebherr</strong> crane fleet working at the Daimler-Benz museum:<br />
Printed in Germany by LBC-573-02.05-gb Subject to technical modifications.<br />
Please contact<br />
<strong>Liebherr</strong>-Werk Biberach GmbH, Postfach 16 63, D-88396 Biberach an der Riss<br />
� +49 7351 41-0, Telefax: +49 7351 41-22 25, www.liebherr.com, E-Mail: info.lbc@liebherr.com<br />
Four more cranes with 45 m jib each and hook heights<br />
between 30 m and 61 m support the three main cranes in<br />
handling building materials.<br />
Reliability and high load handling capacities<br />
In order to meet the tight completion deadlines, work on<br />
the construction site is proceeding 14 hours per day.<br />
Reliable operation and high load handling capacities are<br />
therefore demanded from the tower cranes used.<br />
All cranes work in two-fall operation in case of maximum<br />
load handling as well as at empty-hook speeds thus<br />
avoiding the need to change from two-fall to four-fall<br />
operation. This not only makes considerable time savings<br />
but also increases load handling capacity.<br />
Type Radius Hook height Max. capacity Capacity at jib head<br />
Crane 1: 550 EC-H 20 Litronic 41.5 m 49.0 m 20,000 kg 18,000 kg<br />
Crane 2: 256 HC 65.0 m 85.8 m 12,000 kg 3,200 kg<br />
Crane 3: 112 EC-H 10 45.0 m 61.4 m 10,000 kg 2,400 kg<br />
Crane 4: 280 EC-H 12 Litronic 45.0 m 60.3 m 12,000 kg 7,800 kg<br />
Crane 5: 280 EC-B 12 Litronic 45.0 m 73.7 m 12,000 kg 7,000 kg<br />
Crane 6: 112 EC-H 10 45.0 m 30.0 m 10,000 kg 2,400 kg<br />
Crane 7: 140 EC-H 6 Litronic 45.0 m 39.0 m 6,000 kg 3,700 kg