2j7YOwO

2j7YOwO 2j7YOwO

26.01.2017 Views

02 MARKET AND INDUSTRY TRENDS Hydropower capacity in Brazil increased in 2015 by 2.5 GW (2.8%), including 2.3 GW of large-scalei hydro (>30 MW) capacity, for a year-end total of 91.7 GW. 10 Despite the increase in capacity, hydropower output, at 382 TWh, dropped again (2.7% relative to 2014) due to continuing drought conditions. Between 2011 and 2015, Brazil’s hydropower output declined about 15%, even as capacity expanded by about 11%. 11 New capacity is being built in a manner to improve the power system’s resilience to drought. 12 In 2015, 17 additional 75 MW turbines (1,275 MW) became operational at Brazil’s Jirau plant, with just over 3 GW in place by year’s end. 13 Jirau’s sister plant, Santo Antonio (3.57 GW when completed), also along the Madeira River, added three units (212 MW) for a total of 2.5 GW. 14 Two units (728 MW) came online at the Teles Pires plant, which will yield 1.82 GW when completed. 15 The 11.2 GW Belo Monte was partially commissioned in early 2016, with full commissioning to follow when new transmission infrastructure is in place. Transmission lines continue to be one of the main bottlenecks for development of renewable energy projects in Brazil, with the majority of the country’s transmission projects behind schedule. 16 Turkey appears to be on track to achieve its target of 34 GW of hydropower capacity by 2023; this target is part of the country’s plan to pursue all available resources to meet rapidly growing electricity demand. 17 Turkey added 2.2 GW in 2015, bringing the total to 25.9 GW. 18 Hydropower production has been affected by severe fluctuations in rainfall: following a particularly dry period and sharp drop in output in 2014, production rebounded in 2015 by nearly 66%, to 66.9 TWh. 19 India ranked fourth for new installations. In 2015, the country brought online approximately 1.9 GW of new hydropower capacity, most (1.8 GW) of which was in the category of largescale hydro (>25 MW per facility), and ended the year with a total of 47 GW. Generation in 2015 was an estimated 135 TWh; output of large-scale facilities was 123 TWh, a drop of 5.7% from 2014. 20 Completed facilities included the 800 MW Koldam project; this plant in the lap of the Himalayas in the northern state of Himachal Pradesh was long-delayed due to ecological and geological concerns. 21 In the state of Uttarakhand, the 330 MW Shrinagar run-of-river project started operation, with a portion of the plant’s output designated for local consumption at no charge. 22 Neighbouring Bhutan completed the 126 MW Dagachhu runof-river station, the first transboundary Clean Development Mechanism (CDM) project registered with the UNFCCC. 23 All of the plant’s output is destined for the Indian power market. 24 In Nepal, construction of new plants, such as the 111 MW Rasuwagadi and the 456 MW Upper Tamakoshi, suffered severe setbacks due to damage from the April 2015 earthquake and its aftershocks. 25 Nepal temporarily lost 150 MW of hydropower capability (about 30% of total), exacerbating an already severe electricity shortfall. 26 Vietnam, which ranked fifth for installations, added a little over 1 GW of capacity in 2015. New capacity included the first of three 400 MW units at the Lai Chau plant; when completed, it will be Vietnam’s third largest hydropower facility. 27 The country also commissioned the first of two 260 MW units at the Huoi Quang plant, with the second to follow in 2016. 28 Serious drought conditions have depleted Vietnam’s reservoirs and strained hydropower production. 29 Several other countries in the region completed projects during the year, including: Malaysia brought online the remaining 708 MW of the 944 MW Murun plant; Lao PDR finalised about 600 MW, including the 180 MW Nam Ngiep 2 plant, which has specially designed turbines for its head height of 495 metres; and Cambodia bolstered its inadequate electricity supply with the 338 MW Russei Chrum River dam (financed and built by Chinese corporations). 30 Myanmar completed a 140 MW plant on the Paunglaung River, which the government considered a major success in dealing with challenges posed by rapidly increasing power demand and very limited access to electricity, while overcoming significant population resettlement challenges. 31 In March 2016, on the eve of the bi-annual meeting of the Mekong River Commission, China announced plans to release additional water into the downstream portions of the Mekong River, continuing into early April 2016 to help alleviate severe water shortages in the drought-stricken downstream countries of Lao PDR, Myanmar, Thailand, Cambodia and Vietnam. 32 In North America, the United States continued to rank third globally for installed hydropower capacity but added only 70 MW to its grid in 2015, for a year-end total of 79.7 GW. 33 The country experienced a fourth consecutive year of decline in output due to unfavourable hydrological conditions, with generation of 251 TWh, 7.6% below the average for the preceding decade. 34 Canada completed 0.7 GW of new facilities and expansions in 2015, raising total installed capacity to 79 GW, while maintaining output at 376 TWh for the year. 35 British Columbia’s Waneta expansion project added 335 MW to an existing facility, cost-effectively capturing power from flow that otherwise would be spilled. 36 Also in 2015, the 270 MW Romaine-1 project – the second of four planned cascading plants – was completed in Québec. 37 The Russian Federation continued to rank fifth globally for total installed capacity, adding a net of 143 MW in 2015 for a year-end total of 47.9 GW. 38 Hydropower generation (160 TWh) was down 4.1% relative to 2014. 39 RusHydro completed several refurbishment projects in 2015 and had plans to continue modernisation efforts for improved reliability, efficiency and security. 40 The Russian Federation's Boguchanskaya plant, which saw completion of the last of nine 333 MW units in late 2014, achieved an effective capacity of 3 GW when its vast reservoir finally reached design capacity in June 2015. 41 Following transmission and other plant upgrades, the effective capacity of the restored Sayano- Shushenskaya plant (6.4 GW) increased by another 700 MW, for a total of 5.1 GW. 42 In Africa, Ethiopia neared completion of its 1.87 GW Gibe III plant, after nine years of construction, bringing 2 of the project’s 10 turbines into service. Gibe III has one of the tallest concrete dams (246 metres) of its type in the world. 43 As of early 2016, UNESCO’s World Heritage Centre continued to monitor the project’s social and ecological impacts. 44 Once completed, the plant is expected to increase Ethiopia’s electricity supply significantly and to pave the way for the country to become a major power exporter. 45 i Brazil reports hydropower capacity separately by size category, at the thresholds of 1 MW (very small) and 30 MW (small). India reports hydropower above a threshold of 25 MW, separately from smaller facilities. 54

HYDROPOWER Figure 12. Hydropower Global Capacity, Shares of Top Six Countriesand Rest of World, 2015 Figure 14. Hydropower Global Capacity, Shares of Top Six Countries and Rest of World, 2015 China 27.9% Brazil 8.6% United States 7.5% Canada 7.4% Russian Federat. 4.5% Rest of World 39.7% Source: See endnote 2 for this section. India 4.4% Global capacity reached 1,064 GW Figure 13. Hydropower Capacity and Additions, Top Nine Countries for Capacity Added, 2015 Figure 15. . Hydropower Capacity and Additions, Top Nine Countries for Capacity Added, 2015 Gigawatts 300 250 + 16.1 100 Gigawatts + 2.5 Added in 2015 2014 total 200 80 + 0.7 02 150 60 + 1.9 100 40 + 2.2 50 0 China 20 0 + 1.0 + 0.6 + 0.7 + 0.6 Brazil Turkey India Vietnam Malaysia Canada Lao PDR Colombia Source: See endnote 5 for this section. Additions are net of repowering and retirements. RENEWABLES 2016 · GLOBAL STATUS REPORT 55

02 MARKET AND INDUSTRY TRENDS<br />

Hydropower capacity in Brazil increased in 2015 by 2.5 GW<br />

(2.8%), including 2.3 GW of large-scalei hydro (>30 MW) capacity,<br />

for a year-end total of 91.7 GW. 10 Despite the increase in capacity,<br />

hydropower output, at 382 TWh, dropped again (2.7% relative to<br />

2014) due to continuing drought conditions. Between 2011 and<br />

2015, Brazil’s hydropower output declined about 15%, even as<br />

capacity expanded by about 11%. 11 New capacity is being built in<br />

a manner to improve the power system’s resilience to drought. 12<br />

In 2015, 17 additional 75 MW turbines (1,275 MW) became<br />

operational at Brazil’s Jirau plant, with just over 3 GW in place<br />

by year’s end. 13 Jirau’s sister plant, Santo Antonio (3.57 GW when<br />

completed), also along the Madeira River, added three units<br />

(212 MW) for a total of 2.5 GW. 14 Two units (728 MW) came online<br />

at the Teles Pires plant, which will yield 1.82 GW when completed. 15<br />

The 11.2 GW Belo Monte was partially commissioned in early<br />

2016, with full commissioning to follow when new transmission<br />

infrastructure is in place. Transmission lines continue to be one<br />

of the main bottlenecks for development of renewable energy<br />

projects in Brazil, with the majority of the country’s transmission<br />

projects behind schedule. 16<br />

Turkey appears to be on track to achieve its target of 34 GW of<br />

hydropower capacity by 2023; this target is part of the country’s<br />

plan to pursue all available resources to meet rapidly growing<br />

electricity demand. 17 Turkey added 2.2 GW in 2015, bringing the<br />

total to 25.9 GW. 18 Hydropower production has been affected by<br />

severe fluctuations in rainfall: following a particularly dry period<br />

and sharp drop in output in 2014, production rebounded in 2015<br />

by nearly 66%, to 66.9 TWh. 19<br />

India ranked fourth for new installations. In 2015, the country<br />

brought online approximately 1.9 GW of new hydropower<br />

capacity, most (1.8 GW) of which was in the category of largescale<br />

hydro (>25 MW per facility), and ended the year with a total<br />

of 47 GW. Generation in 2015 was an estimated 135 TWh; output<br />

of large-scale facilities was 123 TWh, a drop of 5.7% from 2014. 20<br />

Completed facilities included the 800 MW Koldam project; this<br />

plant in the lap of the Himalayas in the northern state of Himachal<br />

Pradesh was long-delayed due to ecological and geological<br />

concerns. 21 In the state of Uttarakhand, the 330 MW Shrinagar<br />

run-of-river project started operation, with a portion of the plant’s<br />

output designated for local consumption at no charge. 22<br />

Neighbouring Bhutan completed the 126 MW Dagachhu runof-river<br />

station, the first transboundary Clean Development<br />

Mechanism (CDM) project registered with the UNFCCC. 23 All<br />

of the plant’s output is destined for the Indian power market. 24<br />

In Nepal, construction of new plants, such as the 111 MW<br />

Rasuwagadi and the 456 MW Upper Tamakoshi, suffered severe<br />

setbacks due to damage from the April 2015 earthquake and its<br />

aftershocks. 25 Nepal temporarily lost 150 MW of hydropower<br />

capability (about 30% of total), exacerbating an already severe<br />

electricity shortfall. 26<br />

Vietnam, which ranked fifth for installations, added a little over<br />

1 GW of capacity in 2015. New capacity included the first of<br />

three 400 MW units at the Lai Chau plant; when completed, it<br />

will be Vietnam’s third largest hydropower facility. 27 The country<br />

also commissioned the first of two 260 MW units at the Huoi<br />

Quang plant, with the second to follow in 2016. 28 Serious drought<br />

conditions have depleted Vietnam’s reservoirs and strained<br />

hydropower production. 29<br />

Several other countries in the region completed projects during<br />

the year, including: Malaysia brought online the remaining<br />

708 MW of the 944 MW Murun plant; Lao PDR finalised about<br />

600 MW, including the 180 MW Nam Ngiep 2 plant, which has<br />

specially designed turbines for its head height of 495 metres;<br />

and Cambodia bolstered its inadequate electricity supply with<br />

the 338 MW Russei Chrum River dam (financed and built by<br />

Chinese corporations). 30 Myanmar completed a 140 MW plant on<br />

the Paunglaung River, which the government considered a major<br />

success in dealing with challenges posed by rapidly increasing<br />

power demand and very limited access to electricity, while<br />

overcoming significant population resettlement challenges. 31<br />

In March 2016, on the eve of the bi-annual meeting of the<br />

Mekong River Commission, China announced plans to release<br />

additional water into the downstream portions of the Mekong<br />

River, continuing into early April 2016 to help alleviate severe<br />

water shortages in the drought-stricken downstream countries of<br />

Lao PDR, Myanmar, Thailand, Cambodia and Vietnam. 32<br />

In North America, the United States continued to rank third<br />

globally for installed hydropower capacity but added only 70 MW<br />

to its grid in 2015, for a year-end total of 79.7 GW. 33 The country<br />

experienced a fourth consecutive year of decline in output due<br />

to unfavourable hydrological conditions, with generation of 251<br />

TWh, 7.6% below the average for the preceding decade. 34<br />

Canada completed 0.7 GW of new facilities and expansions in 2015,<br />

raising total installed capacity to 79 GW, while maintaining output<br />

at 376 TWh for the year. 35 British Columbia’s Waneta expansion<br />

project added 335 MW to an existing facility, cost-effectively<br />

capturing power from flow that otherwise would be spilled. 36<br />

Also in 2015, the 270 MW Romaine-1 project – the second of four<br />

planned cascading plants – was completed in Québec. 37<br />

The Russian Federation continued to rank fifth globally for total<br />

installed capacity, adding a net of 143 MW in 2015 for a year-end<br />

total of 47.9 GW. 38 Hydropower generation (160 TWh) was down<br />

4.1% relative to 2014. 39 RusHydro completed several refurbishment<br />

projects in 2015 and had plans to continue modernisation efforts<br />

for improved reliability, efficiency and security. 40 The Russian<br />

Federation's Boguchanskaya plant, which saw completion of<br />

the last of nine 333 MW units in late 2014, achieved an effective<br />

capacity of 3 GW when its vast reservoir finally reached design<br />

capacity in June 2015. 41 Following transmission and other<br />

plant upgrades, the effective capacity of the restored Sayano-<br />

Shushenskaya plant (6.4 GW) increased by another 700 MW, for<br />

a total of 5.1 GW. 42<br />

In Africa, Ethiopia neared completion of its 1.87 GW Gibe III plant,<br />

after nine years of construction, bringing 2 of the project’s 10<br />

turbines into service. Gibe III has one of the tallest concrete dams<br />

(246 metres) of its type in the world. 43 As of early 2016, UNESCO’s<br />

World Heritage Centre continued to monitor the project’s social<br />

and ecological impacts. 44 Once completed, the plant is expected<br />

to increase Ethiopia’s electricity supply significantly and to pave<br />

the way for the country to become a major power exporter. 45<br />

i Brazil reports hydropower capacity separately by size category, at the thresholds of 1 MW (very small) and 30 MW (small). India reports hydropower above<br />

a threshold of 25 MW, separately from smaller facilities.<br />

54

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!