1. It is envisaged that the project stretch should be implemented on EPC/BOT<br />

basis, therefore, the Consultant shall study the financial viability of the project<br />

under a commercial format and under different user fee scenarios and funding<br />

options. The Consultants shall submit and finalise in consultation with the<br />

NHIDCL officers the format for the analysis and the primary parameters and<br />

scenarios that should be taken into account while carrying out the commercial<br />

analysis. The financial model so developed shall be the property of NHIDCL.<br />

2. The Financial analysis for the project should cover financial internal rate of<br />

return, projected income statements, balance sheets and fund flow statements<br />

and should bring out all relevant assumptions. The sensitivity analysis should<br />

be carried out for a number of probabilistic scenarios.<br />

3. The financial analysis should cover identification, assessment, and mitigating<br />

measures for all risks associated with the project. The analysis shall cover, but<br />

be not limited to, risks related to construction delays, construction costs<br />

overrun, traffic volume, revenue shortfalls, operating costs, exchange rate<br />

variations, convertibility of foreign exchange, interest rate volatility, noncompliance<br />

or default by contractors, political risks and force majeure.<br />

4. The Consultant shall suggest positive ways of enhancing the project Viability<br />

and furnish different financial models for implementing on BOT format.<br />

7. Time period for the service<br />

1. Time period envisaged for the study of the project is indicated in Annex-I to<br />

LOI. The final reports, drawings and documentation shall be completed within<br />

this time schedule.<br />

2. NHIDCL shall arrange to give approval on all sketches, drawings, reports and<br />

recommendations and other matters and proposals submitted for decision by<br />

the Consultant in such reasonable time so as not to delay or disrupt the<br />

performance of the Consultant’s services.<br />

8. Project Team and Project Office of the Consultant<br />

1. The Consultants shall be required to form a multi-disciplinary team for this<br />

assignment. The Consultants Team shall be manned by adequate number of<br />

experts with relevant experience in the execution of similar detailed design<br />

assignments.<br />

2. List of suggested key personnel to be fielded by the Consultant with<br />

appropriate man-month of consultancy services is given in Enclosure I as per<br />

clients assessment.<br />

3. A Manning Schedule for key personnel mentioned above is enclosed as<br />

Enclosure I along with broad job- description and qualification as Enclosure II.<br />

The information furnished in Enclosures I & II are to assist the Consultants<br />

to understand the client’s perception about these requirements and shall be<br />

taken by the Consultants for the purpose of Financial Proposal and<br />

deployment schedule etc. in technical proposal to be submitted by them. Any<br />

deviation proposed may be recorded in the comments on TOR. All the key<br />

personnel mentioned will be evaluated at the time of evaluation of technical<br />

proposal. Consultants are advised in their own interest to frame the technical