(c)<br />

Notwithstanding Clause 6.1(b) hereof, if pursuant to Clauses 5.4 hereof, the Parties<br />

shall agree that additional payments shall be made to the Consultants in order to cover<br />

any necessary additional expenditures not envisaged in the cost estimates referred to<br />

in Clause 6.1(a) above, the ceiling set forth in Clause 6.1(b) above shall be increased by<br />

the amount or amounts, as the case may be, of any such additional payments.<br />

6.2 Currency of Payment<br />

(a) The payment shall be made in Indian Rupees.<br />

6.3 Mode of Billing and Payment<br />

Billing and payments in respect of the Services shall be made as follows:-<br />

(a)<br />

(b)<br />

The Client shall cause to be paid to the Consultants an advance payment as specified<br />

in the SC, and as otherwise set forth below. The advance payment will be due after<br />

provision by the Consultants to the Client of a bank guarantee by a bank acceptable to<br />

the Client in an amount (or amounts) and in a currency (or currencies) specified in the<br />

SC, such bank guarantee (i) to remain effective until the advance payment has been<br />

fully set off as provided in the SC, and ii) in such form as the Client shall have<br />

approved in writing.<br />

Payment Schedule<br />

The Consultant will be paid stage-wise as a percentage of the contract value as per the<br />

schedule given below:<br />

Payment as % of<br />

S. No. Item<br />

Contract Value<br />

On submission of Quality Assurance Plan<br />

5 %<br />

1 and Inception Report<br />

On submission of Draft Feasibility Study<br />

20 %<br />

2 Report including Option Study Report<br />

On Submission of Final Feasibility Study<br />

10 %<br />

3 Report<br />

On submission of Technical Schedules<br />

10 %<br />

4 for EPC projects<br />

5 On submission of Draft DPR 15 %<br />

6 On approval of DPR 10 %<br />

7<br />

On completion of Project Clearances (20<br />

%)<br />

(i)Completion of 3a, 3A and 3D&3G 10 %<br />

(ii)Forest clearance and environmental<br />

5 %<br />

Clearance<br />

(iii)Utility Shifting 5 %<br />

8<br />

On Appointed Date of civil contract of All 10%<br />

Packages*<br />

Total 100%