led to the establishment of the department ”Configuration<br />

Control” whose tasks became to ensure collision-free operation<br />

at all times. These two new departments were combined<br />

with the department ”Design Office” under the umbrella of<br />

one subdivision in order to simplify fast and effective collaboration<br />

between departments that naturally interact<br />

strongly with one another. After about a half year of operation<br />

this organisation has shown its effectiveness in supporting<br />

the device assembly on all aspects by implementing well<br />

defined fast and transparent work flows with a clear distribution<br />

of responsibilities and comprehensive and up-to-date<br />

documentation.<br />

5.1 Configuration Management<br />

The department Configuration Management (DC-CM) plans,<br />

implements and leads the processes that are required to<br />

ensure permanent consistency between the requirements of<br />

the W7-X system specification and the performance attributes<br />

of its components throughout the life time of the<br />

project. The detailed tasks of DC-CM are oriented at the<br />

common standards of configuration management (CM).<br />

CM for W7-X is being implemented with most efficient use<br />

and interlink of existing processes (change request, nonconformances,<br />

interface control, collision control) and tools<br />

(KKS project structure, the PLM-system, data bases).<br />

5.1.1 Change Management<br />

Change Management (CM) controls all change processes,<br />

preserves configuration control at the interfaces, ensures<br />

documentation and consistent implementation in the configuration<br />

of all changes and variances, and provides orderly<br />

communication of change information within the project.<br />

This includes that CM enables change and non-conformance<br />

decisions to be based on the knowledge of complete<br />

change impact. Processes are controlled via a data base.<br />

Highest priority is given to fast handling of change and<br />

non-conformance processes which are time-critical and<br />

might affect the schedule of device assembly. These are<br />

actively guided and driven by CM and thus accelerated.<br />

CM supports preparation and documentation of the configuration<br />

control board (CCB) meetings and the implementation<br />

of its decisions.<br />

5.1.2 Configuration Status Accounting<br />

A PLM-based concept for the W7-X system documentation<br />

has been implemented. It will give access to the complete<br />

configuration information and finally replace the previous<br />

system specification. A central master document for each<br />

W7-X component, the so called loose leaf book, provides<br />

the description of the function of a component and its positioning<br />

in the project structure and the CAD assembly.<br />

Additionally, the loose leaf book is a navigation tool (via<br />

references in the document and links in the PLM system)<br />

Wendelstein 7-X<br />

45<br />

to access specifications, data sheets, interface descriptions,<br />

design changes, and variances that result from non-conformances.<br />

Provision of interface descriptions and accounting<br />

for change impacts across the interfaces is coordinated by<br />

CM. Masses, materials and their composition are documented<br />

for all components within the torus hall in a material<br />

data base. Additionally, the data base documents the certified<br />

relative magnetic permeability of the materials used and<br />

their certified cobalt content as a basis for assessment of<br />

magnetic field errors and to keep track of the amount of<br />

cobalt, which is limited by the authorities due to its high<br />

neutron activation rate.<br />

5.2 Configuration Control<br />

The main missions of the department Configuration<br />

Control (CC) are to ensure collision-free operation of W7-X<br />

for all modes of operation and to coordinate the space<br />

requests of peripheral components in the torus hall and<br />

adjacent buildings. This is being accomplished by developing<br />

the required tools for generating and book-keeping of<br />

the CAD models of the relevant components by performing<br />

the collision checks and finally by initiating and leading the<br />

processes required to eliminate detected conflicts in collaboration<br />

with CM. W7-X is undoubtedly a device with<br />

high geometrical complexity. Especially in the cryostat one<br />

has to deal with three-dimensional free-form shapes of the<br />

coils snugly located between the heat shields of the thermal<br />

insulation of the plasma vessel and the ports, the coil support<br />

structure the meandering lines of the bus-bars and the cryogenic<br />

helium supply, the diagnostic and quench detection<br />

cables and all the required supports and additional components.<br />

Figure 19 illustrates this situation in the cryostat.<br />

Figure 19: Module 5 of the cryostat (outer vessel shell omitted)