Sci Electric Public Company Limited<br />

The new power production capacity during the period from <strong>2015</strong>-2036 is equal to 57,467 megawatt classified by the<br />

category of power plants as follows:<br />

Power Production Capacity<br />

Megawatt<br />

1. Renewable energy plants 12,250<br />

2. Pumped-storage plants 2,101<br />

3. Clean coal plants 7,365<br />

4. Natural Gas Plants 17,478<br />

5. Nuclear energy plants 2,000<br />

6. Gas turbine plants 1,250<br />

7. Cogeneration plants 4,052<br />

8. Purchased from foreign country 11,016<br />

Total 57,467<br />

Based on the present Power Production Capacity Development Plan, related organizations and business enterprises eventually<br />

map out their plans to procure power energy and increase their power production capacity in order to back up the<br />

growing needs of the power energy consequently resulting in the power production industry to expand; power plant development,<br />

the needs of high voltage stations, transmission cables, high voltage towers and general steel fabrications for substations<br />

to substantially increase. From 2012 to 2014, length of the transmission cables and number of high voltage stations in the<br />

country had a trend of an increase all along in accordance with the needs of power and the more increasing power productions.<br />

At present, EGAT is under the process of the transmission cable system development in Northeastern Region to be the size<br />

of 500 kV from the original size of 230 kV in 3 Projects; to wit; 1) Transmission cables to back up Xayaboury Project, 2) Transmission<br />

cables to back up Nam Ngum Project, 3) Transmission cables to link up Eastern Seaboard with Lower Northeastern Region where<br />

the construction of which is expected to gradually complete during the period of 2018 and 2019 and that the power of 2,000<br />

megawatt can be additional received. All constructions will be complete approximately 2024. For the reason that EGAT’s<br />

responsible areas (throughout the country except Bangkok and its perimeter) are beyond the capability of the transmission<br />

cables to take power from renewable energy which would be only 2,000 megawatt within 2018, the additional investment is<br />

therefore necessarily possible. In this connection, the draft of PDP <strong>2015</strong> contains the plan on the electrical system infrastructure<br />

investments in which the transmission and power distribution system to back up ASEAN Economic Community or AEC and<br />

Greater Mekong Sub-region as well as Smart Grid Network in order that the power management can be more efficiently handled<br />

will be developed and ready to take the renewable energy at higher proportion.<br />

Source: Ministry of Energy, Krungthep Turakij newspaper, Prachachart Thurakit newspaper.<br />

Renewable Energy Power Plant Industry Situation<br />

Renewable energy power plant industry situation of Lao PDR in relation to renewable energy are from many origins of<br />

energy such as solar cell energy, wind energy, hydropower energy, biomass, biogas and garbage, etc. Such origins of energy<br />

have caused the rising of the power plants from producing organizations and the consumptions of consumer origins differently<br />

in Lao PDR. In this respect, the power has not yet been thoroughly expanded to household consumer origins while the production<br />

origins in Lao PDR have produced the power for distributions to foreign countries, as well. Because of the reason that the origins<br />

to cause the rising of power energy in Lao PDR, most of the investors have still foreseen that the investments in such part are<br />

still potentially worthwhile due to the reason that the sources of resources for use in the productions are still abundant.<br />