Strategic Moves - Regional Environmental Center for Central and ...

Strategic Moves - Regional Environmental Center for Central and ... Strategic Moves - Regional Environmental Center for Central and ...

07.12.2012 Views

tion of a new Podgorica landfill and recycling centre have been completed and the third phase (recycling centre) has secured significant financing from local and state funds and from the Spanish Government. The remaining EUR 4.3 million are expected to be financed from the state budget. For the project for the construction of a hazardous waste landfill in Montenegro (EUR 9.17 million), an application for IPA financing has been completed and submitted, thus it is highly likely to receive sufficient financing. Many projects that are still on the list also recorded progress between 2007 and 2009. Four of these projects are from the waste sector and 10 from the water sector. These projects have secured a total of EUR 64.55 million to date. In Serbia, a total of EUR 22.7 million was secured for PEIP projects in the period 2007–2009. In total, four projects saw progress, two of which were removed from the lists having successfully secured funding (EUR 20.6 million in total). The project for equipment supply for the recultivation and preservation of the ash and slag deposit at Kolubara (EUR 2 million from own funds) is a relatively small but environmentally important waste project. The other project removed from the lists was a major project in the water sector: the project for the upgrade and extension of the wastewater treatment plant in Subotica. A total of EUR 17.7 million was secured from EAR, the EBRD and municipal funds, and construction started in June 2009. The remaining EUR 0.9 million will be secured through PUC tariff collection. The project included the design of a new tariff system. The other two projects that saw improvements but remained on the lists are both from the waste sector: a project for the remediation of the Nis landfill, where additional funds were secured from the city budget; and a relatively new project on the PEIP lists, for a hazardous waste management facility (phase 1), for which EUR 3 million of the EUR 14 million required in total have been secured through the IPA to prepare a feasibility study. General observations • Developing and updating the PEIP priority lists of projects has been a major learning exercise for the SEE countries. However, for many of the projects it is still difficult to obtain adequate data. • Those projects that made more rapid progress had good-quality project documentation from the outset, and PUC staff had actively participated in the preparation of the documents. • At national level, strong project preparation units are a driving force, as demonstrated in Croatia, Montenegro and Serbia. • The benchmarking and self-assessment of PUCs in order to improve their operational efficiency has proved to have a beneficial effect on project preparation and reform capacities. • The IPA application process provided project preparation capacity building at both local and national level. The proper inclusion of stakeholders from the beginning of the process ensured that any potential problems in relation to location or similar issues were resolved in time. C H A P T E R 8 P R I O R I T I S AT I O N O F I N F R A S T R U C T U R E P R O J E C T S — T H E P E I P L I S T S S T R AT E G I C M O V E S 201

202 S T R AT E G I C M O V E S

tion of a new Podgorica l<strong>and</strong>fill <strong>and</strong> recycling centre have been completed <strong>and</strong> the<br />

third phase (recycling centre) has secured significant financing from local <strong>and</strong> state<br />

funds <strong>and</strong> from the Spanish Government. The remaining EUR 4.3 million are expected<br />

to be financed from the state budget. For the project <strong>for</strong> the construction of<br />

a hazardous waste l<strong>and</strong>fill in Montenegro (EUR 9.17 million), an application <strong>for</strong> IPA<br />

financing has been completed <strong>and</strong> submitted, thus it is highly likely to receive sufficient<br />

financing. Many projects that are still on the list also recorded progress between<br />

2007 <strong>and</strong> 2009. Four of these projects are from the waste sector <strong>and</strong> 10 from the<br />

water sector. These projects have secured a total of EUR 64.55 million to date.<br />

In Serbia, a total of EUR 22.7 million was secured <strong>for</strong> PEIP projects in the period<br />

2007–2009. In total, four projects saw progress, two of which were removed<br />

from the lists having successfully secured funding (EUR 20.6 million in total). The<br />

project <strong>for</strong> equipment supply <strong>for</strong> the recultivation <strong>and</strong> preservation of the ash <strong>and</strong> slag<br />

deposit at Kolubara (EUR 2 million from own funds) is a relatively small but environmentally<br />

important waste project. The other project removed from the lists was<br />

a major project in the water sector: the project <strong>for</strong> the upgrade <strong>and</strong> extension of the<br />

wastewater treatment plant in Subotica. A total of EUR 17.7 million was secured<br />

from EAR, the EBRD <strong>and</strong> municipal funds, <strong>and</strong> construction started in June 2009.<br />

The remaining EUR 0.9 million will be secured through PUC tariff collection. The<br />

project included the design of a new tariff system. The other two projects that saw improvements<br />

but remained on the lists are both from the waste sector: a project <strong>for</strong> the<br />

remediation of the Nis l<strong>and</strong>fill, where additional funds were secured from the city<br />

budget; <strong>and</strong> a relatively new project on the PEIP lists, <strong>for</strong> a hazardous waste management<br />

facility (phase 1), <strong>for</strong> which EUR 3 million of the EUR 14 million required<br />

in total have been secured through the IPA to prepare a feasibility study.<br />

General observations<br />

• Developing <strong>and</strong> updating the PEIP priority lists of projects has been a major<br />

learning exercise <strong>for</strong> the SEE countries. However, <strong>for</strong> many of the projects it is<br />

still difficult to obtain adequate data.<br />

• Those projects that made more rapid progress had good-quality project documentation<br />

from the outset, <strong>and</strong> PUC staff had actively participated in the<br />

preparation of the documents.<br />

• At national level, strong project preparation units are a driving <strong>for</strong>ce, as demonstrated<br />

in Croatia, Montenegro <strong>and</strong> Serbia.<br />

• The benchmarking <strong>and</strong> self-assessment of PUCs in order to improve their operational<br />

efficiency has proved to have a beneficial effect on project preparation<br />

<strong>and</strong> re<strong>for</strong>m capacities.<br />

• The IPA application process provided project preparation capacity building at<br />

both local <strong>and</strong> national level. The proper inclusion of stakeholders from the<br />

beginning of the process ensured that any potential problems in relation to location<br />

or similar issues were resolved in time.<br />

C H A P T E R 8<br />

P R I O R I T I S AT I O N O F I N F R A S T R U C T U R E P R O J E C T S — T H E P E I P L I S T S<br />

S T R AT E G I C M O V E S 201

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!