07.12.2012 Views

Strategic Moves - Regional Environmental Center for Central and ...

Strategic Moves - Regional Environmental Center for Central and ...

Strategic Moves - Regional Environmental Center for Central and ...

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

FIGURE 26: Number of projects on the PEIP lists in 2007 <strong>and</strong> 2009 by sector<br />

80<br />

70<br />

60<br />

50<br />

40<br />

30<br />

20<br />

10<br />

0<br />

2007 2009<br />

Source: REC national PEIP lists<br />

at their own expense <strong>and</strong> do not there<strong>for</strong>e require assistance from national or international<br />

environmental institutions <strong>and</strong> funds. In the waste sector, the number<br />

of projects on the priority lists related to the remediation of hotspots also declined.<br />

These projects had a high level of national importance <strong>and</strong>, in many cases, have already<br />

been successfully implemented.<br />

Croatia moved <strong>for</strong>ward in terms of both the number of projects with significant<br />

progress <strong>and</strong> the total funds secured <strong>for</strong> these projects. As an EU c<strong>and</strong>idate country,<br />

most of the funds <strong>for</strong> project preparation came from the IPA. Funds <strong>for</strong> actual<br />

implementation came from the earlier Phare <strong>and</strong> CARDS programmes. These were<br />

supplemented mostly by earmarked state funds. The IPA accreditation process was<br />

challenging but provided experience that enhanced capacities <strong>for</strong> project preparation<br />

at national, regional <strong>and</strong> local level.<br />

Other countries relied mainly on bilateral donors <strong>and</strong> IFI funding, as national<br />

funds available <strong>for</strong> environmental investments are generally scarce. Among the IFIs,<br />

Kf W applied the practical <strong>and</strong> stimulative approach of the benchmarking <strong>and</strong> selfassessment<br />

of PUCs as a precondition <strong>for</strong> loans, which proved beneficial <strong>for</strong> project<br />

preparation <strong>and</strong> <strong>for</strong> increasing re<strong>for</strong>m capacities, especially at the local level.<br />

Figure 25 shows that the biggest decrease in the net number of projects took<br />

place in Albania in the 2007 to 2009 period. During this period, six projects were<br />

C H A P T E R 8<br />

P R I O R I T I S AT I O N O F I N F R A S T R U C T U R E P R O J E C T S — T H E P E I P L I S T S<br />

Waste Water Air<br />

S T R AT E G I C M O V E S 191

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!