FIGURE 26: Number of projects on the PEIP lists in 2007 <strong>and</strong> 2009 by sector<br />
80<br />
70<br />
60<br />
50<br />
40<br />
30<br />
20<br />
10<br />
0<br />
2007 2009<br />
Source: REC national PEIP lists<br />
at their own expense <strong>and</strong> do not there<strong>for</strong>e require assistance from national or international<br />
environmental institutions <strong>and</strong> funds. In the waste sector, the number<br />
of projects on the priority lists related to the remediation of hotspots also declined.<br />
These projects had a high level of national importance <strong>and</strong>, in many cases, have already<br />
been successfully implemented.<br />
Croatia moved <strong>for</strong>ward in terms of both the number of projects with significant<br />
progress <strong>and</strong> the total funds secured <strong>for</strong> these projects. As an EU c<strong>and</strong>idate country,<br />
most of the funds <strong>for</strong> project preparation came from the IPA. Funds <strong>for</strong> actual<br />
implementation came from the earlier Phare <strong>and</strong> CARDS programmes. These were<br />
supplemented mostly by earmarked state funds. The IPA accreditation process was<br />
challenging but provided experience that enhanced capacities <strong>for</strong> project preparation<br />
at national, regional <strong>and</strong> local level.<br />
Other countries relied mainly on bilateral donors <strong>and</strong> IFI funding, as national<br />
funds available <strong>for</strong> environmental investments are generally scarce. Among the IFIs,<br />
Kf W applied the practical <strong>and</strong> stimulative approach of the benchmarking <strong>and</strong> selfassessment<br />
of PUCs as a precondition <strong>for</strong> loans, which proved beneficial <strong>for</strong> project<br />
preparation <strong>and</strong> <strong>for</strong> increasing re<strong>for</strong>m capacities, especially at the local level.<br />
Figure 25 shows that the biggest decrease in the net number of projects took<br />
place in Albania in the 2007 to 2009 period. During this period, six projects were<br />
C H A P T E R 8<br />
P R I O R I T I S AT I O N O F I N F R A S T R U C T U R E P R O J E C T S — T H E P E I P L I S T S<br />
Waste Water Air<br />
S T R AT E G I C M O V E S 191