04.01.2016 Views

Harnessing Solar energy, Options for India

A study on harnessing solar energy options for India was conducted recently by Shakti Sustainable Energy Foundation, Climate works Foundation and SSN foundation. Supporting this study it has been concluded that solar energy can play a big role in providing electricity to rural areas and thus has been included in India’s rural electrification policy. See more at: http://shaktifoundation.in/report/harnessing-solar-energy-options-for-india/

A study on harnessing solar energy options for India was conducted recently by Shakti Sustainable Energy Foundation, Climate works Foundation and SSN foundation. Supporting this study it has been concluded that solar energy can play a big role in providing electricity to rural areas and thus has been included in India’s rural electrification policy. See more at: http://shaktifoundation.in/report/harnessing-solar-energy-options-for-india/

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

3. Concentrated <strong>Solar</strong> Power Projections<br />

Given the current status of CSP globally and in <strong>India</strong>, it is difficult to <strong>for</strong>esee how the technology will<br />

unfold in <strong>India</strong>, and what the market share of each of the three technologies – parabolic trough,<br />

linear Fresnel mirrors and the power tower – will be. Even the price quoted per megawatt <strong>for</strong> CSP<br />

technologies varies a great deal, with most price points being drawn from the parabolic trough<br />

technology. Keeping in mind the difficulties here, cost curves are not projected. The generationbased<br />

incentive is projected as follows: till 2013 it is held fixed at `15.31 (current tariff), reduced at<br />

5% annually till 2017 (end of Phase 2), and then reduced at an annual rate of 10% till 2022. For<br />

capacity addition, three scenarios are projected <strong>for</strong> 2022; 1,000 MW, 4,250 MW and 8,000 MW will<br />

be the cumulative deployment in 2022. The assumption here is that scaling up CSP in <strong>India</strong> is<br />

difficult under normal circumstances. Even in an optimistic scenario, the achievement will be lower<br />

than the JNNSM target.<br />

4. Additional Tariff per Unit of Electricity<br />

Under the three scenarios considered, the total installed capacity of PV and CSP together would be<br />

6,000 MW, 14,250 MW and 20,000 MW respectively. Considering the weighted average of<br />

generation-based incentives (GBI ) of PV and CSP, <strong>for</strong> capacity additions in each of the scenarios, the<br />

annual outlay <strong>for</strong> the payment of tariffs would be `940 million in the fiscal year 2010–11, assuming a<br />

total capacity addition of 30 MW of PV by the year end. The total outlay <strong>for</strong> tariff payments in 2022–<br />

23 would be `130, `310 and `415 billions <strong>for</strong> a total installed capacity of 6,000 MW to 20,000 MW<br />

in the three scenarios. According to these assumptions, the total net present value of all the tariffs<br />

(annual power purchase agreements [PPAs] signed <strong>for</strong> a twenty-five-year period) will amount to<br />

`620, `1500 and `1800 billion <strong>for</strong> the three scenarios respectively.<br />

The entire cash outlay towards payment of tariffs is currently expected to come from increase in<br />

electricity tariff. Gross generation of electricity (utility and non-utility) <strong>for</strong> the year 2009–10 <strong>for</strong> all<br />

of <strong>India</strong> was 862 billion kWh. a Assuming a 9% GDP growth and a GDP-to-electricity elasticity of 0.9,<br />

the generation in 2021–22 could be around 2,200 billion units. The net electricity supplied in 2009–<br />

10 was 681 billion units and in 2022 it will be 1,616 billion units. b<br />

However, to keep the analysis simple, it is assumed that the annual outlay <strong>for</strong> solar tariff <strong>for</strong> a<br />

particular year is borne by the electricity (grid) consumers of that year. Further, it is assumed that<br />

the cost of the tariff is evenly distributed to all customers without differentiating based on<br />

consumption levels. In the current year, it is assumed (generously) that 30 MW of solar PV will be<br />

installed in all three scenarios. The total electricity generated this year will be a maximum of 53<br />

million kWh. c The total tariff cost associated with this will be around `940 millon, d but when<br />

distributed over around 681 billion units of electricity, it works out to be less than a paisa per unit.<br />

However, by 2022 the installed capacity (PV and CSP) will be significant at 6,000 MW, 14,250 MW<br />

and 20,000 MW in the three scenarios respectively. The total generation associated with these<br />

installations will be 11 billion kWh, 25 billion kWh and 35 billion kWh respectively. Distributing this<br />

over the number of units of electricity supplied, it works out that the additional tariff <strong>for</strong> each unit<br />

a Gross generation from utilities is 772 billion kWh (Ministry of Power) plus 90 billion kWh of captive<br />

generation (estimate).<br />

b Assumption: 7% auxiliary consumption and 15% T&D losses.<br />

c Assumption: the capacity utilisation factor (CUF) is 20% or 1,752 MWh of generation per MW of installed<br />

capacity.<br />

d At `17.91 per kWh of current tariff this year <strong>for</strong> solar PV. No CSP-based generation is assumed this year.<br />

Cumulative Capacity, Grid Parity and Cost CSTEP | Page 54

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!