Minnesota River Basin <strong>Watershed</strong> <strong>Achievements</strong> <strong>Report</strong> 2015<br />

9. Permanent easements are a difficult sell.<br />

10. Interest in filter strips dropped off as commodity<br />

prices increased.<br />

11. Requiring escrows from the land owners helped<br />

make sure they followed through on applications and<br />

that the SWCDs did not spend a lot of time designing<br />

only to have the application canceled. We only had<br />

three cancellations over the course of the project.<br />

12. Staff time providing technical assistance was critical<br />

and was an additional project cost of about 35% to<br />

50% (as a percentage of the BMPs).<br />

13. Encumber the dollars early so that the last year of the<br />

project is spent finishing projects.<br />

14. Over-encumber some of the dollars in anticipation<br />

that some of the applicants will not get their practices<br />

completed. The Scott WMO could do this since the<br />

grant was not the only source of funding for the<br />

Technical Assistance and Cost Share (TACS) program<br />

and therefore could still fund all the projects even if<br />

they all finished on time – otherwise there is a risk.<br />

The partners are appreciative of the support provided<br />

by the USEPA and MPCA through the grant. The only<br />

suggestions we have for improving the program are:<br />

1. To review the grant contract language from<br />

the perspective of the receiving local unit of<br />

government. The language is a little one sided<br />

toward the agencies when the grant recipient is<br />

providing 45% to 50% of the project cost. Should<br />

reflect more of a partnership.<br />

2. Keep the same reporting form every year. Having<br />

to use a new form every year requires unproductive<br />

time to populate repeat information.<br />

Financial information<br />

Funding type: Section 319<br />

Grant amount: $489,765<br />

In-kind: $30,971<br />

Matching funds: $424,143<br />

Contact information<br />

Paul Nelson, Environmental Services Program Manager<br />

Scott County<br />

200 Fourth Avenue West<br />

Shakopee, MN 55379<br />

952-496-8054<br />

pnelson@co.scott.mn.us<br />

MPCA Project Manager: Chris Zadak<br />

After<br />

Before<br />

Maynard Schmidt, 27740 Keystone Lane, Belle Plaine, Minnesota<br />

– Grade Stabilization<br />

This project addressed a head cut of a large ravine in the Blakeley<br />

bluff area that was eroding due to runoff and groundwater<br />

seeps, and a cattle access lane. Multiple conservation practices<br />

including a water and sediment control basin, check dams,<br />

critical area shaping, subsurface drainage, livestock exclusion<br />

and water bars were installed to stabilize this site<br />

Minnesota Pollution Control Agency www.pca.state.mn.us 72