Upgrade SAP Business Warehouse to release 7.40

1OvZJLn

1OvZJLn

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

3 Usage of the ASU <strong>to</strong>olbox for <strong>SAP</strong> BW<br />

Typical project duration 6-8 weeks for a 3-system landscape<br />

<strong>Upgrade</strong> Tasks<br />

<strong>Upgrade</strong> Planning<br />

<strong>Upgrade</strong> of Development<br />

Steps/Miles<strong>to</strong>nes<br />

3d<br />

3d + 1w Test<br />

<strong>Upgrade</strong> of Test<br />

Additional testing<br />

3d + 1w Test<br />

Ongoing (several weeks)<br />

<strong>Upgrade</strong> of Production<br />

<strong>SAP</strong> Java Server/EP<br />

Setup of BWA or BW on HANA<br />

Start after first <strong>Upgrade</strong> (2d/Sys.)<br />

3d<br />

Start after System readiness<br />

Go Live BWA or BW on HANA<br />

2w<br />

<strong>to</strong>day 6 weeks 8 weeks<br />

Legend: Duration Miles<strong>to</strong>ne<br />

Time in <strong>to</strong>tal: 9d <strong>Upgrade</strong>, 10+d testing, 6d Java Inst, 9d het. Systemcopy, conversion IC/DSO individually, BW on HANA testing individually<br />