3 Usage of the ASU <strong>to</strong>olbox for <strong>SAP</strong> BW<br />
Typical project duration 6-8 weeks for a 3-system landscape<br />
<strong>Upgrade</strong> Tasks<br />
<strong>Upgrade</strong> Planning<br />
<strong>Upgrade</strong> of Development<br />
Steps/Miles<strong>to</strong>nes<br />
3d<br />
3d + 1w Test<br />
<strong>Upgrade</strong> of Test<br />
Additional testing<br />
3d + 1w Test<br />
Ongoing (several weeks)<br />
<strong>Upgrade</strong> of Production<br />
<strong>SAP</strong> Java Server/EP<br />
Setup of BWA or BW on HANA<br />
Start after first <strong>Upgrade</strong> (2d/Sys.)<br />
3d<br />
Start after System readiness<br />
Go Live BWA or BW on HANA<br />
2w<br />
<strong>to</strong>day 6 weeks 8 weeks<br />
Legend: Duration Miles<strong>to</strong>ne<br />
Time in <strong>to</strong>tal: 9d <strong>Upgrade</strong>, 10+d testing, 6d Java Inst, 9d het. Systemcopy, conversion IC/DSO individually, BW on HANA testing individually<br />