<strong>Jail</strong> <strong>Management</strong> <strong>System</strong> (JMS)<br />

Sheriff's Office- JMS Report<br />

February 2012<br />

Audit Response - April 25, 2012<br />

Recommendation B: MCSO should limit developers' access to JMS and/or implement<br />

system monitoring controls to identify and review the appropriateness of system changes.<br />

Response: Concur. This issue will be addressed in the formal change management<br />

process referenced above.<br />

Target Completion Date: 1/31/13<br />

Benefits/Costs: Increased accountability and control.<br />

Issue #5:<br />

MCSO does not have a formal IT strategic plan or project management process that<br />

effectively aligns IT resource spending with MCSO's core mission. A strategic plan<br />

helps ensure that critical IT projects are completed efficiently and economically.<br />

Recommendation A: MCSO should consider developing an IT strategic plan that<br />

supports the overall MCSO strategy.<br />

Response: Concur. As a requirement of the Board of Supervisors' Resolution dated June<br />

20,2011, MCSO and OET are reviewing current systems and future requirements to<br />

develop a strategic technology roadmap for MCSO. This comprehensive plan will closely<br />

align technology initiatives with MCSO core business functions.<br />

Target Completion Date: 12/31/12<br />

Benefits/Costs: Increased accountability and control.<br />

Recommendation B: MCSO should consider developing a formalized project<br />

management methodology to help manage and control IT-related projects.<br />

Response: Concur. MCSO recognizes the importance of a formalized project<br />

management methodology. As additional personnel are employed based upon the<br />

staffing study currently in process, resources will be applied to formalizing the project<br />

management process.<br />

Target Completion Date: 4/30/13<br />

Benefits/Costs: Increased accountability and control.<br />