07.12.2012 Views

Yards Moving Forward - GL Group

Yards Moving Forward - GL Group

Yards Moving Forward - GL Group

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

of pipelines?<br />

in order to identify those parameters critical to the risk of the<br />

whole system. Semi-quantitative methods have been found to<br />

be adequate for such an analysis, enabling the most costeffective<br />

remedial measures to be taken for any identified<br />

risks. Using a stepwise, semi-quantitative method, the riskdriving<br />

parameters and the quantification of the risk for a<br />

pipeline network can be calculated.<br />

<strong>GL</strong> Methodology<br />

The <strong>GL</strong> methodology splits the pipeline system to be<br />

assessed into different sections, called TAGs. Each TAG is<br />

deemed to have a relatively constant risk associated with it<br />

because the physical characteristics of the section and its<br />

environment remain unchanged. However, each change in<br />

the pipe’s wall thickness, or a known damage, for example, or<br />

a change in water depth for an offshore pipeline, would require<br />

a split into different TAGs. Consequence-specific factors<br />

will also impact how a pipeline system is split up into TAGs.<br />

Such factors include pipeline location, volumes transported<br />

and the product being transported. For land pipeline the<br />

location factor would take into account aspects such as population<br />

density, road crossings and the proximity of buildings<br />

for a given area along the route. In addition, the risk assessment<br />

must accommodate any readjustments, such as the<br />

construction of new installations in the vicinity of the pipeline,<br />

that may take place over time.<br />

The <strong>GL</strong> methodology also utilizes an index-based<br />

approach to risk evaluation. Risk is presented by using a risk<br />

matrix to provide a clear overview of the relative contribution<br />

of the probability of failure (PoF) and consequence of failure<br />

(CoF) factors. Considerable effort is required to estimate the<br />

PoF factor and criteria such as design, operation, third party<br />

impact and corrosion are weighed up in the analysis.<br />

Consequences considered in the determination of the CoF<br />

factor include human safety, environmental impact, economic<br />

repercussions and reputational/political fallout.´The<br />

PoF and CoF factors are incorporated in the <strong>GL</strong> Index which is<br />

used to indicate the relative severity of the risk. The highest<br />

risk is when both the PoF and CoF are serious. Risk acceptance<br />

criteria are the limits above which the operator will not<br />

tolerate risk to the installation.<br />

Optimising Pipeline Inspections<br />

Risk acceptance criteria are also used to help determine<br />

the most appropriate type of inspection and the optimum<br />

timing for inspections of relevant parts of the pipeline system.<br />

SAFETY PRECAUTION<br />

Obviously, it is important that an inspection is carried out<br />

prior to the acceptance limit being breached. This could be<br />

likened to preventative maintenance. Timely inspections will<br />

enable not only a reassessment of the risk level based upon<br />

the gathering of firsthand information onsite but also the<br />

detailed evaluation of any damage. Such an evaluation could<br />

necessitate the timely repair or replacement of the degraded<br />

component, i.e. corrective maintenance. The main reason for<br />

implementing a risk-based approach to inspection planning<br />

is to focus inspection efforts on items where the safety, economic,<br />

environmental or reputational risks are identified as<br />

being high. At the same time, inspections of those parts of the<br />

pipeline network identified as low-risk systems can be scaled<br />

down in an appropriate manner.<br />

Software Package<br />

Germanischer Lloyd has incorporated its newly developed<br />

procedure into an RBI software package called GALIOM<br />

for Pipelines. The software not only enables application of the<br />

<strong>GL</strong> methodology to all types of onshore and offshore pipeline<br />

systems but also facilitates the time-consuming iterative processes<br />

for determining the probability and consequences of<br />

failure for each TAG section in a system. This risk-based<br />

evaluation and inspection methodology provides a powerful<br />

tool for improving pipeline inspection strategies. To determine<br />

the risk it is important to consider the time-dependent and<br />

time-independent factors, as both are required for a sufficiently<br />

accurate risk assessment.<br />

Germanischer Lloyd believes that simple qualitative<br />

methods should be replaced with more accurate semi-quantitative<br />

risk evaluation whenever possible. Nevertheless, the<br />

qualitative approach is still required for many technical<br />

aspects because it provides an efficient process for determining<br />

the major contributors to risk. Based on semi-quantitative<br />

methods, the GALIOM for Pipelines risk evaluation and<br />

inspection program enables an accurate assessment of the<br />

probability of failure due to factors such as design, loads, fatigue<br />

and corrosion as well as the consequences. The project<br />

has confirmed that for most pipeline systems corrosion represents<br />

a significant contribution to the overall risk. The <strong>GL</strong><br />

methodology enables an estimation of the probability of corrosion,<br />

the size of flaws and their annual growth rate, taking<br />

into account different boundary conditions as well as inspection<br />

data, if available. The probability index is calculated<br />

using a limit state function for corrosion flaws to provide a<br />

relatively fine graduation of the probability of failure. ■ MC<br />

For further information: Ulrich Adriany, Pipelines and Infrastructure, Deputy Head of Dept.,<br />

Phone: +49 40 36149-7423, ulrich.adriany@gl-group.com<br />

nonstop 3/2006 59

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!