04.09.2015 Views

Henry Ford West Bloomfield Hospital Turner Construction Company ...

Henry Ford West Bloomfield Hospital Turner Construction Company ...

Henry Ford West Bloomfield Hospital Turner Construction Company ...

SHOW MORE
SHOW LESS
  • No tags were found...

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

<strong>Henry</strong> <strong>Ford</strong> <strong>West</strong> <strong>Bloomfield</strong> <strong>Hospital</strong><br />

<strong>West</strong> <strong>Bloomfield</strong>, MI<br />

<strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong><br />

Diagnostic & Treatment – Miscellaneous Interior Trades<br />

February 7, 2007<br />

Revised June 19, 2007<br />

SECTION II<br />

SUPPLEMENTAL CONDITIONS OF THE CONTRACT<br />

general conduct of operations is maintained in a safe and efficient manner, and that disruption<br />

and inconvenience to existing streets and property is minimized.<br />

The subcontractor shall work whenever conditions permit, regardless of anticipated or orderly<br />

procedure, schedule, the operations of other subcontractors, the Owner’s operations, or<br />

because of conditions encountered, and to proceed without delay and to maintain early<br />

completion.<br />

The existing <strong>Henry</strong> <strong>Ford</strong> <strong>Hospital</strong> facility is highly sensitive to noise, dust, or vibration. The<br />

Owner reserves the right to halt construction activity when patient care activities in the<br />

hospital are impacted by these factors.<br />

H. DEVIATIONS<br />

The Scope of Work shall include any or all deviations in the Contract Documents required to<br />

meet job conditions and complete the work under the intent of the specific Contract<br />

requirements. The subcontractor shall bring these deviations, if any, to the attention of <strong>Turner</strong><br />

<strong>Construction</strong> at bid time or as soon as they become necessary before commencement of<br />

work.<br />

I. EXTRA WORK<br />

1. It should be understood that award of a Contract for a portion of the work shall in no<br />

way obligate <strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong> to extend the Agreement to cover<br />

additional work throughout the total project.<br />

2. All quotations for extra work/scope revisions must be submitted within ten (10)<br />

calendar days of issuance and must have a detailed breakdown in the format as<br />

outlined below for each line item in a Bulletin on a standardized form which will be<br />

provided to the successful bidder. Pricing for SIS (Superintendent Instructions to<br />

Subcontractor) work must be submitted in twenty-four (24) hours using the wage<br />

rates established in the Subcontract Agreement.<br />

PRICING FORMAT<br />

(For information only and not required to be filled out as part of this Bid<br />

Proposal)<br />

Labor: Hours x Hourly Wage = $_______________<br />

Material: Quantity x Unit Price = $_______________<br />

Equipment Rental:Hours x Rate = $_______________<br />

Insurance = $_______________<br />

Taxes = $_______________<br />

Bond = $_______________<br />

Overhead & Profit = $_______________<br />

J. PERMITS<br />

TOTAL<br />

$_______________<br />

<strong>Turner</strong> <strong>Construction</strong> will secure the general building permit. The Subcontractor shall secure<br />

all other necessary permits, etc. covering his operations, including permits from the public<br />

authorities having jurisdiction over the streets, roads, sidewalks, utilities and all other public<br />

properties in or near which the work is located and the improvements therein. The<br />

Page 2 of 16<br />

T:\Purchasing\Bid Packs\Master Bid Pack Sections\Supplemental Conditions - Diagnostic & Treatment Miscellaneous Interior Trades.doc


<strong>Henry</strong> <strong>Ford</strong> <strong>West</strong> <strong>Bloomfield</strong> <strong>Hospital</strong><br />

<strong>West</strong> <strong>Bloomfield</strong>, MI<br />

<strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong><br />

Diagnostic & Treatment – Miscellaneous Interior Trades<br />

February 7, 2007<br />

Revised June 19, 2007<br />

SECTION II<br />

SUPPLEMENTAL CONDITIONS OF THE CONTRACT<br />

Subcontractor shall ascertain the amount of any charges, which he or she may have to pay,<br />

including fees or inspection charges required by such authorities and include them in the bid.<br />

K. EXPEDITING<br />

The Subcontractor shall be responsible for the cost of expediting all equipment and delivery of<br />

his materials on a timely basis. Should it become necessary, in order to maintain job<br />

progress, for <strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong> to supplement the Subcontractor's expediting<br />

effort, then all costs incurred by <strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong> shall be backcharged to the<br />

Subcontractor by <strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong>. Prior written notice of such Backcharge to<br />

the Subcontractor by <strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong> will be required for reimbursement.<br />

L. MATERIAL SPECIFICATIONS<br />

All manufacturer’s material which is called for in the Design Specifications and Design<br />

Drawings shall be installed in strict accordance with the manufacturer’s published<br />

recommendation for that material.<br />

M. CORRECTIVE ACTION<br />

The Subcontractor shall, upon receipt of notice in writing of any non-compliance work or<br />

material, take corrective action within twenty-four (24) hours or <strong>Turner</strong> will perform corrective<br />

action and forward all associated costs to the Subcontractor.<br />

N. CONSTRUCTION RESPONSIBILITY<br />

The Subcontractor shall be responsible for his work and every part thereof, and for all<br />

materials, tools, appliances and property of every description used in connection therewith.<br />

O. PROCEDURE OF THE WORK<br />

1. The nature of the project is such that close coordination will be required by the<br />

Subcontractor with <strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong>, the Owner and others having<br />

interest in the project to assure that work on the site, access to and from the site, and<br />

the general conduct of operations is maintained in safe and efficient manner, and that<br />

disruption and inconvenience to existing streets and property is minimized.<br />

2. The Subcontractor shall conduct operations in a manner which will control construction<br />

debris and toxic fumes from material and other equipment from impacting hospital<br />

operations.<br />

3. The Subcontractor shall, at all times, be responsible for the care and custody of the site<br />

and shall take all measures to ensure that responsibility.<br />

4. The Subcontractor shall provide a list of supervisory or management personnel and<br />

home telephone numbers who can be contacted after hours in the event of an<br />

emergency.<br />

Page 3 of 16<br />

T:\Purchasing\Bid Packs\Master Bid Pack Sections\Supplemental Conditions - Diagnostic & Treatment Miscellaneous Interior Trades.doc


<strong>Henry</strong> <strong>Ford</strong> <strong>West</strong> <strong>Bloomfield</strong> <strong>Hospital</strong><br />

<strong>West</strong> <strong>Bloomfield</strong>, MI<br />

<strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong><br />

Diagnostic & Treatment – Miscellaneous Interior Trades<br />

February 7, 2007<br />

Revised June 19, 2007<br />

SECTION II<br />

SUPPLEMENTAL CONDITIONS OF THE CONTRACT<br />

P. PROGRESS SCHEDULE AND TIME OF COMPLETION<br />

1. It is understood that the work is to be carried to completion with utmost speed<br />

consistent with good workmanship and to meet the construction schedule including<br />

project staging requirements.<br />

2. The Subcontractor shall begin work under the Contract without delay upon receipt of<br />

the fully executed Letter of Intent or Notice to Proceed and shall substantially complete<br />

the project ready for unobstructed occupancy and use of the Owner for the purposes<br />

intended within the completion time stated in the contact.<br />

3. The Subcontractor shall prepare and submit a detailed progress schedule and<br />

schedule of values within 10 (10) calendar days of the Notice to Proceed, in as much<br />

detail as is satisfactory to <strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong> for approval.<br />

4. The Subcontractor shall execute all portions of the work in accordance with the<br />

approved schedule.<br />

5. In the event the Subcontractor by his own actions fails to meet his interim milestones of<br />

his contractual schedule, he or she will be required at his own expense to take the<br />

necessary action (additional manpower, overtime, shift time, etc.) to meet his schedule<br />

commitments.<br />

Q. LAWS, ORDINANCES & REGULATIONS<br />

The Subcontractor shall, in the performance of the Contract, comply with and give all<br />

stipulations and representatives required by all applicable Federal, State and Local Laws,<br />

Ordinances and Regulations and shall require such compliance, stipulations and<br />

representations by all other persons with whom he or she shall enter into any Contract<br />

pertaining to the work hereunder. Any deviations from the Contract Drawings and/or<br />

Specifications and any additional work necessary to meet code requirements shall be made<br />

by the Subcontractor with no additional cost to the Owner. The Subcontractor shall be liable<br />

for, and indemnify and hold harmless, the Owner and <strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong> from any<br />

and all liability or damage arising by reason of the breach of the provisions herein set forth.<br />

R. MBE/WBE<br />

The Owner and <strong>Turner</strong> <strong>Construction</strong> have assigned a goal of 15% City of Detroit MBE<br />

participation and an additional 15% MBE/WBE Southeastern Michigan participation. The<br />

successful contractor will be required to demonstrate proof of achievement of these goals.<br />

Copies of MBE/WBE purchase orders must be submitted to <strong>Turner</strong> <strong>Construction</strong> for record.<br />

S. SUBCONTRACTOR RESPONSIBLE FOR COORDINATION & PROMPTNESS OF WORK<br />

<strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong> will notify the Subcontractor when to begin, to cease, or<br />

resume work on individual operations. <strong>Turner</strong> <strong>Construction</strong> is not responsible to give early<br />

notice of the rejections of faulty work and will not in any way superintend so as to relieve the<br />

Subcontractor of responsibility or of any consequence of neglect of carelessness by him or his<br />

Subcontractors. All materials and labor shall be furnished at such time as shall be for the best<br />

interest of all Subcontractors concerned, to the end that all work shall be properly coordinated<br />

and completed in accordance with applicable schedules.<br />

Page 4 of 16<br />

T:\Purchasing\Bid Packs\Master Bid Pack Sections\Supplemental Conditions - Diagnostic & Treatment Miscellaneous Interior Trades.doc


<strong>Henry</strong> <strong>Ford</strong> <strong>West</strong> <strong>Bloomfield</strong> <strong>Hospital</strong><br />

<strong>West</strong> <strong>Bloomfield</strong>, MI<br />

<strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong><br />

Diagnostic & Treatment – Miscellaneous Interior Trades<br />

February 7, 2007<br />

Revised June 19, 2007<br />

T. PROTECTION<br />

SECTION II<br />

SUPPLEMENTAL CONDITIONS OF THE CONTRACT<br />

Before beginning any construction work, carefully survey the existing work and examine the<br />

accompanying Drawings and/or Specifications to determine the extent of the work. Take all<br />

necessary precautions to ensure against damage to the property not included in the work<br />

area. The land areas outside the limits of the work area under the Contract shall be preserved<br />

in their present conditions. Damage to such property and land shall be repaired or replaced<br />

at no additional cost to <strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong>.<br />

U. SECURITY<br />

Subcontractors are advised that they will be required to provide all necessary security, etc. for<br />

their materials, machinery, equipment, tools, temporary offices, etc. No security will be<br />

provided by the Owner or <strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong>. <strong>Turner</strong> and/or the Owner may at its<br />

option and for its own use provide any surveillance and security he/she deems necessary<br />

within the construction site.<br />

V. SAFETY<br />

1. Safety is a vital concern within the construction workplace and as such a “Safety<br />

Commitment” must be included. This “Safety Commitment” must be submitted on the<br />

Bidder’s letterhead and signed by a Principal of the firm. The “Safety Commitment”<br />

should be current and should address the Bidder’s position and positive endorsement<br />

of safety procedures that are required of the Bidder’s workforce at the project jobsite.<br />

This “Safety Commitment” will be posted at the project jobsite.<br />

2. Includes, at a minimum, a quarterly safety tour at the jobsite by a Principal of the<br />

Bidder’s firm with <strong>Turner</strong> <strong>Construction</strong>’s Safety Coordinator. <strong>Turner</strong>’s Safety<br />

Coordination will provide a safety report card of the Bidder’s workforce in advance of<br />

the tour. The purpose of the tour is to commend the Bidder’s workforce on the positive<br />

aspects of the report card and reinforce the need for improvement for the areas that<br />

require safety improvement.<br />

3. All subcontractors shall comply with <strong>Turner</strong> <strong>Construction</strong>’s Return to Work program as<br />

specified in the Site Specific Safety Program and the OCIP manual.<br />

4. All subcontracts with Contract values over $5,000,000.00 will be required to provide a<br />

fulltime safety professional for the duration of their work. This individual shall be<br />

approved by <strong>Turner</strong> <strong>Construction</strong>. High risk subcontractors may be required to provide<br />

a fulltime safety professional for their Scope of Work at the discretion of the Project<br />

Executive.<br />

5. All personnel visiting or performing work within the construction limit shall participate in<br />

the <strong>Turner</strong> Safety Orientation. All personnel performing work shall comply with the<br />

<strong>Turner</strong> <strong>Construction</strong> Substance Abuse program prior to Safety Orientation.<br />

6. All personnel must sign and acknowledge that they have received and participated in<br />

the <strong>Turner</strong> <strong>Construction</strong> Safety Orientation.<br />

W. SUBSTANCE ABUSE TESTING<br />

All personnel performing work within the construction limits shall participate in the <strong>Turner</strong><br />

<strong>Construction</strong> Substance Abuse Program. The substance abuse testing includes a five (5)<br />

Page 5 of 16<br />

T:\Purchasing\Bid Packs\Master Bid Pack Sections\Supplemental Conditions - Diagnostic & Treatment Miscellaneous Interior Trades.doc


<strong>Henry</strong> <strong>Ford</strong> <strong>West</strong> <strong>Bloomfield</strong> <strong>Hospital</strong><br />

<strong>West</strong> <strong>Bloomfield</strong>, MI<br />

<strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong><br />

Diagnostic & Treatment – Miscellaneous Interior Trades<br />

February 7, 2007<br />

Revised June 19, 2007<br />

SECTION II<br />

SUPPLEMENTAL CONDITIONS OF THE CONTRACT<br />

pointing substance abuse test. The testing shall be performed with the results received<br />

before personnel commence to work on site. The test kits will cost Forty-Five Dollars<br />

($45.00) and will be charged back to the subcontractor. All cost for subcontractors’<br />

employees substance abuse testing shall be the responsibility of the subcontractors.<br />

X. IDENTIFICATION BADGES<br />

All personnel performing work on this project shall be issued a <strong>Henry</strong> <strong>Ford</strong> Health System<br />

identification badge. The identification badging shall be issued by <strong>Henry</strong> <strong>Ford</strong> Health System<br />

once the employee has participated in the project safety orientation and substance abuse<br />

testing approved. Identification badges must be displayed by the employee at all times within<br />

the <strong>Henry</strong> <strong>Ford</strong> Health System facility. All cost for identification badges including lost,<br />

stolen, or damaged badges shall be the responsibility of the subcontractor. The cost<br />

for each badge will be Five Dollars ($5.00).<br />

Y. TRAFFIC CONTROL<br />

1. The Subcontractor shall coordinate and schedule his work to conform to the <strong>West</strong><br />

<strong>Bloomfield</strong> Township or County Department of Transportation and the Owner's<br />

requirements for traffic control. The Subcontractor shall furnish, install and maintain all<br />

signage, barricading, flagmen, etc., necessary for the maintenance and safety of traffic<br />

and the general public.<br />

2. Roads, walks, driveways, alleys emergency exits and entrances to buildings shall not<br />

be blocked. Approved protection and temporary crossings shall be provided for<br />

pedestrians if necessary.<br />

Z. CONSTRUCTION TRAFFIC<br />

Access to the site shall be restricted to the routes indicated on the site logistics plan or as<br />

otherwise directed by <strong>Turner</strong>.<br />

All construction traffic, including employee traffic, trucking, and delivery of materials and<br />

equipment shall be controlled by <strong>Turner</strong> or the owner's security forces, and shall enter the<br />

site only by routes prescribed on the site logistics plan. ACCESS TO THE SITE BY OTHER<br />

ROUTES IS PROHIBITED.<br />

For traffic on areas other than the site or hospital property, the subcontractor shall coordinate<br />

such use with property owners, <strong>West</strong> <strong>Bloomfield</strong> Township or other agency(s) having<br />

jurisdiction.<br />

AA.<br />

BARRIERS AND BARRICADES (Applicable to work in or near the existing building)<br />

The subcontractor shall continuously maintain adequate protection of all work from damage<br />

and shall protect the new and existing <strong>Henry</strong> <strong>Ford</strong> facility building and property from injury or<br />

loss. In addition, the contractor shall minimize the visible impact of construction activity and<br />

take steps to afford the smooth flow of pedestrian and vehicular traffic around and through<br />

the construction zone. The contractor shall provide all barriers and barricades at places such<br />

as pits, floor openings, building perimeter, stairways, construction activities in corridors, and<br />

other areas requiring the same and shall maintain such barriers and barricades until the<br />

permanent work is in place. <strong>Turner</strong> will monitor the installation and removal of barriers and<br />

barricades. <strong>Construction</strong> and warning signs shall be placed so they are visible before or as<br />

the construction activities are encountered.<br />

Page 6 of 16<br />

T:\Purchasing\Bid Packs\Master Bid Pack Sections\Supplemental Conditions - Diagnostic & Treatment Miscellaneous Interior Trades.doc


<strong>Henry</strong> <strong>Ford</strong> <strong>West</strong> <strong>Bloomfield</strong> <strong>Hospital</strong><br />

<strong>West</strong> <strong>Bloomfield</strong>, MI<br />

<strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong><br />

Diagnostic & Treatment – Miscellaneous Interior Trades<br />

February 7, 2007<br />

Revised June 19, 2007<br />

SECTION II<br />

SUPPLEMENTAL CONDITIONS OF THE CONTRACT<br />

The subcontractor shall provide blocker boy barricades (available through McMaster-Carr<br />

Supply Co., Chicago or equal) around any openings and around contractor's ladders in the<br />

existing building’s corridors.<br />

The subcontractor shall erect and properly maintain dust-tight temporary partitions around the<br />

proposed construction area. The temporary partitions shall be of fire-rated drywall from floor<br />

to ceiling, taped, and painted, with vinyl/rubber base at the bottom. A 24” by 18" sign<br />

furnished by the <strong>Turner</strong> <strong>Construction</strong> shall be installed by <strong>Turner</strong> <strong>Construction</strong> on the<br />

temporary wall with the following wording:<br />

CONSTRUCTION IN PROGRESS<br />

PLEASE EXCUSE THE TEMPORARY<br />

INCONVENIENCE<br />

QUESTIONS OR PROBLEMS CALL<br />

_____________________<br />

TURNER CONSTRUCTION<br />

The subcontractor shall post danger warning signs against the hazards created by such<br />

features of construction such as protruding nails, hoists, hobs, elevator hatchways,<br />

scaffolding, window or door openings, stairways, falling materials and other such features.<br />

The area shall be barricaded with yellow barricade banner tape. Attach the barrier tape to<br />

traffic cones or delineators with barrier tape clips.<br />

All DANGER and WARNING signs installed by subcontractor shall include the <strong>Turner</strong><br />

<strong>Construction</strong> name, contact name, and telephone number.<br />

For temporary construction work, the subcontractor shall remove the temporary barricades<br />

(blocker boy) at the end of the day's work. <strong>Turner</strong> and the Owner shall have the right to<br />

establish a safe construction area with the full participation of the contractor(s).<br />

The construction work shall be enacted in a manner that will cause as little inconvenience as<br />

possible to the owner in the owner's use of the property and existing facilities and structures.<br />

When any door, doorway entrance, corridor, exit, etc. is closed or blocked by subcontractor's<br />

construction activity, the subcontractor shall furnish and install barricades/barriers as<br />

described above to safely and securely prohibit pedestrian traffic. Custom directional<br />

signage (symbols and words) as approved by <strong>Turner</strong> and the Owner shall be conspicuously<br />

posted as well.<br />

BB.<br />

TEMPORARY SIGNS<br />

Except as provided herein, no signs, billboards, posters or any type of advertising matter will<br />

be permitting on, about or adjacent to the premises, or on any structure on the premises,<br />

except by written permission from the Owner. Strictly no “graffiti” or any other marking on the<br />

new construction or existing construction will be allowed.<br />

CC.<br />

BUILDING EQUIPMENT AND SYSTEMS SHUTDOWN<br />

All shutdowns/outages of building systems and equipment shall be coordinated through<br />

<strong>Turner</strong> <strong>Construction</strong> with the Owner’s Facilities Department. A minimum of ten (10) weeks<br />

advance notice in writing (not counting weekends or holidays) is required. See<br />

Page 7 of 16<br />

T:\Purchasing\Bid Packs\Master Bid Pack Sections\Supplemental Conditions - Diagnostic & Treatment Miscellaneous Interior Trades.doc


<strong>Henry</strong> <strong>Ford</strong> <strong>West</strong> <strong>Bloomfield</strong> <strong>Hospital</strong><br />

<strong>West</strong> <strong>Bloomfield</strong>, MI<br />

<strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong><br />

Diagnostic & Treatment – Miscellaneous Interior Trades<br />

February 7, 2007<br />

Revised June 19, 2007<br />

SECTION II<br />

SUPPLEMENTAL CONDITIONS OF THE CONTRACT<br />

shutdown notification process and required form included in the Bidders Information<br />

Package. Failure to notify does not constitute a claim for further delays.<br />

DD.<br />

INFECTION CONTROL<br />

All subcontractors, suppliers, etc. must strictly adhere to, and comply with the Infection<br />

Control Policy issued by <strong>Turner</strong> <strong>Construction</strong> and <strong>Henry</strong> <strong>Ford</strong> Health System Infection Control<br />

Committee, for the prevention of infections during construction, renovation, alterations, and<br />

maintenance work. Refer to the policy included in the Bidders Information Package.<br />

EE.<br />

ENVIRONMENTAL<br />

The subcontractor’s Scope of Work is to conform in accordance with the State,<br />

County, and <strong>West</strong> <strong>Bloomfield</strong> Township woodlands, wetlands, and environmental<br />

standards. This subcontractor will restore, replace, or repair any portion of the job<br />

fences, signage, gates, erosion controls, woodland/wetland protection systems, or<br />

existing site conditions damaged or related as a result of their work on a daily basis.<br />

All construction impacts related to the woodland and wetland areas is prohibited<br />

except for trade contractors who are performing contract work specific to the<br />

woodlands and wetlands areas.<br />

FF.<br />

SNOW REMOVAL<br />

The Subcontractor will be responsible for the removal of all snow as related to his work.<br />

Removal of snow for access to the site will be provided by the <strong>Turner</strong> <strong>Construction</strong>.<br />

GG. STREET CLEANING<br />

The Subcontractor will be responsible for street cleaning due to their associated truck<br />

deliveries leaving any soil, grease, debris, or contaminants behind on the hospital facility’s<br />

ring road, parking lots, and Maple Road. The Subcontractor is to immediately clean up the<br />

materials from road surfaces. Failure to confirm will result in <strong>Turner</strong> <strong>Construction</strong> performing<br />

the clean up services and will charge back all costs to the responsible subcontractor.<br />

2. REQUIRED MEETINGS<br />

The Subcontractor will be required to attend weekly coordination meetings, safety orientation<br />

meetings, monthly safety meetings, preconstruction meetings and any other jobsite specific<br />

meetings necessary for successful completion of the project.<br />

3. RECORD DRAWINGS<br />

Subcontractors are advised that they will be required to submit As-Built Drawings as required by the<br />

Contract Documents. The cost of these As-Builts shall be included in the Subcontractor's price.<br />

<strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong>'s Project Superintendent will inspect these drawings to determine<br />

timely and accurate revisions are being made prior to the monthly billing application being<br />

processed. Please note that updated electronic CAD files are required to be submitted in<br />

accordance with the project Specifications.<br />

Page 8 of 16<br />

T:\Purchasing\Bid Packs\Master Bid Pack Sections\Supplemental Conditions - Diagnostic & Treatment Miscellaneous Interior Trades.doc


<strong>Henry</strong> <strong>Ford</strong> <strong>West</strong> <strong>Bloomfield</strong> <strong>Hospital</strong><br />

<strong>West</strong> <strong>Bloomfield</strong>, MI<br />

<strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong><br />

Diagnostic & Treatment – Miscellaneous Interior Trades<br />

February 7, 2007<br />

Revised June 19, 2007<br />

SECTION II<br />

SUPPLEMENTAL CONDITIONS OF THE CONTRACT<br />

4. SHOP DRAWINGS AND SUBMITTALS<br />

A. Where required under any particular section, product information, samples and/or shop<br />

drawings shall be promptly furnished to the Architect for design approval. Utilize the<br />

Contractor Submittal Form in Specification Section 01301.<br />

B. Subcontractor shall furnish a shop drawing schedule within fourteen (14) calendar days<br />

after award of the Contract. If any of the required submittals cannot be obtained within this<br />

time period, the Contractor shall notify <strong>Turner</strong> <strong>Construction</strong> immediately upon receiving notice<br />

of that fact.<br />

See the Submittal schedule below for the number of submittals required. For additional<br />

information, refer to the Specification Section 01300 and applicable sections for each specific<br />

work.<br />

C. The Subcontractor shall check and approve the shop drawings before submission to <strong>Turner</strong><br />

and they shall bear his/her stamp so indicating. The Contractor’s shop drawing stamp shall<br />

state that He or She has verified, or will verify, that He or She has checked and coordinated<br />

the shop drawing information submitted with the requirements of the Contract Documents.<br />

D. The review of any shop drawing by the Architect will not relieve the Subcontractor from liability<br />

for errors therein. The intent is to assist the Subcontractor in complying with the Drawings<br />

and specification, but not in any respect assume any responsibility for his noncompliance<br />

therewith.<br />

E. The Subcontractor shall be responsible for the reproduction and number of shop drawings<br />

required for distribution to his/her subcontractor(s) and for the distribution thereof.<br />

5. PARKING AND TEMPORARY ROADS<br />

<strong>Turner</strong> <strong>Construction</strong> will be responsible for automobile parking for construction personnel unless<br />

noted otherwise. <strong>Turner</strong> <strong>Construction</strong> will identify specific parking locations for construction<br />

personnel and reserves the right to change locations on the facility grounds during the duration of<br />

the project.<br />

6. MATERIAL STORAGE<br />

Originals Copies Each<br />

Shop Drawings/Design Coordination Drawings 1 4<br />

Product Data/Manufacture’s literature 1 4<br />

Color Charts/Catalogs 5<br />

Samples 3<br />

Test Certificates 1 2<br />

Mockups<br />

As required<br />

Warranty/Guarantee 3 2<br />

Record Documents 1 2<br />

O & M Manuals 1 4<br />

Submittals For Information 4<br />

The storage of materials and equipment at the site shall be permitted only to the extent it is<br />

approved in advance by <strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong>. Coordination with <strong>Turner</strong>’s Superintendent<br />

is required prior to purchasing and storing all material on site.<br />

Page 9 of 16<br />

T:\Purchasing\Bid Packs\Master Bid Pack Sections\Supplemental Conditions - Diagnostic & Treatment Miscellaneous Interior Trades.doc


<strong>Henry</strong> <strong>Ford</strong> <strong>West</strong> <strong>Bloomfield</strong> <strong>Hospital</strong><br />

<strong>West</strong> <strong>Bloomfield</strong>, MI<br />

<strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong><br />

Diagnostic & Treatment – Miscellaneous Interior Trades<br />

February 7, 2007<br />

Revised June 19, 2007<br />

SECTION II<br />

SUPPLEMENTAL CONDITIONS OF THE CONTRACT<br />

7. MOVING OF MATERIALS<br />

If it becomes necessary at any time during the progress of the work under the Contract to move<br />

materials or equipment which has been temporarily placed, the Subcontractor responsible for said<br />

materials or equipment shall, when directed by <strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong>, move them or cause<br />

them to be moved at no additional cost to the project.<br />

8. CLEAN-UP<br />

Subcontractors are advised that their work areas, material storage areas, and temporary offices<br />

must be maintained daily in a safe and clean condition to the satisfaction of <strong>Turner</strong> <strong>Construction</strong><br />

<strong>Company</strong> at all times. <strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong> will at no time allow storage of debris or<br />

equipment outside the assigned work area of the contractor. If these work areas are not maintained<br />

properly, <strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong> will correct the situation at the Contractor's expense.<br />

Each Subcontractor is responsible for removal of their own debris to a dumpster provided by the<br />

Contractor unless otherwise noted in the Purchasing Requisition. This includes all packaging, crates,<br />

scrape material, and construction debris, demolished material, etc.<br />

A. Each subcontractor shall conduct operations in such a manner, which will control blowing<br />

dust. The amount of dust resulting from the contractor's operations shall be controlled to<br />

prevent the spread of dust to adjacent public and private properties and to avoid creation of a<br />

nuisance in the surrounding area. Temporary methods consisting of sprinkling or similar<br />

methods will be permitted to control dust. Use of water will not be permitted when it will result<br />

in, or create, hazardous or objectionable conditions such as ice, flooding and pollution. Dust<br />

control shall be performed as the work proceeds and whenever a dust or nuisance or hazard<br />

occurs.<br />

B. Each subcontractor and subcontractor at all times shall keep the premises free from<br />

accumulation of waste materials or rubbish caused by his operations, keep the premises<br />

clean and free from fire hazards, and maintain his work and materials stockpiles neat and<br />

orderly throughout the construction period to permit safe and convenient access and<br />

movement of workmen and materials throughout the building and site and to prevent the<br />

spread of debris. Dust or other contaminants into the air or surrounding areas at all times.<br />

C. <strong>Construction</strong> debris and rubbish as generated by the subcontractor's activity shall be<br />

removed by the contractor from the point of origin daily and not allowed to accumulate. It<br />

shall be deposited in a trash container provided by <strong>Turner</strong> (except where noted otherwise) on<br />

the site until hauled away. Scrap materials for reuse in temporary work shall be segregated<br />

and properly stored, protected and covered as for new materials. The result of the above<br />

shall be the maintenance of a clean project, in keeping with the proximity of a hospital facility<br />

and with a minimum of fire hazards. <strong>Turner</strong> and the Owner shall have the right to establish a<br />

clean-up routine with the full participation of the contractor(s).<br />

D. <strong>Construction</strong> debris removed from the upper levels of the site shall be deposited directly into<br />

a dumpster via an enclosed chute constructed and provided by the subcontractor. This<br />

subcontractor shall comply with the proper removal, segregating, and disposal of all excess<br />

materials (i.e., lumber, resteel, construction debris/trash, etc.) and concrete spoils. This<br />

project will be a LEED silver certified project and subcontractors are responsible to abide by<br />

all the LEED construction waste management procedures.<br />

Page 10 of 16<br />

T:\Purchasing\Bid Packs\Master Bid Pack Sections\Supplemental Conditions - Diagnostic & Treatment Miscellaneous Interior Trades.doc


<strong>Henry</strong> <strong>Ford</strong> <strong>West</strong> <strong>Bloomfield</strong> <strong>Hospital</strong><br />

<strong>West</strong> <strong>Bloomfield</strong>, MI<br />

<strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong><br />

Diagnostic & Treatment – Miscellaneous Interior Trades<br />

February 7, 2007<br />

Revised June 19, 2007<br />

SECTION II<br />

SUPPLEMENTAL CONDITIONS OF THE CONTRACT<br />

E. If the subcontractor fails to keep the premises clean and orderly, to the satisfaction of <strong>Turner</strong>,<br />

<strong>Turner</strong> may, after 24 hours written notice to the contractor, cause the premises to be cleaned<br />

and organized in accordance with the owner's right to carry out the work, and the contractor<br />

will be charged for the cost of the clean-up.<br />

F. All subcontractors shall cooperate with each other and shall use reasonable diligence and<br />

shall make every effort, in connection with their work, to avoid excessive dirt, rubbish and<br />

general refuse and to minimize the extent of cleaning and removal thereof required<br />

hereunder of the contractor.<br />

G. Each subcontractor shall remove from the premises and site all tools, scaffolding, surplus<br />

materials and all temporary work and structures upon completion of the work and shall leave<br />

the work and the premises clean and acceptable to <strong>Turner</strong> and the Owner.<br />

To the greatest extents possible, all carts, buggies or containers containing debris shall be<br />

covered when leaving the construction site or the building.<br />

9. INSPECTIONS AND TESTS<br />

A. The Architect/Engineer shall at all times have access to the work wherever it is in preparation or<br />

in progress and the Subcontractor shall provide proper facilities for such access and for<br />

observation.<br />

B. Failure of the Architect/Engineer, during the progress of the work, to discover or reject materials<br />

or work not in accordance with the Contract Specifications and Drawings shall not be deemed an<br />

acceptance thereof or a waiver of defects therein. Likewise, no acceptance or waiver shall be<br />

inferred or implied due to payments made to Subcontractor or by partial or entire occupancy of<br />

the work, or installation of materials, which are not strictly in accordance with the Contract<br />

Specifications and Drawings.<br />

C. If any inspections or tests reveal that the workmanship or materials used by the Subcontractor<br />

are not in conformity with the Drawings, Specifications, and/or approved shop drawings, the<br />

Subcontractor shall pay for all re-tests and shall remove all work and materials so failing to<br />

conform and replace with work and materials, which are in full conformity.<br />

10. TEMPORARY FACILITIES<br />

A. OFFICES<br />

Each Subcontractor shall provide his/her own space for his/her use, complete with power,<br />

heat, light, telephone & data lines, fire extinguishers, etc. as required. All expenses in<br />

connection with this office, metering, fees, etc. shall be paid by the using Subcontractor,<br />

unless indicated otherwise in these documents.<br />

A complete set of Drawings/Specifications, As-Built documents with up to date revisions, and<br />

all permits and shop drawings shall be maintained in each trade contractor and/or<br />

subcontractor’s temporary office.<br />

No shanties or temporary job offices will be allowed in or outside the area without prior<br />

approval of <strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong>'s Job Superintendent. All shanties installed by the<br />

Subcontractor, or his/her Subcontractor(s), ten feet (10') or less from a building shall be<br />

constructed of fireproof lumber, steel, masonry or other approved incombustible materials,<br />

Page 11 of 16<br />

T:\Purchasing\Bid Packs\Master Bid Pack Sections\Supplemental Conditions - Diagnostic & Treatment Miscellaneous Interior Trades.doc


<strong>Henry</strong> <strong>Ford</strong> <strong>West</strong> <strong>Bloomfield</strong> <strong>Hospital</strong><br />

<strong>West</strong> <strong>Bloomfield</strong>, MI<br />

<strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong><br />

Diagnostic & Treatment – Miscellaneous Interior Trades<br />

February 7, 2007<br />

Revised June 19, 2007<br />

SECTION II<br />

SUPPLEMENTAL CONDITIONS OF THE CONTRACT<br />

including wire glass. If valuable material or extraordinary fire hazards are present, shanties<br />

installed more than ten feet (10') from buildings, shall also be fireproof.<br />

Shanties or temporary job offices shall be maintained by the using Subcontractor and<br />

removed by the using contractor, subject to <strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong>’s approval.<br />

Each Subcontractor will be responsible to leave the trailer storage and material storage in the<br />

original condition. Any damage will be the subcontractor’s responsibility<br />

B. TOILETS<br />

Temporary toilets are to be furnished and maintained by <strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong>.<br />

C. TELEPHONE AND FAX MACHINE<br />

1. The Subcontractor shall provide telephones, as required, in their temporary offices for<br />

their own use during the progress of the work. Telephones shall remain until<br />

completion of the work under this Contract.<br />

2. Any costs associated with the installation, usage charges and removal shall be paid by<br />

the subcontractor.<br />

D. POWER<br />

1. The Subcontractor will be responsible to make arrangements for power needed to their<br />

temporary offices.<br />

2. Any costs associated with the installation, usage charges and removal shall be paid by<br />

the Subcontractor.<br />

3. Subcontractors and their subcontractors requiring 120 VAC localizing lighting and<br />

single phase power shall furnish their own extension cords and lamps.<br />

4. Subcontractors and their subcontractors shall be allowed to use the service provided<br />

for general temporary lighting and fractional horsepower hand tools at no cost to them.<br />

5. Subcontractors and their subcontractors shall compensate the electrical subcontractor<br />

for wiring of construction equipment requiring circuits larger than 120 VAC, 20 amps<br />

single phase. Such arrangements shall be coordinated in advance with the electrical<br />

subcontractor.<br />

6. Subcontractors and their subcontractors requiring lighting or other electrical service<br />

outside of the building shall pay for the installation and removal of service and<br />

maintenance charges (i.e. jobsite trailer).<br />

7. Subcontractors and their subcontractors requiring service for construction equipment<br />

and testing in access of the capacity of the temporary construction service shall make<br />

separate arrangements at their own expense.<br />

E. WATER<br />

The Subcontractor will furnish all temporary water unless otherwise noted, inclusive of any job<br />

office trailers.<br />

Page 12 of 16<br />

T:\Purchasing\Bid Packs\Master Bid Pack Sections\Supplemental Conditions - Diagnostic & Treatment Miscellaneous Interior Trades.doc


<strong>Henry</strong> <strong>Ford</strong> <strong>West</strong> <strong>Bloomfield</strong> <strong>Hospital</strong><br />

<strong>West</strong> <strong>Bloomfield</strong>, MI<br />

<strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong><br />

Diagnostic & Treatment – Miscellaneous Interior Trades<br />

February 7, 2007<br />

Revised June 19, 2007<br />

SECTION II<br />

SUPPLEMENTAL CONDITIONS OF THE CONTRACT<br />

F. EATING AREAS<br />

The Subcontractor shall, subject to the approval of <strong>Turner</strong> <strong>Construction</strong>, designate areas for<br />

eating, provide adequate receptacles, and maintain the area in a sanitary condition free of<br />

rodents and pests. Remnants of food shall not be allowed to spread beyond the trash<br />

receptacles in the designated eating areas. The trash receptacles for the designated eating<br />

areas shall be emptied at least once each workday.<br />

11. PAYMENT PROCESS:<br />

A. BILLING BREAKDOWN<br />

The Subcontractor shall provide <strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong>, within fifteen (15) days after<br />

release, a complete detailed Schedule of Values in such a fashion as required by <strong>Turner</strong><br />

<strong>Construction</strong> <strong>Company</strong> for the cost of material, labor and equipment of each level or section<br />

of the project. At a minimum, the Schedule of Values should contain the following line items:<br />

Mobilization, Demobilization, Safety and Clean Up, Engineering and Submittals, LEED<br />

Participation, EEO/MBE Participation, and Closeout and Punchlist. Also, include breakdown<br />

for items such as General Conditions, Engineering, Submittals, Warranties, Guarantees, As-<br />

Builts, Closeout Documents, safety, and cleanup.<br />

B. BILLING PROCEDURE<br />

1. Bidders are advised that billings for this project will be on a monthly basis (from the 16 th<br />

day of the previous month to the 15th day of the current month). The subcontractor<br />

shall submit a pencil copy of its Application for Payment to the Project Superintendent<br />

by the 1st of the month for review and comment, and submit a hard copy by the 5th of<br />

the month (including projections through the last day of the month). The Subcontractor<br />

can expect payment only after <strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong> receives payment from<br />

the Owner (<strong>Turner</strong> anticipates a 60 day payment cycle). A retainage of 10% will be<br />

held until substantial completion, then 5% retainage will be held until all punchlist and<br />

closeout is complete.<br />

2. The form of Application for Payment shall be AIA Document G-702, Application and<br />

Certification for Payment. An up to date Status of <strong>Construction</strong>, and material delivery<br />

schedule must accompany the progress payment application. It will also be necessary<br />

to submit a Sworn Statement and Unconditional Partial Waiver of Lien with each<br />

application.<br />

3. In the event that changes are required during the progress of the work, changes will be<br />

based on the mutually agreed to price between <strong>Turner</strong> and the Subcontractor.<br />

4. For subcontract work, Subcontractor’s markup for handling, overhead, profit and<br />

bonding on Subcontractor’s sell price, shall not exceed 5%.<br />

5. For work by his or her own organization, Subcontractor’s markup for job and general<br />

overhead, profit and bonding shall not exceed 10% of the net labor and material<br />

costs.<br />

6. Before final payment is made, the Subcontractor shall submit As-Built Plans,<br />

Operating and Maintenance Manuals, Guarantees, and Final Lien Waivers for the<br />

total amount of the Contract.<br />

Page 13 of 16<br />

T:\Purchasing\Bid Packs\Master Bid Pack Sections\Supplemental Conditions - Diagnostic & Treatment Miscellaneous Interior Trades.doc


<strong>Henry</strong> <strong>Ford</strong> <strong>West</strong> <strong>Bloomfield</strong> <strong>Hospital</strong><br />

<strong>West</strong> <strong>Bloomfield</strong>, MI<br />

<strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong><br />

Diagnostic & Treatment – Miscellaneous Interior Trades<br />

February 7, 2007<br />

Revised June 19, 2007<br />

SECTION II<br />

SUPPLEMENTAL CONDITIONS OF THE CONTRACT<br />

C. MONTHLY BILLING<br />

This subcontractor must submit an application on AIA form for all work performed each and<br />

every month to our Superintendent. Any work performed and not billed for any given month of<br />

the payment cycle will result in <strong>Turner</strong> <strong>Construction</strong> determining the amount of work<br />

performed. Five percent (5%) of that monthly billable amount will be permanently deducted<br />

from the subcontractor’s contract amount for his failure to submit a monthly application for<br />

payment.<br />

D. PAYMENT FOR STORED MATERIAL<br />

<strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong> will consider payment for purchased materials that are stored<br />

off site provided the following stipulations are met:<br />

1. Subcontractor shall provide a detailed listing of the materials along with proof of<br />

purchase and payment.<br />

2. Subcontractor shall provide proof that materials are stored in acceptable locations<br />

that will prevent any deterioration from weather, storage configuration, sun, or any<br />

other elements that might affect the quality of the products.<br />

3. Subcontractor shall provide to <strong>Turner</strong> <strong>Construction</strong> a certificate of insurance covering<br />

the full value of the material against damage, theft, or other hazards.<br />

4. Payment shall not constitute acceptance or ownership of the materials by <strong>Turner</strong><br />

<strong>Construction</strong> or the Owner.<br />

5. The storage location shall be open to inspection to <strong>Turner</strong> <strong>Construction</strong>.<br />

6. <strong>Turner</strong> <strong>Construction</strong> and <strong>Henry</strong> <strong>Ford</strong> Health System will not pay for off-site storage of<br />

any raw materials or unassembled materials.<br />

12. DAILY CONSTRUCTION REPORTS<br />

A. The Subcontractor will be required to provide complete, detailed and accurate written<br />

construction reports daily, stating the manpower, trades, weather, description of work, etc., as<br />

required by <strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong>'s Project Superintendent. Failure to provide Daily<br />

<strong>Construction</strong> Reports as requested will result in delays of Progress Payment approval.<br />

B. The Subcontractor must notify <strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong> of any unusual circumstance<br />

upon discovery, before commencing work. If unusual conditions, etc., which cause additional<br />

expense to the Subcontractor are not reported to and authorized by <strong>Turner</strong> <strong>Construction</strong><br />

<strong>Company</strong>, no extra compensation will be approved.<br />

13. LAYOUT<br />

This Subcontractor is to include all necessary control lines in order to layout their portion of the<br />

work. <strong>Turner</strong> will provide the property line and main building benchmark only.<br />

Page 14 of 16<br />

T:\Purchasing\Bid Packs\Master Bid Pack Sections\Supplemental Conditions - Diagnostic & Treatment Miscellaneous Interior Trades.doc


<strong>Henry</strong> <strong>Ford</strong> <strong>West</strong> <strong>Bloomfield</strong> <strong>Hospital</strong><br />

<strong>West</strong> <strong>Bloomfield</strong>, MI<br />

<strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong><br />

Diagnostic & Treatment – Miscellaneous Interior Trades<br />

February 7, 2007<br />

Revised June 19, 2007<br />

SECTION II<br />

SUPPLEMENTAL CONDITIONS OF THE CONTRACT<br />

14. ACCEPTANCE OF PRIOR WORK BY OTHERS<br />

The Subcontractor is required to review work completed by others that is contiguous or related to<br />

his/her work and notify <strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong> in writing of any unacceptable work. Failure<br />

to do so and start of Contract work constitutes acceptance of the work by others.<br />

15. PROTECTION OF COMPLETED WORK<br />

The Subcontractor is required at the completion of his work to provide protection for his work<br />

against damage or theft, to the largest extent possible. Failure to do so will result in the<br />

Subcontractor having to replace or repair the damaged work at no additional cost to the project.<br />

16. WORK AREA<br />

A. Work, which will interfere with the existing businesses/buildings, including interruptions to any<br />

utilities, mechanical, and electrical services, road and traffic blocking, and noisy operations (such<br />

as jack hammering) shall be scheduled in advance.<br />

B. The construction trades will not be permitted to use toilet rooms or any other facilities in any<br />

adjacent existing buildings during the course of construction. The only time the Subcontractor<br />

will be allowed near adjacent buildings is for preliminary inspections, construction layout, or to<br />

actually perform the Scope of Work which the Owner contracted for.<br />

C. In accordance with State, Federal, and Local Rules and Regulations, there will be no smoking<br />

allowed inside the new and existing facility in accordance with Local and State Regulations.<br />

17. WARRANTIES AND GUARANTEES<br />

A. WARRANTY<br />

1. The subcontractor, and their subcontractors, as to their portion of the work under the<br />

general Contract, warrants to the Owner and/or his assignees that all work performed<br />

and materials furnished shall be in complete accordance with the Plans and<br />

Specifications.<br />

2. This Warranty is in addition to, and not in place of, any and all other warranties and<br />

guarantees provided for hereunder.<br />

B. GUARANTEES<br />

1. The Subcontractor shall guarantee all work executed under this Contract, both as to<br />

material and workmanship, for a period of one (1) Year after the date of the Certificate<br />

of Substantial Completion, unless otherwise specifically provided for in the Contract<br />

Plans and Specifications, or as provided by law. He or she shall replace with new<br />

materials, including the installation thereof, any or all, defective material, or faulty<br />

workmanship so found defective or faulty during such time. Any replacing or repairing<br />

shall be done promptly and at no additional cost to the Owner and at such time as will<br />

occasion the least inconvenience to Owner.<br />

2. The guarantee period herein stated shall in no way limit or modify longer guarantee<br />

periods whether such guarantee periods are imposed or implied by law or normally<br />

given by manufactures on their products, equipment, or as specified and any such<br />

Page 15 of 16<br />

T:\Purchasing\Bid Packs\Master Bid Pack Sections\Supplemental Conditions - Diagnostic & Treatment Miscellaneous Interior Trades.doc


<strong>Henry</strong> <strong>Ford</strong> <strong>West</strong> <strong>Bloomfield</strong> <strong>Hospital</strong><br />

<strong>West</strong> <strong>Bloomfield</strong>, MI<br />

<strong>Turner</strong> <strong>Construction</strong> <strong>Company</strong><br />

Diagnostic & Treatment – Miscellaneous Interior Trades<br />

February 7, 2007<br />

Revised June 19, 2007<br />

SECTION II<br />

SUPPLEMENTAL CONDITIONS OF THE CONTRACT<br />

guarantee imposed or implied by law or such manufacturer's guarantee shall be in<br />

addition to Subcontractor's guarantee.<br />

3. In the event the Owner shall occupy and use a portion of the building prior to the<br />

issuance of the Certificate of Substantial Completion, as noted above, the guarantee<br />

period as to occupied portions only shall begin on the date all work is completed and<br />

equipment is operating in the occupied portion.<br />

Page 16 of 16<br />