66<br />

1) The surface of the pipe to be insulated should be properly cleaned.<br />

2) Hot bitumen should be applied uniformly @ 1.5 kg. per sq. mm. on the surface<br />

of the pipe.<br />

3) A similar layer of bitumen should be applied on the inner surface and on the<br />

edges of the insulation section.<br />

4) The sections should then be stuck to the coated pipe with joints staggered.<br />

Adjacent sections should be tightly pressed together.<br />

5) All joints should be properly sealed with bitumen.<br />

6) A thick vapour seal of hot bitumen @ 2.5 kg per sq. mm. should be applied<br />

uniformly on the outer surface of the pipe sections and allowed to dry.<br />

7) The chilled water and Glycol lines, after insulation must then be covered with<br />

22 gauge aluminium sheet with proper grooves and overlaps and secured in<br />

position with 12 mm. self tapping Parker screws.<br />

8) In case the insulation sweats or the specified/required insulation properties are<br />

not attained, the entire insulation in such region shall be redone with fresh<br />

material, entirely by the erector at his own cost.<br />

50.2 Insulation of Steam condensate & Hot water pipe lines :<br />

All the steam and hot water pipes shall be insulated with 50 mm. thick mineral<br />

wool or equivalent. The insulation shall be carried out in the following manner:<br />

1) Cleaning of surface to be insulated. Applying a coat of red oxide primer and<br />

fixing glass wool/mineral wool of suitable thickness tightly to the pipe, butting<br />

all joints to be tied with lacking wire.<br />

2) The insulation should be covered with GI wire netting.<br />

3) The steam and hot water lines, after insulation must be covered with 22 gauge<br />

aluminium sheet with proper grooves and overlaps and secured in position with<br />

12 mm. self tapping Parker screws.<br />

4) In case the insulation does not have the desired insulation properties, the entire<br />

insulation will have to be redone at the erector‟s cost to give the desired results.<br />

5) In case of condensate return piping, all the steps mentioned above shall be<br />

executed except that the thickness of insulation shall be 30 mm.<br />

50.3 Insulation of chilled water tank (if specified in the Purchase Order) :<br />

a) The surface is cleaned with the help of brushes to remove any loose particles.<br />

(Signed & sealed by the tenderer<br />

in token of acceptance of above)<br />

(RCDF)<br />

Jaipur

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!