18.12 Erector shall not sell, assign, mortgage, hypothecate or remove equipment or<br />
materials which have been installed or which may be necessary for the<br />
completion of the contract without the consent of RCDF in writing.<br />
18.13 Inspection of work :<br />
RCDF of any person appointed by them shall have access and right to inspect<br />
the work, or any part thereof at all times and places during the progress of the<br />
work. The inspection and supervision is for the purpose of assuring RCDF that<br />
the plans and specifications are being properly executed and while RCDF and<br />
their representatives will extend to the erector all desired assistance in<br />
interpreting the plan and specifications, such assistance shall not relieve erector<br />
of any responsibility for the work. Any work which proves faulty shall be<br />
corrected by erector without delay. The fact that RCDF or their representatives<br />
have not pointed out faulty work or work which is not in accordance with plans<br />
and specifications shall not relieve the erector from correcting such work as<br />
directed by RCDF without additional compensation. RCDF their<br />
representatives and the employees shall at all reasonable times have free access<br />
to the works and/or to the workshop factories or other places where materials<br />
are being prepared or constructed or fabricated for the contract and also to any<br />
place where the materials are lying or from where they are being obtained and<br />
erector shall give every facility to RCDF and his representative for inspection<br />
examination and test of the materials and workmanship even to the extent of<br />
discontinuing portion of the work temporarily or of uncovering or taking down<br />
portion of finished work.<br />
19.0 Protection to Plant :<br />
19.1 Except in case where RCDF‟s express permission, is applied for and received<br />
in writing no use of RCDF‟s plant facilities such as cranes, passenger elevator,<br />
toilets showers or machine shop etc. shall be made by erector or his employees.<br />
19.2 RCDF shall not be responsible or held liable for any damage to person or<br />
properly consequent upon the use, misuse or failure of any construction tools<br />
and equipment used by erector of any of his subcontractors, even though such<br />
constructions tools and equipment may be furnished rented or loaned to erector<br />
or any of this contractors. The acceptance and/or use of any such constructions<br />
tools and equipment by erector or his subcontractor shall be constructed to<br />
mean that erector accepts all responsibility for and agrees to indemnify and<br />
save harmless RCDF from any and all claims for said damages resulting from<br />
said use, misuse or failure of such construction tools and equipments.<br />
19.3 Erector and his subcontractors shall be responsible during work for protection<br />
of the work which has been completed by other contractors/suppliers.<br />
Necessary care shall be taken to see that no damage to the same is caused by<br />
his own men during the course of execution of their work.<br />