7.2.2 Whenever, in the opinion of the RCDF, erector has made marked departures<br />
from the schedule of the completion laid down in the agreement or when<br />
untoward circumstances force a such departure from the said schedule, RCDF<br />
in order to assure the compliance with the schedule and the provisions of the<br />
agreement, shall direct the order, pace and method of conducting the work,<br />
which shall be adhered to by the erector.<br />
7.2.3 If, in the judgement of RCDF, it become necessary at any time to accelerate the<br />
over all pace of the plant erection work erector when, ordered and directed by<br />
RCDF shall cease work at any particular point and transfer his men to such<br />
other point or points and execute such portion of his work, as may be required,<br />
to enable RCDF to hasten and properly engage and carry on their work, all<br />
directed by the RCDF.<br />
7.2.4 Night work will be permitted only with prior approval of RCDF, RCDF may<br />
also direct erector to operate extra shifts over and above normal day shift to<br />
ensure completion of contract as scheduled or due to exigent circumstances, if<br />
in his opinion, such work is required.<br />
7.3 Right to order Modifications of Methods & Equipment:<br />
If at any time the erectors methods, materials or equipment appear to RCDF to<br />
be unsafe, inefficient or inadequate for securing the safety of workmen or the<br />
public, the quality of work or the rate of progress required, he may order<br />
erector to ensure their safety, and increase their efficiency and adequacy and<br />
the erector shall promptly comply with such orders. If at any time erectors<br />
working force and equipment are in the opinion of RCDF is inadequate for<br />
securing the necessary progress as herein stipulated erector shall if so directed<br />
increase the working force and equipment to such an extent as to give<br />
reasonable assurance of compliance with the schedule of completion. The<br />
absence of such demands from RCDF shall not relieve erector of his<br />
obligations to secure the quality, the safe conducting of the work and the rate<br />
of progress required by the contract the erector alone shall be and remain liable<br />
and responsible for the safety, efficiency and adequacy of his methods,<br />
materials, working force and equipment, irrespective of whether or not he<br />
makes any changes as a result or any order or orders received from RCDF.<br />
8 Changes in the work :<br />
8.1 If it becomes necessary or desirable to modify the contract and the<br />
specifications therein contained and the drawings, in a manner not materially<br />
affecting the substance thereof, or to make changes by altering, adding to or<br />
deducting from the work, or to add correlated work not now covered by the<br />
contract to the work to be done under his contract RCDF may, without<br />
invalidating the contract, direct such changes increase the cost of work and<br />
payment therefore is not covered by the prices bid for the various items, erector<br />
shall be reimbursed for such changes under a supplementary contract. In case<br />
(Signed & sealed by the tenderer<br />
in token of acceptance of above)<br />
(RCDF)<br />
Jaipur