63<br />

outside of the carbon steel pipe (black) shall receive two coats of red lead<br />

paint.<br />

47.0 Testing for :<br />

1. HP Steam 4. Soft and Raw Water<br />

2. LP Steam 5. Air<br />

3. Glycol 6. SS Piping<br />

7. Insulation 8. Electricals<br />

9. Motors 10. Equipments.<br />

Should conform to the latest ISI standards.<br />

48.0 Service piping Installation guide lines :<br />

48.1 Chilled water & Glycol piping (if mentioned in purchase order)<br />

The scope of erection and installation if mentioned, comprises a set of GI „B‟<br />

class pipes and fittings for chilled water and glycol including supports,<br />

isolation and non-return valves etc. for providing chilled water or glycol to all<br />

the equipment which would require chilled water or glycol. All the necessary<br />

headers for interconnecting all the chilled water and glycol pumps and<br />

auxiliary materials like adapters, reducers, flanges, union, valves/cocks/ (of<br />

gun-metal/brass for valves upto 100 mm. dia), strainers, gaskets, packing etc.<br />

required for the pipe should also be supplied and installed by the erector. The<br />

pipeline should be insulated as per the specification detailed.<br />

48.2 Steam & Hot Water and molasses Piping (if mentioned in purchase order)<br />

The scope of supply and installation of mentioned, comprises the following set<br />

of steam pipes and fittings for providing steam connections from the indicated<br />

battery point to all the equipments requiring steam in accordance with IBR, MS<br />

Class „C‟ pipes, fittings and auxiliary items. The scope of supply and<br />

installation includes the necessary pipes supports, isolation supports, isolation<br />

valves, nonreturn valves, safety valves, check valves, pressure reducing valves<br />

steam traps, strainers, expanders, bends, gaskets, packing, sight glasses,<br />

pressure gauges etc. The manufacturer‟s certificates that the material conforms<br />

to IBR duly attested by concerned authority should be furnished for all items as<br />

per requirements. The necessary check valves(s) and other fittings required at<br />

the sources of tapping at the battery point should also be supplied and installed<br />

by the erector.<br />

Set of condensate pipes and fittings of MS Class „C‟ to interconnect the<br />

condensate return line. The supply is inclusive of necessary pipe supports<br />

isolation valves, check valves, bends, gaskets, packing etc.<br />

48.3 Soft well water piping (if mentioned in purchase order)<br />

(Signed & sealed by the tenderer<br />

in token of acceptance of above)<br />

(RCDF)<br />