62 g) Erector shall hydrostatically test all piping systems including valves and specialities & instrument impulse line at suitable pressures. h) All piping shall be internally cleaned and flushed by Erector before and after erection in a manner suited to the service as directed by RCDF. i) For hydrostatic testing and water flushing, erector shall furnish necessary pumps, equipment and instruments, piping etc. Purchase will provide water at available points of supply to which Erector‟s temporary piping will be connected. 46.4 Colour code shall be used to identify pipe material. Erector shall be able to identify on request all random piping prior to any field fabrication. 46.5 All steam piping shall be fabricated in complete accordance with Indian Boiler Code and all approval required shall be obtained by Erector from the inspecting authority. 46.6 Erector shall be responsible for the quality of welding done by his organisation and shall conduct tests to determine the suitability of the welding procedure used by him. 46.7 Erector shall employ welded construction for all black steel piping. All black steel pipes 50 mm. and below shall have socket welded joints unless otherwise specified. 46.8 All piping supports, guides, anchors, rod hangers, spring hangers, rollers with incidental structural sub framing shall be furnished and erected by Erector. 46.9 All piping shall be suspended, guided and anchored with due regard to general requirements and to avoid interference with other pipes, hangers, electrical conduits and their supports, structural members and equipment and to accommodate insulation to conform to purchaser‟s loading limitation. It is the responsibility of the piping Erector to avoid all interferences while locating hangers and supports. 46.10 Anchors and/or guides for pipe lines or for other purpose shall be furnished when specified for holding the pipe line in position or alignment. Hangers shall be designed fabricated and assembled in such a manner that they cannot become disengaged by any movement of the support pipe. 46.11 All piping shall be wire brushed and purged with air blast to remove all dust, mill scale from inner surface. The method of cleaning shall be such that no material is left on the inner or outer surfaces which will affect the serviceability of the pipe. 46.12 Effective precaution such as capping and sealing shall be taken to protect all pipes ends against ingress of dirt and damage during transit or storage. The (Signed & sealed by the tenderer in token of acceptance of above) (RCDF) Jaipur
63 outside of the carbon steel pipe (black) shall receive two coats of red lead paint. 47.0 Testing for : 1. HP Steam 4. Soft and Raw Water 2. LP Steam 5. Air 3. Glycol 6. SS Piping 7. Insulation 8. Electricals 9. Motors 10. Equipments. Should conform to the latest ISI standards. 48.0 Service piping Installation guide lines : 48.1 Chilled water & Glycol piping (if mentioned in purchase order) The scope of erection and installation if mentioned, comprises a set of GI „B‟ class pipes and fittings for chilled water and glycol including supports, isolation and non-return valves etc. for providing chilled water or glycol to all the equipment which would require chilled water or glycol. All the necessary headers for interconnecting all the chilled water and glycol pumps and auxiliary materials like adapters, reducers, flanges, union, valves/cocks/ (of gun-metal/brass for valves upto 100 mm. dia), strainers, gaskets, packing etc. required for the pipe should also be supplied and installed by the erector. The pipeline should be insulated as per the specification detailed. 48.2 Steam & Hot Water and molasses Piping (if mentioned in purchase order) The scope of supply and installation of mentioned, comprises the following set of steam pipes and fittings for providing steam connections from the indicated battery point to all the equipments requiring steam in accordance with IBR, MS Class „C‟ pipes, fittings and auxiliary items. The scope of supply and installation includes the necessary pipes supports, isolation supports, isolation valves, nonreturn valves, safety valves, check valves, pressure reducing valves steam traps, strainers, expanders, bends, gaskets, packing, sight glasses, pressure gauges etc. The manufacturer‟s certificates that the material conforms to IBR duly attested by concerned authority should be furnished for all items as per requirements. The necessary check valves(s) and other fittings required at the sources of tapping at the battery point should also be supplied and installed by the erector. Set of condensate pipes and fittings of MS Class „C‟ to interconnect the condensate return line. The supply is inclusive of necessary pipe supports isolation valves, check valves, bends, gaskets, packing etc. 48.3 Soft well water piping (if mentioned in purchase order) (Signed & sealed by the tenderer in token of acceptance of above) (RCDF) Jaipur
- Page 11 and 12: 11 2.8 The specifications, conditio
- Page 13 and 14: 4.0 Price : 4.0.1 The price should
- Page 15 and 16: (b) (c) 15 Suppliers are requested
- Page 17 and 18: 17 adjusted. The execution of agree
- Page 19 and 20: Clause 2 :- 19 The Managing Directo
- Page 21 and 22: 21 of default the contractor for wh
- Page 23 and 24: 23 18.3 Removal of Rejected Stock :
- Page 25 and 26: 25 c) Three sets of installation/op
- Page 27 and 28: 27 Additional General Terms and Con
- Page 29 and 30: 8.0 GUARANTEE : The supply of equip
- Page 31 and 32: GENERAL TERMS AND CONDITIONS FOR ER
- Page 33 and 34: 33 provide all Labour materials and
- Page 35 and 36: 35 inseparable part of the work con
- Page 37 and 38: 37 If any part of Erector‟s work
- Page 39 and 40: 39 and other surfaces which have be
- Page 41 and 42: 41 18.7 In the execution of the wor
- Page 43 and 44: 43 19.5 Erector shall effectively p
- Page 45 and 46: 45 21.6 Erector shall furnish RCDF
- Page 47 and 48: 47 23.10 If, at any time before the
- Page 49 and 50: 49 25.9 All the necessary items/goo
- Page 51 and 52: 51 30.0 Progress of Work : If the e
- Page 53 and 54: 53 circumstances) the security of t
- Page 55 and 56: 55 c) The cable of electric power s
- Page 57 and 58: 42.0 Cable Installation : 57 42.1 E
- Page 59 and 60: 42.10 Connections shall be made to
- Page 61: 45.5 All underground connections fo
- Page 65 and 66: 65 49.2 Piping (SS) (if mentioned i
- Page 67 and 68: TENDER ACCEPTANCE LETTER (To be giv
- Page 69 and 70: SECTION-I 69 ANNEXURE-II MANUFACTUR
- Page 71 and 72: 71 ANNEXURE-IV SECTION-II - SCHEDUL
- Page 73 and 74: 73 ANNEXURE-VI RATE QUOTATION FORM
- Page 75 and 76: 75 3(a) 3(b) The Federation do here
- Page 77 and 78: ANNEXURE-VIII (Form of Bank Guarant
- Page 79 and 80: (Performa of Bank Guarantee for rel
- Page 81 and 82: TECHNICAL SPECIFICATION FOR SUPPLY,
- Page 83: 83 (Signed & sealed by the tenderer
62<br />
g) Erector shall hydrostatically test all piping systems including valves and<br />
specialities & instrument impulse line at suitable pressures.<br />
h) All piping shall be internally cleaned and flushed by Erector before and<br />
after erection in a manner suited to the service as directed by RCDF.<br />
i) For hydrostatic testing and water flushing, erector shall furnish necessary<br />
pumps, equipment and instruments, piping etc. Purchase will provide water<br />
at available points of supply to which Erector‟s temporary piping will be<br />
connected.<br />
46.4 Colour code shall be used to identify pipe material. Erector shall be able to<br />
identify on request all random piping prior to any field fabrication.<br />
46.5 All steam piping shall be fabricated in complete accordance with Indian Boiler<br />
Code and all approval required shall be obtained by Erector from the inspecting<br />
authority.<br />
46.6 Erector shall be responsible for the quality of welding done by his organisation<br />
and shall conduct tests to determine the suitability of the welding procedure<br />
used by him.<br />
46.7 Erector shall employ welded construction for all black steel piping. All black<br />
steel pipes 50 mm. and below shall have socket welded joints unless otherwise<br />
specified.<br />
46.8 All piping supports, guides, anchors, rod hangers, spring hangers, rollers with<br />
incidental structural sub framing shall be furnished and erected by Erector.<br />
46.9 All piping shall be suspended, guided and anchored with due regard to general<br />
requirements and to avoid interference with other pipes, hangers, electrical<br />
conduits and their supports, structural members and equipment and to<br />
accommodate insulation to conform to purchaser‟s loading limitation. It is the<br />
responsibility of the piping Erector to avoid all interferences while locating<br />
hangers and supports.<br />
46.10 Anchors and/or guides for pipe lines or for other purpose shall be furnished<br />
when specified for holding the pipe line in position or alignment. Hangers shall<br />
be designed fabricated and assembled in such a manner that they cannot<br />
become disengaged by any movement of the support pipe.<br />
46.11 All piping shall be wire brushed and purged with air blast to remove all dust,<br />
mill scale from inner surface. The method of cleaning shall be such that no<br />
material is left on the inner or outer surfaces which will affect the serviceability<br />
of the pipe.<br />
46.12 Effective precaution such as capping and sealing shall be taken to protect all<br />
pipes ends against ingress of dirt and damage during transit or storage. The<br />