RAJASTHAN CO-OPERATIVE DAIRY FEDERATION LIMITED

RAJASTHAN CO-OPERATIVE DAIRY FEDERATION LIMITED RAJASTHAN CO-OPERATIVE DAIRY FEDERATION LIMITED

sarasmilkfed.rajasthan.gov.in
from sarasmilkfed.rajasthan.gov.in More from this publisher
28.08.2015 Views

60 44.2 Conduits or pipes shall run along walls, floors and ceilings, on steel supports, embedded in soil, floor, wall or foundation, in accordance with relevant layout drawings, under ground portions of conduit installation to be embedded in the foundation or structural concrete shall be installed in close coordination with collateral work. Exposed conduit shall be neatly run and evenly spaced, with conduits parallel when in racks or in banks. Conduits embedded in foundation or structural concrete shall be run as directly as possible among with generally indicated route between two points with a minimum length and with a minimum of crossing bending and cutting but without creating interferences with other installations. 44.3 When two lengths of conduits are joined together through a coupling, running threads equal to twice the length of coupling shall be provided on any one length to facilitate easy dismantling of the two conduits whenever required. 44.4 When one or more cables are drawing through a conduit, cross sectional area of the cables shall be 40% of the internal cross sectional area of the conduit. 44.5 Conduits and accessories shall be adequately protected against mechanical damage as well as corrosion. 45.0 Earthing : 45.1 The scope of supply and installation should also include absolutely independent double earthing of individual electric motors, control gears and switchboards, complete with necessary copper/GI wire, copper strip, earthing plate, top funnel, salt, cola etc. The earthing process include digging of earthing pit, filling the same with alternative layers of coal and salt, refilling the pit and providing perforated GI pipe making housing pit and cover as per IER & ISI code of practice No. ISI:3034-1966. 45.2 Erector shall install bare/insulated aluminium/GI Cables and strips, etc. required for system and individual equipment earthing. All work such as cutting, bending, supporting soldering, coating drilling, brazing, clamping, bolting and connecting into structures, pipes, equipment frames, terminals, rails or other devices shall be in Erector‟s scope of work. Unless otherwise specified, the excavation and trenching shall be done by Erector. Erector shall also backfill and reinstate the trenches after installation of earthing conductors. 45.3 Earthing shall conform to the Indian Standard Code of practice IS:3043 and Indian Electricity Rules, 1956. All materials and fittings used in the earthing installation shall conform to the relevant Indian Standards or approved by RCDF‟s Engineer. Any change in routing, size of conductors etc. shall be subject to the prior approval of RCDF Engineers. 45.4 Metallic frame of all electrical equipment shall be earthed by two separate and district connections with earthing system. (Signed & sealed by the tenderer in token of acceptance of above) (RCDF) Jaipur

45.5 All underground connections for the earthing system shall be brazed/welded. Connections to equipment and devices shall be normally of the bolted type. 45.6 On completion of the installation, continuity of all conductors and efficiency of all bends and joints shall be tested. The earth resistance shall be tested in the presence of RCDF Engineer‟s/representative. All equipment necessary for the test shall be furnished by Erector. 46.0 Supply, Fabrication, Erection and Testing of Piping : 46.1 Codes and standards : All piping system including sub-contracted materials shall comply with the latest editions of the following wherever applicable : a) Indian Boiler Regulation b) Regulation of Inspector of Explosives c) All applicable Indian Standards d) All applicable State Laws. 46.2 Scope of Supply : Erector shall supply all piping materials like pipes, fittings, flanges and other items as shown in his scope in the flow diagrams/specifications. 46.3 Scope of erection to be performed by Erector is outlined below : a) The scope of erection for piping includes all system covered under his scope of work in the flow diagram/specification. b) Erector shall also install small accessory, piping an any specialities furnished with or for equipment such as relief valves, built is bypass, and other items of this type. c) Erector‟s work terminates at the final tube or pipe connection at pumps, including the final connection. d) Erector shall install primary elements for flow measurement, control valves, and on line metering equipment. e) Erector shall perform necessary internal machining of pipe for installing crevices, flow nozzles, straightening vances, control valves. f) Erector shall install all valves and specialities being procured from others. 61 (Signed & sealed by the tenderer in token of acceptance of above) (RCDF) Jaipur

60<br />

44.2 Conduits or pipes shall run along walls, floors and ceilings, on steel<br />

supports, embedded in soil, floor, wall or foundation, in accordance with<br />

relevant layout drawings, under ground portions of conduit installation to be<br />

embedded in the foundation or structural concrete shall be installed in close coordination<br />

with collateral work. Exposed conduit shall be neatly run and evenly<br />

spaced, with conduits parallel when in racks or in banks. Conduits embedded in<br />

foundation or structural concrete shall be run as directly as possible among<br />

with generally indicated route between two points with a minimum length and<br />

with a minimum of crossing bending and cutting but without creating<br />

interferences with other installations.<br />

44.3 When two lengths of conduits are joined together through a coupling, running<br />

threads equal to twice the length of coupling shall be provided on any one<br />

length to facilitate easy dismantling of the two conduits whenever required.<br />

44.4 When one or more cables are drawing through a conduit, cross sectional area of<br />

the cables shall be 40% of the internal cross sectional area of the conduit.<br />

44.5 Conduits and accessories shall be adequately protected against mechanical<br />

damage as well as corrosion.<br />

45.0 Earthing :<br />

45.1 The scope of supply and installation should also include absolutely<br />

independent double earthing of individual electric motors, control gears and<br />

switchboards, complete with necessary copper/GI wire, copper strip, earthing<br />

plate, top funnel, salt, cola etc. The earthing process include digging of<br />

earthing pit, filling the same with alternative layers of coal and salt, refilling<br />

the pit and providing perforated GI pipe making housing pit and cover as per<br />

IER & ISI code of practice No. ISI:3034-1966.<br />

45.2 Erector shall install bare/insulated aluminium/GI Cables and strips, etc.<br />

required for system and individual equipment earthing. All work such as<br />

cutting, bending, supporting soldering, coating drilling, brazing, clamping,<br />

bolting and connecting into structures, pipes, equipment frames, terminals, rails<br />

or other devices shall be in Erector‟s scope of work. Unless otherwise<br />

specified, the excavation and trenching shall be done by Erector. Erector shall<br />

also backfill and reinstate the trenches after installation of earthing conductors.<br />

45.3 Earthing shall conform to the Indian Standard Code of practice IS:3043 and<br />

Indian Electricity Rules, 1956. All materials and fittings used in the earthing<br />

installation shall conform to the relevant Indian Standards or approved by<br />

RCDF‟s Engineer. Any change in routing, size of conductors etc. shall be<br />

subject to the prior approval of RCDF Engineers.<br />

45.4 Metallic frame of all electrical equipment shall be earthed by two separate and<br />

district connections with earthing system.<br />

(Signed & sealed by the tenderer<br />

in token of acceptance of above)<br />

(RCDF)<br />

Jaipur

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!