47<br />

23.10 If, at any time before the completion of the work, changes are made<br />

necessitating revision of approved drawings, erector shall make such revision<br />

and proceed in the same routine as for the original approval.<br />

24.0 Inspection Right & Privileges :<br />

24.1 RCDF reserves the right to inspect any machinery or material or equipment<br />

furnished or used by erector under the contract, and to project any, which is<br />

found defective in workmanship or otherwise unsuitable for the use and<br />

purpose intended, or which is not in accordance with the intent of the contract.<br />

24.2 Should RCDF waive the right to inspect any equipment, such waiver shall not<br />

relieve erector in anyway of his obligation under the contract.<br />

24.3 RCDF representatives shall be permitted free access to erector‟s or his<br />

subcontractor‟s shop at all working hours for the purpose of inspecting work at<br />

all stages of progress.<br />

24.4 RCDF representatives shall be given full assistance in the form of necessary<br />

tools, instruments, equipment and qualified operations to facilitate inspection.<br />

24.5 RCDF reserves the right to call for certificate of origin and test certificates for<br />

all raw material and equipment at any stage of manufacture.<br />

24.6 In the event of RCDF inspection reveals poor quality of goods RCDF shall be<br />

at liberty to specify additional inspection procedures, if required, to ascertain<br />

Vendor‟s compliance with the equipment specifications.<br />

24.7 Even though inspection is carried out by RCDF or his representatives, such<br />

inspection shall not however, relieve Vendor of all responsibility for furnishing<br />

equipment conforming to the requirements of the contract, nor prejudice any<br />

claim right or privilege which RCDF may have because of the use of defective<br />

or unsatisfactory equipment.<br />

24.8 A set of latest prints of the approved drawings shall be kept available by the<br />

controller, in the shop floor for reference of RCDF representative during<br />

inspection.<br />

25.0 Storage of equipment :<br />

25.1 In general, erector is responsible for the proper storage and maintenance of all<br />

materials/equipments entrusted to him. He shall take all required steps to carry<br />

out frequent inspection of equipment/materials/stores as well as erected<br />

equipments until the same is taken over by the RCDF. The following procedure<br />

shall apply for the same.<br />

(Signed & sealed by the tenderer<br />

in token of acceptance of above)<br />

(RCDF)<br />

Jaipur