18.7 In the execution of the work no person other than erector or his duly<br />
appointed representatives, his subcontractors and their workman shall be<br />
allowed to do work at the site except by the special permission, in writing of<br />
RCDF or their representatives, but access to everywhere in the site at all times<br />
shall be accorded to RCDF and their representatives and other authorized<br />
officials and statutory public authorities. Nevertheless, erector shall not object<br />
to the execution of the work by other erector/contractor or tradesman whose<br />
names shall have been previously communicated in every facility for the<br />
execution of their several functions simultaneously with his own.<br />
18.8 Erector shall carry out the required „minor modification work‟ at site as<br />
required to efficiently complete the work covered in this contract at no extra<br />
cost over his contracted sum. However „minor modifications‟ shall not involve<br />
more than 24 man hours per each item of such work. However, in case of<br />
„major modifications‟ which are required to be done on the equipment, for no<br />
fault of erector he shall be compensated on the basis of man day rates. It is the<br />
responsibility of the erector to get the prior approval for such „major<br />
modifications work‟ from RCDF before such works are taken up. Erector shall<br />
also get the estimates and the actual time sheets certified by RCDF and these<br />
certified time sheets will be the basis for processing his bills for the „Major<br />
modifications‟.<br />
18.9 If the work or any portion thereof shall be damaged in any way excepting by<br />
the acts of RCDF, or if defects not readily detected on prior inspection and<br />
which shall develop before the final completion and acceptance of the whole<br />
work, erector shall forthwith make good, without compensation, such damage<br />
or defects in a manner satisfactory to RCDF. In no case shall defective or<br />
imperfect work will be retained.<br />
18.10 Erector at all times shall work in co-ordination with RCDF‟s engineering staff<br />
and after them all reasonable facilities to become familiar with the erection,<br />
operation and maintenance of the equipments.<br />
18.11 In respect of observation of local rules, administrative orders, working staff<br />
and the like, erector and his personnel shall co-operate with the RCDF.<br />
18.12 Erector shall not sell, assign, mortgage, hypothecate or remove equipment or<br />
materials which have been installed or which may be necessary for the<br />
completion of the contract without the consent of RCDF in writing.<br />
(Signed & sealed by the tenderer<br />
in token of acceptance of above)<br />
(RCDF)<br />
Jaipur