41<br />

18.7 In the execution of the work no person other than erector or his duly<br />

appointed representatives, his subcontractors and their workman shall be<br />

allowed to do work at the site except by the special permission, in writing of<br />

RCDF or their representatives, but access to everywhere in the site at all times<br />

shall be accorded to RCDF and their representatives and other authorized<br />

officials and statutory public authorities. Nevertheless, erector shall not object<br />

to the execution of the work by other erector/contractor or tradesman whose<br />

names shall have been previously communicated in every facility for the<br />

execution of their several functions simultaneously with his own.<br />

18.8 Erector shall carry out the required „minor modification work‟ at site as<br />

required to efficiently complete the work covered in this contract at no extra<br />

cost over his contracted sum. However „minor modifications‟ shall not involve<br />

more than 24 man hours per each item of such work. However, in case of<br />

„major modifications‟ which are required to be done on the equipment, for no<br />

fault of erector he shall be compensated on the basis of man day rates. It is the<br />

responsibility of the erector to get the prior approval for such „major<br />

modifications work‟ from RCDF before such works are taken up. Erector shall<br />

also get the estimates and the actual time sheets certified by RCDF and these<br />

certified time sheets will be the basis for processing his bills for the „Major<br />

modifications‟.<br />

18.9 If the work or any portion thereof shall be damaged in any way excepting by<br />

the acts of RCDF, or if defects not readily detected on prior inspection and<br />

which shall develop before the final completion and acceptance of the whole<br />

work, erector shall forthwith make good, without compensation, such damage<br />

or defects in a manner satisfactory to RCDF. In no case shall defective or<br />

imperfect work will be retained.<br />

18.10 Erector at all times shall work in co-ordination with RCDF‟s engineering staff<br />

and after them all reasonable facilities to become familiar with the erection,<br />

operation and maintenance of the equipments.<br />

18.11 In respect of observation of local rules, administrative orders, working staff<br />

and the like, erector and his personnel shall co-operate with the RCDF.<br />

18.12 Erector shall not sell, assign, mortgage, hypothecate or remove equipment or<br />

materials which have been installed or which may be necessary for the<br />

completion of the contract without the consent of RCDF in writing.<br />

(Signed & sealed by the tenderer<br />

in token of acceptance of above)<br />

(RCDF)<br />

Jaipur