18.0 Erection & Inspection :<br />
18.1 Erector shall prepare a detailed and comprehensive erection schedule for<br />
review and approval of RCDF‟s site Engineer and supplier‟s erection<br />
supervisors. This „Approved‟ erection schedule shall form the basis for<br />
evaluating the pace of all the erection works to be performed by erector.<br />
18.2 The schedule shall show approximately the date on which each part of<br />
divisions of the work is expected to begin based on his knowledge of the works<br />
of the other contractors and the date when the work is schedules to be finished.<br />
Upon the request of RCDF erector should be prepared to discuss his schedule<br />
in relation to the master schedule and shall co-ordinate his work with that of<br />
the other erectors/contractors as determined by RCDF.<br />
18.3 The work so far as it is carried out on RCDF‟s promised shall be carried out at<br />
such time as RCDF may approve consistent with the construction schedule and<br />
so as not to interfere unnecessarily with the conduct of RCDF‟s business and<br />
RCDF will give erector all reasonable assistance for carrying out the work.<br />
18.4 Erector shall revise and up date his erection schedule periodically (atleast once<br />
every calendar month) to indicate actual progress of works, in relation to<br />
scheduled progress. Erector shall also submit monthly progress reports<br />
indicating progress work giving scheduled and actual percentage completions,<br />
causes for delay etc. as well as such other reasonable reports RCDF may<br />
request from time to time.<br />
18.5 Adherence to the instructions of supervisory engineers of manufacturers, where<br />
provided by RCDF is compulsory. Erector shall work as per the procedure<br />
suggested by manufacturer and shall complete erection of equipment in such a<br />
way so as not to interfere with or prevent equipment from functioning as<br />
intended, as well as to the entire satisfaction of the manufacturer‟s<br />
supervisor/RCDF. Erector shall also permit and provide all facilities for<br />
manufacturer‟s erection super visors to carry out all checks that they may wish<br />
to and approve any erection procedure and/or final setting and alignment of<br />
components, in order to satisfy themselves that erection has been carried out as<br />
intended by them. This shall, however, in no way relieve erector of his<br />
responsibility for providing adequate and competent supervision and quality<br />
workmanship. In case of any dispute, the decision of the RCDF/Manufacturer‟s<br />
erection supervisor shall be final and binding on the erector.<br />
18.6 Erector shall haul materials and equipment furnished at RCDF‟s storage or<br />
unloading areas to the points where they are to be used, in the construction<br />
work, install the materials and equipment in their final location and classify<br />
and store all surplus and auxiliary parts in a systematic manner in the<br />
warehouse, where they can be readily identified and located when needed at a<br />
later date.<br />