33<br />

provide all Labour materials and equipments necessary for the entire<br />

completion of the work describe and shall not avail himself of any manifesting<br />

or unintentional error, omission or inconsistency that may exist. Erector shall<br />

carry out and complete the work in every respect in accordance with the<br />

contract and accordance with the directions and to the entire satisfaction of<br />

RCDF and the manufacture‟s representatives.<br />

6.0 Engineer’s Instructions :<br />

RCDF may in his absolute discretion, from time to time issue further drawings<br />

and/or written instructions, details directions and explanations which are<br />

collectively referred to as „Engineer‟s instructions‟ in regard to :<br />

6.1 Any additional drawings and explanations to exhibit or illustrate details.<br />

6.2 The variation or modifications of the design, quality or quantity of work or the<br />

additional or omissions or substitutions of any works.]<br />

6.3 Any discrepancy in the drawings or between the schedule of quantities and/or<br />

specifications.<br />

6.4 The removal from the site of any material brought thereon by erector and the<br />

substitution of any other material thereof.<br />

6.5 The removal and/or re-execution of any work executed by the erector.<br />

6.6 The dismissal from the work of any persons employed thereupon.<br />

6.7 The opening up for inspection of any work covered up.<br />

6.8 The amending and making good of any defects.<br />

7.0 Right of RCDF :<br />

7.1 The various parts of the contract are intended to be complementary to each<br />

other but should any discrepancy appear or any misunderstandings arises as to<br />

the interpretations of anything contained therein, the explanation of RCDF<br />

shall be final and binding.<br />

7.2 Right to direct work :<br />

7.2.1 RCDF shall have the right to direct the manner in which all work under this<br />

contract shall be conducted in so far as it may be necessary to secure the safe<br />

and proper progress and specified quality of the work, all work shall be done<br />

and all materials shall be furnished to the satisfaction and approval of RCDF.<br />

7.2.2 Whenever, in the opinion of the RCDF, erector has made marked departures<br />

from the schedule of the completion laid down in the agreement or when<br />

untoward circumstances force a such departure from the said schedule, RCDF<br />

in order to assure the compliance with the schedule and the provisions of the<br />

(Signed & sealed by the tenderer<br />

in token of acceptance of above)<br />