Aracruz Uses a Dynamic Simulator for Control System ... - Andritz

Aracruz Uses a Dynamic Simulator for Control System ... - Andritz Aracruz Uses a Dynamic Simulator for Control System ... - Andritz

05.12.2012 Views

Aracruz Uses a Dynamic Simulator for Control System Staging and Operator Training By André Luis Bogo 1 Patrícia Nunes 1 Gabriel Hidalgo 2 and Donald Wayne Herschmiller 3 Key words: Simulator, Dynamic, Pulp, DCS, configuration and training. ABSTRACT This paper provides a summary of experiences at Aracruz Celulose S.A. in applying a dynamic process Simulator to the challenges of distributed control system staging and operator training on the Mill “C” project in Espírito Santo, Brasil. The tasks of creating dynamic models for most areas of this world-scale market Kraft pulp mill were challenging with respect to schedule and complexity. The ability to import and export the actual control system configuration to-and-from the Simulator allowed not only a comprehensive check-out of the process models, but also verification of the process control strategy and the application programming composed to implement it. The entire control system was thoroughly prepared for start-up and the operators were trained to a high standard of readiness. These factors contributed to a comprehensive commissioning process and to one of the fastest and most effective start-ups yet witnessed in the industry. The benefits to the project are assessed in a qualitative way. 1 Aracruz Celulose S.A. - Espirito Santo, Brasil 2 IDEAS Simulation, Inc. - Vancouver, Canada 3 Veracel Celulose S.A. - São Paulo, Brasil www.andritz.com 1 of 16

<strong>Aracruz</strong> <strong>Uses</strong> a <strong>Dynamic</strong> <strong>Simulator</strong> <strong>for</strong><br />

<strong>Control</strong> <strong>System</strong> Staging and Operator Training<br />

By<br />

André Luis Bogo 1<br />

Patrícia Nunes 1<br />

Gabriel Hidalgo 2 and<br />

Donald Wayne Herschmiller 3<br />

Key words: <strong>Simulator</strong>, <strong>Dynamic</strong>, Pulp, DCS, configuration and training.<br />

ABSTRACT<br />

This paper provides a summary of experiences at <strong>Aracruz</strong> Celulose S.A. in applying a dynamic process<br />

<strong>Simulator</strong> to the challenges of distributed control system staging and operator training on the Mill “C” project<br />

in Espírito Santo, Brasil. The tasks of creating dynamic models <strong>for</strong> most areas of this world-scale market<br />

Kraft pulp mill were challenging with respect to schedule and complexity.<br />

The ability to import and export the actual control system configuration to-and-from the <strong>Simulator</strong> allowed<br />

not only a comprehensive check-out of the process models, but also verification of the process control<br />

strategy and the application programming composed to implement it. The entire control system was<br />

thoroughly prepared <strong>for</strong> start-up and the operators were trained to a high standard of readiness.<br />

These factors contributed to a comprehensive commissioning process and to one of the fastest and most<br />

effective start-ups yet witnessed in the industry. The benefits to the project are assessed in a qualitative way.<br />

1 <strong>Aracruz</strong> Celulose S.A. - Espirito Santo, Brasil<br />

2 IDEAS Simulation, Inc. - Vancouver, Canada<br />

3 Veracel Celulose S.A. - São Paulo, Brasil<br />

www.andritz.com 1 of 16


INTRODUCTION<br />

With capital expenditures of US$ 850 million (US$ 575 million <strong>for</strong> the pulp mill), Mill “C” will add 700.000<br />

air dry tons per year of market pulp capacity to the existing two-line <strong>Aracruz</strong> mill. The new line began<br />

operations on May 23, 2002, significantly ahead of schedule.<br />

The implementation plan <strong>for</strong> the Mill “C” project included an innovative partnering concept with the EPC<br />

(Engineer, Procure and Construct) process “island” suppliers and their various sub-contractors, in order to<br />

achieve common quality, schedule and budgetary goals. One noteworthy innovation within this concept was<br />

the development and use of a dynamic process <strong>Simulator</strong>.<br />

In mid-March 2001, the company which is now called IDEAS Simulation, Inc. of Atlanta, USA, was asked to<br />

proceed with process model development <strong>for</strong> the <strong>Simulator</strong> project. The <strong>Simulator</strong> project involved the<br />

development of dynamic process models in seven Mill “C” operating areas: Digester and Pressure Diffusers;<br />

Oxygen-Delignification and Screening; Bleaching; Chlorine Dioxide Plant; Pulp Drying; Evaporation; and<br />

Recausticizing and Lime Re-burning.<br />

The <strong>Simulator</strong> was aimed at assisting the project team in achieving an exceptional mill start-up and rapid<br />

ramp-up to full production. To do this, the <strong>Simulator</strong> was applied to the role of Distributed <strong>Control</strong> <strong>System</strong><br />

(DCS) staging and operator training.<br />

Besides the project objectives, the <strong>Simulator</strong> can be used, after the start-up, to support operations by testing<br />

the effect of changes in the process, including process configuration, operating conditions, or equipment<br />

changes, and predict un<strong>for</strong>eseen process complications. In addition, the process control systems in each area<br />

can be analyzed, tested and improved, all be<strong>for</strong>e attempting changes in the field.<br />

WHAT IS THE SIMULATOR?<br />

The <strong>Simulator</strong> is a combination of mostly standard computer hardware and some highly specialized software.<br />

In short, the structure adopted by <strong>Aracruz</strong> consists of three essential parts:<br />

• The operator’s workstation, using exactly the same operator-interface graphics as in the real plant.<br />

• Specialized emulation software and hardware to run the DCS configuration, again exactly as it will be<br />

run in the field.<br />

• Specialized process modeling software to simulate the processes in the real mill, and standard<br />

computers upon which to run the models.<br />

www.andritz.com 2 of 16


A simplified view of the overall architecture of the system compared to the real life situation is shown in<br />

Figure 1, below.<br />

Figure 1 The Simulated and Actual Plants Compared<br />

At the workstation the operator has full use of the same screens that he will use in the real plant. If the process<br />

models are well executed, the process has much the same “feel” as the real-life process. Thus his window and<br />

his world are similar, if not exactly like his reality.<br />

Using the emulation software and hardware, it is possible to load a copy of the configuration taken from the<br />

field equipment. Thus the system replaces the DCS hardware process controllers (CP) needed in the real<br />

world, with the control logic in the <strong>Simulator</strong> functioning exactly as in the real-world hardware. In our case,<br />

depending on the size of the mill, or area configuration, it is possible to “replace” nearly one-half of a mill’s<br />

hardware CPs in just one emulation system.<br />

The virtual signals upon which the emulated DCS configuration code acts are generated by the process<br />

models.<br />

The next section in this paper will present an actual working example of part of a model developed <strong>for</strong> the<br />

project. This section is written primarily <strong>for</strong> the reader who has some background knowledge in modeling, but<br />

is unfamiliar with the modeling suite used. Those who are primarily interested in strategic issues can bypass<br />

this section and go directly to the sections on “STAGING THE DCS AND THE SIMULATOR” and<br />

“TRAINING OPERATORS USING THE PROCESS SIMULATOR”.<br />

www.andritz.com 3 of 16


DEVELOPMENT OF THE PROCESS MODELS<br />

General<br />

The modeling software, a proprietary product called IDEAS, was developed by our contractor specifically <strong>for</strong><br />

dynamic process simulation. While it proved to be a competent and robust tool, IDEAS does require<br />

considerable training and practice, <strong>for</strong> a good process engineer to become a proficient modeler.<br />

Process models are created by graphically connecting pre-programmed “Objects” in a logical sequence on a<br />

“Worksheet”. The Worksheet looks somewhat like a process and instrument diagram (P&ID). The icons <strong>for</strong><br />

many of the objects, or groups of objects, usually take on the appearance of a specific piece of process<br />

equipment, while the models themselves become functioning pressure-flow networks of pipes, pumps, valves,<br />

tanks and other equipment.<br />

Appropriately programmed, models can predict the operating characteristics of the process and track variables<br />

of interest. The modeling software allows the developer to combine discrete and continuous simulation on a<br />

single Worksheet. The solution engine uses first principles equations to calculate mass, energy and<br />

momentum balances across multi-component systems. One particularly valuable feature of the modeling<br />

software is its ability to interface directly with most distributed control systems.<br />

Objects<br />

An object, or a group of objects, possess an icon-style representation; a dialog box <strong>for</strong> entering and viewing<br />

equipment specifications and other data; and connectors, so that a number of objects can be assembled into<br />

models on a Worksheet. See Figure 2, below. Objects can be obtained from one of a number of libraries.<br />

Objects, in effect, emulate the behavior of specific parts of the process; from a simple mixing tee to a sizable<br />

piece of process equipment. In<strong>for</strong>mation is passed into the object through the input connectors where it is<br />

processed by internal computer code. The object transmits in<strong>for</strong>mation, via its output connectors, to the next<br />

part of the model.<br />

Object Libraries<br />

In<br />

Fouling Fouling<br />

Factor<br />

Rejects<br />

Accepts<br />

Figure 2 <strong>Dynamic</strong> Pressure Screen Icon<br />

An Object Library is a repository <strong>for</strong> a group of pre-programmed objects. An individual library normally<br />

holds objects that possess a common purpose or which belong to an associated equipment family. A few of<br />

the objects used to build the <strong>Aracruz</strong> models have the following names: Pressure Screen, Macro Conveyor,<br />

<strong>Dynamic</strong> Wash Stage and Incompressible Tank.<br />

www.andritz.com 4 of 16


Worksheet Building - Featuring a Modern Commercial Pressure Washer<br />

The Wash Stage Object<br />

The DD Washer TM , a commercially available, multi-stage pressure washer, is one of the key pieces of process<br />

equipment selected <strong>for</strong> the Mill “C” fiberline. The <strong>Aracruz</strong> supply includes three different models of this<br />

washer, although some general principles apply. Fresh wash liquor is fed to the last zone of the washer. After<br />

passing through the pulp mat, the filtrate is collected in a chamber and pumped to the preceding zone of the<br />

washer. This counter-current washing continues until the filtrate exits the washer at the first zone(s) which see<br />

the incoming pulp. A vacuum suction zone follows the last washing zone, after which the pulp is discharged<br />

by means of pressurized air. Figure 3, below, shows one example of DD Washer TM internal flows.<br />

Figure 3 Drum Displacer Washer (DD Washer TM ) Internal Flows<br />

The Wash Stage object can be used to model each of the three zones of a typical washing operation; mat<br />

<strong>for</strong>mation, displacement washing and vacuum dewatering. See Figure 4, below.<br />

Gas Shower R1 R2 Speed<br />

D1<br />

D2<br />

WASH STAGE<br />

Mat<br />

In Flush K1 Filtrate<br />

K<br />

Mat<br />

Out<br />

Figure 4 Wash Stage Object<br />

The modeler can select the appropriate washing zone by choosing the correct options from the Input<br />

Parameters tab in the object’s dialog box. This simple approach allows the modeler the flexibility of<br />

configuring any given commercial washer by combining appropriate Wash Stage objects to match the<br />

equipment design. The Wash Stage object’s computer code includes the following engineering concepts:<br />

www.andritz.com 5 of 16


Drainage velocity ( w ) equation:<br />

⎛ ρ ⎞<br />

∆P ⎜<br />

⎜1−<br />

c⎟<br />

⎝ ρ ⎟<br />

fib ⎠<br />

w = − 2 2 2<br />

S µρ c kZ<br />

Where,<br />

v m<br />

3<br />

dp / dZ = pressure gradient across a mat of thickness Z<br />

S v = specific surface area of the fibers<br />

(m 2 fiber/kg fiber)<br />

µ = viscosity of filtrate (kg/m-s)<br />

ρ = mat density (kg mat/ m 3 mat)<br />

ρ fib = fiber density (kg fiber/ m 3 fiber)<br />

c = consistency of the mat<br />

(kg fiber/kg mat)<br />

w = linear velocity of the filtrate (m/s)<br />

k = Kozeny factor<br />

Assuming that curvature, compared to the thickness, of the mat within the wash zone is small, then the mat<br />

can be modeled as a flat surface. Consider a flat section of mat of thickness Z m , width y , arc length S , as<br />

shown in Figure 5, below.<br />

Consistency equation:<br />

C<br />

B<br />

RZmC A<br />

=<br />

Z + Z C ( R − 1) − w( 1−<br />

C ) dt<br />

m m A A<br />

Figure 5 Flat Mat Surfaces in Wash Zone<br />

Where the new consistency CB at the end of a zone is a function of the consistency CA at the beginning of<br />

the zone. When this calculation is repeated over all N z slices in the zone, we can obtain the consistency<br />

profile over a full wash zone.<br />

www.andritz.com 6 of 16


Washing calculations:<br />

( 100 C)<br />

C<br />

DF = W / P − − /<br />

Where DF is the dilution factor (mass of water per unit mass of pulp that enters the filtrate system), W is the<br />

mass flow of water per unit time, P is the mass flow of pulp per unit time and C is the discharge consistency.<br />

( C − C ) ( C C )<br />

DR = / −<br />

f<br />

d<br />

f<br />

s<br />

Where DR is the displacement ratio, C f is the feed consistency, d C is the discharge consistency, and C s is<br />

the shower consistency.<br />

The DD Washer TM Hierarchical Block<br />

The DD Washer TM is built as a series of dynamic Wash Stage objects. The first Wash Stage object represents<br />

the <strong>for</strong>mation zone, the next object, two or more displacement washing zones, and the last one, the vacuum<br />

zone. In addition, a Macro Conveyor object linked with an Incompressible Tank object represent the repulper,<br />

located at the pulp outlet side of the washer.<br />

A hierarchical block, or H-Block, is a collection of objects, which become a subsystem, or a significant piece<br />

of vendor equipment, in the Worksheet. To complete our washer example, a filtrate tank, vacuum tank,<br />

pumps, inlet valves and the standpipe also are joined to the H-Block connectors. The whole DD Washer TM<br />

subsystem becomes an integral part of the brown stock fiberline or the bleach plant area of the model.<br />

In developing the models, the essential engineering in<strong>for</strong>mation was drawn from project documentation<br />

provided to <strong>Aracruz</strong> by each EPC supplier. When working versions of the models were achieved, the EPC<br />

suppliers were invited to witness trials and provide feedback on the completeness of models in their<br />

respective areas.<br />

In order to test the models, a rudimentary control strategy must be included in each model Worksheet. This<br />

strategy need not be as extensive, nor a duplicate of the real strategy as it will be “turned –off” when the<br />

actual DCS control logic is “joined” to the model during staging.<br />

Following some additional work, the models were ready <strong>for</strong> their role in DCS staging.<br />

www.andritz.com 7 of 16


STAGING THE DCS AND THE SIMULATOR<br />

Initial Plan<br />

During the course of <strong>Simulator</strong> staging activities in each process area, three important steps stand out:<br />

1. Mapping of DCS/<strong>Simulator</strong> inputs and outputs (I/O Mapping);<br />

2. Verification of the individual control loops; and<br />

3. Verification of the EPC operating procedures and final validation of the process models (the Joint –<br />

FAT).<br />

Foxboro<br />

Activities<br />

1st SaveAll<br />

AMEC <strong>Simulator</strong><br />

Staging Activities<br />

Foxboro Pre - FAT<br />

(CP Hardware)<br />

Duration : Variable<br />

I/O Mapping<br />

Personnel : AMEC, Si ndus<br />

Duration : 1 week<br />

2nd SaveAll<br />

Fox App SW Fox App SW<br />

Foxboro FAT<br />

(CP Hardware)<br />

Duration : Variable<br />

IDEAS Mini - Sys te m IDEAS Mini - Sys te m<br />

Activities : build cross -<br />

reference database,<br />

finalize I/O addresses , I/O<br />

communications check<br />

Modifications to<br />

Fox App SW<br />

Initial <strong>System</strong> - W ide<br />

Check<br />

Preparation <strong>for</strong> Final Joint FAT<br />

Activities : Individual control<br />

loops and motor start -<br />

stops tested tes ted , Foxboro App<br />

SW & model pre - check ,<br />

controller pre - tuning<br />

Personnel : AMEC, Si ndus ,<br />

<strong>Aracruz</strong> Operator<br />

Duration : 1 week<br />

3rd SaveAll<br />

Fox App SW<br />

IDEAS Model<br />

Figure 6 Initial In<strong>for</strong>mation and Workflows during Staging<br />

Final SaveAll<br />

(CP Hardware)<br />

Fox App SW<br />

Final SaveAll<br />

(FSIM Softwar e)<br />

IDEAS Mini - Sys te m<br />

Joint Fox App S W FAT<br />

Activities : Area - wide start - up<br />

& shutdown witnessed by<br />

EPC Supplier & Foxboro ,<br />

group starts tested ; changes<br />

made to Foxboro App SW<br />

Personnel : AMEC, <strong>Aracruz</strong>,<br />

Foxboro , EPC Supplier<br />

Duration : 1 week<br />

At the onset, we developed a diagram, which describes the flow of in<strong>for</strong>mation and activities of the <strong>Simulator</strong><br />

in relation to DCS staging. It is shown as Figure 6, below.<br />

To support this work process and the proposed schedule, we also developed three so-called "mini-systems".<br />

These systems were hardware abbreviations of our final system architecture, but they were able to run the<br />

same software <strong>for</strong> a single area. Later in the staging process we developed techniques to allow the staging of<br />

two areas using a slightly modified mini-system.<br />

www.andritz.com 8 of 16


DCS/<strong>Simulator</strong> I/O Mapping<br />

On the <strong>Simulator</strong> side, the first step executed is the mapping into the system of all DCS inputs and outputs. In<br />

this step, each I/O device in the process model and the matching entities in the DCS configuration must be<br />

aligned. The product of this activity is called the "Cross-Reference Database".<br />

The model developer accomplishes this activity, as the onus is on him to match the DCS system, not the other<br />

way around. The modeler needs only support from a DCS technician in obtaining an appropriate SaveAll.<br />

At this stage, the DCS configuration does not have to be a highly developed one. With his Cross-Reference<br />

Database assembled, the model developer could appear at staging perhaps three days be<strong>for</strong>e the finish of the<br />

conventional DCS contractor’s FAT, <strong>for</strong> a final pre-check of process model-DCS communications.<br />

<strong>Control</strong> Loops Verification<br />

After the construction of the Cross-Reference Database, the <strong>Simulator</strong> team is ready to begin the verification<br />

of configuration coding. In this step, the model developer must have the support of a DCS technician, <strong>for</strong><br />

adjustment of control parameters. He also needs an experienced console operator to run the <strong>Simulator</strong> and the<br />

DCS contractor’s configuration coder, <strong>for</strong> correction of mistakes in the configuration that might impede the<br />

continuity of the checkout work<br />

However, if a more integrated procedure were to be used, we feel that a "control configuration ready <strong>for</strong><br />

<strong>Simulator</strong> staging" must at a minimum be complete (no areas marked “to come”), including all features such<br />

as group starts and sequencing. It also must be pre-checked to the best of the coders´ ability. Extending<br />

conventional staging too long is a questionable use of resources. However, coming into staging without a<br />

complete control configuration is an even worse waste of resources.<br />

As soon as the console operator starts to execute the start-up, shutdown and emergency procedures of the<br />

plant, the real business of <strong>Simulator</strong> staging starts.<br />

Using ever more advanced SaveAlls (configuration loads) from the DCS side, individual control loops were<br />

tested, by trying to start the area. Motor start/stops also were tested and controllers pre-tuned. The work might<br />

seem to have been relatively routine, but it was made more complex by the existence of three types of<br />

possible “deviations”; deviations in the process models themselves, in the logic underlying the DCS control<br />

strategy and in the DCS configuration coding. Every deviation, or potential improvement, was logged on a<br />

<strong>for</strong>mal, so-called, “punch list”.<br />

On the Mill “C” project, punch lists were augmented daily and delivered to the DCS coder <strong>for</strong> correction of<br />

outstanding items in the course of his work. As well, the coder might be asked to make emergency corrections<br />

of items blocking the progress of <strong>Simulator</strong> staging work.<br />

For each new EPC area, the <strong>Simulator</strong> had to prove to the uninitiated that it was a potent tool. In this regard,<br />

the punch lists became the focus. Either the items on it were valid, or they were not. The alternative of the<br />

EPC signing off on staging be<strong>for</strong>e the <strong>Simulator</strong> was employed soon became passé. As soon as the <strong>Simulator</strong><br />

was used, mistakes that conventional checking methods could not find were revealed.<br />

As the work proceeded, it also became necessary to make modeling corrections or changes. Often, the<br />

changes made to the models were not to correct mistakes; they were more often aimed at achieving the<br />

desired process response, to accomplish training objectives. The demands on a model <strong>for</strong> staging are<br />

somewhat lower than <strong>for</strong> training, but step-wise changes were considered, and often made, to prepare the<br />

<strong>Simulator</strong> <strong>for</strong> training. The net effect was a higher fidelity <strong>Simulator</strong> <strong>for</strong> both purposes.<br />

www.andritz.com 9 of 16


In general, because loop testing did not involve the EPCs, but was essentially a check of the configuration<br />

coder’s implementation of the EPC’s control philosophy; the issues were identified only, and listed on the<br />

punch lists. They were usually held <strong>for</strong> the next step of the process, the Joint-FAT.<br />

As the work progressed towards a fully functioning <strong>Simulator</strong>, the <strong>Aracruz</strong> operators (later our Trainers)<br />

began to have an opportunity to take a more detailed look at the control philosophy, interlock strategies and<br />

the patterns of implementation, or slight variations in standards or norms adopted by each EPC supplier and<br />

his contractors.<br />

Joint Factory Acceptance Test<br />

In this last step of staging, it was again necessary to have the support of the model developer, the DCS<br />

technicians, the <strong>Aracruz</strong> operators, the DCS coder and, most importantly, the EPC supplier’s start-up engineer<br />

and ideally his lead area control specialist.<br />

In the Joint-FAT the majority of modeling problems were identified and corrected. In addition, we could<br />

address also the “held” questions on our punch lists; items concerning the EPCs control philosophy.<br />

In this activity, the EPC supplier was primarily responsible <strong>for</strong> verifying the faithful execution of the start-up,<br />

shutdown and other important emergency procedures. In most cases, we also were able to obtain detailed<br />

input from the EPC’s people about the control philosophy employed, process details and validation of the<br />

<strong>Simulator</strong> as ready <strong>for</strong> training in the EPCs area.<br />

<strong>Simulator</strong> Per<strong>for</strong>mance Issues - What do the Punch Lists Tell Us?<br />

The punch lists were generated at two steps in staging; after initial system checkout (mostly loop testing) and<br />

after the Joint-FAT. They identified mistakes in DCS configuration coding; modeling errors or suggested<br />

changes; control strategy errors or suggested changes in philosophy; and miss-specified or poorly<br />

communicated items. The lists are the essence of what was accomplished with the <strong>Simulator</strong> during DCS<br />

staging.<br />

Figure 7, next column, summarizes overall data <strong>for</strong> <strong>Simulator</strong>/DCS staging. The data shown are weighted<br />

according to the approximate level of ef<strong>for</strong>t that would be required to either correct or address the item. Note<br />

that the owner of each item determined the weighting <strong>for</strong> his items.<br />

Be<strong>for</strong>e we discuss the data, a brief explanation of what a punch list item actually means is in order. For the<br />

DCS coder, errors could be as simple as wrong addresses and screen errors to more serious disconnects, say<br />

the logic in group starts. For the model developer, errors would usually be divided into two categories;<br />

process conceptual errors (such as an incorrect reaction equation or wrong pump data) and logic errors (a<br />

wrong address). EPC items were 90 to 95% operator suggestions <strong>for</strong> control strategy improvement and 5 to<br />

10% errors in the control strategy. The later might be as simple as the wrong action on a valve to something<br />

much more complex. <strong>Aracruz</strong> items could be such things as DCS or control standards not correctly defined,<br />

or missing.<br />

As shown in Figure 7, the dominant items relate to control configuration coding, about 70% of all weighted<br />

errors. At least 50 to 60% of these errors were caught during loop testing, and most of the remainder surfaced<br />

in the Joint – FAT.<br />

www.andritz.com 10 of 16


Simulation<br />

Company<br />

18%<br />

Figure 7 Overall Punch List Data<br />

What is the value of catching these errors? Some of the errors are trivial, but others might delay the start-up of<br />

the plant or the continuance of operations until they are corrected. Still other errors might not stop the plant,<br />

but could lead to a drop in operating efficiency. Both of the last two categories might result in a loss of<br />

product quality.<br />

On the modeling side, most of the<br />

significant issues surfaced during the Joint –<br />

FAT. They were primarily issues that deal<br />

with the fidelity or truth of the model<br />

response. Modeling errors are usually not<br />

trapped during loop testing because the<br />

focus is on configuration coding. Fidelity<br />

issues are also likely to surface later as well,<br />

during training, when the focus of the team<br />

is even more on process response.<br />

A DCS configuration which could start the<br />

“virtual mill” was considered highly likely<br />

to be a configuration which would start the<br />

real mill. The virtual mill (in essence a<br />

dynamic process model, an area DCS<br />

control configuration and an array of<br />

supporting hardware and software) was at<br />

this point ready to be applied to operator training.<br />

General Statistics of Configuration<br />

Check Out Phase<br />

EPC<br />

Supplier<br />

14%<br />

Customer<br />

1%<br />

DCS<br />

Company<br />

67%<br />

www.andritz.com 11 of 16


TRAINING OPERATORS USING THE PROCESS SIMULATOR<br />

The <strong>Simulator</strong> training program was as comprehensive as we could make it in the time available. The primary<br />

goal was to allow the operators to become totally competent in the start-up and shut-down procedures. In<br />

addition, operating fault scenarios, some already used in staging, were installed on the system and Trainees<br />

were instructed to react to them as they would a normal task in a working mill.<br />

The advantage to <strong>Aracruz</strong> of this training was that the operators experienced a close to real life workout, but<br />

in a virtual setting. This setting eliminated any ill-effects on production, damage to process equipment, or<br />

negative effects on the environment. The training was provided well be<strong>for</strong>e we had to start-up the real mill.<br />

Training the Trainers<br />

In order to accomplish training on the <strong>Simulator</strong>, we decided to implement a concept of lead operators acting<br />

as Trainers <strong>for</strong> their peers. We nominated the best operators that we could find from the existing <strong>Aracruz</strong><br />

Mills “A” and “B”. The operators were released from their duties and put through a rigorous program of<br />

schooling and work, to prepare them <strong>for</strong> their new role as Trainers in their assigned areas.<br />

A number of the activities were part of the conventional training and commissioning designed by <strong>Aracruz</strong> and<br />

the EPCs <strong>for</strong> Mill “C”. Our <strong>Simulator</strong> Trainers received this training alongside their colleagues in classrooms<br />

or other settings. The remainder of the training was specific to the <strong>Simulator</strong>, or actually consisted of work<br />

that we had to do to prepare the <strong>Simulator</strong> <strong>for</strong> training.<br />

The seven stages of development of our Trainers are described below:<br />

1) EPC training<br />

Under the EPC suppliers’ contracts, they were required to deliver a comprehensive classroom program to<br />

<strong>Aracruz</strong> operating and maintenance personnel. For each EPC area, the lectures were delivered over a period<br />

of about fifteen days, based upon eight-hour days, and were supplemented by the EPC-prepared Operating<br />

Manuals.<br />

2) Training Scenarios development<br />

The first involvement of the operators with the <strong>Simulator</strong> was prior to staging, immediately after EPC model<br />

checkout in Atlanta, Georgia. It involved the elaboration of training scenarios. In a general way, the scenarios<br />

were based on two causes; operational and equipment failures.<br />

3) DCS Staging and FAT<br />

The Trainers were involved also in the DCS contractor’s Factory Acceptance Test (FAT). That activity built a<br />

practical understanding of the control philosophy.<br />

www.andritz.com 12 of 16


4) DCS Staging using the <strong>Simulator</strong><br />

Following the conventional FATs, the Trainers were employed on <strong>Simulator</strong> staging. This work allowed them<br />

to become familiar with the simulation software and to learn how to use the <strong>Simulator</strong> to verify interlocks,<br />

sequencing, the operation of valves and many other things.<br />

5) Joint-FAT<br />

The Trainer next played a key role in the Joint-FAT by actually running the virtual area. At the conclusion of<br />

this step, the EPC start-up engineer, in consultation with the Trainer and the development team, validated the<br />

<strong>Simulator</strong> as ready <strong>for</strong> training.<br />

6) Scenarios testing – a post Joint-FAT<br />

After validation of the <strong>Simulator</strong> in a given area, the Trainer and model developer pre-tested the scenarios and<br />

established such metrics as target response times and expected Trainee per<strong>for</strong>mance. By this time the Trainers<br />

were extremely well versed in virtually all aspects of the DCS, the controls and the <strong>Simulator</strong>.<br />

7) Training with IDEAS Instructor<br />

The Trainer was also taught how to use the <strong>Simulator</strong> “Instructor” software. This training was particularly<br />

important because, “Instructor” was used to launch the model and other application programs (it effectively<br />

starts-up the <strong>Simulator</strong>). It also allows the Trainer to login a student and keep an administrative record of the<br />

training.<br />

Operator Training Program<br />

In order to determine the minimum number of hours of <strong>Simulator</strong> training required <strong>for</strong> each area of the mill,<br />

we developed with the Trainer, a list of important activities and estimates of the time that we would need on<br />

the <strong>Simulator</strong> to accomplish them. We determined that the Trainee should complete these activities at least<br />

twice.<br />

For example, the training plan <strong>for</strong> the Bleaching Area is listed below:<br />

• Review of the main process differences and interlock strategies, in Mills "A" and "B" compared to<br />

Mill "C";<br />

• Start-up from an empty system, in a manual mode, with water;<br />

• Start-up from an empty system, in a manual mode, with pulp;<br />

• An emergency shut-down of the plant;<br />

• Start-up from a full system;<br />

• Planned shut-down with a total emptying of the plant;<br />

• Start-ups and shut-downs in automatic; and<br />

• Evaluation of the training: start-up, shutdown and selected operating scenarios.<br />

The training schedule was based on training in pairs, with individual evaluations only. We also prioritized the<br />

program in some of the last areas by giving the front-line console operators as much time as we had available.<br />

www.andritz.com 13 of 16


Figure 8, below, displays the number of training hours <strong>for</strong> each area operator. In all, 52 operators, including<br />

the Trainers, received <strong>Simulator</strong> training. The configuration of the <strong>Simulator</strong> <strong>for</strong> ongoing training and other<br />

post start-up activities is shown in Figure 9, on page 13.<br />

Trainee Feedback<br />

Training Hours<br />

45<br />

40<br />

35<br />

30<br />

25<br />

20<br />

15<br />

10<br />

5<br />

0<br />

Cooking<br />

40<br />

Hours Training per Operator by Area<br />

Bleaching<br />

38<br />

Recaust/Lime Kiln<br />

24 24 24<br />

Evaporation<br />

Figure 8 Operator Training Summary Data<br />

Trainee feedback was very positive. In most cases Trainee evaluations were offered in considerable detail<br />

concerning experiences. There was a unanimous feeling that the <strong>Simulator</strong> had indeed helped them and had<br />

been important to the start-up of Mill “C”. In fact, EPC start-up engineers echoed these sentiments, remarking<br />

upon the ease with which the operators navigated the DCS screens and the confidence that they displayed in<br />

enacting the various start-up and shutdown procedures.<br />

ClO2<br />

Delig<br />

16<br />

Screening<br />

www.andritz.com 14 of 16<br />

16<br />

Drying<br />

11


OBSERVATIONS AND CONCLUSIONS<br />

The <strong>Simulator</strong> was purchased <strong>for</strong> the Mill “C” project primarily <strong>for</strong> the perceived values it would have in<br />

DCS staging and operator training. Did it pay its way? Or more specifically, did it help to produce a faster<br />

start-up and faster ramp-up curve?<br />

These questions cannot be answered fully yet because the start-up was less than one month ago. Nevertheless,<br />

this question still will be difficult to address in precise quantitative terms. The difficulty lies in the fact that a<br />

good start-up and a steep ramp-up curve are the sum product of many things: good planning and well-<br />

executed engineering throughout the project; good construction technique and superior execution; all facets of<br />

training (in addition to operator training); well-planned and executed commissioning and many other aspects.<br />

Figure 9 Final Architecture of the <strong>Aracruz</strong> <strong>Simulator</strong><br />

www.andritz.com 15 of 16


The pertinent question is can one separate these and many more factors and assign realistic monetary values?<br />

On the <strong>Aracruz</strong> Mill “C” project, we believe that we executed many of these factors as well, if not better, than<br />

many who came be<strong>for</strong>e us. However, in addition, we had an experienced and well-educated team of operators<br />

and maintenance people, drawn from the Mills “A” and “B” and a smoothly functioning management and<br />

supervisory structure already in place.<br />

These aspects acknowledged, we believe that there is ample evidence to support the conclusion that the<br />

<strong>Simulator</strong> was a strong contributor to our overall success. The project was executed on an exceedingly tight<br />

schedule. It is arguable that without the <strong>Simulator</strong> as an incentive (to get ready <strong>for</strong> operating training) and as a<br />

prod (the team did its best to keep the pressure on to accomplish this) that we probably would not have done<br />

as well in getting the control systems ready, not just <strong>for</strong> start-up, but significantly <strong>for</strong> commissioning as well.<br />

The punch list items are “hard” evidence that we made the control systems more error-free. The lists<br />

constitute a body of real errors caught be<strong>for</strong>e commissioning and start-up. There were, in fact, many<br />

improvements made to the control logic as well.<br />

During commissioning, virtually no problems surfaced regarding the DCS and the control configuration. This<br />

advanced stage of readiness, we feel contributed to our strong commissioning per<strong>for</strong>mance, in that the team<br />

was free to concentrate on other aspects, primarily the physical ones.<br />

The mill start-up, from first chips to the digester to<br />

the first bale of pulp, proceeded continuously over a<br />

period of 45 hours, without a single control<br />

configuration stoppage. The first significant stoppage<br />

was mechanical in nature. In fact, at this time in the<br />

mill’s ramp-up, we still have not observed any<br />

significant problems with the DCS due to<br />

configuration errors in the areas prepared by the<br />

<strong>Simulator</strong>.<br />

From the first hour of the start-up, the operators<br />

exhibited a confidence and knowledge of the start-up<br />

procedures and the controls not seen be<strong>for</strong>e by many<br />

of the EPCs experienced start-up people. The<br />

operators’ familiarity with the DCS screens, the<br />

instrument tags, and the control and inter-lock details has allowed them to contribute on an equal basis with<br />

the EPCs start-up personnel. For the main part, the <strong>Aracruz</strong> operators “owned” the mouse from the very<br />

beginning and have never released it from their grasp.<br />

www.andritz.com 16 of 16

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!