IEE Haveri (23-05-09).pdf - kuidfc
IEE Haveri (23-05-09).pdf - kuidfc IEE Haveri (23-05-09).pdf - kuidfc
NKUSIP (Package I - Dharwad)Tranche I Sub-Projects in Haveri CMCInitial Environmental Examination80. Under Drainage component, two secondary drain links are proposed to servethe low-laying areas of Chicknan Kere area and Chouki Gunda. Thesesecondary drains will be constructed to dispose the storm water from theselow-lying areas by providing links with Dodda Halla - primary drain of Haveritown. The proposed drain will be constructed partially along the roads ofresidential areas and further extends through agricultural fields to reachprimary drain. There are no sensitive environmental features along its length.KUIDFC35WSAPL
NKUSIP (Package I - Dharwad)Tranche I Sub-Projects in Haveri CMCInitial Environmental ExaminationV. SCREENING OF POTENTIAL ENVIRONMENTALIMPACTS AND MITIGATION MEASURES81. Potential environmental impacts of the proposed infrastructure components arepresented in this section. Mitigation measures to minimize/mitigate negativeimpacts, if any, are recommended along with the agency responsible forimplementation. Monitoring actions to be conducted during theimplementation phase is also recommended to reduce the impact.82. Screening of potential environmental impacts is categorized into four categoriesconsidering Investment Program phases: location impacts and design impacts(pre construction phase), construction phase impacts and operations andmaintenance phase impacts.i) Location impacts include impacts associated with site selection andinclude loss of on-site biophysical array and encroachment either directlyor indirectly on adjacent environments. It also includes impacts on peoplewho will lose their livelihood or any other structures by the developmentof that site.ii) Design impacts include impacts arising from Investment Program design,including technology used, scale of operation/throughput, wasteproduction, discharge specifications, pollution sources and ancillaryservices.iii) Construction impacts include impacts caused by site clearing, earthworks,machinery, vehicles and workers. Construction site impacts includeerosion, dust, noise, traffic congestion and waste production.iv) O&M impacts include impacts arising from the operation andmaintenance activities of the infrastructure facility. These include routinemanagement of operational waste streams, and occupational health andsafety issues.83. Screening of environmental impacts has been based on the impact magnitude(negligible/moderate/severe – in the order of increasing degree) and impactduration (temporary/permanent). The following table shows the screening ofimpacts; N/T represents the lowest impact while S/P represents the highestimpact. Numerator represents the Degree of Impact and denominatorrepresents the Duration of impact.84. In case of sewerage components, no significant impacts are anticipated sincethe laying of sewer line will be along the already built up area. STP location hasKUIDFC36WSAPL
- Page 1 and 2: Karnataka Urban Infrastructure Deve
- Page 3 and 4: NKUSIP (Package I - Dharwad)Tranche
- Page 5 and 6: NKUSIP (Package I - Dharwad)Tranche
- Page 7 and 8: NKUSIP (Package I - Dharwad)Tranche
- Page 9 and 10: NKUSIP (Package I - Dharwad)Tranche
- Page 11 and 12: NKUSIP (Package I - Dharwad)Tranche
- Page 13 and 14: NKUSIP (Package I - Dharwad)Tranche
- Page 15 and 16: NKUSIP (Package I - Dharwad)Tranche
- Page 17 and 18: NKUSIP (Package I - Dharwad)Tranche
- Page 19 and 20: NKUSIP (Package I - Dharwad)Tranche
- Page 22 and 23: NKUSIP (Package I - Dharwad)Tranche
- Page 24 and 25: NKUSIP (Package I - Dharwad)Tranche
- Page 26: NKUSIP (Package I - Dharwad)Tranche
- Page 29: NKUSIP (Package I - Dharwad)Tranche
- Page 32 and 33: NKUSIP (Package I - Dharwad)Tranche
- Page 34 and 35: NKUSIP (Package I - Dharwad)Tranche
- Page 36 and 37: NKUSIP (Package I - Dharwad)Tranche
- Page 38 and 39: NKUSIP (Package I - Dharwad)Tranche
- Page 42 and 43: NKUSIP (Package I - Dharwad)Tranche
- Page 44 and 45: NKUSIP (Package I - Dharwad)Tranche
- Page 46 and 47: NKUSIP (Package I - Dharwad)Tranche
- Page 48 and 49: NKUSIP (Package I - Dharwad)Tranche
- Page 50 and 51: NKUSIP (Package I - Dharwad)Tranche
- Page 52 and 53: NKUSIP (Package I - Dharwad)Tranche
- Page 54 and 55: NKUSIP (Package I - Dharwad)Tranche
- Page 56 and 57: NKUSIP (Package I - Dharwad)Tranche
- Page 58 and 59: NKUSIP (Package I - Dharwad)Tranche
- Page 60 and 61: NKUSIP (Package I - Dharwad)Tranche
- Page 62 and 63: NKUSIP (Package I - Dharwad)Tranche
- Page 64 and 65: NKUSIP (Package I - Dharwad)Tranche
- Page 66 and 67: NKUSIP (Package I - Dharwad)Tranche
- Page 68 and 69: NKUSIP (Package I - Dharwad)Tranche
- Page 70 and 71: NKUSIP (Package I - Dharwad)Tranche
- Page 72 and 73: NKUSIP (Package I - Dharwad)Tranche
- Page 74 and 75: NKUSIP (Package I - Dharwad)Tranche
- Page 76 and 77: NKUSIP (Package I - Dharwad)Tranche
- Page 78 and 79: NKUSIP (Package I - Dharwad)Tranche
- Page 80 and 81: NKUSIP (Package I - Dharwad)Tranche
- Page 82: NKUSIP (Package I - Dharwad)Tranche
NKUSIP (Package I - Dharwad)Tranche I Sub-Projects in <strong>Haveri</strong> CMCInitial Environmental ExaminationV. SCREENING OF POTENTIAL ENVIRONMENTALIMPACTS AND MITIGATION MEASURES81. Potential environmental impacts of the proposed infrastructure components arepresented in this section. Mitigation measures to minimize/mitigate negativeimpacts, if any, are recommended along with the agency responsible forimplementation. Monitoring actions to be conducted during theimplementation phase is also recommended to reduce the impact.82. Screening of potential environmental impacts is categorized into four categoriesconsidering Investment Program phases: location impacts and design impacts(pre construction phase), construction phase impacts and operations andmaintenance phase impacts.i) Location impacts include impacts associated with site selection andinclude loss of on-site biophysical array and encroachment either directlyor indirectly on adjacent environments. It also includes impacts on peoplewho will lose their livelihood or any other structures by the developmentof that site.ii) Design impacts include impacts arising from Investment Program design,including technology used, scale of operation/throughput, wasteproduction, discharge specifications, pollution sources and ancillaryservices.iii) Construction impacts include impacts caused by site clearing, earthworks,machinery, vehicles and workers. Construction site impacts includeerosion, dust, noise, traffic congestion and waste production.iv) O&M impacts include impacts arising from the operation andmaintenance activities of the infrastructure facility. These include routinemanagement of operational waste streams, and occupational health andsafety issues.83. Screening of environmental impacts has been based on the impact magnitude(negligible/moderate/severe – in the order of increasing degree) and impactduration (temporary/permanent). The following table shows the screening ofimpacts; N/T represents the lowest impact while S/P represents the highestimpact. Numerator represents the Degree of Impact and denominatorrepresents the Duration of impact.84. In case of sewerage components, no significant impacts are anticipated sincethe laying of sewer line will be along the already built up area. STP location hasKUIDFC36WSAPL