13.07.2015 Views

Earl J. Kenzie, P.E., Ann Arbor WWTP Manager Nicole B. Spieles ...

Earl J. Kenzie, P.E., Ann Arbor WWTP Manager Nicole B. Spieles ...

Earl J. Kenzie, P.E., Ann Arbor WWTP Manager Nicole B. Spieles ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>Earl</strong> J. <strong>Kenzie</strong>, P.E., <strong>Ann</strong> <strong>Arbor</strong> <strong>WWTP</strong> <strong>Manager</strong><strong>Nicole</strong> B. <strong>Spieles</strong>, P.E., Greeley and HansenMWEA <strong>Ann</strong>ual ConferenceTuesday, June 28, 2011


<strong>Ann</strong> <strong>Arbor</strong> <strong>WWTP</strong> Background•West Plant (9.5 MGD): 1937 - 1939•East Plant (20 MGD): 1977 - 1981•Serves City of <strong>Ann</strong> <strong>Arbor</strong> andTownships of <strong>Ann</strong> <strong>Arbor</strong>, Pittsfield andScio


<strong>Ann</strong> <strong>Arbor</strong> <strong>WWTP</strong> Background•Modified A/O process‣Activated sludge‣Biological phosphorus removal•Tertiary filtration•UV disinfection


<strong>Ann</strong> <strong>Arbor</strong> <strong>WWTP</strong> Background


History of Biosolids Management• 1960s:• 1970s:• 1980s:• 1990s:Digestion/IncinerationLand application (liquid) anddigestion/incinerationIncineration and landfillingLand application (liquid) in nonwintermonths; incinerationotherwise• Current: Land application (liquid) in nonwintermonths; dewatering andlandfill otherwise


Former Solids Handling Facilities• Three Gravity Thickeners (Comingled)• Four Sludge Holding Tanks• Lime Stabilization (Liquid Biosolids)• Three Plate and Frame Presses


Former Solids Handling Facilities


Former Solids Handling Facilities


Former Solids Handling Facilities


Former Solids Handling Facilities


Project Drivers•Existing systems became obsolete•Increasing O&M costs•Declining operating efficiencyLABOR INTENSIVE!


Project Study•Stakeholder Engagement‣Plant Staff‣Community Members•Selection Criteria‣Operating History‣O & M‣Aesthetics‣Implementation•Alternatives Evaluation


Project Design•Stakeholder Engagement•Site Visits to <strong>WWTP</strong>s•Pilot Testing•Project Workshops


Design Goals•Provide process flexibility•Improved efficiency•Removal of obsolete equipment•Reuse of existing facilities


Removal of Obsolete Equipment


Removal of Obsolete Equipment


Construction•Schedule‣Construction Start: February 2009‣Anticipated Completion: October 2011•Budget‣Bid: $42,444,927‣Change Orders: $500,000 to date


Construction Challenges•Maintaining plant operations‣Temporary Liquid Biosolids LoadingStation‣Temporary Cake Conveyor‣Temporary Ferric Chloride Tank•Retrofit of new equipment into existingstructure


Temporary Liquid BiosolidsLoading


Temporary Cake Conveyor


Temporary Ferric Chloride Tank


New Solids Handling Facilities• Rehabilitated Gravity Thickener (primarysludge)• Converted Two Gravity Thickeners toBlend Tanks• Two New Gravity Belt Thickeners (WAS)• Three New Centrifuges• New Truck Loading Facility• New Odor Control Equipment


Gravity Thickener Tank


Blend Tanks


Gravity Belt Thickeners


Centrifuges


Solids Handling Building BeforeAddition


New Truck Loading Facility


New Truck Loading Facility -Cake Lime Addition


New Truck Loading Facility –Liquid Biosolids Loading


New Truck Loading Facility -Cake Loading


Odor Control


Benefits - Solids Concentrations40353025201510ThickeningDewateringDewatering Chemicals50Pre-project averagePost-project average


Benefits – Biosolids Storage1,2001,000800600400Thickened biosolids(mGal)Dewatered cake (CY)2000Pre-project volumePost-project volume


How Staff Adapted•New Equipment & Processes•Management Strategy Changes•Staff Scheduling


Questions?

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!