13.07.2015 Views

Washington Works - DuPont

Washington Works - DuPont

Washington Works - DuPont

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Contract Administration Initiated: 07/1992 CAG-07Site Conditions SC1 Revised: 05/2013 Monitor: John SorokaRetention: 3 yrs after obsolete or superseded Revision Due: 10/2015 Page 19Rigging from the platform or boom will not be permitted.Climbing out of the aerial work platform to another elevated work location will not bepermitted.No one shall be permitted to operate a lifting device (material or personnel) unless they havebeen properly trained on the specific piece of equipment being utilized to perform the work.Documentation of this training shall be furnished to <strong>DuPont</strong> before the operation of theequipment on <strong>DuPont</strong> property. The manufacturer’s operating instructions shall accompanyand/or be affixed to the device.Crane operator qualification reports must be completed and signed by Contractor managementand furnished to <strong>DuPont</strong> prior to any work utilizing a crane. This includes any crane work to bedone by their subcontractors. <strong>DuPont</strong> corporate Engineering Standard PH84 will be suppliedas required during pre-job meeting.Contractor shall submit a rigging preplan to <strong>DuPont</strong> for review and acceptance 15 days prior toany “critical” lift, as specified in <strong>DuPont</strong> Safety Standard PH84. A critical lift is defined whenany one of the following conditions exists:The load exceeds 75% of the crane capacity as the crane is configured to perform the lift.Lifts involving more than one crane to handle a common load.The crane or lifting device is used in an application that deviates from the manufacturer'srecommendations including, but not limited to:o Boom configuration not per boom make-up charto Moving a crane with longer boom than recommendedo Exceeding capacities or restrictions shown restrictions shown on the load charto Electrical panel boards are being lifted.The rigging preplan shall include:Manufacturer, model, and capacity of the crane(s)Capacity charts (see above)Working radiusBoom lengthWeight of load including riggingHow the weight was determinedNumber of parts of line to be usedSize and capacity of rigging hardware (slings, shackles, etc.)If requested by <strong>DuPont</strong>, Contractor shall submit a rigging preplan (as outlined above) no laterthan 7 calendar days before each non-critical lift is scheduled to be made.Structural steel members or other loads that are similar in configuration that are being lifted by asingle choker shall be double-wrapped to insure that the material will not slide out of therigging.1.40 Chain Falls and Mechanical LiftersContractor shall perform rigging work in accordance with instruction set forth in <strong>DuPont</strong>’s“Hand Rigging Book” (Orange Book), EN3964. This rigging handbook applies to the use ofchain falls, come-a-longs, lug-alls and similar mechanical lifting devices. (This handbook willCopyright © 2012 E. I. du Pont de Nemours and Company. All rights reserved

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!