13.07.2015 Views

Jurong Island, phase IV, Singapore - BAM International

Jurong Island, phase IV, Singapore - BAM International

Jurong Island, phase IV, Singapore - BAM International

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Project<strong>Jurong</strong> <strong>Island</strong>, <strong>phase</strong> <strong>IV</strong>, <strong>Singapore</strong>Thirty years of operational life have been added to the <strong>Jurong</strong> <strong>Island</strong> oil offloading facilities with twonew jetties, berthing facilities and two pipelines on newly reclaimed land. They replaced the existingthirty-year-old single mooring buoys and pipelines. Oil tankers up to 387,000 ton are now able to berthand offload along the platforms in a minimum water depth of 25 metres.The <strong>Jurong</strong> Phase <strong>IV</strong> reclamation project included the procurement and construction of the jetties,berthing facilities and pipelines.LocationClientContractorContract periodContract sum<strong>Jurong</strong> <strong>Island</strong>, <strong>phase</strong> <strong>IV</strong> land reclamation, <strong>Singapore</strong>Penta-Ocean / Koon / Dredging Int. / Boskalis / HAM (PKDBH) Consortium<strong>BAM</strong> <strong>International</strong> (in joint venture with McConnell Dowell of Australia)July 2000 – June 2002€85 million‘A multidisciplinary design and build contractfor the <strong>Singapore</strong> oil refinery industry.’February 2011800232-152


Dolphins under constructionPreparations – locally and overseasThe main materials were prepared in two separate yards, onelocal yard and one in Batam, Indonesia. In the overseas yard, steelfoundation piles were spliced. They were carried in batches by bargeacross 50 kilometres of sea. All precast units, such as capping beams,main roadway girder beams, platform main beams, tie-in beams,secondary tie-beams and slab units were fabricated at a precast yardin <strong>Singapore</strong>. Quality control systems were in place throughout thepreparation stage, as well as strict monitoring of concrete quality,finishing works and dimensional control.ConstructionThe trestles were constructed on steel open-ended piles, whichwere driven where the seabed was soft and drilled where hard tomoderate rock was encountered. The piles were provided withrock anchors to achieve the required tension capacity. A similarconstruction was used for the platforms: steel foundations withrock anchors, concrete precast beams and ties resting on pile caps,precast double T-slabs and concrete topping. Each jetty has eightdolphins which were constructed using false work and temporarypiles. The breasting dolphin and mooring dolphins were cast in situ,with the use of a floating batching plant.Start sink pipeAccess trestleMechanical worksThe mechanical installation works comprised,amongst others, four marine loading armson each platform, marine gangway towers,maintenance cranes and three sea intakepumps.Welding elbows<strong>BAM</strong> <strong>International</strong> bvP.O. Box 414H.J. Nederhorststraat 12800 AK GoudaThe NetherlandsT +31 (0)182 59 06 30F +31 (0)182 59 08 70E info@baminternational.comI www.baminternational.com

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!