13.07.2015 Views

TILT-UP CONSTRUCTION - Brock White

TILT-UP CONSTRUCTION - Brock White

TILT-UP CONSTRUCTION - Brock White

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

General and TechnicalInformationGeneral andTechnical InformationPanel ConstructionAfter the floor slab has been cleaned, the tilt-up panels areoutlined directly on the floor slab with chalk. The chalk linescan be sprayed with a coat of bondbreaker to prevent rainfrom washing them away. The panel edge forms, and anyopening forms can then be set in place.Fog the casting area with clean, potable water prior toapplication of the bondbreaker. The fogging should saturatethe slab, but any standing water must be removed before thebondbreaker is applied. The bondbreaker should be appliedin a two-coat application; the first coat of the material sprayedin one direction and the second coat sprayed perpendicularto the first. Be sure to let the first coat dry before applying thesecond coat. Applying the bondbreaker in this manner willhelp ensure a smooth, uniform coating.Check the slab and bondbreaker before pouring anyconcrete. The slab should have a slightly tacky, soapyfeeling. Bondbreaker can be tested by dropping a smallamount of water on the casting bed, from a height of about24” above to allow it to splatter. If the bondbreaker is appliedcorrectly, the water will bead into small droplets as it wouldon a freshly waxed automobile. If the water does not bead,respray all of the suspected areas of the casting slab.When all of the panel preparations are complete and thepanel is ready for placement of the concrete, the entire panelarea should be fogged with potable water to be certain thatthe pores of the concrete slab have been properly saturated.Make sure there is no standing water, and proceed with theconcrete placement.The panel concrete must be properly consolidated using anappropriate concrete vibrator. It is preferable to use the vibratorin an up and down motion. Laying the vibratorhorizontal and dragging it along the reinforcing steel will oftenleave the pattern of the rebar visible on the down side face ofthe panel. Avoid over vibration; it may cause segregation ofthe aggregate and bring excess water to the surface.Preparation for LiftingClean the panel and the surrounding floor slab area.Locate and prepare all pertinent embedded devices that areaccessible. Do any dressing or patching that can be accomplishedon the ground. Attach all pipe braces and strongbacksas required.Each panel should be numbered and clearly identifiedaccording to the panel layout/erection sequence plan. Placethe identifying mark in a position that will not be exposedwhen the structure is completed. The structure footing shouldalso be marked with the corresponding identifying numbersto give the erection crew clear indication where each panelgoes. The footing should be appropriately marked to showthe proper position of each panel on the footing.All lifting inserts should be uncovered, cleaned out andtested with a hardware unit several days prior to erection day.Rotary hammers, drills, leveling shims, cutting torch, steelwedges, pry bars, level and plumb bob and a full set of handtools should be available at the job site.Panel Erection TechniquesThe following panel erection techniques are suggested asan aid for the safe and efficient erection of tilt-up wall panels.• Layout — Prior to the day of erection, the panels should belaid out on the exterior foundations and the exterior wall lineestablished.• Alignment — One method of alignment is to mark thelimits of each panel, then drill 3/4” holes into the foundationapproximately 5” deep. Install two #5 rebars (approximately10” long) on each side of each panel.• Leveling — Prior to day of erection, install leveling shimswith a level so that the top of all panels are in line. Groutshould be installed around the shims to hold them in position.• Grout — After panels are erected and aligned, grout asspecified should be placed under each panel. Groutingshould be accomplished as early as possible after panelerection. Care should be taken to make certain the grout fillsthe void between bottom of panel and top of footing.After the LiftWhen constructing the floor slab, a perimeter strip,generally three to five feet wide is often open to facilitate thefooting excavation. This excavated area can be up to five orsix feet deep, depending on the building design, and won’tbe backfilled until after the wall panels have been erected.The perimeter strip must be backfilled and compacted verycarefully to avoid movement or bending of the panels.Usually there are reinforcing steel bars projecting from theslab into the perimeter area which will overlap the bars thatproject from the panels. If the panel is a “dock-high” panel, itmay be best to weld the floor rebar to the panel rebar. Afterthe backfill is in place and properly compacted, concrete isplaced into the perimeter strip to connect the floor slab to thewall panels.Wall braces should never be removed until all structuralconnections are complete. Note that the perimeter stripbetween the floor slab and the wall panels is considered astructural connection.If the building’s structural drawings do not indicate whenthe braces can be removed, the engineer of record should beconsulted.14 02-09

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!