Presentation update A15 project - Port of Rotterdam
Presentation update A15 project - Port of Rotterdam
Presentation update A15 project - Port of Rotterdam
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Update <strong>A15</strong> MaVa-<strong>project</strong>Summer 2011
Content• Introduction• What is A-Lanes <strong>A15</strong> going to do?• Planning• Mobility2
Introduction• A-Lanes <strong>A15</strong> is the consortium that closed a DBFM contract withRijkswaterstaat for the expansion <strong>of</strong> the <strong>A15</strong>.• The contract also includes building a new Botlek bridge andmaintaining the <strong>A15</strong> for the up-coming 25 years.• A-Lanes <strong>A15</strong> is situated at the Seattleweg 15 , Pernis,Netherlands• Contactperson: c.davidse@a-alanes.a15.nl3
What is A-Lanes <strong>A15</strong> going to do?Build and adjusting crossings• Design and build <strong>of</strong> a new Botlek bridge• Renovation <strong>of</strong> the Botlek tunnel and the Thomassen tunnel• Renovation <strong>of</strong> app. 36 crossings• Building <strong>of</strong> app. 12 new crossings• Installation <strong>of</strong> a dynamic traffic management systemMaintenance• Maintaining the current and new traffic lanesuntil 20354
Planning constructionRoad part Start FinishCrossing Benelux-Barendrecht- Zuidbaan September 2011 2e quarter 2014- Noordbaan September 2011 1e quarter 2015Hoogvliet-crossing Benelux- Zuidbaan November 2011 2e quarter 2014- Noordbaan November 2011 1e quarter 2015Stenen Baakplein-Hartelkruis- Both sides January 2013 2e quarter 2015Hartelkruis-Hoogvliet- Both sides April 2013 2e quarter 2015Botlekbrug- Constructions September 2011 4e quarter 2014- Breakdown old Botlek bridge 1e quarter 2016 4e quarter 2016Maintenance April 2011 April 20355
The <strong>project</strong> scope: Maasvlakte – Vaanplein <strong>A15</strong>A: Maasvlakte -RozenburgD: Spijkenisse-VaanpleinB: Rozenburg-Spijkenisse:C: Nieuwe BotlekbrugE: Vaanplein enA296
Mobility during realisation• Most <strong>of</strong> the work takes place during the night (22.00 - 05:00).– Reduction <strong>of</strong> road capacity only when necessary.• During daytime the traffic lanes have a regular appearance.– Regular speed limits– Consistent information provided– Regular road sings.7
XWork methodA-Lanes <strong>A15</strong>DAYWork methodA-Lanes <strong>A15</strong>NIGHT8