Property_Manu - Final - The New India Assurance Co. Ltd.
Property_Manu - Final - The New India Assurance Co. Ltd. Property_Manu - Final - The New India Assurance Co. Ltd.
The New India Assurance Co.Ltd.The tender set issued to the contractors must contain:SCHEDULE ‘A’(1) Details of all the materials, if any, being supplied to the contractors with terms andconditions.(2) Extent of facilities and amenities extended to the contractor with terms and conditions.(3) The facilities could be light, power, water, telephone, office space, space for site office,permission for staying, canteen, godown, security etc. etc.SCHEDULE ‘B’(1) Detailed tender with estimated items and estimated quantity.(2) Specifications(3) Mode of measurement(4) Detailed plans, elevations, sections(5) Designs(6) List of approved materials(7) List of approved manufacturer(8) Mode of payment(9) Permissible limit of variation in quantity(10) Admissibility of deviation in specification(11) Site clearance(12) Obligation of contractor towards workers, machinery, equipments, security, safeguards,precautions while executing the work(13) Amenities and facilities for the workers(14) Normal working hours(15) Establishment of site office(16) Establishment of sample room(17) Establishment of site laboratory for testing(18) Arranging for model laminated mounted plans, at the site office.114 MANUAL ON ESTATE & ESTABLISHMENT
The New India Assurance Co.Ltd.(19) Maintenance of site instructions book.(20) Procedure for arbitration.(21) Procedure for payment under escalation clause.TIME LIMIT :(1) Clear indication for recording the date of commencement and the date of completionshould be made.(2) Clear indication whether the time limit is inclusive or exclusive of monsoon should bemade.(3) Permissible extension in time limit without any extra compensation/penalty should beindicated.(4) Quantum of compensation/penalty to be imposed for further extension in time limit shouldbe indicated.(5) Maximum limit of compensation/penalty should be indicated.(6) Clarification about escalation in accepted tender rate either on account of material indexor labor index should be indicated, along with the basis being adopted for consideration.VARIATION IN QUANTITY :Generally, there should be no variation in quantities of executed items of work. But if thisoccur, the same should be explained by Contractor/ Architect/ Consulting Engineer &necessary permission of Chief Regional Manager/ Deputy General Manager/ GeneralManager needs to be obtained.(1) Extra items, if required, should be executed at the prevailing market rate. However, thequantum of such extra item executed should not exceed 15% of the sanctioned estimatedcost.(2) Deviation in specification will not be entertained except for compelling situations.CORRIGENDUM :(1) In case for any reason, there is a necessity to issue any corrigendum to the tender noticereleased earlier, for indicating changes, modifications etc. the same corrigendum mustappear in the same newspapers where the original tender notice had been published.(2) The intimation should be made available immediately to all the contractor who haveMANUAL ON ESTATE & ESTABLISHMENT115
- Page 63 and 64: The New India Assurance Co.Ltd.CIRC
- Page 65 and 66: The New India Assurance Co.Ltd.CIRC
- Page 67 and 68: The New India Assurance Co.Ltd.Sata
- Page 69 and 70: The New India Assurance Co.Ltd.No.0
- Page 71 and 72: The New India Assurance Co.Ltd.PROP
- Page 73 and 74: The New India Assurance Co.Ltd.Acco
- Page 75 and 76: The New India Assurance Co.Ltd.so f
- Page 77 and 78: The New India Assurance Co.Ltd.24.
- Page 79 and 80: The New India Assurance Co.Ltd.DRAF
- Page 81 and 82: The New India Assurance Co.Ltd.· T
- Page 83 and 84: The New India Assurance Co.Ltd.· T
- Page 85 and 86: The New India Assurance Co.Ltd.empl
- Page 87 and 88: The New India Assurance Co.Ltd.3. T
- Page 89 and 90: The New India Assurance Co.Ltd.(2)
- Page 91 and 92: The New India Assurance Co.Ltd.(3)
- Page 93 and 94: The New India Assurance Co.Ltd.3. F
- Page 95 and 96: The New India Assurance Co.Ltd.evid
- Page 97 and 98: The New India Assurance Co.Ltd.ESTA
- Page 99 and 100: The New India Assurance Co.Ltd.Esta
- Page 101 and 102: The New India Assurance Co.Ltd.(xvi
- Page 103 and 104: The New India Assurance Co.Ltd.Guid
- Page 105 and 106: The New India Assurance Co.Ltd.· E
- Page 107 and 108: The New India Assurance Co.Ltd.(3)
- Page 109 and 110: The New India Assurance Co.Ltd.Howe
- Page 111 and 112: The New India Assurance Co.Ltd.Tend
- Page 113: The New India Assurance Co.Ltd.All
- Page 117 and 118: The New India Assurance Co.Ltd.L-I
- Page 119 and 120: The New India Assurance Co.Ltd.B. M
- Page 121 and 122: The New India Assurance Co.Ltd.l Me
- Page 123 and 124: The New India Assurance Co.Ltd.ii.A
- Page 125 and 126: The New India Assurance Co.Ltd.Exec
- Page 127 and 128: The New India Assurance Co.Ltd.(12)
- Page 129 and 130: The New India Assurance Co.Ltd.(38)
- Page 131 and 132: The New India Assurance Co.Ltd.Exec
- Page 133 and 134: The New India Assurance Co.Ltd.(e)F
- Page 135 and 136: The New India Assurance Co.Ltd.Prin
- Page 137 and 138: The New India Assurance Co.Ltd.Issu
- Page 139 and 140: The New India Assurance Co.Ltd.Inst
- Page 141 and 142: The New India Assurance Co.Ltd.12.
- Page 143 and 144: The New India Assurance Co.Ltd.11.
- Page 145 and 146: The New India Assurance Co.Ltd.7. Y
- Page 147 and 148: The New India Assurance Co.Ltd.7. D
- Page 149 and 150: The New India Assurance Co.Ltd.Norm
- Page 151 and 152: The New India Assurance Co.Ltd.Any
- Page 153 and 154: The New India Assurance Co.Ltd.The
- Page 155 and 156: The New India Assurance Co.Ltd.If t
- Page 157 and 158: The New India Assurance Co.Ltd.The
<strong>The</strong> <strong>New</strong> <strong>India</strong> <strong>Assurance</strong> <strong>Co</strong>.<strong>Ltd</strong>.(19) Maintenance of site instructions book.(20) Procedure for arbitration.(21) Procedure for payment under escalation clause.TIME LIMIT :(1) Clear indication for recording the date of commencement and the date of completionshould be made.(2) Clear indication whether the time limit is inclusive or exclusive of monsoon should bemade.(3) Permissible extension in time limit without any extra compensation/penalty should beindicated.(4) Quantum of compensation/penalty to be imposed for further extension in time limit shouldbe indicated.(5) Maximum limit of compensation/penalty should be indicated.(6) Clarification about escalation in accepted tender rate either on account of material indexor labor index should be indicated, along with the basis being adopted for consideration.VARIATION IN QUANTITY :Generally, there should be no variation in quantities of executed items of work. But if thisoccur, the same should be explained by <strong>Co</strong>ntractor/ Architect/ <strong>Co</strong>nsulting Engineer &necessary permission of Chief Regional Manager/ Deputy General Manager/ GeneralManager needs to be obtained.(1) Extra items, if required, should be executed at the prevailing market rate. However, thequantum of such extra item executed should not exceed 15% of the sanctioned estimatedcost.(2) Deviation in specification will not be entertained except for compelling situations.CORRIGENDUM :(1) In case for any reason, there is a necessity to issue any corrigendum to the tender noticereleased earlier, for indicating changes, modifications etc. the same corrigendum mustappear in the same newspapers where the original tender notice had been published.(2) <strong>The</strong> intimation should be made available immediately to all the contractor who haveMANUAL ON ESTATE & ESTABLISHMENT115