GAIL (India) Limited
GAIL (India) Limited GAIL (India) Limited
87open or burst pipes or failure of fittings, to the building, furniture and fixtures shall be made good duringthe defects liability period without any extra cost.e) After commissioning of the water supply system, contractor shall test valve by closing and opening it anumber of times to observe if it is working efficiently. Valves which do not effectively operate shall bereplaced by new ones at no extra cost and the same shall be tested as above.5.6 DISINFECTIONa) After completion of the work, contractor shall flush clean the entire system with the City’s filtered waterafter connection has been made.b) After the first flushing, add commercial bleaching powder to achieve a dosage of 2 to 3 mg/Ltr of water inthe system and flushed. This operation should be performed twice to ensure that the system is fullydisinfected and usable.5.7 PRE-COMMISSIONINGa) Ensure that all pipes are free from debris and obstructionsb) Check all valves and for effective opening and closing action Defects should be rectified or valvesreplacedc) Ensure that all connection to branches have been maded) Ensure that mains have been connected to the respective pumps, underground and overhead tankse) Water supply should be available at main underground tankf) All main line valves should be closed5.7.1 COMMISSIONINGa) Fill underground tank with water Add 1 kg of fresh bleaching powder after making a solution, to be addednear inletb) Start water supply pump and allow water to fill main under ground tank Water will first fill the fire tankand then overflow to the domestic tanks.c) After overhead reservoir drain the same to its one forth capacity through tank scour valve. This is toensure removal of all mud, debris, etc. in the tankd) Fill overhead tank to fulle) Release water in the main lines by opened valves in each circuit Drain out water in the system throughscour valves in lower regions Ensure clean water is now coming out of the systemf) Open valves for individual sectors Observe for leakages or malfunctions, check pressure and flow at endof line by opening hydrants etc., remove and rectify defects notice.g) The entire water supply system should be disinfected with bleaching powder and system flush clean.h) Send four samples of water drawn from four extreme locations for testing for bacteriological test insterilized bottles obtained from the concerned laboratory. Laboratory personal may collect the samplesthemselves.5.7.2 RESPONSIBILITY:Responsibility for various activities in pre-commissioning and commissioning procedures will rest withthe contractor.STORM DRAINS6. GENERAL REQUIREMENTSa) All materials shall be new and of the best quality conforming to specification and subject to the approvalof the Consultant/Engineer-in-charge.b) Drainage lines shall be laid to the required gradients and profiles.c) All drainage work shall be done in accordance with the local municipal by laws.d) Contractor shall obtain necessary approval and permission for the drainage system from the municipal orany other competent authority.
88e) Location of all manholes, catch basins etc., shall be got confirmed by the Consultants before the actualexecution of work at site.f) All works shall be executed as directed by Consultants.6.1 RUBBLE MASONRYAs specified under item No. 6.3 of civil works for rubble masonry with black granite stones.6.2 REINFORCED CEMENT CONCRETE PIPESUnderground storm water drainage NP2 pipes shall be centrifugally spun RCC pipes of specified size.Pipes shall be true and straight with uniform bore throughout. Cracked, warped pipes shall not be used onthe work. All pipes shall be tested by manufacturer and the contractor shall produce, when directed acertificate to the effect from the manufacturer.6.3 TESTINGAll pipes shall be tested to a hydraulic test of 1.5 M head for atleast 30 minutes at the highest point in thesection under test. Test shall be carried out similar to those for stoneware pipes given above The smoketest shall be carried out by the contractor, if directed by the Consultant, at the expense and charges of thecontractor. A test register shall be carried out similar to those for stoneware pipes given above. The smoketest shall be carried out by the contractor, if directed by the Consultant, at the expense and charges of thecontractor. A test register shall be maintained which shall be signed and dated by theContractor/Consultant.6.4 PRE CAST SLABSPre cast layer slabs shall be casted in RCC 1:2:4 (1 cement: 2 sand: 4 coarse aggregate of 20 mmaggregate) and shall be placed over RR masonry drain as per drawing.
- Page 37 and 38: 36It shall be ensured that the bars
- Page 39 and 40: 385.1.2 RELATED WORK SPECIFIED ELSE
- Page 41 and 42: 40Oiling shall be done before reinf
- Page 43 and 44: 42For fair faced concrete, the posi
- Page 45 and 46: 446.3 RUBBLE MASONRY:-6.3.1. MATERI
- Page 47 and 48: 467.1.1.2 Hard Wood:Hard wood shall
- Page 49 and 50: 48The glass sheets for glazing shal
- Page 51 and 52: 50finish with minimum anodic film t
- Page 53 and 54: 52The tiles shall generally conform
- Page 55 and 56: 54Plaster as herein specified shall
- Page 57 and 58: 5612.9.5 FLOATING COAT OF NEAT CEME
- Page 59 and 60: 5813.1.a3 Preparation of Surface:Th
- Page 61 and 62: 6014.1.2 Preparation of surface:Pre
- Page 63 and 64: 62solution generously with brush. A
- Page 65 and 66: 64The Gypsum boards used for false
- Page 67 and 68: 661.4.1 Straining posts shall be pr
- Page 69 and 70: 687 Aluminum glazing section Hindal
- Page 71 and 72: 70SPECIFICATIONSPLUMBING AND SANITA
- Page 73 and 74: 722.6 For all pipes, work shall be
- Page 75 and 76: 743.6 As far as possible no GI pipe
- Page 77 and 78: 76Following measures shall be adopt
- Page 79 and 80: 781.15 ANGLE VALVEAngle valve shall
- Page 81 and 82: 803.16 Cast iron gratings shall be
- Page 83 and 84: 82a) The contractor shall at all ti
- Page 85 and 86: 844.5.1 LEADING IN C.I. PIPESThe le
- Page 87: 865.2.4 TRENCH FILLING OF G.I. PIPE
- Page 91 and 92: 90Sr.No. MATERIALS APPROVED MAKE/AG
- Page 93 and 94: 2TECHNICAL CONDITIONS1.1 These spec
- Page 95 and 96: 411. Qualified Competent Supervisio
- Page 97 and 98: 6Ceiling rose: a) A ceiling rose or
- Page 99 and 100: 8The consuming device circuit shall
- Page 101 and 102: 10A cover plate at the top of the v
- Page 103 and 104: 12Mechanical operation indicators s
- Page 105 and 106: 1411. Indicating lamps and push but
- Page 107 and 108: 16CHAPTER 31. Scope:LAYING OF CABLE
- Page 109 and 110: 183.5.4 Provision shall be made to
- Page 111 and 112: 20such that it shall be able to rea
- Page 113 and 114: 22ii) Tappings : OFF load tap chang
- Page 115 and 116: 245.3.2 Installation: The transform
- Page 117 and 118: 26A vertical air termination shall
- Page 119 and 120: 286. Testing:On the completion of t
- Page 121 and 122: 30l. Light Switches/Sockets/Fan Reg
- Page 123 and 124: 2TECHNICAL SPECIFICATIONSA) AIR COO
- Page 125 and 126: 47.0 CONEENSATE & DRAIN PIPING:7.1
- Page 127 and 128: 6B) AIR DISTRIBUTION SYSTEM:1.0 GEN
- Page 129 and 130: 8ii.iii.iv.All necessary allowances
- Page 131 and 132: 10ACTUATOR:In case of motorised smo
- Page 133 and 134: 12D) THERMAL/ACOUSTIC INSULATION. G
- Page 135 and 136: 14BASIS OF DESIGNAC REQUIRED FOROFF
- Page 137 and 138: 162.0 INSULATIONManufacturer Materi
88e) Location of all manholes, catch basins etc., shall be got confirmed by the Consultants before the actualexecution of work at site.f) All works shall be executed as directed by Consultants.6.1 RUBBLE MASONRYAs specified under item No. 6.3 of civil works for rubble masonry with black granite stones.6.2 REINFORCED CEMENT CONCRETE PIPESUnderground storm water drainage NP2 pipes shall be centrifugally spun RCC pipes of specified size.Pipes shall be true and straight with uniform bore throughout. Cracked, warped pipes shall not be used onthe work. All pipes shall be tested by manufacturer and the contractor shall produce, when directed acertificate to the effect from the manufacturer.6.3 TESTINGAll pipes shall be tested to a hydraulic test of 1.5 M head for atleast 30 minutes at the highest point in thesection under test. Test shall be carried out similar to those for stoneware pipes given above The smoketest shall be carried out by the contractor, if directed by the Consultant, at the expense and charges of thecontractor. A test register shall be carried out similar to those for stoneware pipes given above. The smoketest shall be carried out by the contractor, if directed by the Consultant, at the expense and charges of thecontractor. A test register shall be maintained which shall be signed and dated by theContractor/Consultant.6.4 PRE CAST SLABSPre cast layer slabs shall be casted in RCC 1:2:4 (1 cement: 2 sand: 4 coarse aggregate of 20 mmaggregate) and shall be placed over RR masonry drain as per drawing.