GAIL (India) Limited
GAIL (India) Limited GAIL (India) Limited
15iii)All current carrying parts and wiring of power control centre shall be subjected to power frequencyvoltage withstand test16. Drawings: After the award of the contract the contractors shall submit three copies of the followingdrawings for approval of the Department.i) Outline dimensional drawing of the PCC /PDB/MCC showing the general arrangement indicating thefollowing:a) Bus bar clearances:b) Power and control cable entry points;c) Configuration of bus bars;d) Details of support insulation and spacing;e) Outgoing power cable termination arrangements.i) Single line diagram of power control centre showing Protection Metering etcii) cubicle wiring diagramiii) List of Firements with Ratings & makes / Models17. Installation Testing and commissioning:The power control centre shall be installed over the cable trench/cable pit using suitable size of MSchannel including grouting of the channel with necessary bolts and nuts Proper earthing of PCC (PowerControl Centre)/PDB/MCC shall he done using two independent Copper/GI Strip of sizes as indicated inthe schedule. The channel shall be painted with one coat of red oxide primer and two coats ofanticorrosive enamel paint of proper shade as directed by the Engineer-in-charge.The pre-commissioning tests as required shall be done and the PCC (Power Control Centre) shall becommissioned.
16CHAPTER 31. Scope:LAYING OF CABLESThis specification is intended to cover the requirements of installation and energizing of PVC / XLPE /PILCDSTA power cables including jointing of cables.2. Standards:The power cable and its fixing accessories shall comply with the latest relevant Indian Standards andNational Electrical Code.3. Laying of Cables:3 1 General:3.1 Before the commencement of cable laying routing shall be ensured by the engineer- in-charge.3.1.2 The material such as bricks, sand, cable route markers, RCC slab of best quality as approved by theEngineer-in-Charge only shall be used for cable laying works.3.1.3 The contractor shall provide all the necessary labour, tools, plants and other requisites at his own cost forcarrying out pumping of water and removing of water from trenches, if any, where required.3.1.4 Installation shall be carried out in a neat, workman like manner by skilled, experienced and competentworkman in accordance with standard practices.3.1.5 While laving the cable care shall be taken to avoid formation of twists and also damage to the cable. In thecase of cable bends, it shall not have bent radius lesser than 20 times the overall diameter of the cable.3.1.6 A cable loops of about five meters length and as directed by the Engineer-in-Charge shall be provided atthe following locationsa) Near the termination pointsb) Near to the straight through joint3.1.7 The method of cable laying and routing of cables, shall in every, case be as directed by the Engineer-in-Charge / consultant.3 1 8 Whenever cable passes through Hume pipes/GI pipes embedded across the wall in a building, both theends of the pipe shall be suitably sealed.3.1.9 Identification tags indicating the size of (the cable and feeder designation shall be securely attached atboth ends of the cable. Such tags shall also be attached to the cable at intervals of 50 Mtrs. The materialsof the tag shall be of either 12 SWG GI Sheet. In case of plastic, the details have to be engraved andincase of GI sheet, the details should be punched Cable route markers shall be provided at the intervals of200 M with a minimum of one number route marker. The details of the route makers shall be as per thedrawing. At the locations of straight through joints, necessary joint-markers shall be provided.3.1.10 When cable runs vertically, it shall be clamped on mild steel flats or angle iron fixed on walls and isspaced at such intervals as to prevent buckling of the cables. All steelwork shall be painted with a coat ofred oxide and thereafter finished with suitable anticorrosive paints.
- Page 55 and 56: 54Plaster as herein specified shall
- Page 57 and 58: 5612.9.5 FLOATING COAT OF NEAT CEME
- Page 59 and 60: 5813.1.a3 Preparation of Surface:Th
- Page 61 and 62: 6014.1.2 Preparation of surface:Pre
- Page 63 and 64: 62solution generously with brush. A
- Page 65 and 66: 64The Gypsum boards used for false
- Page 67 and 68: 661.4.1 Straining posts shall be pr
- Page 69 and 70: 687 Aluminum glazing section Hindal
- Page 71 and 72: 70SPECIFICATIONSPLUMBING AND SANITA
- Page 73 and 74: 722.6 For all pipes, work shall be
- Page 75 and 76: 743.6 As far as possible no GI pipe
- Page 77 and 78: 76Following measures shall be adopt
- Page 79 and 80: 781.15 ANGLE VALVEAngle valve shall
- Page 81 and 82: 803.16 Cast iron gratings shall be
- Page 83 and 84: 82a) The contractor shall at all ti
- Page 85 and 86: 844.5.1 LEADING IN C.I. PIPESThe le
- Page 87 and 88: 865.2.4 TRENCH FILLING OF G.I. PIPE
- Page 89 and 90: 88e) Location of all manholes, catc
- Page 91 and 92: 90Sr.No. MATERIALS APPROVED MAKE/AG
- Page 93 and 94: 2TECHNICAL CONDITIONS1.1 These spec
- Page 95 and 96: 411. Qualified Competent Supervisio
- Page 97 and 98: 6Ceiling rose: a) A ceiling rose or
- Page 99 and 100: 8The consuming device circuit shall
- Page 101 and 102: 10A cover plate at the top of the v
- Page 103 and 104: 12Mechanical operation indicators s
- Page 105: 1411. Indicating lamps and push but
- Page 109 and 110: 183.5.4 Provision shall be made to
- Page 111 and 112: 20such that it shall be able to rea
- Page 113 and 114: 22ii) Tappings : OFF load tap chang
- Page 115 and 116: 245.3.2 Installation: The transform
- Page 117 and 118: 26A vertical air termination shall
- Page 119 and 120: 286. Testing:On the completion of t
- Page 121 and 122: 30l. Light Switches/Sockets/Fan Reg
- Page 123 and 124: 2TECHNICAL SPECIFICATIONSA) AIR COO
- Page 125 and 126: 47.0 CONEENSATE & DRAIN PIPING:7.1
- Page 127 and 128: 6B) AIR DISTRIBUTION SYSTEM:1.0 GEN
- Page 129 and 130: 8ii.iii.iv.All necessary allowances
- Page 131 and 132: 10ACTUATOR:In case of motorised smo
- Page 133 and 134: 12D) THERMAL/ACOUSTIC INSULATION. G
- Page 135 and 136: 14BASIS OF DESIGNAC REQUIRED FOROFF
- Page 137 and 138: 162.0 INSULATIONManufacturer Materi
- Page 139 and 140: 0G) LIST OF APPROVED MAKES:The foll
- Page 141 and 142: 1IV. TECHNICAL SPECIFICATIONSFORINT
- Page 143 and 144: 316. Unless otherwise provided spec
- Page 145 and 146: 52.9 ROUGH CARPENTRYMaterialAll fra
- Page 147 and 148: 7All joinery to be varnished/spirit
- Page 149 and 150: 9b) After the first coat has fully
- Page 151 and 152: 11b) The Contractor should furnish
- Page 153: 13holes, loose or dead knots or oth
15iii)All current carrying parts and wiring of power control centre shall be subjected to power frequencyvoltage withstand test16. Drawings: After the award of the contract the contractors shall submit three copies of the followingdrawings for approval of the Department.i) Outline dimensional drawing of the PCC /PDB/MCC showing the general arrangement indicating thefollowing:a) Bus bar clearances:b) Power and control cable entry points;c) Configuration of bus bars;d) Details of support insulation and spacing;e) Outgoing power cable termination arrangements.i) Single line diagram of power control centre showing Protection Metering etcii) cubicle wiring diagramiii) List of Firements with Ratings & makes / Models17. Installation Testing and commissioning:The power control centre shall be installed over the cable trench/cable pit using suitable size of MSchannel including grouting of the channel with necessary bolts and nuts Proper earthing of PCC (PowerControl Centre)/PDB/MCC shall he done using two independent Copper/GI Strip of sizes as indicated inthe schedule. The channel shall be painted with one coat of red oxide primer and two coats ofanticorrosive enamel paint of proper shade as directed by the Engineer-in-charge.The pre-commissioning tests as required shall be done and the PCC (Power Control Centre) shall becommissioned.