RFP for BHOPAL & Narmadapuram Division - Madhya Pradesh ...
RFP for BHOPAL & Narmadapuram Division - Madhya Pradesh ... RFP for BHOPAL & Narmadapuram Division - Madhya Pradesh ...
Details of the centre line of the proposed widened SH / MDR along withthe existing and proposed right-of-way limits to appreciate therequirements of land acquisition; The information concerning the area including ownership of land to beacquired for the implementation of the project shall be collected from therevenue and other concerned authorities and presented along with the stripplans; Strip plans showing the position of existing utilities and servicesindicating clearly the position of their relocation; Details for various clearances such as environment and forest clearances; Separate strip plan showing shifting / relocation of each utility services inconsultation with the concerned local authorities; The utility relocation plans should clearly show existing right-of-way andpertinent topographic details including buildings, major trees, fences andother installations such as water-mains, telephone, telegraph andelectricity poles, and suggest relocation of the services along with theircrossings the highway at designated locations as required and preparenecessary details for submission to the Service Departments; The strip plans shall be prepared on the basis of data from reconnaissanceand detailed topographic surveys. The strip plans shall clearly indicate the scheme for widening. The viewsand suggestions of the MPRDC should be duly taken into account whileworking out the widening scheme (left, right or symmetrical). Thewidening scheme shall be finalised in consultation with MPRDC.8.4.1.2 Detailed Project Reports, Documents and Drawings (6 Sets)The Detailed Project Reports, Documents and Drawings, incorporating all revisionsdeemed relevant following receipt of the comments from MPRDC shall be submittedas per the schedule given in Enclosure II.9. Interaction with MPRDC9.1 During entire period of services, the Consultant shall interact continuously withMPRDC and provide any clarification as regards methods being followed and carryout modification as suggested by MPRDC. A programme of various activities shallbe provided to MPRDC and prior intimation shall be given to MPRDC regarding startof key activities such as boring, survey etc. so that inspections of MPRDC officialscould be arranged in time.9.2 The MPRDC officers and other Government officers may visit the site at any time,individually or collectively to acquaint themselves with the field investigation andsurvey works.9.3 The consultant shall be required to send 3 copies of concise monthly Progress Reportby the 5 th day of the following month to the designated officer at his Head Quarter soADB-IV71
that progress could be monitored by the MPRDC. These reports will indicate thedates of induction and de-induction of various key personnel and the activitiesperformed by them. Frequent meetings with the consultant at site office or at Bhopalare foreseen during the currency of project preparation.9.4 All equipment, software and books etc. required for satisfactory services for thisproject shall be obtained by the Consultant at their own cost and shall be theirproperty.10. Payment Schedule10.1 The Consultant will be paid consultancy fee as a percentage of the contract valueexcept boring charges as per the schedule given below:S.No. Description Payment1 On submission of Stage-I Report 10%2 On Submission of Stage-2 reports 20%3 On Submission of Stage-3 report 30%4 On finalisation of Stage-3 reports based on 20%comments of the Employer, and submission ofStage-4 Report and other documents5 On acceptance of Stage-4 documents or 15%finalization of Addenda for the bidders,whichever is earlier6 On Project clearances/ NOC from concerned 5%state/central departments/ agencies.Total 100%Note : For exploratory boring for bridges/fly over/ROBs the payment shall beregulated as per the actual quantum of work done on quoted rate.10.2 DELETED10.3 DELETED11. Data and Software11.1 The floppy diskettes/CD’s containing all basic as well as the processed data from allfield studies and investigations, report, appendices, annexure, documents anddrawings shall be submitted to MPRDC at the time of the submission of the FinalReport. The data can be classified as follows:(i)Engineering Investigations and Traffic Studies: Road Inventory,Condition, Roughness, Test Pit (Pavement composition), Benkelman BeamDeflection, Material Investigation including test results for subgrade soils,Traffic Studies (traffic surveys), axle load surveys, Sub-soil Exploration,Drainage Inventory, Inventory data for bridge and culverts indicatingADB-IV72
- Page 21 and 22: MPRDCDPR - ADB -IVRATINGExcellent 1
- Page 23 and 24: NARRATIVE EVALUATION CRITERIAFOR FU
- Page 25 and 26: F. Counterpart Personnel and Facili
- Page 27 and 28: 2.3 The Detailed Project Report wou
- Page 29 and 30: 3.12 Deleted.3.13 In order to have
- Page 31 and 32: 4.3 The consultant shall plan the a
- Page 33 and 34: 4.7 Traffic Survey4.7.1 Number and
- Page 35 and 36: 4.7.3.5 The distribution of lead an
- Page 37 and 38: pessimistic and most likely traffic
- Page 39 and 40: upgrading costs. The detailed topog
- Page 41 and 42: 4.9.2.7 Details of utility Services
- Page 43 and 44: (ii)(iii)(iv)shoulder condition;emb
- Page 45 and 46: section testing shall involve carry
- Page 47 and 48: 4.9.4.2.3 For bridges and cross dra
- Page 49 and 50: 4.9.4.5.3 Environmental restriction
- Page 51 and 52: (i)(ii)(iii)(iv)(v)horizontal align
- Page 53 and 54: Government guidelines, use of flyas
- Page 55 and 56: 4.9.6.9 Arboriculture and Landscapi
- Page 57 and 58: 4.10.1.10 The consultant shall prep
- Page 59 and 60: feasibility and effectiveness of in
- Page 61 and 62: (ii)(iii)(iv)(v)Civil works contrac
- Page 63 and 64: 4.12 Economic Analysis4.12.1 The ro
- Page 65 and 66: 7. Project Team and Project Office
- Page 67 and 68: e presented as separate sections li
- Page 69 and 70: estimation, environmental aspects,
- Page 71: (ii)(iii)(iv)(v)Locations of median
- Page 75 and 76: A. Selection Criteria for ProjectsS
- Page 77 and 78: Handbook on Resettlement -A Guide t
- Page 79 and 80: TABLE SAF1: PROJECT RANKING CRITERI
- Page 81 and 82: Criterion / Consideration Priority
- Page 83 and 84: A2 : Local AlignmentA3 : JunctionsA
- Page 85 and 86: C3 : JunctionsC4 : Non-Motorised ro
- Page 87 and 88: Schedule for Submission of Reports
- Page 89 and 90: 4. Bridge Engineeri) Educational Qu
- Page 91 and 92: 11. Social Development Specialisti)
- Page 93 and 94: (Form-III)FIRM’S REFERENCESReleva
- Page 95 and 96: (Form-V)COMMENTS/ SUGGESTIONS OF CO
- Page 97 and 98: (Form-VII)Format of Curriculum Vita
- Page 99 and 100: (Form-IX)A. FIELD INVESTIGATION(1st
- Page 101 and 102: FORM FIN-1FINANCIAL PROPOSALS ForPa
- Page 103 and 104: LIST OF ADB MEMBER COUNTRIES1. AFG
- Page 105 and 106: Agreement & General Conditions of C
- Page 107 and 108: 7. Responsibility for accuracy of t
- Page 109 and 110: (a) The Consultants shall carry out
- Page 111 and 112: 1.2 Relation between the PartiesNot
- Page 113 and 114: 2.6 ModificationModification of the
- Page 115 and 116: (e)(f)if, as the result of Force Ma
- Page 117 and 118: or in the Discharge of their obliga
- Page 119 and 120: (b)If required to comply with the p
- Page 121 and 122: value. Such bank guarantee (i) to r
Details of the centre line of the proposed widened SH / MDR along withthe existing and proposed right-of-way limits to appreciate therequirements of land acquisition; The in<strong>for</strong>mation concerning the area including ownership of land to beacquired <strong>for</strong> the implementation of the project shall be collected from therevenue and other concerned authorities and presented along with the stripplans; Strip plans showing the position of existing utilities and servicesindicating clearly the position of their relocation; Details <strong>for</strong> various clearances such as environment and <strong>for</strong>est clearances; Separate strip plan showing shifting / relocation of each utility services inconsultation with the concerned local authorities; The utility relocation plans should clearly show existing right-of-way andpertinent topographic details including buildings, major trees, fences andother installations such as water-mains, telephone, telegraph andelectricity poles, and suggest relocation of the services along with theircrossings the highway at designated locations as required and preparenecessary details <strong>for</strong> submission to the Service Departments; The strip plans shall be prepared on the basis of data from reconnaissanceand detailed topographic surveys. The strip plans shall clearly indicate the scheme <strong>for</strong> widening. The viewsand suggestions of the MPRDC should be duly taken into account whileworking out the widening scheme (left, right or symmetrical). Thewidening scheme shall be finalised in consultation with MPRDC.8.4.1.2 Detailed Project Reports, Documents and Drawings (6 Sets)The Detailed Project Reports, Documents and Drawings, incorporating all revisionsdeemed relevant following receipt of the comments from MPRDC shall be submittedas per the schedule given in Enclosure II.9. Interaction with MPRDC9.1 During entire period of services, the Consultant shall interact continuously withMPRDC and provide any clarification as regards methods being followed and carryout modification as suggested by MPRDC. A programme of various activities shallbe provided to MPRDC and prior intimation shall be given to MPRDC regarding startof key activities such as boring, survey etc. so that inspections of MPRDC officialscould be arranged in time.9.2 The MPRDC officers and other Government officers may visit the site at any time,individually or collectively to acquaint themselves with the field investigation andsurvey works.9.3 The consultant shall be required to send 3 copies of concise monthly Progress Reportby the 5 th day of the following month to the designated officer at his Head Quarter soADB-IV71