RFP for BHOPAL & Narmadapuram Division - Madhya Pradesh ...
RFP for BHOPAL & Narmadapuram Division - Madhya Pradesh ... RFP for BHOPAL & Narmadapuram Division - Madhya Pradesh ...
Scenario – III Base Costs and Base Benefits minus 20%Scenario - IV Drop in traffic growth rates by 50%Scenario - VNo generated traffic benefitsScenario - VITwo-year project implementation delayScenario - VII Less than optimal road maintenance such as delayor omission of periodic maintenanceScenario - VIII Base Costs plus 20% and Base Benefits minus 20%4.12.8 The sensitivity scenarios given above are only indicative. The Consultants shallselect the sensitivity scenarios taking into account possible construction delays,construction costs overrun, traffic volume, revenue shortfalls, operating costs,exchange rate variations, convertibility of foreign exchange, interest ratevolatility, non-compliance or default by contractors, political risks and forcemajeure.4.12.9 The economic analysis shall take into account all on-going and future road andtransport infrastructure projects and future development plans in the project area.4.12.10The consultant shall suggest ways of enhancing/making the projects in termsof project economics attractive.5. Selection and Prioritization of projectsFor the purpose of selection as project for ADB financing, a road project must meetthe selection criteria and evaluation requirements including attaining a minimum 12%estimated economic internal rate of return. The sub-projects shall further be prioritizedusing the ranking criteria. The project selection criteria including evaluation andranking criteria are at Supplement I. The consultant shall prepare and submit a reporton Selection and Prioritization of projects as early as possible, e.g. preliminary list atSTAGE 2 – Interim Report for GoMP and ADB consideration. The preparation of biddocuments and final detailed design report should be carried out only after therespective projects are determined for possible ADB financing.6. Time period for the service6.1 Time period envisaged for the study of each of the projects is nine months. The finalreports, drawings and documentation shall be completed within this time schedule.6.2 MPRDC shall arrange to give observations and comments on all sketches, drawings,reports and recommendations and other matters and proposals submitted for decisionby the Consultant through GM/DM of MPRDC in such reasonable time so as not todelay or disrupt the performance of the Consultant’s services.ADB-IV63
7. Project Team and Project Office of the Consultant7.1 The Consultants shall be required to form a multi-disciplinary team for thisassignment. The consultants Team shall be manned by adequate number of expertswith relevant experience in the execution of similar detailed design assignments.7.2 List of key personnel to be fielded under the technical team is given in Enclosure I asper clients assessment. The key personnel fielded by the consultant shall not beshifted during the entire period of the services.7.3 All the key personnel mentioned will be evaluated at the time of evaluation oftechnical proposal. Consultants are advised in their own interest to frame thetechnical proposal in an objective manner as far as possible so that these could beproperly assessed. The bio-data of the key personnel should be signed on every sheetby the personnel concerned and the last sheet of each bio-data should also be signedby the authorised signatory of the Consultants.7.4 The Consultants shall establish an office at the Project Site manned by senior keypersonnel during the course of the surveys and investigations. All the project relatedoffice work shall be carried out by the consultant in their site office unless there arespecial reasons for carrying out part of the office work elsewhere for which priorapproval of MPRDC shall be obtained. The address of site office including thepersonnel manning it including their Telephone and FAX numbers will be intimatedby the Consultant to MPRDC before commencement of the services.7.5 All necessary technical support staff and office support staff shall be provided by theconsultant. They should however bring out the details of these personnel and theirduration of deployment in the technical proposal.7.6 The consultant shall mobilize all necessary survey equipment, computers, software,other equipment and all other equipment required to fulfill the job7.7 The consultant shall include all necessary vehicles motorcycles etc in his proposalwhich may be required to carry out the job.7.8 The rates to be quoted shall be on per kilometer basis (excluding exploratory boringfor bridges/fly over/ROBs.) and it shall include all costs / expenses, taxes, duties,service tax, cess etc as applicableThe rates for exploratory boring shall be quoted on per meter basis and it shallinclude all costs / expenses, taxes, duties, service tax, cess etc as applicableADB-IV64
- Page 13 and 14: MPRDCDPR - ADB -IVType ofProposalCo
- Page 15 and 16: MPRDCDPR - ADB -IV(b)(c)(d)(e)is pr
- Page 17 and 18: MPRDCDPR - ADB -IVspecified in the
- Page 19 and 20: MPRDCDPR - ADB -IVSection - 3DATA S
- Page 21 and 22: MPRDCDPR - ADB -IVRATINGExcellent 1
- Page 23 and 24: NARRATIVE EVALUATION CRITERIAFOR FU
- Page 25 and 26: F. Counterpart Personnel and Facili
- Page 27 and 28: 2.3 The Detailed Project Report wou
- Page 29 and 30: 3.12 Deleted.3.13 In order to have
- Page 31 and 32: 4.3 The consultant shall plan the a
- Page 33 and 34: 4.7 Traffic Survey4.7.1 Number and
- Page 35 and 36: 4.7.3.5 The distribution of lead an
- Page 37 and 38: pessimistic and most likely traffic
- Page 39 and 40: upgrading costs. The detailed topog
- Page 41 and 42: 4.9.2.7 Details of utility Services
- Page 43 and 44: (ii)(iii)(iv)shoulder condition;emb
- Page 45 and 46: section testing shall involve carry
- Page 47 and 48: 4.9.4.2.3 For bridges and cross dra
- Page 49 and 50: 4.9.4.5.3 Environmental restriction
- Page 51 and 52: (i)(ii)(iii)(iv)(v)horizontal align
- Page 53 and 54: Government guidelines, use of flyas
- Page 55 and 56: 4.9.6.9 Arboriculture and Landscapi
- Page 57 and 58: 4.10.1.10 The consultant shall prep
- Page 59 and 60: feasibility and effectiveness of in
- Page 61 and 62: (ii)(iii)(iv)(v)Civil works contrac
- Page 63: 4.12 Economic Analysis4.12.1 The ro
- Page 67 and 68: e presented as separate sections li
- Page 69 and 70: estimation, environmental aspects,
- Page 71 and 72: (ii)(iii)(iv)(v)Locations of median
- Page 73 and 74: that progress could be monitored by
- Page 75 and 76: A. Selection Criteria for ProjectsS
- Page 77 and 78: Handbook on Resettlement -A Guide t
- Page 79 and 80: TABLE SAF1: PROJECT RANKING CRITERI
- Page 81 and 82: Criterion / Consideration Priority
- Page 83 and 84: A2 : Local AlignmentA3 : JunctionsA
- Page 85 and 86: C3 : JunctionsC4 : Non-Motorised ro
- Page 87 and 88: Schedule for Submission of Reports
- Page 89 and 90: 4. Bridge Engineeri) Educational Qu
- Page 91 and 92: 11. Social Development Specialisti)
- Page 93 and 94: (Form-III)FIRM’S REFERENCESReleva
- Page 95 and 96: (Form-V)COMMENTS/ SUGGESTIONS OF CO
- Page 97 and 98: (Form-VII)Format of Curriculum Vita
- Page 99 and 100: (Form-IX)A. FIELD INVESTIGATION(1st
- Page 101 and 102: FORM FIN-1FINANCIAL PROPOSALS ForPa
- Page 103 and 104: LIST OF ADB MEMBER COUNTRIES1. AFG
- Page 105 and 106: Agreement & General Conditions of C
- Page 107 and 108: 7. Responsibility for accuracy of t
- Page 109 and 110: (a) The Consultants shall carry out
- Page 111 and 112: 1.2 Relation between the PartiesNot
- Page 113 and 114: 2.6 ModificationModification of the
7. Project Team and Project Office of the Consultant7.1 The Consultants shall be required to <strong>for</strong>m a multi-disciplinary team <strong>for</strong> thisassignment. The consultants Team shall be manned by adequate number of expertswith relevant experience in the execution of similar detailed design assignments.7.2 List of key personnel to be fielded under the technical team is given in Enclosure I asper clients assessment. The key personnel fielded by the consultant shall not beshifted during the entire period of the services.7.3 All the key personnel mentioned will be evaluated at the time of evaluation oftechnical proposal. Consultants are advised in their own interest to frame thetechnical proposal in an objective manner as far as possible so that these could beproperly assessed. The bio-data of the key personnel should be signed on every sheetby the personnel concerned and the last sheet of each bio-data should also be signedby the authorised signatory of the Consultants.7.4 The Consultants shall establish an office at the Project Site manned by senior keypersonnel during the course of the surveys and investigations. All the project relatedoffice work shall be carried out by the consultant in their site office unless there arespecial reasons <strong>for</strong> carrying out part of the office work elsewhere <strong>for</strong> which priorapproval of MPRDC shall be obtained. The address of site office including thepersonnel manning it including their Telephone and FAX numbers will be intimatedby the Consultant to MPRDC be<strong>for</strong>e commencement of the services.7.5 All necessary technical support staff and office support staff shall be provided by theconsultant. They should however bring out the details of these personnel and theirduration of deployment in the technical proposal.7.6 The consultant shall mobilize all necessary survey equipment, computers, software,other equipment and all other equipment required to fulfill the job7.7 The consultant shall include all necessary vehicles motorcycles etc in his proposalwhich may be required to carry out the job.7.8 The rates to be quoted shall be on per kilometer basis (excluding exploratory boring<strong>for</strong> bridges/fly over/ROBs.) and it shall include all costs / expenses, taxes, duties,service tax, cess etc as applicableThe rates <strong>for</strong> exploratory boring shall be quoted on per meter basis and it shallinclude all costs / expenses, taxes, duties, service tax, cess etc as applicableADB-IV64