FOG-312ChapterSURFACE(A000)SubjectVendor-Aided Patching(A150)DESCRIPTIONAny patching in which a vendor, along with state forces, participates in aportion of the work (equipment, labor, etc.)This activity covers cost of all state personnel when using FE01maintenance money. (Section Required)SCHEDULINGAs requiredRECOMMENDEDPERSONNELN/ARECOMMENDEDEQUIPMENTN/ARECOMMENDEDMATERIALSN/AENVIRONMENTALIMPACTS Precondition equipment before loading bituminous material. Do not use diesel fuel. Return tool-cleaning solvents to the lot. Follow procedures in the Environmental Handbook (2.1.1, “CleaningAsphalt Tools and Equipment”) for cleaning at the end of the job.PERFORMANCEVALUESFUNCTION Hours Per Unit Daily Expectation Accomplishment UnitFE01N/AN/ATon10/11 Page 1 of 2
SURFACE (A000)Vendor-Aided Patching (A150)FOG-312RECOMMENDEDPROCEDURE1. Discuss with crew the requirements of the job.2. Place traffic-control devices as necessary.3. Clean surface, if required, prior to application of tack coat to surface.4. Apply tack coat of heated liquid asphalt to existing surface, makingsure entire area is covered.5. Apply bituminous mix with paver or grader in layers no more thantwo inches or less than one inch in depth. Square ends.6. Roll for proper compaction after each layer.7. Check for proper crown or cross slope before leaving project. Correctany deficiencies.8. Remove traffic-control devices.Special Note: Determine accomplishment before leaving job site.10/11 Page 2 of 2
- Page 1: COMMONWEALTH OF KENTUCKYTRANSPORTAT
- Page 4 and 5: FOG-01TABLE OF CONTENTS01 TABLE OF
- Page 6: TABLE OF CONTENTSFOG-01600 ROADSIDE
- Page 9 and 10: TABLE OF CONTENTSFOG-011400 SIGNING
- Page 11 and 12: INTRODUCTIONDesign of This ManualFO
- Page 13 and 14: FOG-103ChapterINTRODUCTIONSubjectPe
- Page 15 and 16: INTRODUCTIONReportingACCOUNT STRIPR
- Page 18 and 19: DIVISION OF MAINTENANCEActivity Cod
- Page 20 and 21: DIVISION OF MAINTENANCEAccomplishme
- Page 22 and 23: FOG-301ChapterSURFACE(A000)SubjectP
- Page 24 and 25: FOG-302ChapterSURFACE(A000)SubjectP
- Page 26 and 27: FOG-303ChapterSURFACE(A000)SubjectA
- Page 28 and 29: FOG-304ChapterSURFACE(A000)SubjectP
- Page 30 and 31: FOG-305ChapterSURFACE(A000)SubjectS
- Page 32 and 33: FOG-306ChapterSURFACE(A000)SubjectJ
- Page 34 and 35: FOG-307ChapterSURFACE(A000)SubjectJ
- Page 36 and 37: FOG-308ChapterSURFACE(A000)SubjectM
- Page 38 and 39: SURFACE (A000)Routine Traffic-Bound
- Page 40 and 41: SURFACE (A000)Patching with Traffic
- Page 44 and 45: FOG-313ChapterSURFACE(A000)SubjectM
- Page 46 and 47: FOG-314ChapterSURFACE(A000)SubjectS
- Page 48 and 49: FOG-315ChapterSURFACE(A000)SubjectM
- Page 50 and 51: FOG-317ChapterSURFACE(A000)SubjectB
- Page 52 and 53: FOG-318ChapterSURFACE(A000)SubjectM
- Page 54 and 55: FOG-401ChapterSHOULDERS(B000)Subjec
- Page 56 and 57: FOG-402ChapterSHOULDERS(B000)Subjec
- Page 58 and 59: FOG-403ChapterSHOULDERS(B000)Subjec
- Page 60 and 61: FOG-404ChapterSHOULDERS(B000)Subjec
- Page 62 and 63: FOG-405ChapterSHOULDERS(B000)Subjec
- Page 64 and 65: FOG-406ChapterSHOULDERS(B000)Subjec
- Page 66 and 67: FOG-407ChapterSHOULDERS(B000)Subjec
- Page 68 and 69: FOG-409ChapterSHOULDERS(B000)Subjec
- Page 70 and 71: FOG-410ChapterSHOULDERS(B000)Subjec
- Page 72 and 73: FOG-411ChapterSHOULDERS(B000)Subjec
- Page 74 and 75: FOG-412ChapterSHOULDERS(B000)Subjec
- Page 76 and 77: FOG-413ChapterSHOULDERS(B000)Subjec
- Page 78 and 79: ROADSIDE GENERAL (C000)Repair to Ro
- Page 80 and 81: ROADSIDE GENERAL (C000)Repair to La
- Page 82 and 83: ROADSIDE GENERAL (C000)Rest Area At
- Page 84 and 85: FOG-505ChapterROADSIDE GENERAL(C000
- Page 86 and 87: ROADSIDE GENERAL (C000)Litter Clean
- Page 88 and 89: ROADSIDE GENERAL (C000)Litter Clean
- Page 90 and 91: ROADSIDE GENERAL (C000)Dead Animal
SURFACE (A000)Vendor-Aided Patching (A150)FOG-312RECOMMENDEDPROCEDURE1. Discuss with crew the requirements of the job.2. Place traffic-control devices as necessary.3. Clean surface, if required, prior to application of tack coat to surface.4. Apply tack coat of heated liquid asphalt to existing surface, makingsure entire area is covered.5. Apply bituminous mix with paver or grader in layers no more thantwo inches or less than one inch in depth. Square ends.6. Roll for proper compaction after each layer.7. Check for proper crown or cross slope before leaving project. Correctany deficiencies.8. Remove traffic-control devices.Special Note: Determine accomplishment before leaving job site.10/11 Page 2 of 2