Dancing Towers on Hamburg's Reeperbahn - Putzmeister

Dancing Towers on Hamburg's Reeperbahn - Putzmeister Dancing Towers on Hamburg's Reeperbahn - Putzmeister

02.12.2012 Views

Title story p For some in St. Pauli, this early hour means hometime, but for the workers on the construction site, the day is only just starting: At half past 5 sharp, the first truck mixers arrive. Placing concrete - from a practical viewpoint Laughing when asked what the greatest challenge for placing concrete is, project lead Silke Pförtner from Ed. Züblin AG answers: “When you see the depth of the pit, the type of pit lining and the size of the area set aside for the construction site equipment, it soon becomes clear: There isn‘t actually any space for large machines. In addition, the hours allowed for concreting are clearly delimited because we have to respect our neighbours, and therefore we need as many pumps as possible. So we have teamed up with betonlift to develop a very target-oriented, fair, good and safe solution. Because when placing large amounts of concrete as you see today, we really can‘t leave anything to chance. So, for example, we worked with betonlift to determine first of all the locations of the three pumps (see fig. 7 and 9), restricted as we were by a very small set-up area, the maximum load on the supporting ground at the edge of the pit, and the access options for the truck mixers.” q Don‘t push: Each truck mixer in the convoy is guided to the appropriate pump by the signaller. Pump (far left) has a somewhat larger set-up area and can be fed by two truck mixers at the same time. 6 PM 4307 GB PM 4307 GB 10 Franz Syrowatka from betonlift Hamburg adds: “To us it was clear that we would be using our Putzmeister 52 m booms; three in action and one as a stand-by pump with one machine operator to relieve colleagues during the day. The important thing for pumps 1 and 3 was the one side support, and that we have a working area of 180°. This was the only way that we were able to reach all corners of the area to be concreted. With pump 2, we had somewhat more space. We were able to provide full support there, and were able to load using two truck mixers at the same time. This enabled the P2 to reach a somewhat higher effective pumping rate per hour.” An average pouring rate of 180 m³/h was assumed for the three pumps combined. At 2,650 m³, this meant a pumping duration of approx. 14 hours. Therefore, concreting was set to begin early, at 6:00 am. To save some Title story p Keeping an overview: Three booms, moving construction site cranes, constant changing of truck mixers – the construction site requires the utmost attentiveness from the machine operators. 11 13 time, the four concrete pumps were moved into place the evening before, which meant that all that remained to be done was to set up the machine supports and move the boom into its working position anytime from 5:00 am onwards. Around 5:30 am, the first Holcim truck mixer arrived from the plant approx. 15 km away, and shortly after 6:00 am, the first concrete started to flow. In total, there were 45 truck mixers constantly driving to and fro, transporting the concrete to the “ong>Dancingong> ong>Towersong>”. t A fence reduces the street width by half: On one side, traffic can pass by unhindered, and on the other, the truck mixers control the M 5 , which is supported on one side. The one side support (OSS) for pumps 1 and was crucial for their use in the tight space available. 12

Title story<br />

p For some in St. Pauli, this early hour means hometime, but for the workers <strong>on</strong> the c<strong>on</strong>structi<strong>on</strong> site, the day is <strong>on</strong>ly just starting:<br />

At half past 5 sharp, the first truck mixers arrive.<br />

Placing c<strong>on</strong>crete - from a practical<br />

viewpoint<br />

Laughing when asked what the greatest<br />

challenge for placing c<strong>on</strong>crete is, project<br />

lead Silke Pförtner from Ed. Züblin AG answers:<br />

“When you see the depth of the pit, the<br />

type of pit lining and the size of the area set<br />

aside for the c<strong>on</strong>structi<strong>on</strong> site equipment,<br />

it so<strong>on</strong> becomes clear: There isn‘t actually<br />

any space for large machines. In additi<strong>on</strong>,<br />

the hours allowed for c<strong>on</strong>creting are clearly<br />

delimited because we have to respect our<br />

neighbours, and therefore we need as many<br />

pumps as possible. So we have teamed up<br />

with bet<strong>on</strong>lift to develop a very target-oriented,<br />

fair, good and safe soluti<strong>on</strong>. Because<br />

when placing large amounts of c<strong>on</strong>crete as<br />

you see today, we really can‘t leave anything<br />

to chance. So, for example, we worked with<br />

bet<strong>on</strong>lift to determine first of all the locati<strong>on</strong>s<br />

of the three pumps (see fig. 7 and 9),<br />

restricted as we were by a very small set-up<br />

area, the maximum load <strong>on</strong> the supporting<br />

ground at the edge of the pit, and the access<br />

opti<strong>on</strong>s for the truck mixers.”<br />

q D<strong>on</strong>‘t push: Each truck mixer in the<br />

c<strong>on</strong>voy is guided to the appropriate<br />

pump by the signaller.<br />

Pump (far left) has a somewhat larger<br />

set-up area and can be fed by two truck<br />

mixers at the same time.<br />

6 PM 4307 GB PM 4307 GB<br />

10<br />

Franz Syrowatka from bet<strong>on</strong>lift Hamburg<br />

adds: “To us it was clear that we would be<br />

using our <strong>Putzmeister</strong> 52 m booms; three in<br />

acti<strong>on</strong> and <strong>on</strong>e as a stand-by pump with <strong>on</strong>e<br />

machine operator to relieve colleagues during<br />

the day. The important thing for pumps<br />

1 and 3 was the <strong>on</strong>e side support, and that<br />

we have a working area of 180°. This was<br />

the <strong>on</strong>ly way that we were able to reach all<br />

corners of the area to be c<strong>on</strong>creted. With<br />

pump 2, we had somewhat more space. We<br />

were able to provide full support there, and<br />

were able to load using two truck mixers at<br />

the same time. This enabled the P2 to reach<br />

a somewhat higher effective pumping rate<br />

per hour.”<br />

An average pouring rate of 180 m³/h was<br />

assumed for the three pumps combined. At<br />

2,650 m³, this meant a pumping durati<strong>on</strong> of<br />

approx. 14 hours. Therefore, c<strong>on</strong>creting was<br />

set to begin early, at 6:00 am. To save some<br />

Title story<br />

p Keeping an overview: Three booms, moving c<strong>on</strong>structi<strong>on</strong> site cranes, c<strong>on</strong>stant changing of truck mixers – the c<strong>on</strong>structi<strong>on</strong> site<br />

requires the utmost attentiveness from the machine operators.<br />

11 13<br />

time, the four c<strong>on</strong>crete pumps were moved<br />

into place the evening before, which meant<br />

that all that remained to be d<strong>on</strong>e was to<br />

set up the machine supports and move the<br />

boom into its working positi<strong>on</strong> anytime from<br />

5:00 am <strong>on</strong>wards. Around 5:30 am, the first<br />

Holcim truck mixer arrived from the plant<br />

approx. 15 km away, and shortly after 6:00<br />

am, the first c<strong>on</strong>crete started to flow. In total,<br />

there were 45 truck mixers c<strong>on</strong>stantly driving<br />

to and fro, transporting the c<strong>on</strong>crete to<br />

the “<str<strong>on</strong>g>Dancing</str<strong>on</strong>g> <str<strong>on</strong>g>Towers</str<strong>on</strong>g>”.<br />

t A fence reduces the street width<br />

by half: On <strong>on</strong>e side, traffic can pass<br />

by unhindered, and <strong>on</strong> the other, the<br />

truck mixers c<strong>on</strong>trol the M 5 , which<br />

is supported <strong>on</strong> <strong>on</strong>e side. The <strong>on</strong>e side<br />

support (OSS) for pumps 1 and was<br />

crucial for their use in the tight space<br />

available.<br />

12

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!