In brief<br />
<strong>Putzmeister</strong> at c<strong>on</strong>structi<strong>on</strong> sites in India<br />
Essar Oil Refi nery in Jamnagar:<br />
Four truck-mounted<br />
c<strong>on</strong>crete pumps in acti<strong>on</strong><br />
Essar is using the fi rst <strong>Putzmeister</strong> M 42-5<br />
in India to c<strong>on</strong>crete <strong>on</strong>e of the largest refi<br />
neries in the world at Jamnagar in West<br />
India. Together with three of the eight<br />
M 36 pumps from the fl eet, the “new” editi<strong>on</strong><br />
pumps reliably throughout the day<br />
and night.<br />
The <strong>Putzmeister</strong> India After Sales & Parts<br />
Service is regarded highly by the people at<br />
Essar, but the message from Deepak Kumar<br />
Singh, Managing Director of Essar HED, is<br />
clear: “For me, the machines by <strong>Putzmeister</strong><br />
are simply the best for c<strong>on</strong>creting.”<br />
p Teamwork: Three M 6 and the new<br />
M 4 -5 are placing 1,400 m of c<strong>on</strong>crete<br />
Essar Oil<br />
The Essar Oil Refi nery in Vadinar/Jamnagar<br />
in the state of Gujarat lies <strong>on</strong><br />
India‘s west coast, ideally located close<br />
to the oil-rich Gulf states. It is <strong>on</strong>e of the<br />
largest refi neries in the world.<br />
The Indian c<strong>on</strong>glomerate, Essar Group,<br />
is active in the fi elds of steel, oil and gas,<br />
energy, communicati<strong>on</strong>, transport/logistics,<br />
c<strong>on</strong>structi<strong>on</strong> and raw materials.<br />
45<br />
PM 4307 GB PM 4307 GB<br />
Climbing booms and stati<strong>on</strong>ary pumps<br />
at the Ruby Mill Tower in Mumbai<br />
At the Ruby Mill c<strong>on</strong>structi<strong>on</strong> site in Mumbai,<br />
two MX 32-4T self-climbing stati<strong>on</strong>ary<br />
booms and two pumps of the type BSA<br />
1408 HD are being used. In total, 50,000<br />
cubic metres of c<strong>on</strong>crete has to be placed.<br />
1,100 m 3 of c<strong>on</strong>crete is used for each level,<br />
including the ceilings, columns and inner<br />
walls. Two levels are completed each<br />
m<strong>on</strong>th.<br />
The pumps are cleaned using sp<strong>on</strong>ge balls<br />
and wash-out pigs by simply pumping them<br />
with water. There is no need for any separate<br />
cleaning stati<strong>on</strong>.<br />
46<br />
47<br />
C<strong>on</strong>creting data<br />
Ruby Mill Tower<br />
C<strong>on</strong>crete Compressive<br />
type strength<br />
Slab M 40 > 40 N/mm 2<br />
Column M 50 > 50 N/mm 2<br />
Inner wall M 50 > 50 N/mm 2<br />
Slump measure (ø) 140 mm<br />
In brief<br />
C<strong>on</strong>crete delivery<br />
pressure 200 – 220 bar<br />
Once complete, the Ruby Mill Tower will<br />
be 185 m in height and have 34 levels<br />
(four of which are parking areas). The total<br />
usable area of 78,000 m 2 will mostly<br />
be used as offi ce space.<br />
The building was designed by the New<br />
York architects FxFowle, analysis and<br />
design was carried out by LERA and the<br />
Indian company Vasc<strong>on</strong> Engineers undertook<br />
the c<strong>on</strong>structi<strong>on</strong> of the building.<br />
C<strong>on</strong>structi<strong>on</strong> commenced in 2007 and<br />
the building should be complete by the<br />
end of 2010.<br />
48