In brief<br />

<strong>Putzmeister</strong> at c<strong>on</strong>structi<strong>on</strong> sites in India<br />

Essar Oil Refi nery in Jamnagar:<br />

Four truck-mounted<br />

c<strong>on</strong>crete pumps in acti<strong>on</strong><br />

Essar is using the fi rst <strong>Putzmeister</strong> M 42-5<br />

in India to c<strong>on</strong>crete <strong>on</strong>e of the largest refi<br />

neries in the world at Jamnagar in West<br />

India. Together with three of the eight<br />

M 36 pumps from the fl eet, the “new” editi<strong>on</strong><br />

pumps reliably throughout the day<br />

and night.<br />

The <strong>Putzmeister</strong> India After Sales & Parts<br />

Service is regarded highly by the people at<br />

Essar, but the message from Deepak Kumar<br />

Singh, Managing Director of Essar HED, is<br />

clear: “For me, the machines by <strong>Putzmeister</strong><br />

are simply the best for c<strong>on</strong>creting.”<br />

p Teamwork: Three M 6 and the new<br />

M 4 -5 are placing 1,400 m of c<strong>on</strong>crete<br />

Essar Oil<br />

The Essar Oil Refi nery in Vadinar/Jamnagar<br />

in the state of Gujarat lies <strong>on</strong><br />

India‘s west coast, ideally located close<br />

to the oil-rich Gulf states. It is <strong>on</strong>e of the<br />

largest refi neries in the world.<br />

The Indian c<strong>on</strong>glomerate, Essar Group,<br />

is active in the fi elds of steel, oil and gas,<br />

energy, communicati<strong>on</strong>, transport/logistics,<br />

c<strong>on</strong>structi<strong>on</strong> and raw materials.<br />

45<br />

PM 4307 GB PM 4307 GB<br />

Climbing booms and stati<strong>on</strong>ary pumps<br />

at the Ruby Mill Tower in Mumbai<br />

At the Ruby Mill c<strong>on</strong>structi<strong>on</strong> site in Mumbai,<br />

two MX 32-4T self-climbing stati<strong>on</strong>ary<br />

booms and two pumps of the type BSA<br />

1408 HD are being used. In total, 50,000<br />

cubic metres of c<strong>on</strong>crete has to be placed.<br />

1,100 m 3 of c<strong>on</strong>crete is used for each level,<br />

including the ceilings, columns and inner<br />

walls. Two levels are completed each<br />

m<strong>on</strong>th.<br />

The pumps are cleaned using sp<strong>on</strong>ge balls<br />

and wash-out pigs by simply pumping them<br />

with water. There is no need for any separate<br />

cleaning stati<strong>on</strong>.<br />

46<br />

47<br />

C<strong>on</strong>creting data<br />

Ruby Mill Tower<br />

C<strong>on</strong>crete Compressive<br />

type strength<br />

Slab M 40 > 40 N/mm 2<br />

Column M 50 > 50 N/mm 2<br />

Inner wall M 50 > 50 N/mm 2<br />

Slump measure (ø) 140 mm<br />

In brief<br />

C<strong>on</strong>crete delivery<br />

pressure 200 – 220 bar<br />

Once complete, the Ruby Mill Tower will<br />

be 185 m in height and have 34 levels<br />

(four of which are parking areas). The total<br />

usable area of 78,000 m 2 will mostly<br />

be used as offi ce space.<br />

The building was designed by the New<br />

York architects FxFowle, analysis and<br />

design was carried out by LERA and the<br />

Indian company Vasc<strong>on</strong> Engineers undertook<br />

the c<strong>on</strong>structi<strong>on</strong> of the building.<br />

C<strong>on</strong>structi<strong>on</strong> commenced in 2007 and<br />

the building should be complete by the<br />

end of 2010.<br />