Project Status
Project Status Project Status
Changes since the System CoDR in Feb2010‣ focus on Phase 1‣ SKA Memos 125, 130‣250 dishes, 50 low frequency aperture arrays‣ science design reference mission for SKA 1‣ δCoDR documents‣ delineation of the Advanced Instrumentation Program‣ Phased array feeds for dishes, mid-frequency aperturearrays, ultra-wideband single pixel feeds‣ decision points 2014 and 2016‣ formation of the PrepSKA WP2 Management Team‣ WP2 Project Plan in place
Project Phases2009 2010 2011 2012 2013 2014 2015 2016 2017 2018SKA Preparatory PhasePhase 1 Pre-Construction PhasePhase 1 Construction, Verification, Commissioning,Acceptance, Integration & First ScienceScienceSKA1REVDRMDevelopment(Ph 1 part)SKA1 UserTech.RequirementsREVScience / EngineeringTradeoffsREVEarly Science ProposalsRefinement ofEarly ScienceSharedRiskScienceSKA1SystemCoDRConceptdCoDRConceptDefinition*SRRPDRPreliminary DesignCDRDetailedDesignSys Eng& Change managementREVREVContinuous Performance EvaluationSKA1 Systems integrationSKA1 System TestingPDRSKA2Early PreliminaryDesignSystem Definition (includes non-science requirements)Preliminary DesignScienceSKA2REVDRMDevelopmentREVInitial SKA2User Tech.RequirementsExtraction of detailed SKA2 requirementsREVREVScience / Engineering tradeoffsAIPAIP definition, development and fabricationDemonstration& testingProjectMilestonesRev K2010-08-18SKA1BaselineDesignSite decisionCostedsystemdesignSKA1constructionapprovalStart of SKA1ConstructionAIP DecisionBaselineDesign forSKA22009 2010 2011 2012 2013 2014 2015 2016 2017 2018* Includes definition of non-science requirements.SKA2constructionapproval
- Page 1: Welcome and overview of theproject
- Page 5 and 6: Goals of the Pre-Construction Phase
- Page 7 and 8: Expected management structure in 20
- Page 9 and 10: Work Packages1. Management2. System
- Page 11 and 12: Assignment of Work Packages (2)2.
- Page 13 and 14: Site selection‣Physical requireme
- Page 15 and 16: Tropospheric phase monitoring equip
- Page 17: Top level schedule for the SKATechn
<strong>Project</strong> Phases2009 2010 2011 2012 2013 2014 2015 2016 2017 2018SKA Preparatory PhasePhase 1 Pre-Construction PhasePhase 1 Construction, Verification, Commissioning,Acceptance, Integration & First ScienceScienceSKA1REVDRMDevelopment(Ph 1 part)SKA1 UserTech.RequirementsREVScience / EngineeringTradeoffsREVEarly Science ProposalsRefinement ofEarly ScienceSharedRiskScienceSKA1SystemCoDRConceptdCoDRConceptDefinition*SRRPDRPreliminary DesignCDRDetailedDesignSys Eng& Change managementREVREVContinuous Performance EvaluationSKA1 Systems integrationSKA1 System TestingPDRSKA2Early PreliminaryDesignSystem Definition (includes non-science requirements)Preliminary DesignScienceSKA2REVDRMDevelopmentREVInitial SKA2User Tech.RequirementsExtraction of detailed SKA2 requirementsREVREVScience / Engineering tradeoffsAIPAIP definition, development and fabricationDemonstration& testing<strong>Project</strong>MilestonesRev K2010-08-18SKA1BaselineDesignSite decisionCostedsystemdesignSKA1constructionapprovalStart of SKA1ConstructionAIP DecisionBaselineDesign forSKA22009 2010 2011 2012 2013 2014 2015 2016 2017 2018* Includes definition of non-science requirements.SKA2constructionapproval