12.07.2015 Views

PORT WORKS DESIGN MANUAL PART 3 Guide To - The University ...

PORT WORKS DESIGN MANUAL PART 3 Guide To - The University ...

PORT WORKS DESIGN MANUAL PART 3 Guide To - The University ...

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

113D.3 Example 3 - Monitoring of Pore Pressure for Stability during Fill PlacementGivenA piezometer installed in the marine deposit layer revealed abnormalities during the fillplacement works. Increase of excess pore water pressure was found larger than thepredicted value as shown in Figure D2. Pause of filling works was considered necessary(see Section 5.3.2).<strong>The</strong> dimensions of vertical drains were the same as those in Example D.2. <strong>The</strong> coefficientof consolidation (horizontal) was taken as 1.5m 2 /year.TaskEstimate the time required (f) for the excess pore water pressure to fall back to the normalmagnitude.Approach(1) Define the abnormal excess pore pressure as the initial excess pore pressure (M O ).(2) Define the target normal excess pore pressure (u e \(3) Determine the required degree of consolidation (U h ) for dissipation of excess porepressure from u 0 to u e .(4) Back calculate the time factor (T h ) from the required U h .(5) Obtain the actual time t required from T h .SolutionInitial excess pore pressure, u 0 = 20.0 kN/m 2 (see Figure D2)Excess pore water pressure at time t, u e = 14.9 kN/m 2 (see Figure D2)Pore pressure to be dissipated, d p = 20.0 - 14.9 = 5.1 kN/m 2Neglecting vertical drainage, average degree of consolidation required to dissipate the abovepore pressure is given by:[/ =11 = 0.255* 20

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!