Neighbour Contributions Letters of Objection Mr Hart, 7 The Merryfields, Haresfield Mrs A Robinson, Dovetail, Haresfield Lane M Stone, Willow House, Haresfield Lane Planning Schedule Date: 10/08/2004 • Loss of view. • Loss of sunlight. • Rerouting of HT Cable will pose a danger to writers property. • Noise pollution. • Parking problems. • Playground next to a dangerous road and oil tank. • Devalue property. • Materials don't match existing. Letters of Comment E Waterson, The Beeches, Haresfield Lane • Development not in keeping with existing Listed Buildings and surrounding properties. • Proportions of the construction overwhelm the site. • Road safety - entrance to the school is by the road. • Different plans submitted to those that were shown to the public during an open viewing session, the original plans were acceptable. 196

Site Location: Site Report: Planning Schedule Date: 10/08/2004 This application is brought before the committee due to the Council's initial opinion to oppose the application. Site Report This application is for the replacement of three temporary classrooms at Haresfield Church of England School with a large extension to the listed, original school building. The existing buildings are located within the playground area, to the north of the original building. The proposed extension would also extend to the north of the property and provide four additional classrooms, associated areas and a multi purpose hall to the north western corner of the site. This proposal would be phased with three overall phases, to accommodate the day to day functions of the school. Relevant Planning History There are several applications relating to the site in question, mainly concerning the provision of temporary classroom accommodation with the most recent application being S.99/1005 for the retention of the Elliott Classroom that was permitted on the 13th July 2000. Planning Considerations. 197

Site Location:<br />

Site Report:<br />

<strong>Planning</strong> <strong>Schedule</strong> <strong>Date</strong>: <strong>10</strong>/<strong>08</strong>/<strong>2004</strong><br />

This application is brought before the committee due to the <strong>Council</strong>'s initial opinion to oppose the<br />

application.<br />

Site Report<br />

This application is for the replacement of three temporary classrooms at Haresfield Church of<br />

England School with a large extension to the listed, original school building.<br />

The existing buildings are located within the playground area, to the north of the original building.<br />

The proposed extension would also extend to the north of the property and provide four<br />

additional classrooms, associated areas and a multi purpose hall to the north western corner of<br />

the site. This proposal would be phased with three overall phases, to accommodate the day to<br />

day functions of the school.<br />

Relevant <strong>Planning</strong> History<br />

There are several applications relating to the site in question, mainly concerning the provision of<br />

temporary classroom accommodation with the most recent application being S.99/<strong>10</strong>05 for the<br />

retention of the Elliott Classroom that was permitted on the 13th July 2000.<br />

<strong>Planning</strong> Considerations.<br />