12.07.2015 Views

Department of Health: The Paddington Health Campus Scheme

Department of Health: The Paddington Health Campus Scheme

Department of Health: The Paddington Health Campus Scheme

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

part twoRisk management2.14 <strong>The</strong> NHS Capital Investment Manual requires NHSTrusts to assess risk at a level sufficient to assure the Trustthat the preferred option in an OBC is affordable andrepresents the optimum solution. <strong>The</strong> 2000 OBC did nothave a risk register. In early 2001 the <strong>Campus</strong> partnerscommissioned a risk assessment from Ernst & Young whichwas delivered in May 2001. It was a static assessmentand was not integrated into the scheme’s ongoingmanagement. While there were plans to update theassessment in 2002, it was not updated until the autumn<strong>of</strong> 2003. A further update took place in the autumn <strong>of</strong>2004 and was incorporated into the 2004 OBC.2.15 <strong>The</strong>re were a number <strong>of</strong> areas specific to the <strong>Campus</strong>scheme which were not covered in the risk assessments.<strong>The</strong>re was no risk/impact assessment <strong>of</strong>;nnnnhaving two sponsor NHS Trusts and three SeniorResponsible Officers;commissioners’ reluctance to support the scheme’sdevelopment costs;the absence <strong>of</strong> strategic support; orthe cost-benefit implications <strong>of</strong> Imperial College’sresearch to the vision <strong>of</strong> the <strong>Campus</strong>.Although the <strong>Campus</strong> partners recognised the need toaddress the final bullet after the 2003 Gateway review(Appendix 2), they were unable to identify an appropriatemethodology to quantify either risk or benefit inconjunction with Imperial College.2.16 None <strong>of</strong> the risk assessments were used in astructured way as active risk registers for the ongoingmanagement <strong>of</strong> the scheme. As the 2005 IndependentReview Panel noted (Appendix 2), in 2003 the schemewas focussed on procurement when in reality it stillneeded to satisfy the pre-conditions <strong>of</strong> a robust OutlineBusiness Case.2.17 Following the Gateway review in November 2003(Appendix 2), the <strong>Campus</strong> partners accepted the needto introduce and embed a risk register, assumptionslog and issues log as primary project control tools.However, during the summer and autumn <strong>of</strong> 2004 theProject Director recognised that the project team didnot have the capacity, or financial resources, to absorbsignificantly different ways <strong>of</strong> working at the same timeas producing a new OBC. <strong>The</strong> Project Director decidedto concentrate on the OBC with the firm intention <strong>of</strong>introducing the Gateway recommendations for projectcontrols immediately after submission <strong>of</strong> the revised OBC.<strong>The</strong> <strong>Campus</strong> partners’ December 2004 OBC included arisk management strategy, an updated risk register and thecommitment to an active risk management process.Project management2.18 In October 2000, the <strong>Department</strong>’s guidance onfunding operational planning for PFI schemes was thatthe then London Regional Office would re-imburse thescheme with 1. 75 per cent <strong>of</strong> the capital costs to fund thecost <strong>of</strong> developing the scheme to Full Business Case. <strong>The</strong>scheme, with projected capital costs in the 2000 OBC <strong>of</strong>£360 million was therefore based on a funding ceiling <strong>of</strong>£6.3 million. <strong>The</strong> project team understood that this couldnot vary, despite the significant increase in the estimatedcapital cost <strong>of</strong> the scheme.2.19 <strong>The</strong> abolition <strong>of</strong> NHS Regional Offices inMarch 2002 transferred the responsibility for fundingproject costs to the local NHS. <strong>The</strong> North West LondonStrategic <strong>Health</strong> Authority provided £2 million for projectcosts in 2002/03 and £1.5 million in 2003/04. Howeverfrom April 2004 the eight main commissioning PrimaryCare Trusts only agreed to cover half the sum sought fromthem. PUK agreed to match this funding.2.20 <strong>The</strong> Royal Brompton and Harefield NHS Trust hadactivity commissioned by all 303 Primary Care Trusts overthe period the scheme was being developed. Since mostPCTs therefore had little activity carried out by the RoyalBrompton and Harefield NHS Trust, it had correspondinglylittle influence over their commissioning decisions.In addition, approximately 20 per cent <strong>of</strong> the RoyalBrompton and Harefield NHS Trust’s income came fromspecialist clinical service commissioners and researchand development funding, neither <strong>of</strong> which consideredthat their resources had been increased to enable themto support project development costs. As noted by theIndependent Review Panel, inadequate and inappropriatefunding handicapped the scheme’s management capabilitythroughout the planning phase.18<strong>The</strong> <strong>Paddington</strong> <strong>Health</strong> <strong>Campus</strong> scheme

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!